Materials Requirement Plan Activity Part 1

1. MPS parent X has planned order releases of 300 in weeks 2 and 4. Given the following product
tree, complete the MRP records for parts Y and Z. Quantities required are shown in brackets.

Part Y Week
Lead Time: 2 Weeks
Lot Size 500 1 2 3 4
Gross Requirement 300 300
Scheduled Receipts 500
Projected Available 300 300 0 0 200
Net Requirements 300
Planned Order Receipts 500
Planned Order Release 500

Part Z Week
Lead Time: 1 Week
Lot Size 1000 1 2 3 4
Gross Requirement 1000
Scheduled Receipts 1000
Projected Available 200 200 200 200 200
Net Requirements 800
Planned Order Receipts 1000
Planned Order Release 1000
2. Using the following product tree, determine the planned order receipts and planned order
releases if 2000 As are to be produced in week 5. All lead times are 1 week except for
component E, which has a lead time of 2 weeks.

Week 1 2 3 4 5
Part A Planned Order Receipt 2000
Lead Time: 1Week Planned Order Release 2000
Part B Planned Order Receipt 2000
Lead Time: 1Week Planned Order Release 2000
Part C Planned Order Receipt 2000
Lead Time: 1Week Planned Order Release 2000
Part D Planned Order Receipt 2000
Lead Time: 1Week Planned Order Release 2000
Part E Planned Order Receipt 2000
Lead Time: 1Week Planned Order Release 2000