Unit 6:

Network Models
Part 6
Subject: PMOR
Faculty: Prof. Y. M. Khan
Asst. Professor,
Dept. of Mechanical Engineering, ICEEM,
Aurangabad
Activity on Node(AON) Diagram
 It represents ACTIVITIES by NODE or CIRCLE with arrow
connecting them.
 In this AON diagram all the arrows are like dummies ( do not
require any time or resource).
 Tail of the arrow is on the predecessor activity and head is on the
successor activity.

A B A, 3 B, 5

3 5

A) Arrow Diagram B) Activity on Node Diagram


Example for Practice

 The dependency relationships between the activites


of a project are shown below. Draw Arrow and AON
diagram.

Activity A B C D E F
Immediate Predecessor - - - A,B B B,C
Activity A B C D E F

Immediate - - - A,B B B,C


Predecessor

D
A

B E

C
F
A D

START B E END

C F
Comparative Summary of
Arrow Vs AON Diagram
Basis Arrow Diagram Activity on Node
Activity Represented by Arrow Node/Circle
Dummy May be required Not required
Length of Network Lengthy Short
Tail of Arrow Start Event Predecessor Activity
Head of Arrow End Event Successor Activity
Complexity More Less
Reviews and Revise Less Easy Easy
Application PERT, CPM Not Limited Limited to CPM
Representation
A B
A, 3 B, 5
3 5
Thank You