LABOR ITEM RATE COST OF


WORK DESCRIPTION REQUIRED QUANTITY UNIT SQ.FT WORK
WINDOW BREAKING
LABOR 4   NOS 600 2400
WINDOW REPAIRING 1   NOS 600 600
GRANITE FITTING   34 RFT 200 6800
FABRICATION WORK   110 KG 131 14410
FABRICATION CARTING
AND FITTING     1   1500
SLIDING WINDOW   2 4200   8400
SLIDING WINDOW   1 4500   4500
TILE BREAKING FOR
FABRICATION INSTALL 1     600 600
NEW TILE REINSTALL
FOR FABRICATION
RAILING   18 SQ.FT 80 1440
TOTAL AMOUNT         40650

PENDING WORK-

1.SHUTTER NET