Download as pdf or txt
Download as pdf or txt
You are on page 1of 12

3875 © 2021 The Authors Water Supply | 21.

7 | 2021

A holistic reliability system approach of a water


distribution network in Saudi Arabia
Laith Hadidi, Awsan Mohammed, Ahmed Ghaithan and Firas Tuffaha

ABSTRACT

Saudi Arabia, with no perennial rivers, is considered to be an arid land where water losses in the Laith Hadidi
Awsan Mohammed (corresponding author)
water distribution network (WDN) supply increase the need for sea water desalination. This paper Ahmed Ghaithan
Firas Tuffaha
provides a reliability model to enhance the WDN for a water pumping station in Saudi Arabia. The King Fahd University of Petroleum and Minerals,
Dhahran 31261,
paper utilizes the fault tree analysis (FTA) reliability tool to mitigate water supply stoppages. In the
Saudi Arabia
case under study, the pump station utilizes two groundwater aquifers in the eastern part of Saudi E-mail: awsan.mohammed@kfupm.edu.sa

Arabia to meet the raw water demand through a water distribution network (28 km-long pipelines).
Data has been gathered from the maintenance history to estimate the system reliability based on the
loss of water by which each component of the system is assessed on its contribution to the overall
system reliability and water supply. The findings revealed that system availability can be improved by
adding a new pump in the booster station which further enhances the availability of the system to
99.99% and saves the WDN more than 740,974.60 gallons of water loss per year. It is hoped that the
paper’s recommendations will enhance reliability practices in similar water network stations.
Key words | availability, failure tree analysis, reliability, Saudi Arabia, water distribution system,
water loss

HIGHLIGHTS

• The reliability of a community raw water distribution system in Saudi Arabia is assessed.

• A reliability tool based on fault tree analysis is utilized to mitigate water supply stoppage.

• Real data are collected to estimate system reliability.

• The water distribution system availability is analyzed and improved.

INTRODUCTION

A water system is a hydrologically and hydraulically engin- facilities. In addition, it contains pressurizing equipment
eered system consisting of many components and parts such as booster and transfer pumps, a piping network, and
with various rates of failure (Laucelli & Giustolisi ). a drainage system (Alegre et al. ). The water supply
These components are utilized together to supply water system is the most costly urban system. Moreover, leakage
to end users. The system can be highly sophisticated and and failures significantly contribute to an increase in the
automated. It normally includes a raw water source, a pro- water supply and distribution network cost Giustolisi et al.
duction water plant, water storage, and water treatment (). The expenses of this network are more than 85%
of the whole water supply system. In 2012, the maintenance
This is an Open Access article distributed under the terms of the Creative
of aging and deteriorating components of water supply
Commons Attribution Licence (CC BY 4.0), which permits copying,
adaptation and redistribution, provided the original work is properly cited
systems cost $25.9 billion in Canada (Canadian
(http://creativecommons.org/licenses/by/4.0/). Infrastructure Report Card ). Furthermore, in 2013, a
doi: 10.2166/ws.2021.149

Downloaded from http://iwaponline.com/ws/article-pdf/21/7/3875/1104580/ws021073875.pdf


by guest
3876 L. Hadidi et al. | A reliability system approach of a water distribution network Water Supply | 21.7 | 2021

low grade was assigned to the water supply system in the reliability is usually an issue in large-capacity production
United States (ASCE ). In the Middle East, many regions supply systems. Thus, more resources, such as over-time
are facing major problems regarding their water supply. and raw materials, are required to obtain the expected
Qatar, for instance, has the highest rate of evaporation revenue (Huang ).
and the lowest rate of precipitation (approximately Water supply is a vital resource for the population,
82 mm/year) in the world. The water distribution network general welfare, and community health (Alegre et al. ).
in the country loses around 33% of its water as a result of Water is normally obtained from four sources, namely, non-
failures (Scott ). Likewise, Saudi Arabia is one of the renewable groundwater from deep aquifers, desalinated
driest desert regions in the world and relies heavily on sea water, surface water such as rivers, and renewable ground-
water desalination. Hence, water treatment and distribution water from shallow aquifers. A part of the master plan of
is an essential source to satisfy water demand for around any community is the water distribution network, which
30 million people living in Saudi Arabia. has to be planned and designed by expert engineers. Critical
Saudi Arabia has used a government agency known as the factors such as the proper location, current demand, future
presidency of meteorology, in addition to local departments, anticipated growth, pressure, pipe size, required firefighting
to look after the fresh water supply in the country. Reliability flow, etc. must be considered while planning and designing
and availability are important measures for the quality of water distribution networks. Designing such systems without
water supply. However, these measures have not been failures is hard, if not impossible, because of technological
linked with the amount of supplied water. A lack of such concerns and higher cost. Consequently, reliability and avail-
measures may have a severe effect on the water supply ability concepts need to be taken into account at the early
which is usually caused by frequent failure breakdowns of design stage for production performance.
systems and poor reliability studies. The estimation of Reliability improvements in water supply networks can
system reliability has a great impact on the quantity of the be reached by reducing failures in the future. Several studies
produced supply which greatly concerns the decision have been conducted to evaluate water distribution network
makers who strive to predict the expected supply capacity reliability. Tabesh et al. () addressed three techniques for
by assessing reliability. Kawas et al. () developed a forecasting the failure rate of pipes. The developed methods
robust optimization model to enhance the reliability of a were the fuzzy approach, artificial neural network, and
production system in satisfying demand and in terms of pro- regression. A real case study involving a big network for
viding guarantees on profits. Kanakoudis & Tolikas () water distribution in Iran used an application of the proposed
introduced an approach to compute the optimal time of models. Model prediction outcomes were compared with
replacement for water system pipes. The approach is based the data calculated for pipe failure. The findings showed
on techno-economic analysis. In addition, Kanakoudis & that the neural network outperformed the other developed
Tolikas () and Kanakoudis & Tolikas (a) evaluated techniques. Kanakoudis & Tsitsifli () applied the discri-
water network performance by analyzing the possible minant analysis and classification approach to assess and
actions of preventive maintenance in a water network. The predict the reliability of a water pipe system. The results indi-
authors utilized techno-economic analysis to accomplish cated the ability of the applied method to forecast the
the work. Similar work was conducted by Kanakoudis reliability of an urban water pipe network. Another study
() to determine the optimal schedule of preventive was conducted by the same authors (Tsitsifli & Kanakoudis
maintenance. The author compared the optimal obtained ). They discussed the reliability evaluation of pipes in
schedule with empirical schedules. Tsitsifli et al. () uti- two pipe networks using the DAC approach. Each network
lized the discriminant analysis and classification approach piping was divided into two groups on the basis of whether
to assess and forecast the behavior of water system pipes. or not it failed at least once (failures group, successes
The results of this work were very promising. The authors group). The ‘critical Z-score’ criterion was utilized as a
used the DAC method to classify the pipes into success measure of the potential pipe status. Moreover, Piadeh
and failure pipes. Alternatively, overestimating a system’s et al. () developed a hybrid model based on the

Downloaded from http://iwaponline.com/ws/article-pdf/21/7/3875/1104580/ws021073875.pdf


by guest
3877 L. Hadidi et al. | A reliability system approach of a water distribution network Water Supply | 21.7 | 2021

combination of fault tree analysis and event tree analysis for bar at the household supply) (Racoviceanu & Karney ).
the reliability assessment of water treatment systems. The WDN must be reliable and maintained at a positive
Gheisi & Naser () applied a multi-criteria decision pressure at all times. It must also prevent leakages, which
analysis approach for ranking some alternative distribution should be tackled immediately. WDNs usually have a
layouts of a WDN employing statistical flow entropy and con- designed pumping station with storage tanks and pumps.
sidering various states of reliability (the probability that a Although there is agreement that reliability is an important
WDN satisfies water demands during different states of simul- trait of any distribution system, there is no universally recog-
taneous pipe failures). In addition, Shafiqul Islam et al. () nized definition for ‘reliability’.
developed an approach for evaluating the overall reliability of An effective analysis of reliability and availability
WDNs in terms of nodal pressures and the quantity and qual- improves the performance of production systems. In this
ity of nodal available discharges using a fuzzy technique. They regard, it is essential to understand the relationship between
applied demand-driven analysis (DDA), which is the disadvan- the productivity of a WDN and its reliability in satisfying
tage of their work. Pressure-driven analysis (PDA) that certain production levels. In general, a water supply has
considers the pressure dependency of nodal discharges pro- to be reliable and available to all end-users at all times,
vides more realistic results than DDA (Shirzad et al. ). even during maintenance. The performance level of a water
Liu et al. () considered surrogate metrics to take reliability supply system under normal and abnormal operating con-
in water distribution networks into account under normal ditions can be evaluated using the appropriate indices such
working conditions. Furthermore, Xu & Goulter () as percentage of use, grade and quality of service, reliability,
proposed a novel method for optimizing the reliability of a and availability (Kanakoudis ). Moreover, Kanakoudis &
water distribution network under uncertainty of pipe capacity Tolikas (b) presented an assessment simulation model
and nodal demand. The model included a strategy to identify for an integrated water supply system in Athens. The objec-
significant nodes that are subject to reliability constraints in tive was to determine the best configuration and flow
the cost-minimization step. A sensitivity analysis was con- through the water system to minimize the total cost. Other
ducted to evaluate the efficiency of the proposed model. related works have been carried out by Kanakoudis & Toli-
Other studies that considered reliability assessment in water kas (c) and Kanakoudis & Tolikas (d).
distribution systems have been conducted by Shafiqul Islam In general, reliability can be assessed and measured
et al. (). Shirzad & Safari () compared random forest using different tools including reliability hazard analysis,
and multivariate regression methods for predicting failures in failure mode and effects analysis (FMEA), fault tree analysis
a WDN. (FTA), reliability-centered maintenance (RCM), and other
This paper aims to improve the reliability of the current methods. FMEA is used at the beginning to identify poten-
community raw WDN systems by estimating the failure prob- tial failures and the associated impacts. Then an FTA is
ability, availability, and unavailability indices for WDN system constructed which can be used to describe all the causes
components to determine the reliability of the current system. of the events that lead to failure mode. Stiff et al. ()
The contribution of this study is to link developed reliability used a HAZID (Hazard Identification) technique to define
measures with the water supply loss in the WDN by applying the differences between turrets and spread mooring systems.
sensitivity analysis at the component level to understand their Quantitative risk assessment between the turret and spread
influences on the system reliability as a whole, in addition to mooring was calculated using structural reliability analysis.
modeling the faults using fault tree analysis. In this paper, a system reliability analysis for a commu-
nity raw WDN in Saudi Arabia is analyzed. First, the major
input variables (components or equipment) that the system
MATERIALS AND METHODS reliability depends on are identified and selected. Then,
the failure probabilities of each input variable are calculated.
The aim of a water distribution network (WDN) is to supply Then, a fault tree analysis diagram is constructed and the
water to consumers with sufficient pressure (2.75 bar to 5.5 system reliability is computed quantitatively using indices

Downloaded from http://iwaponline.com/ws/article-pdf/21/7/3875/1104580/ws021073875.pdf


by guest
3878 L. Hadidi et al. | A reliability system approach of a water distribution network Water Supply | 21.7 | 2021

such as system availability. Lastly, the failure effect of each ). In this paper, the following assumptions are used to
component is measured in terms of water loss in the system. develop the model:

1. The failure rate is constant during the normal operating


Input parameters lifecycle.
2. System study is under the normal operating phase of the
In this study five main input variables are identified as: system lifecycle.

1. Water wells (11 components) 3. Failures occur independently. The occurrence of one

2. Booster pumps at the source (three pumps) failure does not affect the probability of occurrence of

3. Network pipelines (two pipelines) the second failure.

4. Booster pumps at destination (four pumps) 4. The time between failures is not affected by the repair time.

5. Diesel engine driven pumps (two pumps) To calculate these indices, the following equations are

These are the main components of the system. Any fail- used:

ure in these components will cause the system to fail. In


1
order to calculate the system reliability, failure probabilities MTTF ¼
λ
have to be calculated. Table 1 shows the average repair time
total operating hours
for each major component in the system. MTBF ¼
number of failures
Other water wells were not included in the study because
their components do not contribute much to the operation, 1
MTTR ¼
i.e., their capacities are small compared with the main μ
water wells. The maintenance history for each component
is extracted from the Enterprise Resource Planning (ERP) where μ is a constant repair rate.
system. Sometimes the system does not give accurate data.
For example, maintenance activity is completed today, μ
Availability Rate ¼
μþλ
while the ERP gets updated after one month. This will
cause an offset in the history data and, hence, there will be MTBF ¼ MTTF þ MTTR
reasons to take experts’ judgments into consideration.
MTBF
System Availability ¼
(MTBF þ MTTR)
Reliability analysis R(T ) ¼ eλT

Reliability can be assessed using various models, including


Fault tree analysis
failure rate λ (t), Mean Time to Failure (MTTF), Mean
Time between Failures (MTBF), Mean Time to Repair
FTA is a popular reliability analysis tool used globally. It was
(MTTR), and Availability and Unavailability (Duffuaa et al.
introduced in 1962 at Bell Telephone Laboratories, in con-
Table 1 | Average repair time and rate for each major component in the system nection with a safety evaluation of the launching system for
the intercontinental Minuteman missile (Rausand & Høyland
Average repair
). FTA depends on identifying failure events that may
No. Equipment time (days/failure) Repair rate (μ)
occur in a system. It graphically represents the interrelation-
1 Water well pumps 60 6.94 × 104
ships between potential critical failure events which impact
2 Booster pumps at the source 30 1.39 × 103
the occurrence of a specific undesirable event that is called
3 Network pipelines 1 4.17 × 102
a ‘top event’. In drawing up the tree we use the so-called func-
4 Booster pumps at destination 30 1.39 × 103
tions (logic gates), specifying, among other things, the logical
5 Diesel engine driven pumps 15 2.78 × 103
product of events and the logical sum of events.

Downloaded from http://iwaponline.com/ws/article-pdf/21/7/3875/1104580/ws021073875.pdf


by guest
3879 L. Hadidi et al. | A reliability system approach of a water distribution network Water Supply | 21.7 | 2021

There are two basic logic gates, as shown in Figure 1: Table 2 | Water wells at the source of the water supply system

‘OR’ gate: an event above the gate occurs if at least one


Capacity gallon Number of
event below the gate occurs; Well no. Voltage Motor HP per minute (GPM) stages

‘AND’ gate: an event above the gate occurs if all the 25 2,300 150 540 3
events below the gate occur. 26 2,300 150 1,365 6
27 2,300 150 1,410 3
28 2,300 150 1,485 3
CASE STUDY 30 2,300 150 672 4
31 2,300 150 753 2
To illustrate the methodology of this work, the case study 45 2,300 150 901 2
focuses on a community raw water system located in 46 2,300 150 731 4
Saudi Arabia. First, the system inputs are identified. Then, 49 2,300 150 563 2
the ERP system is used to find the failure probabilities for 64 2,300 150 1,170 5
each input. Finally, fault tree analysis (FTA) is constructed 71 2,300 150 1,125 2
and reliability analysis is conducted.
importance and criticality of the water differs from one pro-

Water distribution network ponent to another. The loss of drinking water may not be
that important; however, it is crucial to continuously

The considered community area depends solely on ground- supply the fire hydrants.

water as the only source of water. There are 18 scattered The water distribution network consists of pumps, pipes,

water wells producing different amounts of water. The tanks, valves, fire hydrants, instruments, etc. In order to deli-

majority of these water wells are located in the eastern pro- ver water to the community, all of these components must

vince of Saudi Arabia (11 water wells) which is around operate reliably and be 100% available at all times. Figure 2

28 km away from the community area. The water produced illustrates the water distribution network.

from the source of the water system is then transferred through


a carbon steel pipe to the community area. The remaining System input
water wells are located in the community area. All of these
water wells are connected to the water distribution network. A community water distribution system is a sophisticated
Table 2 gives information about the main water wells. system with many small and large components. In this
The produced water is used for cleaning, showering, case study the major components are investigated, whereas
drinking, feeding the fire system, irrigation, etc. Hence, the other components such as valves, instrumentation and

Figure 1 | Logic gates: (a) OR gate; (b) AND gate.

Downloaded from http://iwaponline.com/ws/article-pdf/21/7/3875/1104580/ws021073875.pdf


by guest
3880 L. Hadidi et al. | A reliability system approach of a water distribution network Water Supply | 21.7 | 2021

Figure 2 | The community water distribution network diagram.

small piping branches are not considered. The main com- FTA analysis
ponents that are included in this study are:
The first step in constructing the FTA diagram is to identify
1. water well pumps and motors (11 components) (1,000
the ‘top event’. In this study the ‘top event’ is a failure to
gallons per minute (GPM) each);
meet the daily water demand for the community, which is
2. booster pumps at the source of a water system (three
7.26 MMGD (5,000 GPM). After that, the events that lead
pumps) (9,000 GPM each);
to the occurrence of the ‘top event’ are identified. In this
3. network water pipelines (NWP-11 and NWP-12) (6,000
system, the identical components are working in active
GPM each);
4. booster pumps at destination (four pumps) (2,500 GPM redundancy. Referring to Figure 3, these events are as

each); follows:

5. diesel engine driven pumps (two pumps) (2,500 GPM 1. Event 1: the failure of more than six water wells simul-
each). taneously will cause the system to fail as five water
wells, at least, must be operational to satisfy the daily
Failure probability water demand for the community. It is assumed that the
capacities of all water wells at the source (WPSs) are simi-
An ERP system is utilized to get the maintenance history of lar (1,000 GPM). The probability of this failure can be
the system inputs identified in the previous section. The found based on the binomial distribution (simultaneous
number of failures reported for each piece of equipment is failures of more than six water wells) (see Table 4).
shown in Table 3. The failure rate of each system component 2. Event 2: the simultaneous failure of the three booster
is calculated on the basis of its lifetime and the number of pumps will cause the system to fail as at least two of
failures occurring during its lifecycle. them must be operational at the source. The probability

Downloaded from http://iwaponline.com/ws/article-pdf/21/7/3875/1104580/ws021073875.pdf


by guest
3881 L. Hadidi et al. | A reliability system approach of a water distribution network Water Supply | 21.7 | 2021

Table 3 | Major system component failure rates

Location Equipment No. of failures No. of years Failure per year Failure per hour

Booster station at the source WPS-25 2 10 0.200 2.28 × 105


WPS-26 2 0.200 2.28 × 105
WPS-27 3 0.300 3.42 × 105
WPS-28 2 0.200 2.28 × 105
WPS-30 7 0.700 7.99 × 105
WPS-31 1 0.100 1.14 × 105
WPS-45 4 0.400 4.57 × 105
WPS-46 3 0.300 3.42 × 105
WPS-49 2 0.200 2.28 × 105
WPS-64 3 0.300 3.42 × 105
WPS-71 1 0.100 1.14 × 105
Pump L-22 8 15 0.533 6.09 × 105
Pump L-23 19 1.267 1.45 × 104
Pump L-24 16 1.067 1.22 × 104
Network water pipelines (two pipelines) 20 25 0.800 9.13 × 105
Booster station at destination/community area Pump 17 A 5 15 0.333 3.81 × 105
Pump 17 B 4 0.267 3.04 × 105
Pump 17 C 3 0.200 2.28 × 105
Pump 37 4 0.267 3.04 × 105
Diesel engine driven pump 23 8 20 0.400 4.57 × 105
Diesel engine driven pump 24 13 0.650 7.42 × 105

Figure 3 | FTA diagram for the case study.

of this failure can be found based on the binomial distri- 3. Event 3: the failure of the two pipelines will jeopardize
bution (simultaneous failures of more than two booster the distribution operation. The network water pipelines
pumps) (see Table 4). transporting water from the source to the community

Downloaded from http://iwaponline.com/ws/article-pdf/21/7/3875/1104580/ws021073875.pdf


by guest
3882 L. Hadidi et al. | A reliability system approach of a water distribution network Water Supply | 21.7 | 2021

Table 4 | Probabilities of system failure operational or the two diesel engine driven pumps must
be available (simultaneous failures of at least one
Probability of
Scenario system failure diesel engine and more than three booster pumps) (see

Event 1 The failure of more than six water wells 1 × 106


Table 4).
simultaneously 5. Event 5: the failure of three booster pumps and two diesel
4
Event 2 The failure of the three booster pumps 3.01 × 10 pumps will cause the system to fail (simultaneous failures
simultaneously of two diesel engines and more than two booster pumps)
Event 3 The failure of both network water 4.76 × 106 (see Table 4).
pipelines
Event 4 The failure of the four booster pumps 4.08 × 108
and one diesel pump
Event 5 The failure of three booster pumps and 1.54 × 108
RESULTS
one diesel pump

In this section, system reliability is assessed utilizing the


area must be available all times (simultaneous failures of aforementioned data. In addition, sensitivity analysis is
the two pipelines) (see Table 4). conducted to find which component is more influential
4. Event 4: The failure of the four booster pumps and one on overall system reliability. Figure 4 presents the mean
diesel pump will cause the system to fail. At least two time to failure and the mean time to repair of the
booster pumps in the community area must be system components. Based on the MTTF and MTTR of

Figure 4 | System components’ MTTF and MTTR.

Downloaded from http://iwaponline.com/ws/article-pdf/21/7/3875/1104580/ws021073875.pdf


by guest
3883 L. Hadidi et al. | A reliability system approach of a water distribution network Water Supply | 21.7 | 2021

the major system components, the availability and unavail- the binomial distribution. Table 4 shows the different scen-
ability of the main components are computed as shown in arios and corresponding probabilities of system failure.
Figure 5. As can be seen, the network water pipelines Then the failure probability of the whole system is calcu-
(two pipelines), WPS-71, booster pump 17 C, and diesel lated by summing up all of the basic event probabilities:
engine driven pump 23 are the most available components.
In order to simplify the calculation process, the average Psystem ¼ P1 þ P2 þ P3 þ P4 þ P5 ¼ 0:000307 ¼ 0:030686%
of the unavailability for each similar piece of equipment is
taken:
Hence, the system availability is 99.96931%.

• Water wells (11 components) ¼ P(WPS) ¼ 0.040 Since the minimum required capacity of the system to

• Booster pumps at the source (three pumps) ¼ P(BPS) ¼ meet the daily water demand is 5,000 GPM, the minimum
water loss due to unavailability is:
0.067
• Network pipelines (two pipes) ¼ P(NEP) ¼ 0.0022
• Booster pumps in the community area (four pumps) ¼ Water loss > 5,000 × (1  0:9996931) > 1:5345 GPM
P(BPCO) ¼ 0.021
• Diesel engine driven pumps (two pumps) ¼ P(DEDP) ¼ This implies that the yearly water loss is more than
0.021 806,533 gallons. The water loss is the amount of distributed
water that does not reach the end users from the water
Furthermore, the probabilities of each basic event (scen- supply system, which will be supplied from other water
ario) that cause the top event to happen are computed using sources.

Figure 5 | The system’s major components availability and unavailability.

Downloaded from http://iwaponline.com/ws/article-pdf/21/7/3875/1104580/ws021073875.pdf


by guest
3884 L. Hadidi et al. | A reliability system approach of a water distribution network Water Supply | 21.7 | 2021

Table 5 | Sensitivity analysis

1st Scenario 2nd Scenario 3rd Scenario 4th Scenario 5th Scenario

Additional WPS Additional BPS Additional NEP Additional BPCO Additional DEDP
New availability 99.9693 99.9975 99.9699 99.9694 99.9694
Minimum saving of water (gallon per year) 262.80 740,974.60 15,346.21 2,858.48 2,850.59

Sensitivity analysis community area have been constructed which may last for
at least three consecutive days and more than that if we
In this section, sensitivity analysis is conducted to evaluate reduce the amount of unnecessary demand such as for
system reliability by adding an extra unit as a back-up to irrigation.
enhance the overall system reliability. Five scenarios are
tested as shown in Table 5. From Table 5 it can be noticed
that having an additional booster pump in the source of
the water system will enhance and boost system reliability CONCLUSIONS
by around 0.028%, which is the highest among all of the
scenarios. In addition, the minimum quantity of water The main purpose of this paper is to assess the reliability of a

saved is computed to illustrate the effectiveness of enhan- community raw water distribution system in Saudi Arabia

cing system reliability. Table 4 shows that it is worthwhile and to conduct a sensitivity analysis. The analysis was

to add an extra unit of BPS as a back-up to save more built on five failure scenarios which, if any one of them

than 740,974.60 gallons per year. occurred, would cause the system to malfunction. These
scenarios were used to build and construct the fault tree
analysis.
Despite the fact that the system is very complex and
IMPLICATIONS sophisticated, the major components are considered, and
some logical and legitimate assumptions are made. This is
In many production systems if an unexpected failure hap- in order to have a more convenient system for analysis
pens, the failed machines have an impact on the line and to have a sense of the behavior and characteristics of
upstream by causing them to operate without processing a real system. The analysis shows that the system availability
material and causing a gap in production downstream of is around 99.97%. The system availability is improved by
the failure. Furthermore, this may lead to a gap in the pro- adding a new pump in the booster station at the source of
duction interruption upstream. This is due to quality the water system, which results in boosting the availability
problems during the breakdowns that lead to scrapping to 99.99%.
the material interruption upstream. Therefore, the real pro- This study helps management to be aware of the
duction rate is less than the nominal production rate. strengths and weaknesses of the system. Moreover, most
Despite the fact that the system availability of 99.97% is reliability studies focus only on system reliability indicators.
considered to be high, there is still a very minimal chance of This study links the reliability indicator with the production
failure (0.030%) which, if it happens, may be dangerous and output of the plant (in our case, cubic metres of fresh water).
will raise safety concerns. This is because of the fact that the This would enable estimation of the service level provided
community water system feeds different facilities such as by the plant and also help to justify the maintenance cost
residential, offices, plants, labs, recreational facilities, etc. as it can be easily translated into cost–benefit analysis. Fur-
Moreover, it feeds the fire system and fire hydrants. This is thermore, the study, in conjunction with the sensitivity
why we cannot tolerate this small percentage occurring. analysis, will assist management to make decisions with
Hence, huge storage tanks in the booster station in the regard to the feasibility of adding extra equipment to the

Downloaded from http://iwaponline.com/ws/article-pdf/21/7/3875/1104580/ws021073875.pdf


by guest
3885 L. Hadidi et al. | A reliability system approach of a water distribution network Water Supply | 21.7 | 2021

system to enhance its reliability. The method applied in this Huang, N.  Mean station reliabilities cause throughput
paper is applicable to other similar water supply systems and overestimates in production system design. Journal of
Manufacturing Systems 31, 184–194.
can be used in assessing the reliability of these systems. Cer- Kanakoudis, V.  The Role of Failure Events in Developing
tain assumptions can be made in order to simplify the Water Systems Pipes Preventive Maintenance and
calculations. However, we should not ignore any major Replacement Criteria. PhD thesis, Department of Civil
Engineering, Division of Hydraulics and Environmental
input to the system so as not to jeopardize the quality of
Engineering, Aristotle University of Thessaloniki, Greece.
the results. Kanakoudis, V. K.  Vulnerability based management of water
resources systems. Journal of Hydroinformatics 6 (2),
133–156.
Kanakoudis, V. K. & Tolikas, D. K.  The role of leaks and
ACKNOWLEDGEMENTS breaks in water networks: technical and economical
solutions. Journal of Water Supply: Research and Technology
– AQUA 50 (5), 301–311.
The authors thank King Fahd University of Petroleum and Kanakoudis, V. & Tolikas, D. a Managing water resources
Minerals for the support and facilities that made this and supply systems: fail-safe vs safe-fail. In: Proceedings
research possible. The feedback of the anonymous of the EWRA 5th International Conference ‘Water
Resources Management in the Era of Transition’
reviewers, which helped in improving the paper, is highly (G. Tsakiris, ed.), Symetria Publications, Athens, Greece,
appreciated. pp. 194–204.
Kanakoudis, V. & Tolikas, D. b Water supply systems
modeling, optimization & vulnerability assessment. In:
Proceedings of the 5th EWRA International Conference
‘Water Resources Management in the Era of Transition’
DATA AVAILABILITY STATEMENT (G. Tsakiris, ed.), Symetria Publications, pp. 566–579.
Kanakoudis, V. K. & Tolikas, D. K. c Performance indices of a
All relevant data are included in the paper or its Supplemen- water network – part I: theory. In: Proceedings of the
International Conference ‘Protection and Restoration of the
tary Information.
Environment VI’ (A. G. Kungolos, A. B. Liakopoulos, G. P.
Korfiatis, A. D. Koutsospyros, K. L. Katsifarakis & A. C.
Demetracopoulos, eds), Skiathos, Greece, pp. 257–265.
Kanakoudis, V. K. & Tolikas, D. K. d Performance indices of a
REFERENCES water network – part III: risk analysis. In: Proceedings of the
International Conference ‘Protection and Restoration of the
Alegre, H., Baptista, J. M., Cabrera Jr., E., Cubillo, F., Duarte, P., Environment VI’ (A. G. Kungolos, A. B. Liakopoulos, G. P.
Hirner, W., Merkel, W. & Parena, R.  Performance Korfiatis, A. D. Koutsospyros, K. L. Katsifarakis & A. C.
Indicators for Water Supply Services. IWA Publishing, Demetracopoulos, eds), Skiathos, Greece, pp. 277–285.
London, UK. Kanakoudis, V. K. & Tolikas, D. K.  Assessing the
American Society of Civil Engineers  Report Card for performance level of a water system. Water, Air and Soil
America’s Infrastructure. Available from: http://www. Pollution: Focus 4 (4), 307–318.
infrastructurereportcard.org. Kanakoudis, V. & Tsitsifli, S.  Water pipe network reliability
Canadian Infrastructure Report Card  The 2012 Report Card. assessment using the DAC method. Desalination and Water
Available from: http://www.canadainfrastructure.ca/en/report. Treatment 33 (1–3), 97–106.
html. Kawas, B., Laumanns, M. & Pratsini, E.  A robust
Duffuaa, S. O., Raouf, A. & Campbell, J. D.  Planning and optimization approach to enhancing reliability in production
Control of Maintenance Systems: Modeling and Analysis. planning under non-compliance risks. OR Spectrum 35,
John Wiley, New York, USA. 835–865.
Gheisi, A. & Naser, G.  Simultaneous multi-pipe failure Laucelli, D. & Giustolisi, O.  Vulnerability assessment of
impact on reliability of water distribution systems. Procedia water distribution networks under seismic actions. Journal of
Engineering 89, 326–332. Water Resources Planning and Management 141 (6),
Giustolisi, O., Laucelli, D. & Savic, D.  Development of 04014082. https://doi.org/10.1061/(ASCE)WR.1943-5452.
rehabilitation plans for water mains replacement considering 0000478.
risk and cost–benefit assessment. Civil Engineering and Liu, H., Savić, D. A., Kapelan, Z., Creaco, E. & Yuan, Y. 
Environmental Systems 23 (3), 175–190. Reliability surrogate measures for water distribution system

Downloaded from http://iwaponline.com/ws/article-pdf/21/7/3875/1104580/ws021073875.pdf


by guest
3886 L. Hadidi et al. | A reliability system approach of a water distribution network Water Supply | 21.7 | 2021

design: comparative analysis. Journal of Water Resources regression splines and random forest techniques. Urban
Planning and Management 143 (2), 04016072. Water Journal 16 (9), 653–661.
Piadeh, F., Ahmadi, M. & Behzadian, K.  Reliability Shirzad, A., Tabesh, M., Farmani, R. & Mohammadi, M. 
assessment for hybrid systems of advanced treatment units of Pressure–discharge relations with application to head-driven
industrial wastewater reuse using combined event tree and simulation of water distribution networks. Journal of Water
fuzzy fault tree analyses. Journal of Cleaner Production 201, Resources Planning and Management 139 (6), 660–670.
958–973. doi:10.1016/j.jclepro.2018.08.052. Stiff, J., Ferrari, J., Ku, A. & Spong, R.  Comparative risk
Racoviceanu, A. I. & Karney, B. W.  Life-cycle perspective on analysis of two FPSO mooring configurations. In: Offshore
residential water conservation strategies. Journal of Technology Conference, 5–8 May, Houston, TX, USA, paper
Infrastructure Systems 16 (1), 40–49. number OTC-15377-MS.
Rausand, M. & Høyland, A.  System Reliability Theory: Tabesh, M., Soltani, J., Farmani, R. & Savic, D.  Assessing
Models, Statistical Methods, and Applications. John Wiley & pipe failure rate and mechanical reliability of water
Sons, Hoboken, NJ, USA. distribution networks using data-driven modeling. Journal of
Scott, V.  Managing water supply a key challenge facing Qatar, Hydroinformatics 11 (1), 1–17.
expert says. Doha News (26 November). Available from: Tsitsifli, S. & Kanakoudis, V.  Predicting the behavior of a pipe
https://www.dohanews.co/managing-water-supply-a-key- network using the ‘critical Z-score’ as its performance
challenge-facing-qatar-expert-says/. indicator. Desalination 250 (1), 258–265.
Shafiqul Islam, M., Sadiq, R., Rodriguez, M. J., Najjaran, H. & Tsitsifli, S., Kanakoudis, V. & Bakouros, I.  Pipe networks risk
Hoorfar, M.  Reliability assessment for water supply assessment based on survival analysis. Water Resources
systems under uncertainties. Journal of Water Resources Management 25 (14), 3729–3746.
Planning and Management 140 (4), 468–479. Xu, C. C. & Goulter, I. C.  Reliability-based optimal design of
Shirzad, A. & Safari, M. J. S.  Pipe failure rate prediction in water distribution networks. Journal of Water Resources
water distribution networks using multivariate adaptive Planning and Management 125 (6), 352–362.

First received 20 November 2020; accepted in revised form 7 May 2021. Available online 19 May 2021

Downloaded from http://iwaponline.com/ws/article-pdf/21/7/3875/1104580/ws021073875.pdf


by guest

You might also like