Professional Documents
Culture Documents
MCC in Nepal
MCC in Nepal
1
MCC IS A U.S. GOVERNMENT AGENCY THAT GIVES GRANTS TO INCREASE
ECONOMIC GROWTH AND REDUCE POVERTY
Focused mandate: Reduce poverty through economic growth
Corporate structure: Led by a governing public/private Board of Directors
• Secretary of State Mike Pompeo (chair)
• Secretary of Treasury Steven T. Mnuchin (vice chair)
• U.S. Trade Representative Robert E. Lightizer
• USAID Administrator Mark Green
• MCC Chief Executive Officer
• 4 private sector members
• Focus on results: MCC only funds projects that are expected to have
demonstrable impact on economic growth.
• Methodical approach to project selection
• Rigorous tracking and evaluation of projects
3
MCC IS SELECTIVE AND IS CURRENTLY ONLY WORKING WITH 18 COUNTRIES
ON A COMPACT
• The objective of the Electricity Transmission Project (ETP) is to increase electricity consumption by
improving the availability and reliability of electricity supply in Nepal’s electricity grid and by facilitating
power trade:
• Investment in Nepal’s transmission network by constructing transmission lines and three substations
to expand the high voltage transmission backbone inside Nepal and support increased supply of
electricity to consumers, allowing more efficient movement of electricity across the grid, with lower
technical losses, such that supply is better able to meet demand
• Investments in cross-border interconnection by constructing Nepal side of a second cross-border
transmission line with India to facilitate increased electricity export when domestic generation
exceeds domestic demand in the rainy season, and increased electricity import when domestic
generation is at its lowest in the dry season
• Provide Technical Assistance (TA) to improve sustainability of the power sector and the infrastructure
investments by enabling Nepal Electricity Authority (NEA) to operate, manage, and maintain the new
400kV system and to newly established Electricity Regulatory Commission
• The increase of electricity in Nepal’s grid is expected to allow consumers to use more electricity to meet
their energy needs and incur less expenditures per unit of energy consumed than experienced currently.
The ETP has 3 Components
312 km of Transmission Technical Assistance
Lines 3 Substations to NEA and Nepal ERC
• The objective of the Road Maintenance Project (RMP) is to maintain road quality across the Strategic
Road Network (SRN):
• By equipping the DoR with the data, skills, and experience necessary to plan and implement road
maintenance, combined with an increased level of funding under an improved road maintenance
funding regime, it is expected that the SRN will be adequately maintained and road quality will not
deteriorate
The RMP has 2 activities
1. Technical Assistance to 2. Enhanced road maintenance on up to 305 km
DoR of roads (based on incentive matching from GoN)
Compact
Signing Entry-into- Compact
SEPT-2017 Now Force Closeout
MCC BoD
5-year clock
Selects Nepal
starts ticking
here
Entry into Force Date
• MCC’s implementation method requires that enough time is allotted to the project preparatory phase so
that all conditions for successful project delivery are met prior to the Entry into Force (EIF)
• Following EIF, all implementation activities must be completed within five-years, as there are no provisions
for time extensions or cost increase
Outreach Event
Kathmandu
November 18, 2019
Electricity Transmission Project
Outcomes:
• Add 3,920 MW Tx capacity; reduce losses to 1.9%
• Support 3x increase in electricity consumption per capita
• Approx. 312 km – 400 kV Tx lines (~857 towers)
• 3 x 400 kV substations
Electricity Transmission Line
Status
• Transmission Line Route Alignment frozen for all five segments
• Lapsiphedi ‐ Ratmate
• Ratmate ‐ New Hetauda
• Ratmate ‐ New Damauli
• New Damauli ‐ New Butwal
• New Butwal ‐ Nepal/India Border
• Geotechnical survey works completed
• Draft EIA document in advanced stage of preparation
Electricity Transmission Line (Works)
Transmission Lines
• 400 kV D/C; lots 90-115 km each
• 3.5 year execution
• Design-Build (FIDIC Yellow Book)
• Expected launch: Jan 2020
• Quality-Price Based Selection
• Expected contract sign: Sep 2020
Segment wise physical information
• Lapsiphedi – Ratmate
• Middle Mountain physiographic
zone (Ratmate to Lapsiphedi)
• Section Length : Approx. 59 km
• No. of towers: Approx. 163
• 400 kV Quad Moose Double
Circuit
Lapsiphedi-Ratmate-New Hetauda 400kV D/C
Transmission Line (contd...)
• Resettlement policy
framework completed
• Entitlement Matrix
completed
• RAP of Transmission
lines will be completed
by June 2020
• Land compensation
payment to be
completed by December
2020
Challenges
• Difficult Terrain/Transportation of
materials: Elevations vary from 100
meters (330 ft.) to around 2000
meters (6563 ft.)
• Land Acquisition and securing Right
of Way
• Heavy Monsoon Season of 3
months (9 months effective in a
year)
• Forest Clearance
• Major river crossing
• Trishuli
• Kali Gandaki
• Seti
MCA Partnership program
• ETP includes the MCA Partnership
program as a benefit sharing
component of ETP;
• Framework developed
• Framework workshop conducted
• Data collection for Sub-Activity
ongoing
• Sub-activity consultation to be
done by December 2019
• Expected date for construction
bid release for thematic area 1 by
August 2020
• Expected date for Request for
proposal for Thematic area 2 and
3 by March 2020
Additional Employer’s
Requirements of Note
2020 21 22 23 24 25
Activities
Jan Feb Mar Apr May Jun Jul Aug SepOct Nov Dec Jun Jul Jun
Bid Release (in web &
Newspaper)
Site visit
Pre-bid meeting
Bid Submission
Technical Bid opening
Financial Bid Opening
Award of contract
Construction Period
Defect Notification Period
Future Outreach Event
• Minimize the need for access roads by use of porters, helicopters, etc.
Mitigate (Examples)
• Use of bird diverters.
• Reforestation.
• Slope stabilization/rehabilitation works.
Thank You!
Electricity Transmission
Project
Outreach Event and Feedback
Session-Kathmandu, Nepal
18 November 2019
PROCUREMENT ASPECTS
Open, fair and competitive procedures used in a transparent manner to solicit, award and
administer contracts
Solicitations based on a clear and accurate description of the goods, works or services to be
acquired
Contracts awarded only to qualified and capable suppliers and contractors that perform in
accordance with the terms and conditions of the applicable contracts and on a cost-effective
and timely basis
No more than a commercially reasonable price is paid to procure goods, works or services
MCC Procurement Guidelines and
Principles
• Nepal’s Government Procurement Act and Rules Does Not Apply
• PPG’s Structure
• Fifteen (15) Parts
• Two (2) Attachments
• Ninety-Two Pages (March 2019 Release)
• https://www.mcc.gov/resources/doc/program-procurement-guidelines
• Publication Requirements
• DgMarket
• UNDB
• Local Newspapers
• MCA-Nepal Web Page https://mcanp.org/
• MCC Web Page
• U.S. Embassy
• Specialized Publications
GOE Policy
7
Other Key Aspects
1. MCA runs procurements and manages contracts with Procurement Agent support
2. Firms must be eligible for U.S. funding: There is comprehensive verification
process in place
3. 6 to 9 months from solicitation to contract award
4. Evaluation panel composed of technical experts
5. Best value procurement
6. Price evaluated for reasonableness
7. Infrastructure/Construction Projects require an external (non- MCA) project
manager/Engineer
8
Procurement Method
10
Evaluation Process
17
Tips for Winning Contracts
• Fixed Price Contracts. Understand that most MCC contracts are fixed-price contracts, and
the decision is price-sensitive, so put in your best possible price.
• Zero Tolerance to Fraud and Corruption.
• Bidders are encouraged to request information and clarification from the MCA if there is
anything they do not understand, of if they require more information.
• Understand MCA’s Bid Challenge System
18
Other Key Procurement Tips
• Bid Security required– ensure it accompanies the bid with the corresponding bank
enforceable in Nepal.
19
Procurement Schedule
Thanks!!!
Millennium Challenge Account Nepal (MCA-
Nepal)
Outreach Event
Kathmandu
18/11/2019 1
Electricity Transmission Project
Features:
• Project supports to increase in country per capita
electricity consumption
• 3 x 400 kV major substations
18/11/2019 2
Project Location(route map)
KTM-GALCHI-RATMATE
S/S : 62km
KTM-MUGLING-NEW
DAMAULI S/S : 153km
KTM-NARAYANGHAT-
NEW BUTWAL S/S : 239km
18/11/2019 3
Substation Details-Ratmate S/S
Parameter
Location Nuwakot District
Coordinate 27°51'3.89"N, 85° 3'11.79"E
Type GIS
Nominal Voltage 400 kV and 220 kV
Bus Configuration Breaker and half
Capacity 1,000 MVA
18/11/2019 4
Substation Details-New Damauli S/S
Parameter
Location Tanahu District
Coordinate 27°58'3.57"N, 84°17'41.25"E
Type GIS
Nominal Voltage 400 kV
Bus Configuration Breaker and half configuration
Capacity 1,000 MVA
18/11/2019 5
Substation Details-New Butwal S/S
Parameter
Location Nawalparasi-West District
Coordinate 27°34'25.63"N, 83°41'19.44"E
Type GIS
Nominal Voltage 400 kV
Bus Configuration Breaker and half configuration
Capacity 630 MVA
18/11/2019 6
Substation Works Key Features
Substations
• 400 kV GIS Substation
• 3.5 years construction period
• Design-Build (FIDIC Yellow Book)
• Expected date of bid launch: Jan 2020
• Quality-Price Based Selection
• Expected contract signing date: Oct 2020
18/11/2019 7
Project preparation and construction supervision
18/11/2019 8
Resettlement and Land Acquisition
18/11/2019 9
Project Status
18/11/2019 10
Project Status contd…
• Land acquisition status for other two substations(Only some interface activities)
• New Hetauda Substation: Land acquisition and compensation related issues resolved
• Lapsiphedi Substation: Land acquisition and compensation related issues resolved
• Geotechnical investigation works at S/S locations mostly completed
• Draft EIA document in advanced stage of preparation
• Tender level Engineering Design/Drawing/Tech.Specs nearly complete
18/11/2019 11
Challenges
2020 21 22 23 24 25
Activities
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jun
Bid Release (in web & Newspaper)
Site visit
Pre-bid meeting
Bid Submission
Technical Bid opening
Financial Bid Opening
Award of contract
Construction Period
18/11/2019 13
Possible adverse E&S impacts of substation construction
• Public and/or private land needs to be acquired for Substation and access roads.
• Pollution (Air, Water, Fuel, Lubricating Oil and Noise)
• SF6 Gas Leakage possibility
• Pressure on community resources (e.g. existing roads, water, trees etc)
• Trafficking in person.
18/11/2019 14
MCAN/MCC Policies
• Follow GoN rules and regulations including Land Acquisition Act, Environment Protection Act,
and Regulations, Forest Acts.
• Follow MCC Gender Policy and Social and Gender Integration Guidelines.
• Follow avoid(settlements, cultural heritages, schools, health posts etc), minimize(land requirement
by using GIS technology etc.) and mitigate(using good condition silent DG sets, water sprinkler
etc) hierarchy.
18/11/2019 15
Additional Employer’s Requirements
18/11/2019 16
Future Outreach Event
18/11/2019 17
For more information
18/11/2019 18
Thank you
18/11/2019 19
Power Sector Technical Assistance Activity
Outreach Event
1
Nepal Compact Highlights
• MCC and the Government of Nepal entered into a Compact to help facilitate
poverty reduction through economic growth in the amount of $500 million USD.
• The Millennium Challenge Account-Nepal (MCA-Nepal) has been established as
the legal and accountable entity in Nepal.
• As such, MCA-Nepal is responsible for implementation of the Compact.
• MCA-Nepal will procure all goods, works, and services funded under the
Compact using the MCC Program Procurement Guidelines, and will enter into
contracts and administer all such contracts.
• All program disbursements must be made within five years of entry- into-force
(EIF) of the Compact, which is scheduled for June 2020. (July 2020 to June end
2025)
19-Nov-19 Reducing Poverty Through Growth 2
Electricity Transmission Project
Components of ETP:
• Transmission Line Activity
• Substation Activity
• Power Sector Technical Assistance Activity
• Program Management and Technical Oversight Activity
Overview of ETP
Outcomes:
•Add 3,920 MW Tx capacity; reduce losses to
1.9%
•Support 3x increase in electricity consumption
per capita Approx. 312 km – 400 kV Tx lines
(~850 towers)
3 x 400 kV substations
4
Guiding Key Documents
The Parties will perform their responsibilities under this Agreement in accordance
with the following documents, as amended from time to time (collectively, the “Key
Documents”):
5
MCC Directives
6
Power Sector Technical Assistance Activity
Description of the Project
8
Status of TA Activities to NEA
Spatial load forecast, Sub-transmission expansion plan and system protection coordination study
is ongoing
9
Technical Assistance to ERC/NEA
10
Implementation Framework For ERC TA
Note: Study is still ongoing and presented activities are based on the draft phase
of the study. Activities may change / modify in the final phase of the Study.
11
Support to ERC/NEA
Overall Logic of MCA’s Technical Assistance to ERC
12
Foundation Phase Support Activities
15
Foundation Phase Support Activities
• Management Function
• Assist in developing a system for evaluating employee performance; develop
performance indicators; train supervising employees on employee performance
evaluations.
• Formalize “3-tier” decision-making process; designate advisory staff and assist in
their development.
• Supervise/manage staff of combined interim and permanent employees; advise the
Commission Secretary.
• Advisory Function
• Senior MCA Consultant develops and manages team of advisors to fulfill the
second tier of the decision-making process.
16
Advance Phase Support Activities
17
Advance Phase Support Activities
• Additional Infrastructure
• Provision of office automation system (IT-based workstations) in new offices, including
software/hardware/server and other necessary office logistics.
• Pickup van and vehicles for ERC members and staff.
• E-Court and E-Hearings capability.
• Management Functions
• Support and assist the develop permanent management staff, including
preparation of Terms of Reference and Position Descriptions for use in
recruitment.
• Advise Members on legislative proposals
• Training on E-court and E-hearing system.
19
Overall Logic of MCC’s Technical Assistance
to NEA
20
Technical Assistance Activities for NEA
Technical Assistance
Illustrative Activities
Category
⇒ Work with NEA management to design a regulatory compliance unit.
⇒ Create job descriptions and/or terms of reference for personnel in the regulatory unit.
⇒ Recruit or supply regulatory specialists to staff regulatory unit
Regulatory Readiness ⇒ Support consultant to train and advise regulatory unit staff.
⇒ Establish liaison to engage with ERC members and staff.
Technical Assistance
Illustrative Activities
Category
⇒ Fund consultant to produce or assist in producing TOU/Seasonal
Rate design studies.
⇒ Fund possible international visits to utilities for consultation.
Technical Assistance
Illustrative Activities
Category
23
Key Investments: Regulatory Support
Procure Launch
Activity Description
(Expected)
Embedded Regulatory • Up to 4 embedded technical and mgmt. advisors at ERC Early-2020
Advisors • Capacity building, analysis, guidance & mentoring
Tariff Study • Developing tariff methodology & guidelines Early/mid-2020
• Assessment of subsidies & affordability
Regulatory Info & Docket • Development of requirements/specs & scoping Mid-2020
Mgmt. Systems • Supply & installation of RIMS & DMS w/training Early/Mid-2021
Technical Code • Development of updated Grid Code, planning code Early-2021
Development Support • Training & consultations
Social Equity Integration & • Study/analysis of key issues on social equity in electricity TBD
Consultation sector & integration in regulatory requirements
• Training on stakeholder engagement & social equity issues
Miscellaneous logistical • Basic hardware/software & other operational requirements TBD
support
24
Technical Assistance to NEA
25
NEA Challenges
26
Areas of Activities
Note: Study is still ongoing and presented activities are based on the draft phase
of the study. Activities may change / modify in the final phase of the Study
27
Business Operations Overviews- Asset Management
Business Process
Establishing performance measures and management
Adopting the industry standard Asset Management Model
28
Network Planning
29
System Operation
Activities are:
• Consolidating project management function for
• Transmission line projects
• Substation projects
• Improving staff technical skills in
• design requirements and engineering of construction projects
• project management, contract & procurement management
• Establishing centralized project data and drawings management
system
32
Environment & Social Impact Management
Activities are:
• Improvement of Social and Environmental Policies and Legal Framework
• Environmental and Social Polices and Program
• Corporate Social Responsibility Program
• Project Communication Plan
• Optimization of ESSD structure and role within NEA
• Revision of the ESSD structure and effective
• Establishment of a ESSD mission and system for interaction with other departments
• Improvement of the ESSD team and performance (personnel and equipment)
• Development of methods and tools for ESIA and monitoring of transmission lines
• Development and implementation of a training program
• Development and implementation of a knowledge management system
• Development and implementation of a simplified mechanism to acquire external consulting
services
• Upgrade and modernization of equipment used for data collection and study reports 33
Support Activities : Finance
Need Recommendation
Implementation of Fully Integrated ERP Identify and support in areas where additional resources and
System capacity could be supplement the ongoing ERP implementation
process
Compliance with Accounting Standards Identify and support in areas where resources and capacity could
be provided in compliance with Accounting Standards
Budget Management and Financial Review and improve financial forecasting, resource planning and
Forecasting budget management processes with capacity building and
systems
Investment Analysis, Capital Budgeting Organization-wide review; Development of Policies and
and Funding Procedures; Implementation of streamlined and up-to-date
techniques
Implementation of Cost-Reflective and Provide additional resources and capacity in ongoing tariff
Regulated Tariffs scheme changes and interface with the Regulator
34
Key Investments: Transmission Business Strengthening
Procure Launch
Activity Description
(Expected)
Asset Management Model • Utility experts for analysis, process review & update, capacity Early-2020
Advisor building to introduce asset mgmt. model
Asset Management Info • Software/info system to support asset mgmt. model at NEA Mid-2020
System • Scoping & requirements/specs; supply & install
Training & equipment to • Network development including design standards/technology, Mid/Late-2020
support Utility environmental/social assessment & monitoring, project &
Operational Activities contract management
• Asset maintenance including condition assessment,
monitoring, live-line maintenance,
System Planning support • Software upgrades & training TBD
• Process strengthening & capacity building
System Operations • Protection & control coordination updates TBD
• Substation automation strengthening
• Analysis & updates to scheduling, dispatching, settlement 35
Thank You
36