Professional Documents
Culture Documents
Transormer Protection
Transormer Protection
(NEC 450.3)
Introduction
Overcurrent protection of transformers >600V
(NEC450.3A)
1. Unsupervised location of transformer
(impedance <6%)
2. Unsupervised location of transformer
(impedance 6% to 10%)
3. Supervised location (in primary side
only) of transformer
4. Supervised location of transformer
(impedance up to 6%)
5. Supervised location of transformer
(impedance 6% to 10%)
6. Difference in C.B between supervised &
unsupervised Location
7. Sumary of overcurrent protection for
more than 600V
Overcurrent Protection of Transformers <600V
(NEC 450.3B)
1. Only primary side protection of
transformer
2. Primary and secondary side protection
of transformer
3. Summary of overcurrent protection for
less than 600V
Introduction
The overcurrent protection required for
transformers is consider for Protection of
Transformer only. Such overcurrent protection will
not necessarily protect the primary or secondary
conductors or equipment connected on the
secondary side of the transformer.
When voltage is switched on to energize a
transformer, the transformer core normally
saturates.
This results in a large inrush current which is
greatest during the first half cycle (approximately
0.01 second) and becomes progressively less
severe over the next several cycles (approximately
1 second) until the transformer reaches its normal
magnetizing current. To accommodate this inrush
current, fuses are often selected which have time-
current withstand values of at least 12 times
transformer primary rated current for 0.1 second
and 25 times for 0.01 second. Some small dry-
type transformers may have substantially greater
inrush currents.
To avoid using over sized conductors, overcurrent
devices should be selected at about 110 to 125
percent of the transformer full-load current rating.
And when using such smaller overcurrent
protection, devices should be of the time-delay
type (on the primary side) to compensate for
inrush currents which reach 8 to 10 times the full-
load primary current of the transformer for about
0.1 s when energized initially.
Protection of secondary conductors has to be
provided completely separately from any
primary-side protection.
A supervised location is a location where conditions
of maintenance and supervision ensure that only
qualified persons will monitor and service the
transformer installation. Overcurrent protection for
a transformer on the primary side is typically a
circuit breaker. In some instances where there is
not a high voltage panel, there is a fused
disconnect instead.
It is important to note that the overcurrent
device on the primary side must be sized
based on the transformer KVA rating and not
sized based on the secondary load to the
transformer.