Tender Name: HOTEL AND BRANDED APARTMENTS

Consolidated Tender Queries


Updated : 26/Jul/20

Contractor's
Query No. Tenderer's Query Consultants Response Discipline Client Response
Query Date

The ceiling finish in Finishes Schedule for WF Pump Room HL00 – 015 is C-011 but in Reflected
160 7/2/2020 Please follow C011 for the ceiling finish Arch As per consultants response
Ceiling plan it is C-004.

The ceiling finish in Finishes Schedule for Shisha Prep. HL00 – 016 is C-005 but in Reflected Ceiling
161 7/2/2020 Please follow C005 for the ceiling finish Arch As per consultants response
plan it is C-004.

The ceiling finish in Finishes Schedule for Store HL00 – 022 is C-002 but in Reflected Ceiling plan it
162 7/2/2020 Please follow C002 for the ceiling finish Arch As per consultants response
is C-001.

The floor finish in Finishes Schedule for Beverage HL00 - 046 is F-0010 but in floor finish drawing it
163 7/2/2020 Please follow F-017 for the floor finish Arch As per consultants response
is F-015.

The ceiling finish in Finishes Schedule for House Keeping HL001 – 005 is C-002 but in Reflected
164 7/2/2020 Please follow C002 for the ceiling finish Arch As per consultants response
Ceiling plan it is C-001.

The ceiling finish in Finishes Schedule for Furniture Store HL006 – 006 is C-002 but in Reflected
165 7/2/2020 Please follow C002 for the ceiling finish Arch As per consultants response
Ceiling plan it is C-001.

The ceiling finish in Finishes Schedule for Shisha Prep. HL006 – 007 is C-005 but in Reflected
166 7/2/2020 Please follow C005 for the ceiling finish Arch As per consultants response
Ceiling plan it is C-001.

The floor finish in Finishes Schedule for MEP Plant Room HL06 - 015 is F-001 but in floor finish
167 7/2/2020 Please follow F-002 for the floor finish Arch As per consultants response
drawing it is F-002.

168 MEP 7/2/2020 Please see the repsonses noted below: As per consultants response

Active components for ICT and Audio-Visual Systems shall be included as part of Contract scope. Refer design layouts and
specification sections 271100,272000,273100,274200 for details.
Audio Visual System Should be part of Contractor scope.
Kindly confirm all the Active components for the IT/ICT, GSM, WiFi and IP Telephony shall be Active components for GSM systems shall be covered as part Lead Mobile Providers scope .However passive backbones
169 7/2/2020 MEP
carried out by Service providers. and terminations, system racks, power distribution units and cable pathways shall be covered as part of Contract scope.
Refer design layouts for details. CNS (ICT/Wifi/IP Telephony) should be Under Provisional Sum.

Converged Network System shall be included as part of Contract scope.

Please confirm whether that the Converged Network System for Hotel & Branded apartment are For specification sections refer response identified under query 169
170 7/2/2020 MEP CNS (ICT/Wifi/IP Telephony) should be Under Provisional Sum.
under Provisional Sum or not.
Not part of provisional sum - under measured works

There shall be no dedicated GRMS system for the project .Guest Room Management for the project shall form part of BMS
system and to be included as part of Contract scope.

IP Telephony system shall be included as part Contract scope. For specification sections refer response identified under
We presume that Guest room management system, IP TV system, IP Telephony system including
171 7/2/2020 query 169 MEP CNS (ICT/Wifi/ IP Telephony) should be Under Provisional Sum.
PABX, Guest room door access control system are under Provisional Sum. Please confirm.
IPTV system for Hotel Zone is not part of this Contract scope.

Not part of provisional sum - under measured works


As per Provisional Sum BOQ ,Bill No.22, Page No.G211, Item 1- Guest room and FOH ID finishes Light fittings, wiring accessories are not part of provisional sum, standard air outlets are part of MEP scope, any decorative
172 are under Provisional Sums, kindly clarify this provisional sum includes MEP services such as light 7/2/2020 air outlet coverings shall be part of provisional sum Commercial As per consultants response
fittings, wiring accessories, air outlets, etc…

See attached Specifcation Documentatation - TD-DCB Hotel Plot F.G Rev.1_20200330


173 Please provide us specifications for soft landscaping. 7/2/2020 Landscape as per consultant's response
Refer also to Plant Schedule 320-LA-SS-PL-10000
Materials selected by designer for Contractor to seek market supply but refer to the following for reference standard
- Mirage Lever for Tiles
174 Provide a list of approved manufacturers/suppliers for the hard landscaping materials. 7/2/2020 Landscape as per consultant's response
- Consent / Transgulf for Concrete products
- Stones & Slates for Natural Stone
With reference to item code HS-01-D stepping stone on the hardscape finishes schedule drawing no.
175 320-LA-HS-HD-10000, please clarify what is the material type required and provide a detailed 7/2/2020 Refer to layout 320-LA-HS-HD-10102-PDF for shower step. Single porcelaine unit for access to shower base. Landscape as per consultant's response
drawing for it.
With reference to item code SE-01-A steel/aluminum edging on the landscape details finishes
schedule drawing no. 320-LA-LD-HD-03000, please clarify whether it is steel or aluminum edging
176 7/2/2020 Aluminium material edging product - follow SE01 - A dimensions. Landscape as per consultant's response
material and what is the correct size required as it is shown differently on detail drawing 320-LA-LD-
HP-03303.
Please provide door schedule for the FOH areas for Apartments building, since the provided one is
177 7/2/2020 Please refer to drawing 17200-AA-BA-20-501 (copy attached for reference) Arch as per consultant's response
for BOH areas only.
In the VT specifications provided, all the lift finishes are mentioned as “ Premium design from
178 manufacturer catalogue” and the tender query QA no 10 mentions ID for the lift finish shall be part of 7/2/2020 This is part of provisional sum for the Hotel Commercial as per consultant's response
provisional sum. Please confirm that the finishes to lift cabin shall be part of PS.

Elevator Contractor to provide separate price for EMS. Final requirement subject to approval by Client / Operator. This is
179 Please confirm that there is no requirement of elevator monitoring system (EMS). 7/2/2020 detailed in Section 1.13 of VT Specifications (Section 142100) - Lift monitoring system is required and to be included as VT as per consultant's response
part of contractor scope of works as per VT specificaiton. Also it needs to be in security control room

As per tender query QA 7 VT drawings and specifications for the apartment building have been
180 issued along with tender documents and also it is mentioned in the tender query “attached”, we did 7/2/2020 Please find attached the VT specifications for reference Arch as per consultant's response
not receive the same, please send us.
Please provide us the details and location for EIFS system as measured in Hotel and Branded
181 7/2/2020 The EIFS refers to interanl podium level walls between AC and Non-AC areas. Arch as per consultant's response
Apartments BOQ page G24 item 36 and page F26 item 37 respectively.

TENDER QUERY TRACKER CONFIDENTIAL 8 of 21