Note:Calender 6 days workweek(Friday off) ,7 days of Moonsoon considered as exceptions

Activity ID Activity Name Original Start Finish 2023 2024


Duration
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
445 28-Jan-23 21-Jul-24 21-Jul-24, IDAP-1 Infrastructure DevelopmentAuthority of the
IDAP-1 Infrastructure Development Authority of the Punjab
445 28-Jan-23 21-Jul-24 21-Jul-24, IDAP-1.1 Category A - Doctors Apartments
IDAP-1.1 Category A - Doctors Apartments
IDAP-1.1.1 Project Milestones 445 28-Jan-23 21-Jul-24 21-Jul-24, IDAP-1.1.1 Project Milestones
A2010 Project Start 0 28-Jan-23 Project Start, 28-Jan-23
A2020 Project Finish 0 21-Jul-24 Project Finish,

IDAP-1.1.2 Pre-Construction Phase 180 28-Jan-23 07-Sep-23 07-Sep-23, IDAP-1.1.2 Pre-Construction Phase
A2040 Mobilization at Site 10 28-Jan-23 07-Feb-23 Mobilization at Site
A2030 Submittals Submission & Approval 150 04-Mar-23 07-Sep-23 Submittals Submission & Approval
IDAP-1.1.3 Civil Works 426 09-Feb-23 11-Jul-24 11-Jul-24, IDAP-1.1.3 Civil Works
A1000 Jungle clearance 2 09-Feb-23 11-Feb-23 Jungle clearance
A2050 Layout for Excavation 1 12-Feb-23 12-Feb-23 Layout for Excavation
A1010 Excavation,Engineering Fill,compaction in foundation 25 13-Feb-23 13-Mar-23 Excavation,Engineering Fill,compaction in foundation
A1020 Spraying Anti Termite 1 14-Mar-23 14-Mar-23 Spraying Anti Termite
A1030 PCC 1:4:8 in foundation 2 15-Mar-23 16-Mar-23 PCC 1:4:8 in foundation
A2060 Layout for footings 1 18-Mar-23 18-Mar-23 Layout for footings
A1040 Form Work & Reinforcement for Foundation 20 19-Mar-23 10-Apr-23 Form Work & Reinforcement for Foundation
A1050 Concrete Pouring for Foundation 6 08-Apr-23 13-Apr-23 Concrete Pouring for Foundation
A1060 Formwork & Reinforcement in Neck Column 10 15-Apr-23 29-Apr-23 Formwork & Reinforcement in Neck Column
A1090 Formwork & Reinforcement for Plinth Beam 15 25-Apr-23 11-May-23 Formwork & Reinforcement for Plinth Beam
A1070 Concrete Pouring for Neck Column 3 27-Apr-23 30-Apr-23 Concrete Pouring for Neck Column
A1100 Concrete Poring for Plinth Beam 2 13-May-23 14-May-23 Concrete Poring for Plinth Beam
A1080 Brick/Block Work in Foundation 10 15-May-23 25-May-23 Brick/Block Work in Foundation
A1110 Damp Proof Coarse 4 15-May-23 18-May-23 Damp Proof Coarse
A1120 Back filling in Foundation 7 20-May-23 27-May-23 Back filling in Foundation
A1130 Back Fill above NSL 4 28-May-23 31-May-23 Back Fill above NSL
A1140 Providing &Laying Watering & ramming Brick Ballast 5 01-Jun-23 06-Jun-23 Providing &Laying Watering & ramming Brick Ballast
A1180 Formwork & Reinforcement for Columns Ground Floor 15 01-Jun-23 18-Jun-23 Formwork & Reinforcement for Columns Ground Floor
A1190 Concrete Poring for Column 3 19-Jun-23 21-Jun-23 Concrete Poring for Column
A1230 Formwork & Reinforcement for Beams & Slab Ground Floor 26 22-Jun-23 01-Aug-23 Formwork & Reinforcement for Beams & Slab Ground Floor
A1240 Formwork & Reinforcement for Stairs Ground Floor 4 22-Jul-23 01-Aug-23 Formwork & Reinforcement for Stairs Ground Floor
A1250 Concrete Poring for Beams , Slab & Stairs Ground Floor 2 02-Aug-23 03-Aug-23 Concrete Poring for Beams , Slab & Stairs Ground Floor
A1150 Sand Filling under Floor 4 24-Aug-23 28-Aug-23 Sand Filling under Floor
A1300 Formwork & Reinforcement for Column First Floor 15 24-Aug-23 10-Sep-23 Formwork & Reinforcement for Column First Floor
A1160 PCC( 1:4:8) under Floor 4 29-Aug-23 02-Sep-23 PCC( 1:4:8) under Floor
A1200 Brick/Block Work in Ground Floor 40 29-Aug-23 14-Oct-23 Brick/Block Work in Ground Floor
A1310 Concrete Poring For Column First Floor 3 11-Sep-23 13-Sep-23 Concrete Poring For Column First Floor
A1350 Formwork & Reinforcement for Beams & Slab First Floor 26 14-Sep-23 14-Oct-23 Formwork & Reinforcement for Beams & Slab First Floor
A1210 Formwork & Reinforcement for Lintel Beam Ground Floor 20 21-Sep-23 14-Oct-23 Formwork & Reinforcement for Lintel Beam Ground Floor
A1360 Formwork & Reinforcement for Stairs First Floor 4 10-Oct-23 14-Oct-23 Formwork & Reinforcement for Stairs First Floor
A1220 Concrete Poring for Lintels Ground Floor 4 15-Oct-23 18-Oct-23 Concrete Poring for Lintels Ground Floor
A1260 Plaster Internal Ground Floor 20 15-Oct-23 06-Nov-23 Plaster Internal Ground Floor
A1370 Concrete Poring for Beams , Slab & Stairs First Floor 2 15-Oct-23 16-Oct-23 Concrete Poring for Beams , Slab & Stairs First Floor
A1420 Formwork & Reinforcement for Column Second Floor 13 17-Oct-23 31-Oct-23 Formwork & Reinforcement for Column Second Floor
A1430 Concrete Poring For Column Second Floor 3 01-Nov-23 04-Nov-23 Concrete Poring For Column Second Floor
A1170 PCC( 1:2:4) under Floor 4 02-Nov-23 07-Nov-23 PCC( 1:2:4) under Floor
A1470 Formwork & Reinforcement for Beams & Slab Second Floor 26 05-Nov-23 04-Dec-23 Formwork & Reinforcement for Beams & Slab Second Floor
A1280 Mosaic, Chips Flooring , Marble on sills,Vanities,Shelves and Porcelain Tiles Ground Floor 30 07-Nov-23 11-Dec-23 Mosaic, Chips Flooring , Marble on sills,Vanities,Shelves and Porcelain Tiles Ground Floor
A1320 Brick/Block Work in First Floor 40 11-Nov-23 26-Dec-23 Brick/Block Work in First Floor
A1290 Wood Work Ground Floor complete 30 30-Nov-23 03-Jan-24 Wood Work Ground Floor complete
A1480 Formwork & Reinforcement for Stairs Second Floor 4 30-Nov-23 04-Dec-23 Formwork & Reinforcement for Stairs Second Floor

Actual Level of Effort Actual Work Critical Remaining Work summary


Primary Baseline Remaining Work Milestone
Note:Calender 6 days workweek(Friday off) ,7 days of Moonsoon considered as exceptions
Activity ID Activity Name Original Start Finish 2023 2024
Duration
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
A1330 Formwork & Reinforcement for Lintel Beam First Floor 20 04-Dec-23 26-Dec-23 Formwork & Reinforcement for Lintel Beam First Floor
A1490 Concrete Poring for Beams , Slab & Stairs Second Floor 2 05-Dec-23 06-Dec-23 Concrete Poring for Beams , Slab & Stairs Second Floor
A1680 Paint & Varnishing internal Ground Floor 20 12-Dec-23 03-Jan-24 Paint & Varnishing internal Ground Floor
A1600 Formwork & Reinforcement for Column Third Floor 10 24-Dec-23 03-Jan-24 Formwork & Reinforcement for Column Third Floor
A1340 Concrete Poring for Lintels First Floor 4 27-Dec-23 31-Dec-23 Concrete Poring for Lintels First Floor
A1380 Plaster Internal First Floor 20 27-Dec-23 18-Jan-24 Plaster Internal First Floor
A1440 Brick/Block Work in Second Floor 40 01-Jan-24 15-Feb-24 Brick/Block Work in Second Floor
A1750 Concrete Pouring for Column Third Floor 3 04-Jan-24 07-Jan-24 Concrete Pouring for Column Third Floor
A1760 Formwork & Reinforcement for Third Floor slab & Beams 26 08-Jan-24 06-Feb-24 Formwork & Reinforcement for Third Floor slab & Beams
A1400 Mosaic, Chips Flooring , Marble on sills,Vanities,Shelves and Porcelain Tiles First Floor 30 20-Jan-24 22-Feb-24 Mosaic, Chips Flooring , Marble on sills,Vanities,Shelves and Porcelain Tiles First Floor
A1450 Formwork & Reinforcement for Lintel Beam Second Floor 20 24-Jan-24 15-Feb-24 Formwork & Reinforcement for Lintel Beam Second Floor
A6290 Concrete Pouring of Third Floor Slab 1 07-Feb-24 07-Feb-24 Concrete Pouring of Third Floor Slab
A1460 Concrete Poring for Lintels Second Floor 4 17-Feb-24 20-Feb-24 Concrete Poring for Lintels Second Floor
A1500 Plaster Internal Second Floor 20 17-Feb-24 10-Mar-24 Plaster Internal Second Floor
A6310 Reinforcement Formwork & Pouring of Lintel Beams Third Floor 20 19-Feb-24 13-Mar-24 Reinforcement Formwork & Pouring of Lintel Beams Third Floor
A1410 Wood Work First Floor complete 30 24-Feb-24 28-Mar-24 Wood Work First Floor complete
A1660 Formwork & Reinforcement for OWT 7 24-Feb-24 02-Mar-24 Formwork & Reinforcement for OWT
A1690 Paint & Varnishing internal First Floor 20 24-Feb-24 17-Mar-24 Paint & Varnishing internal First Floor
A1540 Formwork & Reinforcement for Column Mumty 4 24-Feb-24 28-Feb-24 Formwork & Reinforcement for Column Mumty
A6300 Brick/Block work Third Floor 16 24-Feb-24 13-Mar-24 Brick/Block work Third Floor
A1550 Concrete Poring For Column Mumty 1 28-Feb-24 29-Feb-24 Concrete Poring For Column Mumty
A1590 Formwork & Reinforcement for Beams & Slab Mumty 10 29-Feb-24 12-Mar-24 Formwork & Reinforcement for Beams & Slab Mumty
A1670 Concrete Pouring for OWT 1 03-Mar-24 03-Mar-24 Concrete Pouring for OWT
A1560 Block Work in Mumty 7 12-Mar-24 20-Mar-24 Block Work in Mumty
A1610 Concrete Poring for Beams & Slab of Mumty 1 12-Mar-24 13-Mar-24 Concrete Poring for Beams & Slab of Mumty
A1510 Plaster External complete 25 13-Mar-24 15-Apr-24 Plaster External complete
A6320 Plaster Internal Third Floor 16 13-Mar-24 01-Apr-24 Plaster Internal Third Floor
A1570 Formwork &Reinforcement for Lintel Beam Mumty 4 20-Mar-24 25-Mar-24 Formwork &Reinforcement for Lintel Beam Mumty
A1580 Concrete Poring for Lintels Mumty 1 25-Mar-24 26-Mar-24 Concrete Poring for Lintels Mumty
A1620 Plaster Internal Mumty 4 30-Mar-24 03-Apr-24 Plaster Internal Mumty
A1530 Wood Work Second Floor complete 30 03-Apr-24 11-May-24 Wood Work Second Floor complete
A1630 Plaster External Mumty 2 03-Apr-24 06-Apr-24 Plaster External Mumty
A6340 Mosaic, Chips Flooring , Marble on sills,Vanities,Shelves and Porcelain Tiles third Floor 16 04-Apr-24 27-Apr-24 Mosaic, Chips Flooring , Marble on sills,Vanities,Shelves and Porcelain Tiles third Flo
A1640 Flooring Mumty 2 06-Apr-24 08-Apr-24 Flooring Mumty
A1650 Roof Treatment 10 08-Apr-24 23-Apr-24 Roof Treatment
A6330 Paint & Varnishing Internal Third Floor 12 13-Apr-24 27-Apr-24 Paint & Varnishing Internal Third Floor
A1520 Mosaic, Chips Flooring , Marble on sills,Vanities,Shelves and Porcelain Tiles Second Floor 30 15-Apr-24 20-May-24 Mosaic, Chips Flooring , Marble on sills,Vanities,Shelves and Porcelain Tiles S
A1700 Paint & Varnishing internal Second Floor 20 18-Apr-24 11-May-24 Paint & Varnishing internal Second Floor
A1720 Paint External 30 09-May-24 13-Jun-24 Paint External
A1770 Face Cladding 30 09-May-24 13-Jun-24 Face Cladding
A1730 Aluminium & Iron Works complete 40 12-May-24 01-Jul-24 Aluminium & Iron Works complete
A1710 Paint & Varnishing internal Mumty 4 12-May-24 16-May-24 Paint & Varnishing internal Mumty
A1780 Providing & Laying Tuff Pavers External 30 02-Jun-24 11-Jul-24 Providing & Laying Tuff Pavers External
A1740 False Ceiling 20 04-Jun-24 01-Jul-24 False Ceiling
A1790 Ramp & Outer Entrance Stairs 20 13-Jun-24 11-Jul-24 Ramp & Outer Entrance Stairs
IDAP-1.1.4 Plumbing Works 159 01-Jan-24 11-Jul-24 11-Jul-24, IDAP-1.1.4 Plumbing Works
A1800 Water Supply Piping PPR 60 01-Jan-24 10-Mar-24 Water Supply Piping PPR
A1810 Sewrage Piping u-PVC 45 18-Jan-24 10-Mar-24 Sewrage Piping u-PVC
A1980 GI Pipes 20 17-Feb-24 10-Mar-24 GI Pipes
A1970 Khuras on roof 5 23-Apr-24 29-Apr-24 Khuras on roof
A1820 Floor Drains 15 02-May-24 20-May-24 Floor Drains

Actual Level of Effort Actual Work Critical Remaining Work summary


Primary Baseline Remaining Work Milestone
Note:Calender 6 days workweek(Friday off) ,7 days of Moonsoon considered as exceptions
Activity ID Activity Name Original Start Finish 2023 2024
Duration
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
A1830 Plumbing Fixtures & Accessories 30 20-May-24 29-Jun-24 Plumbing Fixtures & Accessories
A1840 Manhole 30 02-Jun-24 11-Jul-24 Manhole
IDAP-1.1.5 Electrical works 319 22-Jun-23 16-Jul-24 16-Jul-24, IDAP-1.1.5 Electrical works
A1850 Conduits & Pipes for all electrical works 185 22-Jun-23 03-Feb-24 Conduits & Pipes for all electrical works
A1860 Wiring Cables for all electrical works 100 07-Nov-23 02-Mar-24 Wiring Cables for all electrical works
A1870 Cable Tray & Ladder 100 07-Nov-23 02-Mar-24 Cable Tray & Ladder
A1880 Wiring Accessories 20 03-Mar-24 25-Mar-24 Wiring Accessories
A1960 Fire Alarm System 30 03-Mar-24 06-Apr-24 Fire Alarm System
A1920 LV Power Cables 20 26-Mar-24 21-Apr-24 LV Power Cables
A1890 Energy Electric Meter 4 22-Apr-24 25-Apr-24 Energy Electric Meter
A1930 LV Distribution Board 20 22-Apr-24 14-May-24 LV Distribution Board
A1900 Earthing System 20 27-Apr-24 19-May-24 Earthing System
A1910 Fans 20 12-May-24 03-Jun-24 Fans
A1940 Switches,Light & other Electrical Fixtures 30 12-May-24 15-Jun-24 Switches,Light & other Electrical Fixtures
A1990 UPS System 20 16-May-24 09-Jun-24 UPS System
A1995 Fire Fighting System 10 28-May-24 09-Jun-24 Fire Fighting System
A1950 Lightning Protection System 20 13-Jun-24 11-Jul-24 Lightning Protection System
A2000 Testing & Commissioning 4 11-Jul-24 16-Jul-24 Testing & Commissioning
IDAP-1.1.6 Handing/Taking Over 7 13-Jul-24 21-Jul-24 21-Jul-24, IDAP-1.1.6 Handing/Taking Over
A2070 Punch List Rectification 6 13-Jul-24 20-Jul-24 Punch List Rectification
A2080 Handing/Taking Over 1 20-Jul-24 21-Jul-24 Handing/Taking Over
444 28-Jan-23 20-Jul-24 20-Jul-24, IDAP-1.2 Category B - Nursing Hostel & Studio Apar
IDAP-1.2 Category B - Nursing Hostel & Studio Apartment
IDAP-1.2.1 Project Milestones 444 28-Jan-23 20-Jul-24 20-Jul-24, IDAP-1.2.1 Project Milestones
A3060 Project Start 0 28-Jan-23 Project Start, 28-Jan-23
A3070 Project Finish 0 20-Jul-24 Project Finish,

IDAP-1.2.2 Pre-Construction Phase 180 28-Jan-23 07-Sep-23 07-Sep-23, IDAP-1.2.2 Pre-Construction Phase
A3090 Mobilization at Site 10 28-Jan-23 07-Feb-23 Mobilization at Site
A3080 Submittals Submission & Approval 150 04-Mar-23 07-Sep-23 Submittals Submission & Approval
IDAP-1.2.3 Civil Works 428 07-Feb-23 11-Jul-24 11-Jul-24, IDAP-1.2.3 Civil Works
A2090 Jungle clearance 2 07-Feb-23 08-Feb-23 Jungle clearance
A3100 Layout for Excavation 1 09-Feb-23 09-Feb-23 Layout for Excavation
A2100 Excavation,Engineering Fill,compaction in foundation 25 11-Feb-23 11-Mar-23 Excavation,Engineering Fill,compaction in foundation
A2110 Spraying Anti Termite 1 12-Mar-23 12-Mar-23 Spraying Anti Termite
A2120 PCC 1:4:8 in foundation 2 13-Mar-23 14-Mar-23 PCC 1:4:8 in foundation
A3110 Layout for footings 1 15-Mar-23 15-Mar-23 Layout for footings
A2130 Form Work & Reinforcement for Foundation 20 16-Mar-23 08-Apr-23 Form Work & Reinforcement for Foundation
A2140 Concrete Pouring for Foundation 5 09-Apr-23 13-Apr-23 Concrete Pouring for Foundation
A2150 Formwork & Reinforcement in Neck Column 10 15-Apr-23 29-Apr-23 Formwork & Reinforcement in Neck Column
A2160 Concrete Pouring for Neck Column 3 30-Apr-23 02-May-23 Concrete Pouring for Neck Column
A2170 Brick/Block Work in Foundation 10 03-May-23 14-May-23 Brick/Block Work in Foundation
A2180 Formwork & Reinforcement for Plinth Beam 15 15-May-23 31-May-23 Formwork & Reinforcement for Plinth Beam
A2190 Concrete Poring for Plinth Beam 2 01-Jun-23 03-Jun-23 Concrete Poring for Plinth Beam
A2200 Damp Proof Coarse 4 04-Jun-23 07-Jun-23 Damp Proof Coarse
A2210 Back filling in Foundation 7 08-Jun-23 15-Jun-23 Back filling in Foundation
A2220 Back Fill above NSL 4 17-Jun-23 20-Jun-23 Back Fill above NSL
A2230 Providing &Laying Watering & ramming Brick Ballast 5 21-Jun-23 26-Jun-23 Providing &Laying Watering & ramming Brick Ballast
A2270 Formwork & Reinforcement for Columns Ground Floor 15 21-Jun-23 11-Jul-23 Formwork & Reinforcement for Columns Ground Floor
A2280 Concrete Poring for Column 3 12-Jul-23 15-Jul-23 Concrete Poring for Column
A2320 Formwork & Reinforcement for Beams & Slab Ground Floor 28 16-Jul-23 23-Aug-23 Formwork & Reinforcement for Beams & Slab Ground Floor
A2330 Formwork & Reinforcement for Stairs Ground Floor 4 20-Aug-23 23-Aug-23 Formwork & Reinforcement for Stairs Ground Floor

Actual Level of Effort Actual Work Critical Remaining Work summary


Primary Baseline Remaining Work Milestone
Note:Calender 6 days workweek(Friday off) ,7 days of Moonsoon considered as exceptions
Activity ID Activity Name Original Start Finish 2023 2024
Duration
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
A2340 Concrete Poring for Beams , Slab & Stairs Ground Floor 2 24-Aug-23 26-Aug-23 Concrete Poring for Beams , Slab & Stairs Ground Floor
A2240 Sand Filling under Floor 4 27-Aug-23 30-Aug-23 Sand Filling under Floor
A2250 PCC( 1:4:8) under Floor 4 31-Aug-23 04-Sep-23 PCC( 1:4:8) under Floor
A2380 Formwork & Reinforcement for Column First Floor 15 16-Sep-23 02-Oct-23 Formwork & Reinforcement for Column First Floor
A2290 Brick/Block Work in Ground Floor 30 20-Sep-23 24-Oct-23 Brick/Block Work in Ground Floor
A2300 Formwork & Reinforcement for Lintel Beam Ground Floor 20 02-Oct-23 24-Oct-23 Formwork & Reinforcement for Lintel Beam Ground Floor
A2390 Concrete Poring For Column First Floor 3 03-Oct-23 05-Oct-23 Concrete Poring For Column First Floor
A2430 Formwork & Reinforcement for Beams & Slab First Floor 28 07-Oct-23 07-Nov-23 Formwork & Reinforcement for Beams & Slab First Floor
A2310 Concrete Poring for Lintels Ground Floor 4 25-Oct-23 29-Oct-23 Concrete Poring for Lintels Ground Floor
A2350 Plaster Internal Ground Floor 20 25-Oct-23 16-Nov-23 Plaster Internal Ground Floor
A2440 Formwork & Reinforcement for Stairs First Floor 4 04-Nov-23 07-Nov-23 Formwork & Reinforcement for Stairs First Floor
A2450 Concrete Poring for Beams , Slab & Stairs First Floor 2 08-Nov-23 09-Nov-23 Concrete Poring for Beams , Slab & Stairs First Floor
A2490 Formwork & Reinforcement for Column Second Floor 15 11-Nov-23 27-Nov-23 Formwork & Reinforcement for Column Second Floor
A2360 Mosaic, Chips Flooring , Marble on sills,Vanities,Shelves and Porcelain Tiles Ground Floor 30 18-Nov-23 21-Dec-23 Mosaic, Chips Flooring , Marble on sills,Vanities,Shelves and Porcelain Tiles Ground Floor
A2500 Concrete Poring For Column Second Floor 3 28-Nov-23 30-Nov-23 Concrete Poring For Column Second Floor
A2540 Formwork & Reinforcement for Beams & Slab Second Floor 28 02-Dec-23 02-Jan-24 Formwork & Reinforcement for Beams & Slab Second Floor
A2400 Brick/Block Work in First Floor 30 05-Dec-23 08-Jan-24 Brick/Block Work in First Floor
A2370 Wood Work Ground Floor complete 30 11-Dec-23 14-Jan-24 Wood Work Ground Floor complete
A2410 Formwork & Reinforcement for Lintel Beam First Floor 20 17-Dec-23 08-Jan-24 Formwork & Reinforcement for Lintel Beam First Floor
A2260 PCC( 1:2:4) under Floor 4 18-Dec-23 21-Dec-23 PCC( 1:2:4) under Floor
A2740 Paint & Varnishing internal Ground Floor 20 23-Dec-23 14-Jan-24 Paint & Varnishing internal Ground Floor
A2550 Formwork & Reinforcement for Stairs Second Floor 4 30-Dec-23 02-Jan-24 Formwork & Reinforcement for Stairs Second Floor
A2560 Concrete Poring for Beams , Slab & Stairs Second Floor 2 03-Jan-24 04-Jan-24 Concrete Poring for Beams , Slab & Stairs Second Floor
A2420 Concrete Poring for Lintels First Floor 4 09-Jan-24 13-Jan-24 Concrete Poring for Lintels First Floor
A2460 Plaster Internal First Floor 20 09-Jan-24 31-Jan-24 Plaster Internal First Floor
A2510 Brick/Block Work in Second Floor 30 30-Jan-24 04-Mar-24 Brick/Block Work in Second Floor
A2610 Formwork & Reinforcement for Column Mumty 4 30-Jan-24 03-Feb-24 Formwork & Reinforcement for Column Mumty
A2720 Formwork & Reinforcement for OWT 7 30-Jan-24 06-Feb-24 Formwork & Reinforcement for OWT
A2470 Mosaic, Chips Flooring , Marble on sills,Vanities,Shelves and Porcelain Tiles First Floor 30 01-Feb-24 06-Mar-24 Mosaic, Chips Flooring , Marble on sills,Vanities,Shelves and Porcelain Tiles First Floor
A2620 Concrete Poring For Column Mumty 1 04-Feb-24 04-Feb-24 Concrete Poring For Column Mumty
A2660 Formwork & Reinforcement for Beams & Slab Mumty 10 05-Feb-24 15-Feb-24 Formwork & Reinforcement for Beams & Slab Mumty
A2730 Concrete Pouring for OWT 1 07-Feb-24 07-Feb-24 Concrete Pouring for OWT
A2520 Formwork & Reinforcement for Lintel Beam Second Floor 20 11-Feb-24 04-Mar-24 Formwork & Reinforcement for Lintel Beam Second Floor
A2630 Block Work in Mumty 7 17-Feb-24 24-Feb-24 Block Work in Mumty
A2670 Concrete Poring for Beams & Slab of Mumty 1 17-Feb-24 17-Feb-24 Concrete Poring for Beams & Slab of Mumty
A2750 Paint & Varnishing internal First Floor 20 17-Feb-24 10-Mar-24 Paint & Varnishing internal First Floor
A2640 Formwork &Reinforcement for Lintel Beam Mumty 4 25-Feb-24 28-Feb-24 Formwork &Reinforcement for Lintel Beam Mumty
A2650 Concrete Poring for Lintels Mumty 1 29-Feb-24 29-Feb-24 Concrete Poring for Lintels Mumty
A2530 Concrete Poring for Lintels Second Floor 4 05-Mar-24 09-Mar-24 Concrete Poring for Lintels Second Floor
A2570 Plaster Internal Second Floor 20 05-Mar-24 27-Mar-24 Plaster Internal Second Floor
A2580 Plaster External complete 25 05-Mar-24 02-Apr-24 Plaster External complete
A2680 Plaster Internal Mumty 4 05-Mar-24 09-Mar-24 Plaster Internal Mumty
A2480 Wood Work First Floor complete 30 07-Mar-24 14-Apr-24 Wood Work First Floor complete
A2690 Plaster External Mumty 2 10-Mar-24 11-Mar-24 Plaster External Mumty
A2700 Flooring Mumty 2 12-Mar-24 13-Mar-24 Flooring Mumty
A2710 Roof Treatment 10 14-Mar-24 25-Mar-24 Roof Treatment
A2590 Mosaic, Chips Flooring , Marble on sills,Vanities,Shelves and Porcelain Tiles Second Floor 30 03-Apr-24 11-May-24 Mosaic, Chips Flooring , Marble on sills,Vanities,Shelves and Porcelain Tiles Sec
A2600 Wood Work Second Floor complete 30 03-Apr-24 11-May-24 Wood Work Second Floor complete
A2780 Paint External 30 03-Apr-24 11-May-24 Paint External
A2760 Paint & Varnishing internal Second Floor 20 17-Apr-24 09-May-24 Paint & Varnishing internal Second Floor
A2770 Paint & Varnishing internal Mumty 4 17-Apr-24 21-Apr-24 Paint & Varnishing internal Mumty

Actual Level of Effort Actual Work Critical Remaining Work summary


Primary Baseline Remaining Work Milestone
Note:Calender 6 days workweek(Friday off) ,7 days of Moonsoon considered as exceptions
Activity ID Activity Name Original Start Finish 2023 2024
Duration
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
A2790 Aluminium & Iron Works complete 40 17-Apr-24 02-Jun-24 Aluminium & Iron Works complete
A2800 False Ceiling 20 11-May-24 02-Jun-24 False Ceiling
A2810 Face Cladding 30 03-Jun-24 11-Jul-24 Face Cladding
A2820 Providing & Laying Tuff Pavers External 30 03-Jun-24 11-Jul-24 Providing & Laying Tuff Pavers External
A2830 Ramp & Outer Entrance Stairs 20 15-Jun-24 11-Jul-24 Ramp & Outer Entrance Stairs
IDAP-1.2.4 Plumbing Works 144 18-Jan-24 11-Jul-24 11-Jul-24, IDAP-1.2.4 Plumbing Works
A2840 Water Supply Piping PPR 60 18-Jan-24 27-Mar-24 Water Supply Piping PPR
A2850 Sewrage Piping u-PVC 45 05-Feb-24 27-Mar-24 Sewrage Piping u-PVC
A3020 GI Pipes 20 05-Mar-24 27-Mar-24 GI Pipes
A3010 Khuras on roof 5 26-Mar-24 31-Mar-24 Khuras on roof
A2860 Floor Drains 15 24-Apr-24 11-May-24 Floor Drains
A2870 Plumbing Fixtures & Accessories 30 12-May-24 15-Jun-24 Plumbing Fixtures & Accessories
A2880 Manhole 30 03-Jun-24 11-Jul-24 Manhole
IDAP-1.2.5 Electrical works 292 16-Jul-23 04-Jul-24 04-Jul-24, IDAP-1.2.5 Electrical works
A2890 Conduits & Pipes for all electrical works 185 16-Jul-23 22-Feb-24 Conduits & Pipes for all electrical works
A2900 Wiring Cables for all electrical works 100 18-Nov-23 12-Mar-24 Wiring Cables for all electrical works
A2910 Cable Tray & Ladder 100 18-Nov-23 12-Mar-24 Cable Tray & Ladder
A2920 Wiring Accessories 20 13-Mar-24 04-Apr-24 Wiring Accessories
A3000 Fire Alarm System 30 13-Mar-24 20-Apr-24 Fire Alarm System
A2960 LV Power Cables 20 06-Apr-24 01-May-24 LV Power Cables
A3030 UPS System 20 22-Apr-24 14-May-24 UPS System
A2930 Energy Electric Meter 4 02-May-24 06-May-24 Energy Electric Meter
A2970 LV Distribution Board 20 02-May-24 25-May-24 LV Distribution Board
A2940 Earthing System 20 07-May-24 29-May-24 Earthing System
A2950 Fans 20 11-May-24 02-Jun-24 Fans
A2990 Lightning Protection System 20 12-May-24 03-Jun-24 Lightning Protection System
A2980 Switches,Light & other Electrical Fixtures 30 22-May-24 30-Jun-24 Switches,Light & other Electrical Fixtures
A3050 Fire Fighting System 10 03-Jun-24 13-Jun-24 Fire Fighting System
A3040 Testing & Commissioning 4 01-Jul-24 04-Jul-24 Testing & Commissioning
IDAP-1.2.6 Handing/Taking Over 7 13-Jul-24 20-Jul-24 20-Jul-24, IDAP-1.2.6 Handing/Taking Over
A3120 Punch List Rectification 6 13-Jul-24 18-Jul-24 Punch List Rectification
A3130 Handing/Taking Over 1 20-Jul-24 20-Jul-24 Handing/Taking Over
444 28-Jan-23 20-Jul-24 20-Jul-24, IDAP-1.3 Category C - 2 Bed Quarters
IDAP-1.3 Category C - 2 Bed Quarters
IDAP-1.3.1 Project Milestones 444 28-Jan-23 20-Jul-24 20-Jul-24, IDAP-1.3.1 Project Milestones
A4110 Project Start 0 28-Jan-23 Project Start, 28-Jan-23
A4120 Project Finish 0 20-Jul-24 Project Finish,

IDAP-1.3.2 Pre-Construction Phase 180 28-Jan-23 07-Sep-23 07-Sep-23, IDAP-1.3.2 Pre-Construction Phase
A4140 Mobilization at Site 10 28-Jan-23 07-Feb-23 Mobilization at Site
A4130 Submittals Submission & Approval 150 04-Mar-23 07-Sep-23 Submittals Submission & Approval
IDAP-1.3.3 Civil Works 421 07-Feb-23 03-Jul-24 03-Jul-24, IDAP-1.3.3 Civil Works
A3140 Jungle clearance 2 07-Feb-23 08-Feb-23 Jungle clearance
A4150 Layout for Excavation 1 09-Feb-23 09-Feb-23 Layout for Excavation
A3150 Excavation,Engineering Fill,compaction in foundation 20 11-Feb-23 05-Mar-23 Excavation,Engineering Fill,compaction in foundation
A3160 Spraying Anti Termite 1 06-Mar-23 06-Mar-23 Spraying Anti Termite
A3170 PCC 1:4:8 in foundation 2 07-Mar-23 08-Mar-23 PCC 1:4:8 in foundation
A4160 Layout for footings 1 15-Mar-23 15-Mar-23 Layout for footings
A3180 Form Work & Reinforcement for Foundation 15 22-Mar-23 08-Apr-23 Form Work & Reinforcement for Foundation
A3190 Concrete Pouring for Foundation 4 09-Apr-23 12-Apr-23 Concrete Pouring for Foundation
A3200 Formwork & Reinforcement in Neck Column 12 19-Apr-23 06-May-23 Formwork & Reinforcement in Neck Column
A3210 Concrete Pouring for Neck Column 2 07-May-23 08-May-23 Concrete Pouring for Neck Column

Actual Level of Effort Actual Work Critical Remaining Work summary


Primary Baseline Remaining Work Milestone
Note:Calender 6 days workweek(Friday off) ,7 days of Moonsoon considered as exceptions
Activity ID Activity Name Original Start Finish 2023 2024
Duration
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
A3220 Brick/Block Work in Foundation 8 09-May-23 17-May-23 Brick/Block Work in Foundation
A3230 Formwork & Reinforcement for Plinth Beam 15 18-May-23 04-Jun-23 Formwork & Reinforcement for Plinth Beam
A3240 Concrete Poring for Plinth Beam 2 05-Jun-23 06-Jun-23 Concrete Poring for Plinth Beam
A3250 Damp Proof Coarse 2 07-Jun-23 08-Jun-23 Damp Proof Coarse
A3260 Back filling in Foundation 5 15-Jun-23 20-Jun-23 Back filling in Foundation
A3270 Back Fill above NSL 4 21-Jun-23 25-Jun-23 Back Fill above NSL
A3280 Providing &Laying Watering & ramming Brick Ballast 5 26-Jun-23 04-Jul-23 Providing &Laying Watering & ramming Brick Ballast
A3320 Formwork & Reinforcement for Columns Ground Floor 13 26-Jun-23 13-Jul-23 Formwork & Reinforcement for Columns Ground Floor
A3330 Concrete Poring for Column 3 15-Jul-23 17-Jul-23 Concrete Poring for Column
A3370 Formwork & Reinforcement for Beams & Slab Ground Floor 22 18-Jul-23 19-Aug-23 Formwork & Reinforcement for Beams & Slab Ground Floor
A3380 Formwork & Reinforcement for Stairs Ground Floor 3 16-Aug-23 19-Aug-23 Formwork & Reinforcement for Stairs Ground Floor
A3390 Concrete Poring for Beams , Slab & Stairs Ground Floor 2 20-Aug-23 21-Aug-23 Concrete Poring for Beams , Slab & Stairs Ground Floor
A3290 Sand Filling under Floor 3 22-Aug-23 24-Aug-23 Sand Filling under Floor
A3300 PCC( 1:4:8) under Floor 3 26-Aug-23 28-Aug-23 PCC( 1:4:8) under Floor
A3340 Brick/Block Work in Ground Floor 30 16-Sep-23 19-Oct-23 Brick/Block Work in Ground Floor
A3430 Formwork & Reinforcement for Column First Floor 11 16-Sep-23 27-Sep-23 Formwork & Reinforcement for Column First Floor
A3350 Formwork & Reinforcement for Lintel Beam Ground Floor 20 27-Sep-23 19-Oct-23 Formwork & Reinforcement for Lintel Beam Ground Floor
A3440 Concrete Poring For Column First Floor 2 28-Sep-23 30-Sep-23 Concrete Poring For Column First Floor
A3480 Formwork & Reinforcement for Beams & Slab First Floor 22 01-Oct-23 25-Oct-23 Formwork & Reinforcement for Beams & Slab First Floor
A3360 Concrete Poring for Lintels Ground Floor 4 21-Oct-23 24-Oct-23 Concrete Poring for Lintels Ground Floor
A3400 Plaster Internal Ground Floor 37 21-Oct-23 02-Dec-23 Plaster Internal Ground Floor
A3490 Formwork & Reinforcement for Stairs First Floor 4 22-Oct-23 25-Oct-23 Formwork & Reinforcement for Stairs First Floor
A3500 Concrete Poring for Beams , Slab & Stairs First Floor 2 26-Oct-23 28-Oct-23 Concrete Poring for Beams , Slab & Stairs First Floor
A3540 Formwork & Reinforcement for Column Second Floor 15 14-Nov-23 30-Nov-23 Formwork & Reinforcement for Column Second Floor
A3450 Brick/Block Work in First Floor 30 22-Nov-23 26-Dec-23 Brick/Block Work in First Floor
A3310 PCC( 1:2:4) under Floor 3 29-Nov-23 03-Dec-23 PCC( 1:2:4) under Floor
A3550 Concrete Poring For Column Second Floor 3 02-Dec-23 04-Dec-23 Concrete Poring For Column Second Floor
A3410 Mosaic, Chips Flooring , Marble on sills,Vanities,Shelves and Porcelain Tiles Ground Floor 25 03-Dec-23 31-Dec-23 Mosaic, Chips Flooring , Marble on sills,Vanities,Shelves and Porcelain Tiles Ground Floor
A3460 Formwork & Reinforcement for Lintel Beam First Floor 20 04-Dec-23 26-Dec-23 Formwork & Reinforcement for Lintel Beam First Floor
A3590 Formwork & Reinforcement for Beams & Slab Second Floor 22 11-Dec-23 04-Jan-24 Formwork & Reinforcement for Beams & Slab Second Floor
A3470 Concrete Poring for Lintels First Floor 4 27-Dec-23 31-Dec-23 Concrete Poring for Lintels First Floor
A3510 Plaster Internal First Floor 45 27-Dec-23 17-Feb-24 Plaster Internal First Floor
A3600 Formwork & Reinforcement for Stairs Second Floor 4 01-Jan-24 04-Jan-24 Formwork & Reinforcement for Stairs Second Floor
A3420 Wood Work Ground Floor complete 26 06-Jan-24 04-Feb-24 Wood Work Ground Floor complete
A3610 Concrete Poring for Beams , Slab & Stairs Second Floor 2 06-Jan-24 07-Jan-24 Concrete Poring for Beams , Slab & Stairs Second Floor
A3790 Paint & Varnishing internal Ground Floor 20 13-Jan-24 04-Feb-24 Paint & Varnishing internal Ground Floor
A3560 Brick/Block Work in Second Floor 40 01-Feb-24 18-Mar-24 Brick/Block Work in Second Floor
A3620 Plaster Internal Second Floor 37 01-Feb-24 14-Mar-24 Plaster Internal Second Floor
A3660 Formwork & Reinforcement for Column Mumty 4 01-Feb-24 05-Feb-24 Formwork & Reinforcement for Column Mumty
A3770 Formwork & Reinforcement for OWT 7 01-Feb-24 08-Feb-24 Formwork & Reinforcement for OWT
A3670 Concrete Poring For Column Mumty 1 06-Feb-24 06-Feb-24 Concrete Poring For Column Mumty
A3710 Formwork & Reinforcement for Beams & Slab Mumty 10 07-Feb-24 18-Feb-24 Formwork & Reinforcement for Beams & Slab Mumty
A3780 Concrete Pouring for OWT 1 10-Feb-24 10-Feb-24 Concrete Pouring for OWT
A3680 Block Work in Mumty 7 19-Feb-24 26-Feb-24 Block Work in Mumty
A3720 Concrete Poring for Beams & Slab of Mumty 1 19-Feb-24 19-Feb-24 Concrete Poring for Beams & Slab of Mumty
A3570 Formwork & Reinforcement for Lintel Beam Second Floor 20 25-Feb-24 18-Mar-24 Formwork & Reinforcement for Lintel Beam Second Floor
A3690 Formwork &Reinforcement for Lintel Beam Mumty 4 27-Feb-24 02-Mar-24 Formwork &Reinforcement for Lintel Beam Mumty
A3520 Mosaic, Chips Flooring , Marble on sills,Vanities,Shelves and Porcelain Tiles First Floor 30 29-Feb-24 03-Apr-24 Mosaic, Chips Flooring , Marble on sills,Vanities,Shelves and Porcelain Tiles First Floor
A3700 Concrete Poring for Lintels Mumty 1 03-Mar-24 03-Mar-24 Concrete Poring for Lintels Mumty
A3730 Plaster Internal Mumty 4 07-Mar-24 11-Mar-24 Plaster Internal Mumty
A3740 Plaster External Mumty 2 12-Mar-24 13-Mar-24 Plaster External Mumty

Actual Level of Effort Actual Work Critical Remaining Work summary


Primary Baseline Remaining Work Milestone
Note:Calender 6 days workweek(Friday off) ,7 days of Moonsoon considered as exceptions
Activity ID Activity Name Original Start Finish 2023 2024
Duration
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
A3750 Flooring Mumty 2 14-Mar-24 16-Mar-24 Flooring Mumty
A3580 Concrete Poring for Lintels Second Floor 4 19-Mar-24 23-Mar-24 Concrete Poring for Lintels Second Floor
A3630 Plaster External complete 25 19-Mar-24 20-Apr-24 Plaster External complete
A3760 Roof Treatment 10 21-Mar-24 01-Apr-24 Roof Treatment
A3800 Paint & Varnishing internal First Floor 20 24-Mar-24 18-Apr-24 Paint & Varnishing internal First Floor
A3530 Wood Work First Floor complete 30 04-Apr-24 12-May-24 Wood Work First Floor complete
A3810 Paint & Varnishing internal Second Floor 20 17-Apr-24 09-May-24 Paint & Varnishing internal Second Floor
A3840 Aluminium & Iron Works complete 35 17-Apr-24 27-May-24 Aluminium & Iron Works complete
A3820 Paint & Varnishing internal Mumty 4 20-Apr-24 23-Apr-24 Paint & Varnishing internal Mumty
A3640 Mosaic, Chips Flooring , Marble on sills,Vanities,Shelves and Porcelain Tiles Second Floor 30 21-Apr-24 25-May-24 Mosaic, Chips Flooring , Marble on sills,Vanities,Shelves and Porcelain Tiles
A3830 Paint External 30 15-May-24 23-Jun-24 Paint External
A3870 Providing & Laying Tuff Pavers External 30 15-May-24 24-Jun-24 Providing & Laying Tuff Pavers External
A3860 Face Cladding 30 21-May-24 29-Jun-24 Face Cladding
A3650 Wood Work Second Floor complete 30 26-May-24 03-Jul-24 Wood Work Second Floor complete
A3850 False Ceiling 20 28-May-24 24-Jun-24 False Ceiling
A3880 Ramp & Outer Entrance Stairs 20 01-Jun-24 27-Jun-24 Ramp & Outer Entrance Stairs
IDAP-1.3.4 Plumbing Works 148 06-Jan-24 03-Jul-24 03-Jul-24, IDAP-1.3.4 Plumbing Works
A3890 Water Supply Piping PPR 60 06-Jan-24 14-Mar-24 Water Supply Piping PPR
A3900 Sewrage Piping u-PVC 45 23-Jan-24 14-Mar-24 Sewrage Piping u-PVC
A4070 GI Pipes 20 21-Feb-24 14-Mar-24 GI Pipes
A4060 Khuras on roof 5 02-Apr-24 07-Apr-24 Khuras on roof
A3910 Floor Drains 15 08-May-24 25-May-24 Floor Drains
A3930 Manhole 30 15-May-24 24-Jun-24 Manhole
A3920 Plumbing Fixtures & Accessories 30 26-May-24 03-Jul-24 Plumbing Fixtures & Accessories
IDAP-1.3.5 Electrical works 296 18-Jul-23 11-Jul-24 11-Jul-24, IDAP-1.3.5 Electrical works
A3940 Conduits & Pipes for all electrical works 185 18-Jul-23 25-Feb-24 Conduits & Pipes for all electrical works
A3950 Wiring Cables for all electrical works 100 03-Dec-23 27-Mar-24 Wiring Cables for all electrical works
A3960 Cable Tray & Ladder 100 03-Dec-23 27-Mar-24 Cable Tray & Ladder
A3970 Wiring Accessories 20 28-Mar-24 23-Apr-24 Wiring Accessories
A4050 Fire Alarm System 30 28-Mar-24 05-May-24 Fire Alarm System
A4010 LV Power Cables 20 24-Apr-24 16-May-24 LV Power Cables
A4080 UPS System 20 24-Apr-24 16-May-24 UPS System
A4100 Fire Fighting System 10 06-May-24 16-May-24 Fire Fighting System
A4000 Fans 20 11-May-24 02-Jun-24 Fans
A4030 Switches,Light & other Electrical Fixtures 30 11-May-24 13-Jun-24 Switches,Light & other Electrical Fixtures
A3980 Energy Electric Meter 4 18-May-24 21-May-24 Energy Electric Meter
A4020 LV Distribution Board 20 18-May-24 09-Jun-24 LV Distribution Board
A3990 Earthing System 20 22-May-24 13-Jun-24 Earthing System
A4040 Lightning Protection System 20 15-Jun-24 11-Jul-24 Lightning Protection System
A4090 Testing & Commissioning 4 08-Jul-24 11-Jul-24 Testing & Commissioning
IDAP-1.3.6 Handing/Taking Over 7 13-Jul-24 20-Jul-24 20-Jul-24, IDAP-1.3.6 Handing/Taking Over
A4170 Punch List Rectification 6 13-Jul-24 18-Jul-24 Punch List Rectification
A4180 Handing/Taking Over 1 20-Jul-24 20-Jul-24 Handing/Taking Over
444 28-Jan-23 20-Jul-24 20-Jul-24, IDAP-1.4 Category D - 1 Bed Quarters
IDAP-1.4 Category D - 1 Bed Quarters
IDAP-1.4.1 Project Milestones 444 28-Jan-23 20-Jul-24 20-Jul-24, IDAP-1.4.1 Project Milestones
A5160 Project Start 0 28-Jan-23 Project Start, 28-Jan-23
A5170 Project Finish 0 20-Jul-24 Project Finish,

IDAP-1.4.2 Pre-Construction Phase 180 28-Jan-23 07-Sep-23 07-Sep-23, IDAP-1.4.2 Pre-Construction Phase
A5190 Mobilization at Site 10 28-Jan-23 07-Feb-23 Mobilization at Site
A5180 Submittals Submission & Approval 150 04-Mar-23 07-Sep-23 Submittals Submission & Approval

Actual Level of Effort Actual Work Critical Remaining Work summary


Primary Baseline Remaining Work Milestone
Note:Calender 6 days workweek(Friday off) ,7 days of Moonsoon considered as exceptions
Activity ID Activity Name Original Start Finish 2023 2024
Duration
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
IDAP-1.4.3 Civil Works 432 07-Feb-23 16-Jul-24 16-Jul-24, IDAP-1.4.3 Civil Works
A4190 Jungle clearance 2 07-Feb-23 08-Feb-23 Jungle clearance
A5200 Layout for Excavation 1 09-Feb-23 09-Feb-23 Layout for Excavation
A4200 Excavation,Engineering Fill,compaction in foundation 20 11-Feb-23 05-Mar-23 Excavation,Engineering Fill,compaction in foundation
A4210 Spraying Anti Termite 1 06-Mar-23 06-Mar-23 Spraying Anti Termite
A4220 PCC 1:4:8 in foundation 2 07-Mar-23 08-Mar-23 PCC 1:4:8 in foundation
A5210 Layout for footings 1 15-Mar-23 15-Mar-23 Layout for footings
A4230 Form Work & Reinforcement for Foundation 15 22-Mar-23 08-Apr-23 Form Work & Reinforcement for Foundation
A4240 Concrete Pouring for Foundation 4 09-Apr-23 12-Apr-23 Concrete Pouring for Foundation
A4250 Formwork & Reinforcement in Neck Column 12 19-Apr-23 06-May-23 Formwork & Reinforcement in Neck Column
A4260 Concrete Pouring for Neck Column 2 07-May-23 08-May-23 Concrete Pouring for Neck Column
A4270 Brick/Block Work in Foundation 8 09-May-23 17-May-23 Brick/Block Work in Foundation
A4280 Formwork & Reinforcement for Plinth Beam 15 18-May-23 04-Jun-23 Formwork & Reinforcement for Plinth Beam
A4290 Concrete Poring for Plinth Beam 2 05-Jun-23 06-Jun-23 Concrete Poring for Plinth Beam
A4300 Damp Proof Coarse 2 07-Jun-23 08-Jun-23 Damp Proof Coarse
A4310 Back filling in Foundation 5 15-Jun-23 20-Jun-23 Back filling in Foundation
A4320 Back Fill above NSL 4 21-Jun-23 25-Jun-23 Back Fill above NSL
A4330 Providing &Laying Watering & ramming Brick Ballast 5 26-Jun-23 04-Jul-23 Providing &Laying Watering & ramming Brick Ballast
A4370 Formwork & Reinforcement for Columns Ground Floor 13 26-Jun-23 13-Jul-23 Formwork & Reinforcement for Columns Ground Floor
A4380 Concrete Poring for Column 3 15-Jul-23 17-Jul-23 Concrete Poring for Column
A4420 Formwork & Reinforcement for Beams & Slab Ground Floor 22 18-Jul-23 19-Aug-23 Formwork & Reinforcement for Beams & Slab Ground Floor
A4430 Formwork & Reinforcement for Stairs Ground Floor 3 20-Aug-23 22-Aug-23 Formwork & Reinforcement for Stairs Ground Floor
A4440 Concrete Poring for Beams , Slab & Stairs Ground Floor 2 23-Aug-23 24-Aug-23 Concrete Poring for Beams , Slab & Stairs Ground Floor
A4340 Sand Filling under Floor 3 26-Aug-23 28-Aug-23 Sand Filling under Floor
A4350 PCC( 1:4:8) under Floor 3 29-Aug-23 31-Aug-23 PCC( 1:4:8) under Floor
A4360 PCC( 1:2:4) under Floor 3 02-Sep-23 04-Sep-23 PCC( 1:2:4) under Floor
A4390 Brick/Block Work in Ground Floor 30 19-Sep-23 23-Oct-23 Brick/Block Work in Ground Floor
A4480 Formwork & Reinforcement for Column First Floor 11 19-Sep-23 01-Oct-23 Formwork & Reinforcement for Column First Floor
A4400 Formwork & Reinforcement for Lintel Beam Ground Floor 20 01-Oct-23 23-Oct-23 Formwork & Reinforcement for Lintel Beam Ground Floor
A4490 Concrete Poring For Column First Floor 2 02-Oct-23 03-Oct-23 Concrete Poring For Column First Floor
A4530 Formwork & Reinforcement for Beams & Slab First Floor 22 04-Oct-23 29-Oct-23 Formwork & Reinforcement for Beams & Slab First Floor
A4410 Concrete Poring for Lintels Ground Floor 4 24-Oct-23 28-Oct-23 Concrete Poring for Lintels Ground Floor
A4450 Plaster Internal Ground Floor 37 24-Oct-23 05-Dec-23 Plaster Internal Ground Floor
A4540 Formwork & Reinforcement for Stairs First Floor 4 30-Oct-23 02-Nov-23 Formwork & Reinforcement for Stairs First Floor
A4550 Concrete Poring for Beams , Slab & Stairs First Floor 2 04-Nov-23 05-Nov-23 Concrete Poring for Beams , Slab & Stairs First Floor
A4590 Formwork & Reinforcement for Column Second Floor 15 22-Nov-23 09-Dec-23 Formwork & Reinforcement for Column Second Floor
A4500 Brick/Block Work in First Floor 30 30-Nov-23 03-Jan-24 Brick/Block Work in First Floor
A4460 Mosaic, Chips Flooring , Marble on sills,Vanities,Shelves and Porcelain Tiles Ground Floor 25 06-Dec-23 03-Jan-24 Mosaic, Chips Flooring , Marble on sills,Vanities,Shelves and Porcelain Tiles Ground Floor
A4600 Concrete Poring For Column Second Floor 3 10-Dec-23 12-Dec-23 Concrete Poring For Column Second Floor
A4510 Formwork & Reinforcement for Lintel Beam First Floor 20 12-Dec-23 03-Jan-24 Formwork & Reinforcement for Lintel Beam First Floor
A4640 Formwork & Reinforcement for Beams & Slab Second Floor 22 19-Dec-23 13-Jan-24 Formwork & Reinforcement for Beams & Slab Second Floor
A4520 Concrete Poring for Lintels First Floor 4 04-Jan-24 08-Jan-24 Concrete Poring for Lintels First Floor
A4560 Plaster Internal First Floor 45 04-Jan-24 25-Feb-24 Plaster Internal First Floor
A4650 Formwork & Reinforcement for Stairs Second Floor 4 14-Jan-24 17-Jan-24 Formwork & Reinforcement for Stairs Second Floor
A4470 Wood Work Ground Floor complete 26 15-Jan-24 13-Feb-24 Wood Work Ground Floor complete
A4660 Concrete Poring for Beams , Slab & Stairs Second Floor 2 18-Jan-24 20-Jan-24 Concrete Poring for Beams , Slab & Stairs Second Floor
A4840 Paint & Varnishing internal Ground Floor 20 22-Jan-24 13-Feb-24 Paint & Varnishing internal Ground Floor
A4610 Brick/Block Work in Second Floor 40 14-Feb-24 31-Mar-24 Brick/Block Work in Second Floor
A4670 Plaster Internal Second Floor 37 14-Feb-24 27-Mar-24 Plaster Internal Second Floor
A4710 Formwork & Reinforcement for Column Mumty 4 14-Feb-24 18-Feb-24 Formwork & Reinforcement for Column Mumty
A4820 Formwork & Reinforcement for OWT 7 14-Feb-24 21-Feb-24 Formwork & Reinforcement for OWT

Actual Level of Effort Actual Work Critical Remaining Work summary


Primary Baseline Remaining Work Milestone
Note:Calender 6 days workweek(Friday off) ,7 days of Moonsoon considered as exceptions
Activity ID Activity Name Original Start Finish 2023 2024
Duration
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
A4720 Concrete Poring For Column Mumty 1 19-Feb-24 19-Feb-24 Concrete Poring For Column Mumty
A4760 Formwork & Reinforcement for Beams & Slab Mumty 10 20-Feb-24 02-Mar-24 Formwork & Reinforcement for Beams & Slab Mumty
A4830 Concrete Pouring for OWT 1 22-Feb-24 22-Feb-24 Concrete Pouring for OWT
A4730 Block Work in Mumty 7 03-Mar-24 10-Mar-24 Block Work in Mumty
A4770 Concrete Poring for Beams & Slab of Mumty 1 03-Mar-24 03-Mar-24 Concrete Poring for Beams & Slab of Mumty
A4570 Mosaic, Chips Flooring , Marble on sills,Vanities,Shelves and Porcelain Tiles First Floor 30 09-Mar-24 15-Apr-24 Mosaic, Chips Flooring , Marble on sills,Vanities,Shelves and Porcelain Tiles First Floor
A4620 Formwork & Reinforcement for Lintel Beam Second Floor 20 09-Mar-24 31-Mar-24 Formwork & Reinforcement for Lintel Beam Second Floor
A4740 Formwork &Reinforcement for Lintel Beam Mumty 4 11-Mar-24 14-Mar-24 Formwork &Reinforcement for Lintel Beam Mumty
A4750 Concrete Poring for Lintels Mumty 1 16-Mar-24 16-Mar-24 Concrete Poring for Lintels Mumty
A4780 Plaster Internal Mumty 4 20-Mar-24 24-Mar-24 Plaster Internal Mumty
A4790 Plaster External Mumty 2 25-Mar-24 26-Mar-24 Plaster External Mumty
A4800 Flooring Mumty 2 27-Mar-24 28-Mar-24 Flooring Mumty
A4630 Concrete Poring for Lintels Second Floor 4 01-Apr-24 04-Apr-24 Concrete Poring for Lintels Second Floor
A4680 Plaster External complete 25 01-Apr-24 02-May-24 Plaster External complete
A4850 Paint & Varnishing internal First Floor 20 01-Apr-24 27-Apr-24 Paint & Varnishing internal First Floor
A4810 Roof Treatment 10 03-Apr-24 17-Apr-24 Roof Treatment
A4580 Wood Work First Floor complete 30 16-Apr-24 20-May-24 Wood Work First Floor complete
A4890 Aluminium & Iron Works complete 35 18-Apr-24 28-May-24 Aluminium & Iron Works complete
A4870 Paint & Varnishing internal Mumty 4 02-May-24 06-May-24 Paint & Varnishing internal Mumty
A4690 Mosaic, Chips Flooring , Marble on sills,Vanities,Shelves and Porcelain Tiles Second Floor 30 04-May-24 06-Jun-24 Mosaic, Chips Flooring , Marble on sills,Vanities,Shelves and Porcelain Til
A4880 Paint External 30 04-May-24 06-Jun-24 Paint External
A4910 Face Cladding 30 04-May-24 06-Jun-24 Face Cladding
A4860 Paint & Varnishing internal Second Floor 20 06-May-24 28-May-24 Paint & Varnishing internal Second Floor
A4920 Providing & Laying Tuff Pavers External 30 27-May-24 04-Jul-24 Providing & Laying Tuff Pavers External
A4900 False Ceiling 20 29-May-24 25-Jun-24 False Ceiling
A4700 Wood Work Second Floor complete 30 08-Jun-24 16-Jul-24 Wood Work Second Floor complete
A4930 Ramp & Outer Entrance Stairs 20 08-Jun-24 04-Jul-24 Ramp & Outer Entrance Stairs
IDAP-1.4.4 Plumbing Works 148 18-Jan-24 16-Jul-24 16-Jul-24, IDAP-1.4.4 Plumbing Works
A4940 Water Supply Piping PPR 60 18-Jan-24 27-Mar-24 Water Supply Piping PPR
A4950 Sewrage Piping u-PVC 45 05-Feb-24 27-Mar-24 Sewrage Piping u-PVC
A5120 GI Pipes 20 05-Mar-24 27-Mar-24 GI Pipes
A5110 Khuras on roof 5 18-Apr-24 23-Apr-24 Khuras on roof
A4960 Floor Drains 15 21-May-24 06-Jun-24 Floor Drains
A4980 Manhole 30 27-May-24 04-Jul-24 Manhole
A4970 Plumbing Fixtures & Accessories 30 08-Jun-24 16-Jul-24 Plumbing Fixtures & Accessories
IDAP-1.4.5 Electrical works 296 18-Jul-23 11-Jul-24 11-Jul-24, IDAP-1.4.5 Electrical works
A4990 Conduits & Pipes for all electrical works 185 18-Jul-23 25-Feb-24 Conduits & Pipes for all electrical works
A5000 Wiring Cables for all electrical works 100 06-Dec-23 31-Mar-24 Wiring Cables for all electrical works
A5010 Cable Tray & Ladder 100 06-Dec-23 31-Mar-24 Cable Tray & Ladder
A5020 Wiring Accessories 20 01-Apr-24 27-Apr-24 Wiring Accessories
A5100 Fire Alarm System 30 01-Apr-24 08-May-24 Fire Alarm System
A5060 LV Power Cables 20 28-Apr-24 20-May-24 LV Power Cables
A5130 UPS System 20 07-May-24 29-May-24 UPS System
A5150 Fire Fighting System 10 19-May-24 29-May-24 Fire Fighting System
A5030 Energy Electric Meter 4 21-May-24 25-May-24 Energy Electric Meter
A5070 LV Distribution Board 20 21-May-24 12-Jun-24 LV Distribution Board
A5040 Earthing System 20 26-May-24 22-Jun-24 Earthing System
A5050 Fans 20 29-May-24 25-Jun-24 Fans
A5080 Switches,Light & other Electrical Fixtures 30 29-May-24 07-Jul-24 Switches,Light & other Electrical Fixtures
A5090 Lightning Protection System 20 15-Jun-24 11-Jul-24 Lightning Protection System
A5140 Testing & Commissioning 4 08-Jul-24 11-Jul-24 Testing & Commissioning

Actual Level of Effort Actual Work Critical Remaining Work summary


Primary Baseline Remaining Work Milestone
Note:Calender 6 days workweek(Friday off) ,7 days of Moonsoon considered as exceptions
Activity ID Activity Name Original Start Finish 2023 2024
Duration
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
IDAP-1.4.6 Handing/Taking Over 7 13-Jul-24 20-Jul-24 20-Jul-24, IDAP-1.4.6 Handing/Taking Over
A5220 Punch List Rectification 6 13-Jul-24 18-Jul-24 Punch List Rectification
A5230 Handing/Taking Over 1 20-Jul-24 20-Jul-24 Handing/Taking Over
443 28-Jan-23 18-Jul-24 18-Jul-24, IDAP-1.5 Category E - Students Hostel
IDAP-1.5 Category E - Students Hostel
IDAP-1.5.1 Project Milestones 443 28-Jan-23 18-Jul-24 18-Jul-24, IDAP-1.5.1 Project Milestones
A6210 Project Start 0 28-Jan-23 Project Start, 28-Jan-23
A6220 Project Finish 0 18-Jul-24 Project Finish,

IDAP-1.5.2 Pre-Construction Phase 180 28-Jan-23 07-Sep-23 07-Sep-23, IDAP-1.5.2 Pre-Construction Phase
A6240 Mobilization at Site 10 28-Jan-23 07-Feb-23 Mobilization at Site
A6230 Submittals Submission & Approval 150 04-Mar-23 07-Sep-23 Submittals Submission & Approval
IDAP-1.5.3 Civil Works 386 07-Feb-23 19-May-24 19-May-24, IDAP-1.5.3 Civil Works
A5240 Jungle clearance 2 07-Feb-23 08-Feb-23 Jungle clearance
A6250 Layout for Excavation 1 08-Feb-23 08-Feb-23 Layout for Excavation
A5250 Excavation,Engineering Fill,compaction in foundation 20 09-Feb-23 04-Mar-23 Excavation,Engineering Fill,compaction in foundation
A5260 Spraying Anti Termite 1 05-Mar-23 05-Mar-23 Spraying Anti Termite
A5270 PCC 1:4:8 in foundation 2 06-Mar-23 07-Mar-23 PCC 1:4:8 in foundation
A6260 Layout for footings 1 14-Mar-23 14-Mar-23 Layout for footings
A5280 Form Work & Reinforcement for Foundation 15 21-Mar-23 06-Apr-23 Form Work & Reinforcement for Foundation
A5290 Concrete Pouring for Foundation 4 08-Apr-23 11-Apr-23 Concrete Pouring for Foundation
A5300 Formwork & Reinforcement in Neck Column 12 18-Apr-23 04-May-23 Formwork & Reinforcement in Neck Column
A5310 Concrete Pouring for Neck Column 2 06-May-23 07-May-23 Concrete Pouring for Neck Column
A5320 Brick/Block Work in Foundation 8 08-May-23 16-May-23 Brick/Block Work in Foundation
A5330 Formwork & Reinforcement for Plinth Beam 15 17-May-23 03-Jun-23 Formwork & Reinforcement for Plinth Beam
A5340 Concrete Poring for Plinth Beam 2 04-Jun-23 05-Jun-23 Concrete Poring for Plinth Beam
A5350 Damp Proof Coarse 2 06-Jun-23 07-Jun-23 Damp Proof Coarse
A5360 Back filling in Foundation 5 14-Jun-23 19-Jun-23 Back filling in Foundation
A5370 Back Fill above NSL 4 20-Jun-23 24-Jun-23 Back Fill above NSL
A5380 Providing &Laying Watering & ramming Brick Ballast 5 25-Jun-23 03-Jul-23 Providing &Laying Watering & ramming Brick Ballast
A5420 Formwork & Reinforcement for Columns Ground Floor 13 25-Jun-23 12-Jul-23 Formwork & Reinforcement for Columns Ground Floor
A5430 Concrete Poring for Column 3 13-Jul-23 16-Jul-23 Concrete Poring for Column
A5470 Formwork & Reinforcement for Beams & Slab Ground Floor 22 17-Jul-23 17-Aug-23 Formwork & Reinforcement for Beams & Slab Ground Floor
A5480 Formwork & Reinforcement for Stairs Ground Floor 3 19-Aug-23 21-Aug-23 Formwork & Reinforcement for Stairs Ground Floor
A5490 Concrete Poring for Beams , Slab & Stairs Ground Floor 2 22-Aug-23 23-Aug-23 Concrete Poring for Beams , Slab & Stairs Ground Floor
A5390 Sand Filling under Floor 3 24-Aug-23 27-Aug-23 Sand Filling under Floor
A5400 PCC( 1:4:8) under Floor 3 28-Aug-23 30-Aug-23 PCC( 1:4:8) under Floor
A5440 Brick/Block Work in Ground Floor 30 18-Sep-23 22-Oct-23 Brick/Block Work in Ground Floor
A5530 Formwork & Reinforcement for Column First Floor 11 18-Sep-23 30-Sep-23 Formwork & Reinforcement for Column First Floor
A5450 Formwork & Reinforcement for Lintel Beam Ground Floor 20 30-Sep-23 22-Oct-23 Formwork & Reinforcement for Lintel Beam Ground Floor
A5540 Concrete Poring For Column First Floor 2 01-Oct-23 02-Oct-23 Concrete Poring For Column First Floor
A5580 Formwork & Reinforcement for Beams & Slab First Floor 22 03-Oct-23 28-Oct-23 Formwork & Reinforcement for Beams & Slab First Floor
A5460 Concrete Poring for Lintels Ground Floor 4 23-Oct-23 26-Oct-23 Concrete Poring for Lintels Ground Floor
A5500 Plaster Internal Ground Floor 37 23-Oct-23 04-Dec-23 Plaster Internal Ground Floor
A5590 Formwork & Reinforcement for Stairs First Floor 4 29-Oct-23 01-Nov-23 Formwork & Reinforcement for Stairs First Floor
A5600 Concrete Poring for Beams , Slab & Stairs First Floor 2 02-Nov-23 04-Nov-23 Concrete Poring for Beams , Slab & Stairs First Floor
A5760 Formwork & Reinforcement for Column Mumty 4 28-Nov-23 02-Dec-23 Formwork & Reinforcement for Column Mumty
A5550 Brick/Block Work in First Floor 30 29-Nov-23 02-Jan-24 Brick/Block Work in First Floor
A5410 PCC( 1:2:4) under Floor 3 02-Dec-23 05-Dec-23 PCC( 1:2:4) under Floor
A5770 Concrete Poring For Column Mumty 1 03-Dec-23 03-Dec-23 Concrete Poring For Column Mumty
A5810 Formwork & Reinforcement for Beams & Slab Mumty 10 04-Dec-23 14-Dec-23 Formwork & Reinforcement for Beams & Slab Mumty
A5510 Mosaic, Chips Flooring , Marble on sills,Vanities,Shelves and Porcelain Tiles Ground Floor 25 05-Dec-23 02-Jan-24 Mosaic, Chips Flooring , Marble on sills,Vanities,Shelves and Porcelain Tiles Ground Floor

Actual Level of Effort Actual Work Critical Remaining Work summary


Primary Baseline Remaining Work Milestone
Note:Calender 6 days workweek(Friday off) ,7 days of Moonsoon considered as exceptions
Activity ID Activity Name Original Start Finish 2023 2024
Duration
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
A5940 Aluminium & Iron Works complete 60 07-Dec-23 14-Feb-24 Aluminium & Iron Works complete
A5560 Formwork & Reinforcement for Lintel Beam First Floor 20 11-Dec-23 02-Jan-24 Formwork & Reinforcement for Lintel Beam First Floor
A5780 Block Work in Mumty 7 16-Dec-23 23-Dec-23 Block Work in Mumty
A5820 Concrete Poring for Beams & Slab of Mumty 1 16-Dec-23 16-Dec-23 Concrete Poring for Beams & Slab of Mumty
A5870 Formwork & Reinforcement for OWT 7 17-Dec-23 24-Dec-23 Formwork & Reinforcement for OWT
A5790 Formwork &Reinforcement for Lintel Beam Mumty 4 24-Dec-23 27-Dec-23 Formwork &Reinforcement for Lintel Beam Mumty
A5880 Concrete Pouring for OWT 1 25-Dec-23 25-Dec-23 Concrete Pouring for OWT
A5800 Concrete Poring for Lintels Mumty 1 28-Dec-23 28-Dec-23 Concrete Poring for Lintels Mumty
A5830 Plaster Internal Mumty 4 02-Jan-24 06-Jan-24 Plaster Internal Mumty
A5570 Concrete Poring for Lintels First Floor 4 03-Jan-24 07-Jan-24 Concrete Poring for Lintels First Floor
A5610 Plaster Internal First Floor 45 03-Jan-24 24-Feb-24 Plaster Internal First Floor
A5840 Plaster External Mumty 2 07-Jan-24 08-Jan-24 Plaster External Mumty
A5850 Flooring Mumty 2 09-Jan-24 10-Jan-24 Flooring Mumty
A5730 Plaster External complete 25 11-Jan-24 08-Feb-24 Plaster External complete
A5520 Wood Work Ground Floor complete 26 14-Jan-24 12-Feb-24 Wood Work Ground Floor complete
A5860 Roof Treatment 10 16-Jan-24 27-Jan-24 Roof Treatment
A5890 Paint & Varnishing internal Ground Floor 20 21-Jan-24 12-Feb-24 Paint & Varnishing internal Ground Floor
A5920 Paint & Varnishing internal Mumty 4 11-Feb-24 14-Feb-24 Paint & Varnishing internal Mumty
A5950 False Ceiling 20 15-Feb-24 09-Mar-24 False Ceiling
A5620 Mosaic, Chips Flooring , Marble on sills,Vanities,Shelves and Porcelain Tiles First Floor 30 07-Mar-24 14-Apr-24 Mosaic, Chips Flooring , Marble on sills,Vanities,Shelves and Porcelain Tiles First Floor
A5930 Paint External 30 10-Mar-24 16-Apr-24 Paint External
A5960 Face Cladding 30 10-Mar-24 16-Apr-24 Face Cladding
A5900 Paint & Varnishing internal First Floor 20 31-Mar-24 25-Apr-24 Paint & Varnishing internal First Floor
A5970 Providing & Laying Tuff Pavers External 30 02-Apr-24 09-May-24 Providing & Laying Tuff Pavers External
A5630 Wood Work First Floor complete 30 15-Apr-24 19-May-24 Wood Work First Floor complete
A5980 Ramp & Outer Entrance Stairs 20 17-Apr-24 09-May-24 Ramp & Outer Entrance Stairs
IDAP-1.5.4 Plumbing Works 153 02-Dec-23 30-May-24 30-May-24, IDAP-1.5.4 Plumbing Works
A5990 Water Supply Piping PPR 60 02-Dec-23 08-Feb-24 Water Supply Piping PPR
A6000 Sewrage Piping u-PVC 45 19-Dec-23 08-Feb-24 Sewrage Piping u-PVC
A6170 GI Pipes 20 17-Jan-24 08-Feb-24 GI Pipes
A6160 Khuras on roof 5 28-Jan-24 01-Feb-24 Khuras on roof
A6010 Floor Drains 15 25-Mar-24 14-Apr-24 Floor Drains
A6030 Manhole 30 02-Apr-24 09-May-24 Manhole
A6020 Plumbing Fixtures & Accessories 30 27-Apr-24 30-May-24 Plumbing Fixtures & Accessories
IDAP-1.5.5 Electrical works 296 17-Jul-23 10-Jul-24 10-Jul-24, IDAP-1.5.5 Electrical works
A6040 Conduits & Pipes for all electrical works 185 17-Jul-23 24-Feb-24 Conduits & Pipes for all electrical works
A6050 Wiring Cables for all electrical works 100 05-Dec-23 30-Mar-24 Wiring Cables for all electrical works
A6060 Cable Tray & Ladder 100 05-Dec-23 30-Mar-24 Cable Tray & Ladder
A6180 UPS System 20 15-Feb-24 09-Mar-24 UPS System
A6200 Fire Fighting System 10 27-Feb-24 09-Mar-24 Fire Fighting System
A6100 Fans 20 10-Mar-24 01-Apr-24 Fans
A6130 Switches,Light & other Electrical Fixtures 30 19-Mar-24 25-Apr-24 Switches,Light & other Electrical Fixtures
A6070 Wiring Accessories 20 31-Mar-24 25-Apr-24 Wiring Accessories
A6150 Fire Alarm System 30 31-Mar-24 07-May-24 Fire Alarm System
A6110 LV Power Cables 20 27-Apr-24 19-May-24 LV Power Cables
A6080 Energy Electric Meter 4 20-May-24 23-May-24 Energy Electric Meter
A6120 LV Distribution Board 20 20-May-24 11-Jun-24 LV Distribution Board
A6090 Earthing System 20 25-May-24 20-Jun-24 Earthing System
A6140 Lightning Protection System 20 13-Jun-24 10-Jul-24 Lightning Protection System
A6190 Testing & Commissioning 4 07-Jul-24 10-Jul-24 Testing & Commissioning
IDAP-1.5.6 Handing/Taking Over 7 11-Jul-24 18-Jul-24 18-Jul-24, IDAP-1.5.6 Handing/Taking Over

Actual Level of Effort Actual Work Critical Remaining Work summary


Primary Baseline Remaining Work Milestone
Note:Calender 6 days workweek(Friday off) ,7 days of Moonsoon considered as exceptions
Activity ID Activity Name Original Start Finish 2023 2024
Duration
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
A6270 Punch List Rectification 6 11-Jul-24 17-Jul-24 Punch List Rectification
A6280 Handing/Taking Over 1 18-Jul-24 18-Jul-24 Handing/Taking Over
150 18-Jan-24 20-Jul-24 20-Jul-24, IDAP-1.6 External Works
IDAP-1.6 External Works
A6410 Civil Works 150 18-Jan-24 20-Jul-24 Civil Works
A6400 Road Works 120 22-Feb-24 20-Jul-24 Road Works
A6420 Water Supply Network 100 17-Mar-24 20-Jul-24 Water Supply Network
A6540 Electrification (infrastructure) 80 13-Apr-24 20-Jul-24 Electrification (infrastructure)
A6570 Construction of Filtration room 64 30-Apr-24 18-Jul-24 Construction of Filtration room
A6560 ICT Passive Infrastructure 10 08-Jul-24 20-Jul-24 ICT Passive Infrastructure