Idap Mianwali Baseline Submitted
Idap Mianwali Baseline Submitted
IDAP-1.1.2 Pre-Construction Phase 180 28-Jan-23 07-Sep-23 07-Sep-23, IDAP-1.1.2 Pre-Construction Phase
A2040 Mobilization at Site 10 28-Jan-23 07-Feb-23 Mobilization at Site
A2030 Submittals Submission & Approval 150 04-Mar-23 07-Sep-23 Submittals Submission & Approval
IDAP-1.1.3 Civil Works 426 09-Feb-23 11-Jul-24 11-Jul-24, IDAP-1.1.3 Civil Works
A1000 Jungle clearance 2 09-Feb-23 11-Feb-23 Jungle clearance
A2050 Layout for Excavation 1 12-Feb-23 12-Feb-23 Layout for Excavation
A1010 Excavation,Engineering Fill,compaction in foundation 25 13-Feb-23 13-Mar-23 Excavation,Engineering Fill,compaction in foundation
A1020 Spraying Anti Termite 1 14-Mar-23 14-Mar-23 Spraying Anti Termite
A1030 PCC 1:4:8 in foundation 2 15-Mar-23 16-Mar-23 PCC 1:4:8 in foundation
A2060 Layout for footings 1 18-Mar-23 18-Mar-23 Layout for footings
A1040 Form Work & Reinforcement for Foundation 20 19-Mar-23 10-Apr-23 Form Work & Reinforcement for Foundation
A1050 Concrete Pouring for Foundation 6 08-Apr-23 13-Apr-23 Concrete Pouring for Foundation
A1060 Formwork & Reinforcement in Neck Column 10 15-Apr-23 29-Apr-23 Formwork & Reinforcement in Neck Column
A1090 Formwork & Reinforcement for Plinth Beam 15 25-Apr-23 11-May-23 Formwork & Reinforcement for Plinth Beam
A1070 Concrete Pouring for Neck Column 3 27-Apr-23 30-Apr-23 Concrete Pouring for Neck Column
A1100 Concrete Poring for Plinth Beam 2 13-May-23 14-May-23 Concrete Poring for Plinth Beam
A1080 Brick/Block Work in Foundation 10 15-May-23 25-May-23 Brick/Block Work in Foundation
A1110 Damp Proof Coarse 4 15-May-23 18-May-23 Damp Proof Coarse
A1120 Back filling in Foundation 7 20-May-23 27-May-23 Back filling in Foundation
A1130 Back Fill above NSL 4 28-May-23 31-May-23 Back Fill above NSL
A1140 Providing &Laying Watering & ramming Brick Ballast 5 01-Jun-23 06-Jun-23 Providing &Laying Watering & ramming Brick Ballast
A1180 Formwork & Reinforcement for Columns Ground Floor 15 01-Jun-23 18-Jun-23 Formwork & Reinforcement for Columns Ground Floor
A1190 Concrete Poring for Column 3 19-Jun-23 21-Jun-23 Concrete Poring for Column
A1230 Formwork & Reinforcement for Beams & Slab Ground Floor 26 22-Jun-23 01-Aug-23 Formwork & Reinforcement for Beams & Slab Ground Floor
A1240 Formwork & Reinforcement for Stairs Ground Floor 4 22-Jul-23 01-Aug-23 Formwork & Reinforcement for Stairs Ground Floor
A1250 Concrete Poring for Beams , Slab & Stairs Ground Floor 2 02-Aug-23 03-Aug-23 Concrete Poring for Beams , Slab & Stairs Ground Floor
A1150 Sand Filling under Floor 4 24-Aug-23 28-Aug-23 Sand Filling under Floor
A1300 Formwork & Reinforcement for Column First Floor 15 24-Aug-23 10-Sep-23 Formwork & Reinforcement for Column First Floor
A1160 PCC( 1:4:8) under Floor 4 29-Aug-23 02-Sep-23 PCC( 1:4:8) under Floor
A1200 Brick/Block Work in Ground Floor 40 29-Aug-23 14-Oct-23 Brick/Block Work in Ground Floor
A1310 Concrete Poring For Column First Floor 3 11-Sep-23 13-Sep-23 Concrete Poring For Column First Floor
A1350 Formwork & Reinforcement for Beams & Slab First Floor 26 14-Sep-23 14-Oct-23 Formwork & Reinforcement for Beams & Slab First Floor
A1210 Formwork & Reinforcement for Lintel Beam Ground Floor 20 21-Sep-23 14-Oct-23 Formwork & Reinforcement for Lintel Beam Ground Floor
A1360 Formwork & Reinforcement for Stairs First Floor 4 10-Oct-23 14-Oct-23 Formwork & Reinforcement for Stairs First Floor
A1220 Concrete Poring for Lintels Ground Floor 4 15-Oct-23 18-Oct-23 Concrete Poring for Lintels Ground Floor
A1260 Plaster Internal Ground Floor 20 15-Oct-23 06-Nov-23 Plaster Internal Ground Floor
A1370 Concrete Poring for Beams , Slab & Stairs First Floor 2 15-Oct-23 16-Oct-23 Concrete Poring for Beams , Slab & Stairs First Floor
A1420 Formwork & Reinforcement for Column Second Floor 13 17-Oct-23 31-Oct-23 Formwork & Reinforcement for Column Second Floor
A1430 Concrete Poring For Column Second Floor 3 01-Nov-23 04-Nov-23 Concrete Poring For Column Second Floor
A1170 PCC( 1:2:4) under Floor 4 02-Nov-23 07-Nov-23 PCC( 1:2:4) under Floor
A1470 Formwork & Reinforcement for Beams & Slab Second Floor 26 05-Nov-23 04-Dec-23 Formwork & Reinforcement for Beams & Slab Second Floor
A1280 Mosaic, Chips Flooring , Marble on sills,Vanities,Shelves and Porcelain Tiles Ground Floor 30 07-Nov-23 11-Dec-23 Mosaic, Chips Flooring , Marble on sills,Vanities,Shelves and Porcelain Tiles Ground Floor
A1320 Brick/Block Work in First Floor 40 11-Nov-23 26-Dec-23 Brick/Block Work in First Floor
A1290 Wood Work Ground Floor complete 30 30-Nov-23 03-Jan-24 Wood Work Ground Floor complete
A1480 Formwork & Reinforcement for Stairs Second Floor 4 30-Nov-23 04-Dec-23 Formwork & Reinforcement for Stairs Second Floor
IDAP-1.2.2 Pre-Construction Phase 180 28-Jan-23 07-Sep-23 07-Sep-23, IDAP-1.2.2 Pre-Construction Phase
A3090 Mobilization at Site 10 28-Jan-23 07-Feb-23 Mobilization at Site
A3080 Submittals Submission & Approval 150 04-Mar-23 07-Sep-23 Submittals Submission & Approval
IDAP-1.2.3 Civil Works 428 07-Feb-23 11-Jul-24 11-Jul-24, IDAP-1.2.3 Civil Works
A2090 Jungle clearance 2 07-Feb-23 08-Feb-23 Jungle clearance
A3100 Layout for Excavation 1 09-Feb-23 09-Feb-23 Layout for Excavation
A2100 Excavation,Engineering Fill,compaction in foundation 25 11-Feb-23 11-Mar-23 Excavation,Engineering Fill,compaction in foundation
A2110 Spraying Anti Termite 1 12-Mar-23 12-Mar-23 Spraying Anti Termite
A2120 PCC 1:4:8 in foundation 2 13-Mar-23 14-Mar-23 PCC 1:4:8 in foundation
A3110 Layout for footings 1 15-Mar-23 15-Mar-23 Layout for footings
A2130 Form Work & Reinforcement for Foundation 20 16-Mar-23 08-Apr-23 Form Work & Reinforcement for Foundation
A2140 Concrete Pouring for Foundation 5 09-Apr-23 13-Apr-23 Concrete Pouring for Foundation
A2150 Formwork & Reinforcement in Neck Column 10 15-Apr-23 29-Apr-23 Formwork & Reinforcement in Neck Column
A2160 Concrete Pouring for Neck Column 3 30-Apr-23 02-May-23 Concrete Pouring for Neck Column
A2170 Brick/Block Work in Foundation 10 03-May-23 14-May-23 Brick/Block Work in Foundation
A2180 Formwork & Reinforcement for Plinth Beam 15 15-May-23 31-May-23 Formwork & Reinforcement for Plinth Beam
A2190 Concrete Poring for Plinth Beam 2 01-Jun-23 03-Jun-23 Concrete Poring for Plinth Beam
A2200 Damp Proof Coarse 4 04-Jun-23 07-Jun-23 Damp Proof Coarse
A2210 Back filling in Foundation 7 08-Jun-23 15-Jun-23 Back filling in Foundation
A2220 Back Fill above NSL 4 17-Jun-23 20-Jun-23 Back Fill above NSL
A2230 Providing &Laying Watering & ramming Brick Ballast 5 21-Jun-23 26-Jun-23 Providing &Laying Watering & ramming Brick Ballast
A2270 Formwork & Reinforcement for Columns Ground Floor 15 21-Jun-23 11-Jul-23 Formwork & Reinforcement for Columns Ground Floor
A2280 Concrete Poring for Column 3 12-Jul-23 15-Jul-23 Concrete Poring for Column
A2320 Formwork & Reinforcement for Beams & Slab Ground Floor 28 16-Jul-23 23-Aug-23 Formwork & Reinforcement for Beams & Slab Ground Floor
A2330 Formwork & Reinforcement for Stairs Ground Floor 4 20-Aug-23 23-Aug-23 Formwork & Reinforcement for Stairs Ground Floor
IDAP-1.3.2 Pre-Construction Phase 180 28-Jan-23 07-Sep-23 07-Sep-23, IDAP-1.3.2 Pre-Construction Phase
A4140 Mobilization at Site 10 28-Jan-23 07-Feb-23 Mobilization at Site
A4130 Submittals Submission & Approval 150 04-Mar-23 07-Sep-23 Submittals Submission & Approval
IDAP-1.3.3 Civil Works 421 07-Feb-23 03-Jul-24 03-Jul-24, IDAP-1.3.3 Civil Works
A3140 Jungle clearance 2 07-Feb-23 08-Feb-23 Jungle clearance
A4150 Layout for Excavation 1 09-Feb-23 09-Feb-23 Layout for Excavation
A3150 Excavation,Engineering Fill,compaction in foundation 20 11-Feb-23 05-Mar-23 Excavation,Engineering Fill,compaction in foundation
A3160 Spraying Anti Termite 1 06-Mar-23 06-Mar-23 Spraying Anti Termite
A3170 PCC 1:4:8 in foundation 2 07-Mar-23 08-Mar-23 PCC 1:4:8 in foundation
A4160 Layout for footings 1 15-Mar-23 15-Mar-23 Layout for footings
A3180 Form Work & Reinforcement for Foundation 15 22-Mar-23 08-Apr-23 Form Work & Reinforcement for Foundation
A3190 Concrete Pouring for Foundation 4 09-Apr-23 12-Apr-23 Concrete Pouring for Foundation
A3200 Formwork & Reinforcement in Neck Column 12 19-Apr-23 06-May-23 Formwork & Reinforcement in Neck Column
A3210 Concrete Pouring for Neck Column 2 07-May-23 08-May-23 Concrete Pouring for Neck Column
IDAP-1.4.2 Pre-Construction Phase 180 28-Jan-23 07-Sep-23 07-Sep-23, IDAP-1.4.2 Pre-Construction Phase
A5190 Mobilization at Site 10 28-Jan-23 07-Feb-23 Mobilization at Site
A5180 Submittals Submission & Approval 150 04-Mar-23 07-Sep-23 Submittals Submission & Approval
IDAP-1.5.2 Pre-Construction Phase 180 28-Jan-23 07-Sep-23 07-Sep-23, IDAP-1.5.2 Pre-Construction Phase
A6240 Mobilization at Site 10 28-Jan-23 07-Feb-23 Mobilization at Site
A6230 Submittals Submission & Approval 150 04-Mar-23 07-Sep-23 Submittals Submission & Approval
IDAP-1.5.3 Civil Works 386 07-Feb-23 19-May-24 19-May-24, IDAP-1.5.3 Civil Works
A5240 Jungle clearance 2 07-Feb-23 08-Feb-23 Jungle clearance
A6250 Layout for Excavation 1 08-Feb-23 08-Feb-23 Layout for Excavation
A5250 Excavation,Engineering Fill,compaction in foundation 20 09-Feb-23 04-Mar-23 Excavation,Engineering Fill,compaction in foundation
A5260 Spraying Anti Termite 1 05-Mar-23 05-Mar-23 Spraying Anti Termite
A5270 PCC 1:4:8 in foundation 2 06-Mar-23 07-Mar-23 PCC 1:4:8 in foundation
A6260 Layout for footings 1 14-Mar-23 14-Mar-23 Layout for footings
A5280 Form Work & Reinforcement for Foundation 15 21-Mar-23 06-Apr-23 Form Work & Reinforcement for Foundation
A5290 Concrete Pouring for Foundation 4 08-Apr-23 11-Apr-23 Concrete Pouring for Foundation
A5300 Formwork & Reinforcement in Neck Column 12 18-Apr-23 04-May-23 Formwork & Reinforcement in Neck Column
A5310 Concrete Pouring for Neck Column 2 06-May-23 07-May-23 Concrete Pouring for Neck Column
A5320 Brick/Block Work in Foundation 8 08-May-23 16-May-23 Brick/Block Work in Foundation
A5330 Formwork & Reinforcement for Plinth Beam 15 17-May-23 03-Jun-23 Formwork & Reinforcement for Plinth Beam
A5340 Concrete Poring for Plinth Beam 2 04-Jun-23 05-Jun-23 Concrete Poring for Plinth Beam
A5350 Damp Proof Coarse 2 06-Jun-23 07-Jun-23 Damp Proof Coarse
A5360 Back filling in Foundation 5 14-Jun-23 19-Jun-23 Back filling in Foundation
A5370 Back Fill above NSL 4 20-Jun-23 24-Jun-23 Back Fill above NSL
A5380 Providing &Laying Watering & ramming Brick Ballast 5 25-Jun-23 03-Jul-23 Providing &Laying Watering & ramming Brick Ballast
A5420 Formwork & Reinforcement for Columns Ground Floor 13 25-Jun-23 12-Jul-23 Formwork & Reinforcement for Columns Ground Floor
A5430 Concrete Poring for Column 3 13-Jul-23 16-Jul-23 Concrete Poring for Column
A5470 Formwork & Reinforcement for Beams & Slab Ground Floor 22 17-Jul-23 17-Aug-23 Formwork & Reinforcement for Beams & Slab Ground Floor
A5480 Formwork & Reinforcement for Stairs Ground Floor 3 19-Aug-23 21-Aug-23 Formwork & Reinforcement for Stairs Ground Floor
A5490 Concrete Poring for Beams , Slab & Stairs Ground Floor 2 22-Aug-23 23-Aug-23 Concrete Poring for Beams , Slab & Stairs Ground Floor
A5390 Sand Filling under Floor 3 24-Aug-23 27-Aug-23 Sand Filling under Floor
A5400 PCC( 1:4:8) under Floor 3 28-Aug-23 30-Aug-23 PCC( 1:4:8) under Floor
A5440 Brick/Block Work in Ground Floor 30 18-Sep-23 22-Oct-23 Brick/Block Work in Ground Floor
A5530 Formwork & Reinforcement for Column First Floor 11 18-Sep-23 30-Sep-23 Formwork & Reinforcement for Column First Floor
A5450 Formwork & Reinforcement for Lintel Beam Ground Floor 20 30-Sep-23 22-Oct-23 Formwork & Reinforcement for Lintel Beam Ground Floor
A5540 Concrete Poring For Column First Floor 2 01-Oct-23 02-Oct-23 Concrete Poring For Column First Floor
A5580 Formwork & Reinforcement for Beams & Slab First Floor 22 03-Oct-23 28-Oct-23 Formwork & Reinforcement for Beams & Slab First Floor
A5460 Concrete Poring for Lintels Ground Floor 4 23-Oct-23 26-Oct-23 Concrete Poring for Lintels Ground Floor
A5500 Plaster Internal Ground Floor 37 23-Oct-23 04-Dec-23 Plaster Internal Ground Floor
A5590 Formwork & Reinforcement for Stairs First Floor 4 29-Oct-23 01-Nov-23 Formwork & Reinforcement for Stairs First Floor
A5600 Concrete Poring for Beams , Slab & Stairs First Floor 2 02-Nov-23 04-Nov-23 Concrete Poring for Beams , Slab & Stairs First Floor
A5760 Formwork & Reinforcement for Column Mumty 4 28-Nov-23 02-Dec-23 Formwork & Reinforcement for Column Mumty
A5550 Brick/Block Work in First Floor 30 29-Nov-23 02-Jan-24 Brick/Block Work in First Floor
A5410 PCC( 1:2:4) under Floor 3 02-Dec-23 05-Dec-23 PCC( 1:2:4) under Floor
A5770 Concrete Poring For Column Mumty 1 03-Dec-23 03-Dec-23 Concrete Poring For Column Mumty
A5810 Formwork & Reinforcement for Beams & Slab Mumty 10 04-Dec-23 14-Dec-23 Formwork & Reinforcement for Beams & Slab Mumty
A5510 Mosaic, Chips Flooring , Marble on sills,Vanities,Shelves and Porcelain Tiles Ground Floor 25 05-Dec-23 02-Jan-24 Mosaic, Chips Flooring , Marble on sills,Vanities,Shelves and Porcelain Tiles Ground Floor