PROJECT NAME: Construction of SPARK 380/115 kV BSP

ELEMENT 5.19.3
JOB SAFETY PRACTICES

DEPARTMENT/DIVISION PE-199 Mechanical / Pre-cast DATE 08/10/2019


EMPLOYEE JOB TITLE Erector and Technician LOCATION Abqaiq
Personal Protective Helmet, Safety Glass, Coverall, Gloves, Safety
JOB/ TASK TITLE Installation of Anchor Bolts and Railings
Equipment Shoes, visible vest & Harness with 2 lanyards
STEPS HAZARDS
IN EACH STEP, WHAT COULD CONTROL REQUIRED TO MINIMIZE/ ELIMINATE
LIST ALL STEPS IN PERFORMING THIS COMMENTS OF JOB OBSERVATION
STEPS # CAUSE INJURY, LOSS DAMAGE, HAZARD
TASK
INTRRUPTION, OR POLUTION?
 Struck by vehicle  Materials must be secured to prevent it
 Fall of materials due to from falling while traveling
unsecured materials and  Flagman must be present on forklift at
improper loading to all time to guide the movement of the
Preparation of materials (Shifting vehicle by forklift equipment and prevent anyone to go
1. of Materials from store to work  Struck by forklift near the area. Accepted
place by used of vehicle/forklift)  Slip, trip and fall  Arrange materials properly as per
 Back injury due to carrying standard
heavy load  Do not block the access
 Do not carry heavy materials by your
own, ask for help.
 Incompetent person to do
the task that leads to  Provide appropriate PPE
accident  Only competent person will do the task.
 Improper body posture  No Unauthorized and incompetent
while working that can person is allowed.
cause back injury, etc.  Ask help from colleague to make sure Accepted
2. Installation of anchor bolts
 Hand injury work will be done easier.
 Exertion of Tress hold
energy that can lead to
body/muscle pain

3 Installation of Railings  Incompetent person to do  Only competent person are allowed to Accepted
Page 1 of 3 Rev.2 [08-April-2019] Projects Business Unit
PROJECT NAME: Construction of SPARK 380/115 kV BSP
ELEMENT 5.19.3
JOB SAFETY PRACTICES

the task do the job.


 Hand injury  Wear all required PPE (Mask & Gloves,
 Simultaneous activity in etc.,) to avoid any injury and illnesses.
one area.  Proper Supervision of Foreman and
 Following unsafe Supervisor
procedures that can  Activity must be isolated, barricaded
injured workers. and provide proper signage’s to ensure
 Falling object that can no workers are passing or working
injured people under the under the elevated activity.
working area.  Follow proper procedures to prevent
any accident that can lead to injury and
damage to property.

 Workers must be trained in working


 Fall from Height height prior to work in elevated area.
 Incomplete Scaffold  Wear full body harness with double
 Workers are not trained in lanyards and secure 100% tie off.
working at height  Scaffold must be inspected, Green tag
 Unsafe erection of will indicated scaffold is safe to use.
Working at Height Scaffolding  Operator must be trained by third party Accepted
4.
(Use of Man lift and scaffold)  Incompetent Man-lift certifying buddy.
operator  Daily inspection to ensure equipment in
 Equipment failure in good working condition.
 Working under  One more trained operator should be
transmission line (not available for rescue purpose.
applicable)

 Area must be clean and materials must


 Poor housekeeping that be arrange.
Housekeeping can cause trip, slip and fall.  Excess Materials should be return to Accepted
5.
 Scattered Scrap materials store.
 Removed scrap materials at site and
place it on scrap storage area.

Page 2 of 3 Rev.2 [08-April-2019] Projects Business Unit


PROJECT NAME: Construction of SPARK 380/115 kV BSP
ELEMENT 5.19.3
JOB SAFETY PRACTICES

Emergency Response and Arrangements


 The injured person should be given first aid immediately.
 First aid box shall be made available with required medicines in adequate quantity.
 Emergency response team should be available at site.
 All personnel on site should be aware on site evacuation procedure, location of muster point.
 Emergency Numbers shall be posted at different locations.
 One vehicle shall be made available for meeting emergency needs.
 All employees shall be explained about the provisions of first aid, assembly point and contact number, etc.
JSP Prepared By: Mr. Haitham Abouelella Signature: Date: 09/10/2019

JSP Accepted By: Mr. Mohamed Abdellatif Signature: Date: 09/10/2019

JSP Approved By (SEC / Site): Mr. Ronald Marteja Signature: Date: 09/10/2019

JSP Approved By (SEC- PD): Mr. Abdul Majeed Signature: Date: 09/10/2019

Page 3 of 3 Rev.2 [08-April-2019] Projects Business Unit