Sinjhoro Plant Synopsis and future Targets

1) Summary
i) Total 03 main units, Dehydration, LPG Recover and Condensate Stabilization along with
related utilities and flare system was relocated from Dhodak in 2012, re-installed at this site
and commissioned in January 03, 2013.
ii) In second phase, installation of Gathering, Feed & Sales Gas Compressors and LPG Recovery
Unit installed and commissioned on July 07, 2015
iii) On December 17, 2015 Membrane Unit installed and commissioned and downstream of LPG
unit.
iv) On May 17, 2019 Bitrism Block connected with Plant by installing its dedicated separator and
associated piping and finally commissioned.
v) On June 15, 2019 Permeate Gas supply to M/s Hi-Tech started
vi) On June 14, 2021 Got ISO-45001 & 14000 Certification.
vii) On December 20, 2021 Gundenwari well injected into system through Bitrism Block HP
Separator.
viii) On December 29, 2021 Pandhi well injected into system through a dedicated Separator.
ix) Sales Gas Enhancement Project executed in 2022, Membrane Package along with Pre-
Treatment Package shifted from Daru Facilities and Installed at Sinjhoro in addition to Bitrism
Block Medium Pressure Separator and along with associated piping and process control
equipment. This project successfully commissioned on dated April 04, 2022
x) Chabaro well also commissioned on dated April 04, 2022 through Bitrism Block well stream 8”
line and processed along with Bitrism Block Wells in Comingled Form.
xi) On May 31, 2022 Well Hakeem Daho # 3 successfully connected and injected into system for
process.
xii) And Finally on October 03, 2022 Well Lalai Jamli # successfully connected and injected into
system for process.

2) Design & Operating Conditions


Capacities Feed Gas Dehydration LPG Sales Gas Enhancement Total sales
Compression Unit Recovery Compression (New
Membrane)
Design 32 mmscfd 48 mmscfd 168 32 mmscfd 14 mmscfd More than
M.Tons 50 mmscfd

Current 25 mmscfd 44 mmscfd 160 35.5 mmscfd 7 mmscfd 44-45


M.Tons mmscfd
3) Existing Utilities at Sinjhoro.
Installed/ Total
Sr. Available Installed/ Current
Description Units Units
No. Capacity per Available Consumption
Unit Capacity
Power Generation
Capacity 965
1 i 03 Gas engines 2895 KW
KW
Capacity 1000
ii 01 Gas engines 1000 KW
KW
iii 01 Diesel engine Capacity 665 KW 665 KW
Capacity 1000
iv 01 Diesel engine 1000 KW
KW
Total 5560 KW
1400-1500 KW
Instrument Air
Compressor
2 M75 (ML)
i 335 335 SCFM 335 SCFM
Ingersoll Rand
M75 (ML)
ii 335 335 SCFM Stand BY SCFM
Ingersoll Rand
Dhakni Relocated
iii 480 480 SCFM Stand By SCFM
Compressor
Not
3 R.O plant 21 21 m3/hr m3/hr
Commissioned
02 Fire water pump Used as per
4 3200 6400 GPM GPM
capacity Requirement
Both in MMBT
5 02 Hot Oil Heater 24.6 49.2 MMBTU/Hr
Operation U/Hr

4) Future Targets

i) Completion of Bitrism & Chabaro Process gas transfer to Bobi Plant project.
ii) Completion of Produced Water Re-injection project.
iii) ATA-2023 (March 07- March 15)
iv) Up gradation of V-6001B Hot Oil package startup and control PLC.

Submitted By:
Muhammad Sohail Hayat Gill
In-Charge Process, SGF