Professional Documents
Culture Documents
2C The Basis of A Contract
2C The Basis of A Contract
EPM5760
Amir Ghapanchi
Course Coordinator – Master of Project Management
Contact:
Phone +61399194714
Email: Amir.Ghapanchi@vu.edu.au
Read Chapter 1:
Goldfayl, G 2004, Construction contract administration, UNSW Press.
Available in library:
• https://search.ebscohost.com/login.aspx?direct=true&AuthType=shib&db=cat06414a&AN=vic.b4396494&site=eds-live&custid=s1145751
Read Chapter 5:
Construction Specification Institute 2011, Construction contract administration practice guide, John Wiley & Sons, New Jersey, USA.
Available in e-format:
• https://search.ebscohost.com/login.aspx?direct=true&AuthType=shib&db=cat06414a&AN=vic.b5772479&site=eds-live&custid=s1145751
Read Chapter 1:
Phillips, CS 2009, Construction contract administration, Society of Mining, Metallurgy, and Exploration, Littleton, CO.
Available in e-format:
• https://search.ebscohost.com/login.aspx?direct=true&AuthType=shib&db=cat06414a&AN=vic.b5597575&site=eds-live&custid=s1145751
View Video by Anthony Marinac:(He has prepared numerous videos on Contract Law Australia and Case notes)
Marinac, A n.d., Contract Law Australia – Anthony Marinac Videos, YouTube, viewed 15th June 2020 <https://www.youtube.com/user/AnthLovesAdmin/videos>.
Lecture Topics
Contract Models
What Does A Contract Look Like
Key Contractual Clauses
Bespoke Vs Standard Forms of Contract
Acts and Regulations
The Trade Practices Act 1974
Learning Outcomes
After completing this module, you will be able to:
• Once the decision on the most appropriate option of project delivery has been made,
followed closely is then making a decision on the most appropriate option for the
contract price.
• The price payable under the contract to members of a project team for specific work
and services may either be pre-ascertained in the form of a lump sum or price rates.
• The former approach is known as a
o fixed-price contract while the latter is usually cost-plus.
• These two options for a contract price will now be discussed in more detail.
Contract Models
Once the decision on the most appropriate option of project delivery has been made, followed closely is then
deciding on the most appropriate option for the contract price.
Each contract type has its advantages and disadvantages with respect to the owner and the contractor
Categorized in two major groups as per method of payment to the contractor or seller:
https://www.turtons.com/blog/the-5-key-elements-of-a-latent-condition-clause
Fixed-Price Contracts (Cont’d)
▪ Need a well-defined scope/product & cannot change without a price change
▪ The principal’s intent is to shift the risk of cost overruns onto the contractor. This practice
may be justified in some situations but only when:
▪ Risk is on contractor – contractor legally obligated to complete the contract, with possible
financial damages if they do not.
▪ May incorporate financial incentives for achieving or exceeding selected project objectives –
such as schedule delivery dates, cost or technical performance etc.
Types of Fixed-Price Contract
Weaknesses:
▪ The Contractor can be expected to ask for a higher markup in order to take care of unforeseen contingencies.
▪ Besides the fixed lump sum price, other commitments are often made by the Contractor in the form of submittals,
such as a specific schedule, the management reporting system, or a quality control program.
▪ If the actual cost of the project is under estimated, it will reduce the Contractor’s profit by that amount. May cut
cost by reducing the quality.
▪ Any modifications to scope, design, or schedule will give rise to a cost change.
▪ Fixing a contract price for the entire contract period may not be in the principal’s best interest. It is also worth
noting that this practice is likely to lead to the development of an adversarial relationship between the parties to a
contract.
iv. Unit Price Contract
▪ Under this form, the detailed bill of quantities is prepared by the quantity surveyor of the Consultant based
on drawings and specifications.
▪ The contractors quote their rates against these calculated quantities on basis of unit rate method.
However, the contractors are paid for the work measured in place on the basis of actual quantity
multiplied by quoted rate.
▪ This method is advantageous when the quantities cannot be accurately identified in advance or in such
works having a high content of ground surface work where the quantities are rather unpredictable. This
method is particularly favored for linear construction like roads, railway tracks, sewers, water mains, or
buried/aerial utility lines.
▪ The estimated quantities at the proposed unit prices submitted by bidders are used in comparing the bids.
▪ If changes occur, the unit prices and rates in the bill of quantities can be used as a basis for valuation.
Typically, a change or variation in quantities up to 15% is permitted in this type of contract without the
need of a formal change order as long as the items remain generally the same as in the initial contract.
▪ Disadvantage is that total project cost unknown until project is completed.
Unit Price Contract - Strengths and Weaknesses
Strengths: Weaknesses:
• Easy for contract selection. • Final cost not known from the beginning (BOQ only is estimated)
• Early start is possible. • Staff needed to measure the finished quantities and report on
• Saves the heavy cost of preparing many bills the units not completed.
of quantities by the contractors. • Unit price sometime tend to draw unbalanced bid.
• Fair basis for competition. • (For Unit-Price Contracts, a balanced bid is one in which each
• In comparing with lump-sum contract, bid is priced to carry its share of the cost of the work and also its
changes in contract documents can be made share of the contractor’s profit. Contractors raise prices on
easily by the owner. certain items and make corresponding reductions of the prices
• Lower risk for contractor. on other items, without changing the total amount of the bid)
Cost-Reimbursable Contracts
Cost-Reimbursable Contract
• This type of contract involves payments ( cost reimbursements) to the seller for all legitimate
actual costs incurred for completed work, plus a fee representing seller profit.
• Cost-reimbursable contracts may also include financial incentive clauses whenever the seller
exceeds, or falls below, defined objectives such as costs, schedule, or technical performance
targets.
• A cost-reimbursable contract provides the project flexibility to redirect a seller whenever the
scope of work cannot be precisely defined at the start and needs to be altered, or when high
risks may exist in the effort.
• Types of Cost-Reimbursable Contract:
i. Cost Plus Fixed Fee (CPFF) (also known as Cost-Reimbursable Contract)
ii. Cost Plus Incentive Fee (CPIF) (also known as Target Cost Contract)
iii. Cost Plus Award Fee (CPAF)
iv. Guaranteed Maximum Cost Contract (GMC Contract)
v. Time-and-Material (T&M) Contract
i. Cost Plus Fixed Fee (CPFF) (also known as Cost-Reimbursable Contract)
❖ The seller is reimbursed for all allowable costs for performing the contract work, and receives a
fixed-fee payment calculated as a percentage of the initial estimated project costs.
❖ The fixed-fee is set at the beginning of the contract, and even if legitimate expenses increase, this
fixed-fee remains the same – i.e. The fee is paid only for completed work and does not change
due to seller performance.
❖ Fee amounts do not change unless the project scope changes.
ii. Cost Plus Incentive Fee (CPIF) (also known as Target Cost Contract):
❖ The seller is reimbursed for all allowable costs for performing the contract work and receives a predetermined
incentive fee based upon achieving certain performance objectives as set forth in the contract.
❖ For this type of contract, the Contractor agrees to a penalty if the actual cost exceeds the estimated job cost or a
reward if the actual cost is below the estimated job cost.
❖ The Contractor’s fee is made up of two parts: a fixed amount and a variable amount depending upon the
relationship between the target cost and the actual cost.
❖ Furthermore, the project duration is usually specified and the contractor must abide by the deadline for completion.
❖ In CPIF contracts, if the final costs are less or greater than the original estimated costs, then both the buyer and
seller share costs from the departures based upon a pre-negotiated cost-sharing formula, for example, an 90/10
split over/under target costs based on the actual performance of the seller.
CPIF Contract (Cont’d)
❖ This type of contract allocates considerable risk for cost overruns to the Owner but also provides incentives to
contractors to reduce/control costs as much as possible but has the disadvantage of requiring the target cost to
be fixed on the basis of a rough estimate. The variable fee concept is illustrated in the following example:
(Surahyo 2018)
GMC Contract - Example
(Surahyo 2018)
GMC Contract - Example
Scenario 1: Cost Underran
Suppose the cost of construction decreases or underran the target cost, the Owner and Contractor would split
the savings according to the share ratio.
For example: if the cost of work completed is $450,000 ($50,000 less than target cost), the Contractor’s share is
30% of underrun, i.e., $15000. Hence, the Contractor will get:
Cost of work done ($ 450,000) + target profit ($ 50,000) + underrun share $15,000.00 = $515,000
Scenario 2: Cost Overran
In this scenario, consider that the Contractor completes the work with cost overrun but below ceiling price, say at
$520,000.00, overrunning the target cost by $20,000. The Contractor’s share of overrun is 30% of $20,000 ($6,000).
The target profit will be reduced by this amount ($50,000 - $6,000) equal to $44,000. Hence, the Contractor will then
get:
$520,0000 + $44,000 = $564,000, which is $36,000 below the ceiling price
(Rathod 2014)
Cost plus Contracts - Strengths and Weaknesses
Strengths: Weaknesses:
▪ These contracts are faster, as scope or ▪ The total cost is not well defined.
design need not to be defined ▪ It requires close inspection and review of
completely. construction.
▪ There is flexibility for changes during ▪ Since under cost plus contracts, the scope is
execution of the work. not well defined, most of the risks are shifted to
▪ Use of guaranteed maximum cost the Owner.
types provide owners with some cost ▪ Contractor also needs to develop adequate
certainty. accounting systems. Certainty of cost is limited
▪ Additionally, owners have to pay only until the project is complete.
for the actual work performed and cost ▪ Under T&M, the Contractor has no incentive to
actually incurred. be efficient to control the cost; hence, more
efforts for monitoring are required by the Owner.
(Surahyo 2018)
Comparison Between Different Types of Contracts
Point of Differentiation Lump Sum Contract Unit Price Contract Cost Plus Contract Target Cost Contract
Rewards for any savings
Advantages with respect to
Incentives for early finish Low risk No risk between actual and
the contractor
target cost
Disadvantages with respect No incentives for No incentives for Share risk with the
High risk
to the contractor early finish early finish owner
No risk Can start project
Advantages with respect to Share risk with the Target cost is defined at
Total cost is defined at without finishing
the owner contractor early stages
early stages designs
High risk
Contractor desire to Total cost is
Disadvantages with respect Total cost is Share risk with the
decrease costs may be uncertain at early
to the owner uncertain at early contractor
to detriment of quality stages
stages
Has flexibility to More flexible to
Flexibility of design changing Limited flexibility Limited flexibility
change design design stages
Table sourced from: https://theconstructor.org/construction/types-of-construction-contracts-comparison/14268/
Contract Models
Project managers should be aware of the benefits and risks of different
contract types from a buyer’s perspective and a seller’s perspective.
allows buyer to budget fixed price; requires seller to detail scope and
(FFP) Firm Fixed Price
accurately estimate price; very common
(FFIF) Fixed Price Incentive Fee includes incentive to motivate seller to produce at greater speed
(FF EPA) Fixed Price Economic Price Adjustment compensates for year to year economic changes
(T&M) Time and Materials typically used for smaller initiatives
(PO) Purchase Order typically used for commodity items
(CPFF) Cost Plus Fixed Fee typically variable costs are cost-plus and predictable costs are fixed fee
(CPIF) Cost Plus Incentive Fee actual costs plus incentive to motivate seller to produce at greater speed
(CPAF) Cost Plus Award Fee actual costs plus award based on customer satisfaction with agreed criteria
(CPPC) Cost Plus Percent of Cost actual cost plus % of actual; the higher the cost, the higher the fees
Known and unknown risks in contracts
The identification and allocation of risk is a lengthy process that will require a number of iterations for optimum
results. During project appraisal, risks that may occur throughout the whole life of the project should be identified
for the whole supply chain. These could then be considered on the basis of:
2. Project constraints: There isn’t any construction project without constraints. Thus,
project constraints should be considered while selecting type of construction contracts.
▪ Glossary of the terms used in the Section IIIA Special Terms & Conditions
contract ▪ Section which details the work scope
Section IIIB General Terms & Conditions ▪ Clarity of work scope is important
▪ Additional terms and conditions ▪ Sets out the specifications, schedules and
specific to the contract resources
Section IV Schedule of Scope
▪ Clear knowledge of these ▪ Need to consider – what-ifs
negotiated terms Section V Schedule of Prices
▪ Section sets out how the Vendor will be paid
▪ Sets out the manner how the Section VI Administration ▪ Schedule could include hourly rates, unit rates,
contract will be administered over fixed rates – depending on contract scope
the tenure Sections Insurance, Quality, HSSE, ▪ Complexity in pricing schedules will lead to more
▪ Invoicing requirements and monitoring requirements
Local Content, Ethics &
payment cycles ▪ Consider maintenance of the pricing schedule in the
▪ Variation for scope changes
Compliance, Social ERP Systems
▪ Claims process Performance ▪ Include price adjustments mechanism
What does a Contract look like?
The inclusion of these Sections add to the Technical Specification and the Code of Conduct expected or required
of the Vendor
Key Contractual Clauses
Key Contractual Clauses
Suspension
❖ Company may suspend the contract to address issues related to the contractor’s breach of the contract.
❖ Company has suspension rights under the contract but no expressed suspension rights are granted to
contractor. This asymmetry is justified as it may incur significant financial losses if the contractor suspends
work that can affect Company’s operational capabilities
Termination By COMPANY
Company may terminate the contract or reduce scope if contractor breaches Business Principles, violates Anti-
Bribery Laws, applicable competition laws, or HSSE Standards, or Contractor wilfully delays or demonstrates the
intention not to continue performance of the CONTRACT
❖ Termination (or the threat of termination) is a useful remedy to remove an under-performing contractor and to
safeguard Company’s interests
❖ Rights to terminate are narrower for the contractor
❖ Contractors often ask for reciprocal termination rights
❖ A contractor should only be able to terminate for non-payment
Key Contractual Clauses
Liquidated Damages
❖ Company may claim damages if the contractor breaches a contractual obligation
❖ Liquidated damages are “pre-agreed” damages for a breach
❖ Consequences need to be clearly defined
❖ Contractors often seek liquidated damages to define and to limit risk.
❖ May seek a “no harm, no foul” qualification to the liquidated damages provisions. (Company must prove
damages and show that damages were caused by the breach.)
❖ “No harm No foul” qualifications make liquidated damages clauses nearly impossible to claim
❖ Reject such qualifications during negotiations
❖ Parties could amend the contract by agreement or use the variations process.
❖ Liquidated damages will only apply if specifically included in the contract. If liquidated damages are not specified in
the contract, should still be able to claim general damages as a fall back option.
❖ Contractors often request that liquidated damages be the sole remedy (for example, for delay) or that liquidated
damages be capped at a percentage of the contract price. That should be avoided or, if unavoidable, done with
caution.
https://www.interface-consulting.com/construction-claims-articles/no-harm-no-foul-an-equitable-view-on-liquidated-damages-for-
delay/#:~:text=This%20no%20harm%20%E2%80%93%20no%20foul,recover%20compensation%20for%20the%20delay.
Key Contractual Clauses
Knock for Knock Indemnities – risk allocation in offshore oil & Gas Contracts
Key Contractual Clauses
FORCE MAJEURE
❖ A party is relieved from its obligations under the contract to the extent that it cannot perform due to a force
majeure event. In other words, the parties agree that they will not enforce the contract if performance is
prevented by certain named events, which are generally regarded as outside the parties’ control. For example:
“Acts of God”, war, riots, natural disaster and other events beyond the control of the obligated party.
❖ Force majeure events need to be confined to an exhaustive list of specific events. Rather than adding a “catch-
all” force majeure provision (e.g. “any event beyond the reasonable control of a party”)
❖ A party is not excused from its obligations if the force majeure event results from that party’s error, negligence,
or fault, or could have been reasonably been provided for or avoided. Failure to secure funds and other
financial limitations does not constitute a force majeure event.
❖ The contractor, if affected by force majeure, is not entitled to any additional payment or compensation.
However, the scope supply schedule may need to be adjusted. Company may terminate the contract if a force
majeure event causes a delay of 90 consecutive days or 180 cumulative days.
Implied Terms
Items in the Contract document are expressed terms
❖ The more lengthy and comprehensive the contract, the less likely it is that any term will be implied
❖ Implied By Statute
➢ Laws relating to the “Sale of Goods Act”
➢ Provisions in the “Trade Practices Act”
The Contract Cycle
LEGAL CONSIDERATIONS
❖ Purchaser enters into a contract is acting for himself or as an agent for the enterprise that employs him:
❖ In the event of a disagreement, the law of contract has to determine if whether there was a contract, its terms, how a breach is
to be settled, what happens in a particular situation, questions of compensation, ratification, damages or penalties and even
the mode of dealing with the problem. It may provide for negotiation, variance, arbitration or resort to court litigation
AS4000 - 1997
Contracts from a Procurement Perspective
Contract Development Expediency is sometimes a fallacy
❖ Contract Document needs to be comprehensive ❖ Letter of Intent – generally takes the time
❖ Deliver a Clear Message pressure off and requires additional effort
➢ Contract intent ❖ Consider the life of a contract and plan for it
➢ Code of Conduct ❖ Include options to extend the contract
➢ Set outcome expectations
❖ The Contract is more than Terms & Conditions Negotiations
❖ Don’t Be Adversarial in dealing with Vendors
It takes time to negotiate contract terms
❖ Commercial terms – responsibility of CP
❖ Do not use Supplier Terms
❖ Avoid termination and litigation
❖ Check for Battle of Forms
❖ Involve a Legal partner and don’t make
❖ Do not copy and paste from a previous contract concessions if you don’t have the authority
❖ Try not to change Company’s T&Cs
Just because you have done a unit of EPM5710 doesn’t make you a Legal Eagle
Bespoke Vs Standard Forms of Contracts
• Other forms in use in Australia include the Australian Building Industry Contract (ABIC) suite promulgated jointly by
Master Builders Australia (MBA) and the Royal Australian Institute of Architects (RAIA). The major works contract is
designated ABIC MW-1 2003.
• Forms drafted from the point of view of one of the parties also continue to have wide use in the Australian industry.
For example, the Australian Department of Defence has its own suite of facilities contracts for the construction and
maintenance of its significant estate throughout the country.
• Private sector organisations, whether they be procurers of, or contractors for, construction work, likewise commonly
put into the market bespoke forms representing the terms on which they expect to do business. An example of an
industry body promulgating such a form explicitly to represent its preferred contracting strategy is the Project Contract
PC-1 1998 published by the Property Council of Australia.
Above list are just some example of Standard Forms of Contracts – there are many not listed.
• The use of internationally recognised forms is not unknown in Australia. This is especially the case where one or
more of the parties (or their advisers/project personnel) is based outside of Australia. Such forms include the
“rainbow” of forms (nicknamed to reflect the colours used on the covers of the various contracts) published by
o FIDIC (Fédération Internationale des Ingénieurs-Conseils – International Federation of Consulting Engineers),
and
o the New Engineering Contract (NEC) published by the Institution of Civil Engineers based in England
• As Australian contractors, developers, consultants and lawyers continue to win work around the world,
construction personnel are required to be familiar with local and international forms in the jurisdictions in which
they work.
• Therefore, most Australian construction professionals need at least a working knowledge of a wide range of forms
representing a spectrum of risk allocation and procurement models.
Acts and Regulations
• Building and construction contracts are formed, administered and discharged within the
boundaries of common law and statute law.
• Common law is judge-made law based on that originally developed in England, and subsequently
in Australia, over many centuries. Past legal cases.
• Statute law (legislation) is law made by a parliament or pursuant to a power given by a law made
by a parliament. Each parliament has a specific jurisdiction.
• Since (except for Commonwealth Acts) legislation is different in each Australian State or Territory
and from time to time new legislation is made and old legislation is amended or repealed, it is
beyond the scope of this course.
• An Act (of the parliament) is a law made by Parliament; a bill which has passed all three readings
in each house and has received the royal assent.
• A regulation is made by the Governor on the recommendation of a minister pursuant to a power
given in an Act.
• The Trades Practices Act 1974 is an Act of the Commonwealth Parliament of Australia.
• Main purpose of the Act was to eliminate restrictive business practices, namely price fixing, collusion and
restrictions on competition, and to provide protection to the public.
• The effect of the Act on building and construction contracts includes the area of price fixing and collusion among
contractors and subcontractors.
• The Act promotes open competition without undue restrictions and limitation.
• A most important provision of the Act is s. 52 (in Part V) which provides that: ‘A corporation shall not, in trade or
commerce, engage in conduct that is misleading or deceptive or likely to mislead or deceive’.
http://www7.austlii.edu.au/cgi-bin/viewdoc/au/legis/cth/num_act/tpa1974149/s52.html
• Section 82 of the Act provides that ‘A person who suffers loss or damage by conduct of another person that was
done in contravention of a provision of Part IV or Part V may recover the amount of the loss or damage by an
action against that other person or against any person involved in the contravention’.
http://www7.austlii.edu.au/cgi-bin/viewdoc/au/legis/cth/num_act/tpa1974149/s82.html
Clarke J 2012, Agreement, Australian Contract Law, viewed 15th June 2020, < https://www.australiancontractlaw.com/law/formation-agreement.html#offer >.
Clarke J 2013,Terms of contract, Australian Contract Law, viewed 15th June 2020 <https://www.australiancontractlaw.com/law/scope-terms.html >.
Clarke J 2018, Avoidance of contracts, Australian Contract Law, viewed 15th June 2020, < https://www.australiancontractlaw.com/contractlaw/avoidance.html>
Clarke J 2010, Discharge by frustration, Australian Contract Law, viewed 15th June 2020, < https://www.australiancontractlaw.com/law/termination-frustration.html >.
Clarke J 2018, Waltons Stores (Interstate) Ltd v Maher (Promissory Estoppel), Australian Contract Law, viewed 15th June 2020, <
https://www.australiancontractlaw.com/cases/walton.html>.
Munoz E 2020, What are the different types of implied terms?, Legal Vision, viewed 15th June 2020, <https://legalvision.com.au/different-types-of-implied-terms/>.
Bazzi A n.d., What is estoppel?, Gotocourt.com.au, viewed 15th June 2020 <https://www.gotocourt.com.au/civil-law/estoppel/>.
Masson B 2018, Introduction to AS4000, Turtons, viewed 20th June 2020, <https://www.turtons.com/blog/introduction-to-as-4000>.
Henry G 2017, 10 things you should know about AS4000, Turtons, viewed 20th June 2020, <https://www.turtons.com/blog/10-things-you-should-know-about-as-4000 >.
Korotia Y 2017, Time and material vs fixed price: which to choose for your project?, Medium, viewed 15th June 2020 < https://medium.com/@Eugeniya/time-and-
materials-vs-fixed-price-which-to-choose-for-your-project-11dc6adc758b
ANY QUESTIONS?