Professional Documents
Culture Documents
Method Statement For PEB
Method Statement For PEB
Method Statement For PEB
AURIC
SLMG BEVERAGES Ref No-AE/MS/01 ENTERPRISES
Rev:00 Date- 11-05-2022 Page 1 of 9
CONTENTS
S. No. CONTENT PAGE NUMBER REMARKS
01 Purpose 02
02 Scope 02
03 Reference 02
04 Resource or Instrument 02
05 Responsibility 03
06 Procedure 3-8
07 EHS 8-9
2.Scope:
Unloading and loading of PEB structure.
Stacking and Shifting of PEB material.
Structure Erection (Column, Rafter, Girts, Purlin, Sag rods, Bracings,
Crane Beam).
Roof Sheet fixing with all accessories.
Wall sheet fixing with all accessories.
3.Reference:
As per Construction drawing.
4. Resources or Instruments:
Manpower:
Rigger
Fitter
Helper
Machinery:
F-15/ Crane
Rope Ladder
Man Basket
Web slings
D shackles
Wire Sling
Tag Line
5. RESPONSIBILITIES:
3. Store officer –
Provide only good/working condition tools and tackles to workmen and
Keeping all records.
7. Procedure:
7.1 For Unloading and Loading: -
All Necessary documents to be provided for all machineries.
Before starting the work, work permit will be approved.
Tool Box Talk (TBT) will be conducted to workers & operators before
starting the work.
Lifting tools and tackles free from any defect and having valid TPI
certification from competent person.
Ground will have checked for flatness and compactness (clearance taken
by civil agencies) before positioning of the F-15/Hydra/Crane and trailer.
First of all, the trailer will be well positioned near to pre-decided unloading
area location.
Work area to be barricade to prevent any authorized entry.
Rigger will put web sling/wire sling to the PEB member and hook of
F15/Hydra/Crane and tied tag line both end of structure. Task supervisor
will make sure that sling is adequate according to load.
Now rigger will give signal to the Crane /Hydra/F15 operator and will
make sure to unload it safely.
Task supervisor will make sure that nobody will be there nearby to the
suspended weight.
PEB member will be placed in proper manner on wooden slippers. Now
rigger will put off the slings.
Height of materials shall not be more than 1.8 meters.
Same procedure will continue till unload the vehicle.
After unloading material area shall be barricade.
M/s SLMG BEVERAGES
AURIC
SLMG BEVERAGES Ref No-AE/MS/01 ENTERPRISES
Rev:00 Date- 11-05-2022 Page 4 of 9
After tightening of the member nut and bolt, two persons reached at top
of the member with FBSH by Rope ladder/Man Basket for D-slinging
Continue the same procedure for next column erection.
Task supervisor will make sure that nobody will be there nearby to the
suspended weight.
After erection of 2 nos of column bracing (by F-15/ Crane) and girts will
be fix with help of pp rope and rope pulley.
Rope pulley will fix at top of both columns with web sling, PP rope or D-
shackle or with wire rope with U clamp.
Rope ladder/man basket will be used for approaching at height.
Ensure that all lifting tools tackles should be inspect.
Both ends girt will tied with pp rope and hook and 2 people will pull the
rope as girts will reach at position and nut bolting will be done.
After fixing of all girts next column will erect and fix the girts, same
procedure will follow for column and girts erection.
Only authorized operator shall be will operate the equipment.
F-15/Crane will check as per checklist on periodically.
As per planned of erection rafter/structure will assemble.
First part of rafter/beam will keep on wooden packing at near erection
area.
Second part mark of rafter/beam will join together with help of f-15.
Same procedure will apply for next joint.
All nut bolt should be tight using torqueing method or 1/3 rd method.
Nut bolt tightening will have done at one side.
After completion of one side tightening rafter will move another side for
balance nut bolt tightening.
Same procedure will follow for next assembly.
Work area must be checked for ground compaction and level (Clearance
taken from civil agencies) before f-15/crane positioning.
If required two f-15 will use for lifting of rafter/beam as per length and
weight of rafter.
Make sure life line should be fixed before lifting of rafter.
M/s SLMG BEVERAGES
AURIC
SLMG BEVERAGES Ref No-AE/MS/01 ENTERPRISES
Rev:00 Date- 11-05-2022 Page 6 of 9
Rigger will put wire rope to rafter and crane hook. Make sure that proper
packing must be provided.
First of all, Intermediate and Side wall column should be erected before
lifting of rafter.
Make sure all temporary guy rope arrangement should be done before
lifting.
Task supervisor will make sure that sling is adequate according to load
and length.
Rigger/Signalman will give signal to the f-15/crane operator.
Lift the rafter slowly at one-meter height and check the undulation and lift
the rafter slowly at top of column.
Task supervisor must be present during lifting activity.
Tag line must be tied at all corners of rafter to ensure proper controlling of
load.
Ensure that no body stand under suspended load.
When the rafter reaches at required height, 2-3 persons will reach by rope
ladder/man basket to ensure bolting of adequate sizes (as per drawing)
between rafter & Column.
Make sure all connection bolts should to be tightened as per torque
requirement.
After connection of all joints, person will sit on rafter and anchor to FBSH
with fixed life line pp rope for fixing of purlin.
Purlin will lift by manually with help of rope pulley or lift by f-15/crane.
After support of structure sling will remove from rafter.
Same procedure will be followed for next erection of rafter.
Sag rod/Lateral Bracing will fix with help of sag rod platform.
7.3 ROOF SHEET INSTALLATION: -
Scaffolding will use as roof access for ascending and descending at roof.
Ensure that proper support shall provide to roof access.
Before starting of roof sheet safety net/bird mesh will tie below of
structure from starting of 2 bays.
Insulation/ Bird Mesh will shift by rope pulley.
M/s SLMG BEVERAGES
AURIC
SLMG BEVERAGES Ref No-AE/MS/01 ENTERPRISES
Rev:00 Date- 11-05-2022 Page 7 of 9
8. EHS:
Check unloading area & proper access for vehicle movements.
Adequate PPEs i.e. Safety helmet, safety shoes, reflective jacket, Full
body Harness, safety goggle & hand gloves
Work will be carried out under proper supervision and approved Permit to
Work.
Life line should be tied as required.