Professional Documents
Culture Documents
Smart Net
Smart Net
FOR ACQUIRING
ANCILLARY SERVICES
FROM DISTRIBUTION GRIDS
MAY 2019
THE SMARTNET PROJECT FINAL RESULTS
Key Findings . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
Executive Summary . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
ICT Requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 22
Regulatory Analysis . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 31
The legislative package proposed by the SmartNet analyses five different coordination
European Commission in November 2016, schemes between TSO and DSO and different
nicknamed the Clean Energy Package, architectures for the real-time ancillary
assigns a role to Distribution System Operators services markets with reference to three
(DSOs) for local congestion management countries: Italy, Denmark and Spain. For
but not for balancing, whose management each country, the model needed to perform
would remain in the hands of the Transmission significant simulations encompasses nodal
System Operators (TSOs)1. However, such a representation of the transmission network
sharp decoupling risks to lead to inefficient and of the distribution networks (some of
system operation. them represented in detail till medium voltage,
some others in a more synthetic way), detailed
All these issues are addressed by the SmartNet representation of the different resources
European research project (http://smartnet- providing bids for system flexibility (both
project.eu/), which aims at comparing different connected to transmission and distribution),
TSO-DSO interaction schemes and different detailed representation of the aggregation
real-time market architectures with the goal process and of the real-time ancillary services
of finding out which would deliver the best market.
compromise between costs and benefits for
the system. The objective is to develop an ad SmartNet considers five TSO-DSO
hoc simulation platform which models all three coordination schemes characterized by
layers (physical network, market and bidding), different roles and market architectures:
analysing three national cases (Italy, Denmark,
Spain). Subsequently, this simulation platform • centralized AS market model (CS A):
will be scaled to a full replica lab, where the TSO contracts services directly from DER.
performance of real controller devices and No congestion management is carried out
ICT will be tested. for distribution grids;
The consortium, under technical and • local AS market model (CS B): DSO
administrative management by RSE2, manages a local congestion market.
consists of 22 partners from 9 European Unused resources are transferred to the
Countries, including TSOs (Energinet.dk, AS market managed by TSO (procuring
TERNA), DSO (ENDESA, Nyfors/SE/Evonet, balancing and congestion management);
Edyna), manufacturers (SELTA, SIEMENS),
and telecommunication companies • shared balancing Responsibility Model
(VODAFONE). (CS C): TSO transfers to DSO balancing
responsibility for distribution grid. DSO
1 EC (2016) Proposal for a DIRECTIVE OF THE EUROPEAN PARLIAMENT AND OF THE COUNCIL on
common rules for the internal market in electricity – Art.32.
The same platform is also implemented in The last two indicators proved negligible wrt
a laboratory in order to test real network the first two. So, the comparison between the
equipment on the developed simulation different coordination schemes can be carried
scenarios (hardware-in-the-loop). out just by taking into account mFRR and
aFRR costs.
At the same time, big transformations are collector of services for the whole system, in
also affecting distribution and its interactions coordination with the adjoining TSO.
with the transmission system as an effect of
the deployment of distributed generation, A strict real-time coordination will be
local storage and flexible loads. In the future, needed between the different actors that are
distribution networks will inject a growing involved in the provision of ancillary services,
amount of energy into the transmission particularly if connected to secondary and
system, and these electricity volumes could tertiary regulation.
be linked to local storage and provide both
local compensation and services for the entire Sets of bids aggregating availability coming
system. Beyond local services for distribution from distributed generation, especially if
grids (voltage regulation, congestion integrated with local storage (VPPs), as well
management), resource located in distribution as from flexible load, could be presented to
could be helpful for providing reserve provision the trans-national Market Operator allowing a
for the entire system through the connection higher market liquidity and a better availability
points to the transmission grids. of dispatching solutions on the territory. ICT
is going to be key also at this level in order to
This would bring a technological advancement ensure a seamless integration of these bids
of distribution system and the necessity coming from distribution within the trans-
to manage scattered bids coming from national ancillary services market and an
distributed generation and active loads. integration with the control carried out by the
ICT should ensure a seamless integration of DSOs of the dispatching in their relevant areas.
these bids within the trans-national ancillary
services market and the control carried out by The current scenario opens several questions
the DSOs of the dispatching in their relevant that research should tackle in order to optimize
areas. the coordination between TSOs and DSOs
in managing the exchange of information for
A delicate issue in this concern is the interface monitoring and for the acquisition of ancillary
between TSOs and DSOs which is a crucial services both at the domestic level and in the
factor to ensure an overall efficiency target. pan-European context.
On one side, the DSO network would have
to retrieve resources for local services (e.g. The main aspects SmartNet is to investigate
voltage support, congestion management) are the following:
and on the other, it should function as a
Cross-border ICT
exchange of
balancing services
ICT ICT
Bids
G G L
Aggregators
• Which ancillary services could be provided Different TSO-DSO interaction modalities are
from distribution to the whole system (via compared on the basis of national key cases.
Transmission)?
Physical pilots are defined for the same
• Which optimized modalities could be national cases (Italy, Denmark, and Spain)
adopted for managing the network at the in order to analyze issues regarding the
TSO-DSO interface and what monitoring monitoring of distribution parameters from
and control signals could be exchanged to transmission and analyze modalities for the
carry out a coordinated action? acquisition of ancillary services from specific
resources located in distribution systems
• How the architectures of the real time (indoor swimming pools and radio base
markets (in particular the balancing stations of a telecommunication company).
markets) could be consequently revised?
The significant amount of DER, mainly and distribution level, without extensive
connected at the distribution grid, results involvement of the DSO. There is no separate
in a higher need for flexibility services for local market. The TSO is responsible for the
system operators (TSOs and DSOs) and operation of its own market for ancillary
other commercial market parties (i.e. balance services. The TSO does not take DSO
responsible parties (BRPs)). The increase constraints actively into account. A separate
of DER connected at the distribution grid process (system prequalification) could be
provides an additional opportunity for system installed to guarantee that the activation of
operators to use these resources for services resources from the distribution grid by the
such as frequency control, voltage control TSO does not cause additional constraints
and congestion management, both at the at the DSO-grid (e.g. congestion). The DSO
distribution and transmission grid. is not procuring local flexibilities in real-time
or near to real-time. This scheme limits the
Today, resources from the distribution grid involvement of the DSO to a possible role in
are starting to participate to the TSO ancillary the system prequalification process. To note
services (AS) markets which enforces the need that in exceptional cases, the DSO might
for increased cooperation between system want to include DSO grid constraints in the
operators. Within Smartnet, five coordination TSO market clearing process. Consequently,
schemes are proposed that present different the DSO will need to provide the necessary
ways of organizing the coordination between data to the TSO or the TSO should have full
system operators: the Centralized AS market observability of the DSO-grid.
model, the Local AS market model, the
Shared Balancing Responsibility model, the In the Local AS market model, the DSO
Common TSO-DSO market model and the organizes a separate local market for resources
Integrated Flexibility Market model. Each connected at the DSO-grid. The DSO is the
coordination scheme is characterized by operator of a local market for flexibility, clears
a specific set of roles, taken up by system the market and selects the necessary bids
operators, and a detailed market design. for local use. The DSO has priority to use the
Each coordination scheme will determine flexible resources from the local grid. The DSO
the operational processes and information aggregates and transfers the remaining bids
exchanges between system operators related to the TSO-market, after all local constraints
to prequalification, procurement, activation are solved, while ensuring that only bids
and settlement of flexibility-based services respecting the DSO grid constraints can take
that impact both transmission and distribution part in the AS market. The TSO is responsible
system level. for the operation of its own market for ancillary
services, where both resources from the
In the Centralized AS market model, the TSO transmission grid and resources from the
operates a market for ancillary services for distribution grid (after aggregation by the
both resources connected at transmission DSO) can take part. The Local AS market
Flexible resource @ HV
SO/MO
Flexible resource @ HV (Flexibility owner)
(TSO)
SO/MO (Flexibility owner)
(TSO)
Agregator Agregator
(CMP) (CMP)
DER @ MV
DER @ MV (DER owner)
(DER owner)
DER @ LV
SO DER @ LV SO/MO
(DER owner)
(DSO) (DER owner) (DSO)
SO/MO
Flexible resource @ HV (TSO) Flexible resource @ HV
SO/MO
(Flexibility owner) (Flexibility owner)
(TSO)
Agregator
(CMP)
DER @ LV DER @ LV
SO/MO (DER owner) (DER owner)
(DSO)
Role
Flexible resource @ HV (Actor)
SO (Flexibility owner)
(TSO)
Centralized market
Local market
Coordinated market
MO Pre-defined profile
(ISO) exchange
Agregator DER @ MV Agregation
(CMP) (DER owner)
Market bids
Pre-qualification
SO DER @ LV
(DSO) (DER owner)
Allocation principle
Market organization
Coordination scheme Role of the DSO of flexibility from the
(market operator)
distribution grid
Limited to possible
Centralized AS market
process of Common market (TSO) Priority for the TSO
model
prequalification
Organization of local
market
Buyer of flexibility
for local congestion Central market (TSO)
Local AS market model Priority for the DSO
management Local market (DSO)
Aggregation of
resources to central
market
Organization of local
market
Shared Balancing Buyer of flexibility for Central market (TSO) Exclusive use for the
Responsibility model local congestion Local market (DSO) DSO
management and
balancing
Organization of Common market (TSO
flexibility market in and DSO)
Common TSO-DSO AS cooperation with TSO Minimization of total
market model Central market (TSO) costs of TSO and DSO
Buyer of flexibility
for local congestion Local market (DSO)
management
Source: Gerard, H., Rivero Puente, E.I., Six, D., 2018. Coordination between transmission and distributio system operators
in the electricity sector: A conceptual framework. Utilities Policy 50, 40–48.
be seen as a duplication of the same market and DSOs) and the way they currently interact.
architecture as well. Also the Local AS market In addition, the implementation of certain
model and the Common TSO-DSO AS market coordination schemes will have an impact on
model (decentralized variant) share a common other markets, such as the Intraday markets.
market architecture. Dependent on the services offered in the AS
market, and compared to the Intraday markets
The feasibility of the implementation of each (IDM), these markets might be able to co-exist
coordination scheme is very dependent upon or alternatively, may need to be integrated.
the regulatory framework. The Centralized Although TSO-DSO coordination could be
AS market model is the most in line with organized on a country level, it is important to
current regulations. The other coordination integrate national TSO-DSO coordination set-
schemes would require considerable changes ups within the process of EU harmonization
with respect to roles and responsibilities of and integration.
TSOs and DSOs. The implementation of a
coordination scheme is also influenced by the
national organization of TSOs and DSOs, e.g.
the number of system operators (both TSOs
Performance
Domain Coordination scheme
Criteria
Shared Common Integrated
Centralized Local AS
Balancing TSO-DSO Flexibility
AS market market
Responsibility AS market market
model model
model model model
Adequacy
of existing
Interaction
communication High
between
channels, Medium Medium Low Medium
system
including the
operators
use of common
data
Respecting
distribution grid Low High High High High
constraints
Use of resources
Grid from the
High Medium Low High High
operation distribution grid
by the TSO
Recognition of
the evolving role Low High High High High
of the DSO
Possibility to
lower market High Low Low Medium Medium
operation costs
Market
Liquidity of the
operation Medium Low Low Medium High
market
Economies of
Medium Low Low High High
scale
Source: Gerard, H., Rivero Puente, E.I., Six, D., 2018. Coordination between transmission and distribution system operators
in the electricity sector: A conceptual framework. Utilities Policy 50, 40–48.
Figure 5 - Market aims at activating services for balancing and congestion (both transmission and distribution)
purposes
Classic AC Nonconvex exact No exact medium medium medium hard high* low local IP
DistFlow SOCP exact relax Yes exact easy hard hard hard high high global IP
DistFlow
LP IP, simplex
Ben-Tal
Simplified
LP approx.. No neglected hard easy easy easy medium high IP, simplex
DisfFlow
Linearized
LP approx.. No neglected hard hard hard easy low high IP, simplex
‘DC’
Properties of proposed formulations for radial grids (* Nonlinear solvers usually have good tractability for power system
optimization with only continuous variables, but tractability is low for problems including integer variables).
services (AS) market, while reducing the similarities, simplifies the bidding system. As
amount of the passed-on data. An aggregator the market clearing mechanism is able to cope
is also in charge of the disaggregation process, with multiple bid types, belonging to different
leading to the resources activation, after the aggregation models and originating from the
market clearing has taken place. Figure 10 same aggregator, the simplest approach is for
shows the aggregator’s input and output, i.e. the aggregator to allow all five aggregation-
the information flow between the aggregator, type-specific categories (see Figure 11),
individual DERs and the market. to generate bids for their own aggregated
devices. That is to say, a single aggregator
Different aggregation approaches can be can use several aggregation models for
used for bidding in the electricity market, providing its bids. By doing so, every bid
each of them having certain advantages. that is accepted by the market can then be
When considering near real-time AS markets, assigned to the corresponding device-type-
complex aggregation and disaggregation specific disaggregation algorithm, which is
processes must be avoided since they tend best equipped for optimally distributing the
to add latency to both the bidding to the allocated flexibility over its individual devices.
market and to the response to the market The reason behind this approach is the fact
clearing. Hence, the aggregator in SmartNet, that it would not be convenient to build an
uses several technology specific aggregation overarching aggregation model, as it would
models, aimed at separate DER categories, inevitably make the disaggregation complex.
in order to take into account the physical Despite the aforementioned advantages of
constraints of the devices being aggregated, the aggregation approach taken here, its
while enabling a fast, straightforward, drawback is the higher number of bids going
aggregation/disaggregation procedure to the market, since five relatively simpler
(illustrated in the figure 10). Due to this reason aggregation models are used.
only the DERs that are reasonably similar
in terms of their specific core features are Supply and demand are satisfied in a series
grouped together in the same aggregation of consecutive markets. The sequence of
model. markets, comprised of the day-ahead, the
intraday and the AS market, represents a string
The grouping of DERs categories, done of opportunities, for the aggregator, to valorize
according to the individual models’ constraints DERs’ flexibility. The aggregator in SmartNet
forms a vision of the expected clearing price In other words, MDC represents an artificial
for flexibility in the future, enabling it to set cost, incorporated in the existing flexibility
the price for the limited number of activations cost3, that makes the aggregator indifferent
available. Hence, the aggregator takes into between an immediate activation and the one
consideration the possible future market in the future at a potentially better profit.
related variables, as well as its own forecast
error. The market discomfort cost (MDC)
represents a possible additional profit of a
future activation (see Figure 12). This is to say
that the MDC makes the aggregator refrain
from offering its flexibility, in the present
market, at a purely technical cost, when
there is an opportunity to earn more in the
near future. If a bid that considers MDC is
accepted, the additional revenue from MDC
should compensate for the opportunity cost
received from activation in the nearby future.
3 A comprehensive explanation, with equations, can be found in deliverables D2.1 and D2.2.
The challenge is to adequately define and enhances the SGAM approach by embedding
identify ICT requirements for the future energy communication and security requirements in
systems and include them in the parallel each SGAM layer. As a result, ICT requirements
development of communication and grid are specified in business, function, information,
system components. This requires increased communications, and component layers. To
dialogue between energy and communication make the process well adoptable, IEC 62559’s
system developers and providers. design template and ELECTRA project’s use
case design methodologies were utilised.
Another trend is towards more realistic lab They provided structured guidelines for
simulations where SW simulators and HW preparing use case descriptions as well as
components are interconnected (Hardware- mapping business and system functionalities
in-the-Loop (HIL) simulation). As larger parts into SGAM layers. The developed process
of the grid are included in the simulations, the is incremental to enforce close interaction
modelling of communication links becomes between energy and communications system
more important. The process of converting providers and developers. Requirements
field measurements into QoS profiles is for communications tend to change, so
compelling for both lab environments a parametrised architecture model was
and simulation tools. It would give new implemented in SmartNet using Architect
opportunities to test communications and Enterprise with SGAM toolbox that offers
smart energy components already in the a practical tool to validate architecture
prototype stage, which helps to reduce design and assess effects of changing ICT
components and services’ time-to-market, requirements in cases of centralised, local,
time-to-revenue, and deployment costs. shared, common TSO-DSO, and integrated
market models. To support the process, a
Process for capturing ICT requirements conceptual model depicted in Figure 13 was
used for the dialogue between ICT and energy
As a starting point, the Smart Grid Architecture personnel to capture the main data exchange
Model (SGAM) has been a good tool in energy operations and their requirements in different
domain, since it offers a framework for the TSO-DSO coordination schemes.
validation of smart grid use cases and their
support by standards. However, handling of The model presents actors, system
ICT requirements and market designs is not components, and services. In the figure, grey
included in the SGAM model, which may result rounded boxes present core business actors/
in inadequate system designs. Therefore, there roles in different coordination schemes. The
was an evident need for an enhanced SGAM stakeholders can play multiple business actor
model that also includes communication roles. For example, an aggregator can do both
requirements to help interaction between technical aggregation and energy trading. The
energy and communications domains to Market Operator (MO) role can be played by
detect and resolve potential bottlenecks in various stakeholders depending on the market
the future energy systems. scenario: central TSO (market), DSO (local),
TSO-DSO (shared), or IMO (independent).
SmartNet’s ICT requirements capturing
process is an extension to the SGAM Blue boxes represent the main system
approach. The developed analysis process components a.k.a. system actors or entities
Business Actors
Ancillary Services Energy trading and
Information Exchange portfolio management
Frequency control
TSO Day-ahead market CMP
Trading System Congestion management Trading System
High voltage Intraday market
Sub-station
EMS-SCADA Voltage control
Real-time market EMS-SCADA
Figure 13 - A concept model for identifying communication links and their requirements
used by business actors. Trading system (TS) energy and telecom domains to strengthen
is devoted to exchange information with the their collaboration already in the design phase.
market management system, e.g. schedules The process has already been exploited in
for prequalification, procurement, or activation national pilot projects in Finland, so it has
of ancillary services. DMS/EMS-SCADA proven its applicability also to support the
is considered here as the system used for design of smaller systems and system parts
network monitoring and control operations. targeted to e.g. remote monitoring, control, or
Respectively, Market management system protection in medium voltage networks.
(MMS) is dedicated for running market
processes (by the TSO, DSO, or IMO) and to Communication QoS profiles
establish a link between the market operator for combined lab and simulation
and stakeholders. Connecting blue lines
represent external data exchange links between
environment
system components. Thinner lines in the figure
The exploitation of new wireless technologies
are presenting internal communication links.
e.g. 5G is anticipated as the smart remote
The model was used for analysing the system
monitoring and control are extended to
operations from an energy market point of
distant entities in the power grid. 5G cellular
view, but it can be extended to remote control
technology is making a significant advance
and protection. Green boxes represent core
in the combination of latency reduction and
ancillary services including e.g. frequency and
reliability enhancement. This makes 5G an
voltage control, and congestion management.
alternative to replace fixed cable connections.
The pictures in the middle represent the
Electricity distribution has been one of the
grid infrastructure and distributed energy
major use cases for ultra-reliable low-latency
resources, from high-voltage down to low-
communications (URLLC). Until now, mobile
voltage grid, which help mapping the energy
devices have offered connectivity for people,
market events to the physical grid entities.
but 5G is aiming to make a big difference in
offering better connectivity for machines.
For exploiting SmartNet results, the ICT
requirements capturing process and the
SmartNet’s way to generate QoS (Quality of
respective specification templates are
Service) profiles from field measurements is a
promoted to industrial parties operating in
new approach to include the effects of wireless
=
Other
Aggregators ~
Figure 16 - Communication Network Effects on the Interactions of the SCADA/DMS and the PPC
• Italy and Spain are expected to face Figure 18 - Scenario characteristics of the three
a significant increase of photovoltaic simulated regions
ICT costs comparison among TSO DSO coordination schemes and country
This will require significant investments in revocation of the bids accepted locally.
monitoring and control systems, as well as
higher level of expertise on DSO side (which can Furthermore, the local and global markets
especially concern smaller DSO). Additionally, could be implemented with different clearing
the so called “fit-and-forget” reinforcement frequencies, with the possibility that a bid which
policy (oversizing of networks in order not to is offered both at local and at transmission
have to deal with network “problems”, mainly level is accepted twice. To avoid such situation
congestions) which is, currently, often the it is recommended that the setup of the two
basis of DN “operation” must be overtaken. markets, in particular the setup of the bidding
These policies, in fact, may lead some DSOs to procedure, should be carefully coordinated by
develop a resistance to consider flexibility as a TSO and DSOs, e.g. by means of a common
value. Also, some DSOs may underestimate the shared database of resources without time
needs to invest in implementing monitoring correlation.
and control system, mainly during the first
years, in which the DN monitoring systems Local markets could also be affected by scarcity
have to be deployed, as costs would probably of liquidity, with the following two major
overcome benefits. problems:
Long term planning should also be extended • if only a small number of resources are
to cover the whole DN as it already happens reliable or at the DSO disposal, those
for TN. This implies that, apart from all the resources could have potential to exercise
technological improvement needed, DSOs market power;
should also be able to extend their expertise. The
effort needed to achieve this is considerable, • the DSO may not be able to solve
even in the case of the sharing of the market congestion in the DN by means of the
operation responsibilities with TSOs. market and thus be forced to activate
unwanted measures, thus increasing the
If local congestion management markets are costs for the System.
implemented, it will require a good level of
coordination between TSOs and DSOs. Any The very high prices that may occur as result
level of separation between Transmission of illiquidity in the AS market is expected to
and Distribution that may be introduced at encourage investments in new resources in the
the market level with, in the extreme case, local networks, but the consequent boom-and-
balancing responsibilities also given to the bust price cycles could not be tolerable for the
DSOs, could potentially decrease the overall society, bringing the necessity for the regulator
economic efficiency, since the knowledge of to intervene and filter (part of the) price signals.
the global system operation and condition may
not be available to some extent (for instance: Introduction of the local market may raise
counteraction in TN to activation in DN; the important questions of their operation,
rebalancing in DN subsequent to congestion including operation of network areas with
management that increases global imbalance). multiple DSOs, which vary in size and resources
This issue should be tackled at a regulatory availability. Small DSOs may avoid scarcity of
level, e.g. by introducing a mechanism of liquidity by grouping together in a single and
Therefore, the deployment of technological all, each of them focuses on different parts of
pilots is of paramount importance for testing the TSO-DSO coordination value chain, so
and demonstrating the technical feasibility of that one of them looks at the communication
those concepts. requirements between the TSO and the DSO,
another one investigates the issues arising from
Additionally, the results of the simulations the broadcasting of unidirectional price signals
and the CBA described earlier focus on the from the aggregator to the DER and the third
economic aspects of the mid-term scenarios one studies the capability of the DSO to run a
created within the project. However, there may local flexibility market. Furthermore, different
be some implementation difficulties which potential TSO-DSO coordination schemes
cannot be anticipated by the scenario analysis have been demonstrated, so that issues arising
and the CBA, but which can be identified by from each of them can be identified. Moreover,
implementing real-life technological pilots. different types of DER have been considered,
so that their flexibilities can be better assessed
The three technological pilots have been and the advantages and disadvantages for real-
deployed within SmartNet, with a holistic view, life implementation can be properly identified
so that they complement each other. First of and addressed.
Figure 26 - Trend of the active power at the HV/MV primary substation during 2017
require the same contribution to each power by Siemens and Selta adopting different
plant’s DCS, expressed as the percentage of the approaches and algorithms, are:
generator capability, and sends the setpoint.
• The aggregation function, which allows
The tests carried out to evaluate the coordinated for exchanging real-time data of the active
voltage regulation showed the technical and reactive power at the distribution level
feasibility of controlling the reactive power with the TSO’s SCADA. The MV level is
exchange of power plants, despite the effect represented as equivalent aggregations,
on the voltage of the transmission grid and the differentiated by type of source (solar
performance of the power plants controller are resources, hydro resources and load),
not the same of the service provided by big- connected at the HV/MV substation
size programmable power plants connected at (Figure 26). The aggregation is updated
transmission grid. In any case, the system allows every 20 seconds.
the TSO to coordinate the reactive exchange
of these power plants with the area needs, in • The estimation module, to estimate
order to avoid the reactive loop that can be the active power of unmonitored plants
established between the groups and, thus, through algorithms that elaborate and
wasting reactive resources. The potential of the combine available data (e.g. weather data,
HVRS is the opportunity to control different neighbouring plants’ measurements,
power plants and parks of different technology “near real-time” data registered by smart
in a coordinated way, by sending a unique energy meters, historical profiles, etc.). This
setpoint. functionality has been tested offline in order
to evaluate the accuracy of the algorithm
Regarding the MV part of the project, the developed and, in this application, almost
main functionalities of the MVRS, developed all the power plants’ production and the
net power exchange at the interconnection a unique setpoint and provides a smart
points with subtended DSOs have been splitting of reactive power command
measured to guarantee the required among the controlled plants according to
accuracy in network monitoring, so as to single DERs capability.
be able to test ancillary services. The offline
analysis provided the comparison between In case of constraints violation in the distribution
the estimation and the measurement ant grid the priority of the device is to solve the
it highlighted the dependence on the type violation, making the generators unavailable
of source: on the one hand, it is necessary for the voltage regulation.
to measure the 60 % of the installed hydro
power and to choose the right power The tests showed that activation of reactive
plants to monitor, as well as to have access sources at the distribution grid leads to the
to historical data, to have a good accuracy control of the voltage rise effect along the
of the estimation, while, on the other, the feeders of the DSO grid, usually subjected to
estimation of solar production based on overvoltages, in order to maintain the voltage
weather data can achieve quite accurate within required limits. From the point of view
results. of the management of the transmission grid,
the field tests carried out have shown the
• The calculation of the capability of the technical feasibility of controlling the reactive
virtual power plant composed by the power exchange of the power plants, although
embedded generation in order to allow the behaviour of power plants connected at
the TSO to know the available active and transmission grid is more prevalent than the
reactive power margin on DSO network contribution of distributed generation. Figure
considering the capability of each power 28 shows the trend of the voltage at the HV
plant and the operational limits of the busbar during the tests: voltage reacts to the
distribution grid. setpoints in the two feeders (red and green),
although other elements of the grid may also
• The voltage regulation of HV busbar of the affect the voltage, as happened at 15:55, when
Primary Substation through the embedded a decreasing of voltage was independent of any
generation connected at the transformers MV regulation.
of the substation. As shown in Figure 27,
through the computation of the virtual
capability, the MVRS provides to the TSO an
instrument to know the reactive availability
in the distribution grid, considering the
availability of each generator and taking
into account the DSO’s grid constraints.
The TSO can control the reactive power of
the embedded generators to regulate the
HV busbar voltage considering them as a Figure 29 - Diagram of operation of voltage
unique power plant: the MVRS receives regulation functionality of MVRS
At the moment, the involvement of embedded The tests provided promising results, with the
generation in this service does not provide activation of 7 power plants and a variation of
evident advantages in the management of the production of more than 6 MW. Regarding
the HV grid because the voltage trend follows the quality of the regulation, the dynamic
the performance of the HV power plants. response did not comply with the technical
Nevertheless, the coordination of the reactive requirements of the service, due to delays in the
power exchange of these power plants can communication and the inaccurate regulation
contribute to avoid wasting of sources that of power plant controller. Moreover, the tests
provide reactive power regulation. Moreover, it is showed that the reliability and the quality of
very likely to have a big importance in the future the regulation of the virtual power plant at the
as the contribution of renewables increases. interconnection point does not depend solely
on the single power plant performance, but the
• The frequency/power regulation (aFRR), trend is influenced by other elements of the grid,
through the generators connected at uncontrolled and unforeseeable. An example
the MV side of the transformers of the is reported in Figure 30, where the blue line
substation and involved in the pilot. It
consists of providing a modulation of the
active power of the embedded generation
according to a signal level sent by Terna to
the control system every 4 seconds. The
MVRS calculates and sends to the TSO the
program value and the half-band available
for the regulation, considering all the power
plants available for the service. The tests
were performed by sending a level signal
with a ramp profile, composed by a ramp-
down to reach the minimum production
made available and a ramp-up to return to Figure 31 - Ramp of the level signal used for the f/P
the initial program value (Figure 29). regulation tests
is the expected contribution calculated from improve the performance and the reliability
the percentage setpoint sent by Terna and the of the behavior of renewable energy sources.
red line is the real contribution of embedded Moreover, the tests highlighted the importance
generation calculated by subtracting an of a continuous monitoring of the sources and of
offset value to better appreciate the trend. In the actuation of the services so as to guarantee
the lower part of the graph, the trend of the the efficiency, the safety, the adequacy and the
dynamic error has been reported in comparison quality of the dispatching.
with the limit value used for acceptance to the
secondary frequency control service (10%). Pilot B: Common TSO-DSO market
The error increases with increasing response with pool flexibility
inaccuracy and delay.
Summer houses with indoor swimming pools
In general, an important value of the pilot is consume substantial amounts of electricity
the results of tests and the detection of the for heating water and humidity control. The
aspects to be improved in order to integrate the electricity demand from summer houses is
renewable energy sources in the electrical grid. particularly flexible. For example, swimming
It is clear the need of further experimentations, pools have a large thermal capacity and, thus, the
some of which are already in place, in order to load to heat pool water can be disconnected or
out both prices and price forecasts. Such requirement specification. As can be seen in
communication intends to create a balanced Figure 32, the SN-10 is a hardware component
situation for the relevant market operator (MO) inside the system installed at the summer
for the next hours. The technical aggregator houses. The system also includes a 5V/12V DC
then receives two rates; one is the forecasted power supply, a 230V switch and sensors for
price, and the other is the actual price. In temperature measurements. The SN-10 also
addition, it also collects weather forecasts has an interface and access to the electricity
and booking information, to calculate the meter in the summer house to provide the
optimal set points for the thermostats of all total amount of electricity consumption in the
the summer houses. Measurements from the property to the controller and forecast model.
summer houses are then collected and used to
feed price-responsiveness information in the The actuators, labeled as ACT1 and ACT2 in
flexibility model. Figure 33, are controllable thermostats, which
open or close depending on a Pulse Modulated
The implementation of the Pilot has been made Signal (24VDC) from the SN-10 controller.
in a step-wise manner. The laboratory tests, the Water temperature is measured for the pool
first demonstrative implementations which water going in and out of the pool and the air
were completed in late 2016, were carried out temperature sensor measures the heat from
by using a water tank as a small representation the pool room. The pool pump can be switched
of a swimming pool installed in Eurisco’s lab. off during high-energy periods, but only for
The tank had sensors and actuators connected a limited time due to constraints in the water
to it and was connected to ENFOR’s platform cleaning process. The power consumption is
for the remote-control purposes. Upon measured with an internal electricity meter
completing the lab experiments, a full field-test (sub-meter) and with the household revenue
was conducted on selected summer houses meter.
during 2017 and 2018. The selection has been
based on the summer house characteristics, The SN-10 controller is an internet-of-things
the stability of their communication network (IoT) unit, which is connected to the internet
and their booking status. and can collect the measurements and send
the controlling signals received from the smart
ICT deployment and digital communication controller. The main part in the controller is
have been pivotal in this pilot to ensure a “Particle Electron” (http://www.particle.io),
reliability of the service and for models and which is connected to the internet via a 2G/3G
the controller to provide accurate output. To communication. Every 5 minutes, the SN-10
achieve a reliable communication, an SN 10 sends data to a cloud server, and then relays to
controller has been designed for this pilot and the data management system (DMS). Control
installed in the selected summer houses. These signals are calculated and sent to the SN-10
controllers were used as data communication unit on a 5-minute basis. The control signal is
interfaces from the Technical Aggregator to a temperature set-point, with which the SN-10
the summer houses. This device was made controller will regulate the water temperature.
specially for the SmartNet project, because no If the SN-10 is installed with an electrical
existing commercial products could meet the boiler, it will activate the relay when heating is
needed and deactivate it when the set-point The architecture of the Danish Pilot has been
is reached. In order to prevent fast switches, a based on the current situation in Denmark (in
1-degree Celsius hysteresis is used. If the SN- terms of DER penetration and uniform taxation
10 is installed in a house with a central heating scheme). The Pilot assessed to what extent
system, a thermal actuator is used instead of flexible summer houses could provide ancillary
the relay. services as balancing services and voltage
regulation. The control models and algorithms
An estimated flexibility function can be of the pilot were drawn from the models devised
seen in Figure 34 . This flexibility function is in various contributions in the SmartNet project.
estimated during the trial of the pilot when Danish Pilot benefited from utilising Smart-
the swimming pools were operating according Energy Operating System (SE-OS) concept,
to a penalty signal based on CO2-intensity in which is a framework for implementing energy
the electricity mix. It is seen that the response flexible solutions consisting of top-down, one-
to an increase in penalty is slow, with the full way communication from aggregators to DERs
effect taking approximately 10 hours to be using price-based control method. A similar
reached. This extremely slow response is due idea for the Danish pilot has been implemented
to two things. Firstly, the heat pumps used to in the cloud with a dedicated DMS. It promotes
heat the swimming pools are not designed
to be turned on and off frequently, and thus
a Model Predictive Control (MPC) has been
designed to limit how of often this happens,
to prevent damaging them. This meant that
the MPC often chose not to react immediately
to changes in penalties. Secondly, technical
issues with the hardware meant that the SN-
10 was occasionally unresponsive to MPC due
to some communication barriers. However, if
the concepts developed within the pilot are Figure 36 - Estimated step-response, based on data
widespread used, the hardware will be updated from October 2017, where the penalty was based on
to be able to react as quickly as required. CO2-intensity.
and under real usage conditions. To ensure on historical consumption data for each of the
the technology used is enough and the 5 primary substations involved in the pilot. In
usage doesn’t impact to the radio station order to ensure the fulfilment of such profile,
consumers. the DSO monitors in real-time the exchanged
power in each substation. In parallel, the DSO
Fundamentally, the pilot aims to implement monitors the status of the distribution grid
balancing and congestion management and identifies potential constraints that may
services for the distribution network through arise if demand flexibility is not used. Based
direct bidirectional signals to the aggregator. on the requirements arising from both the
This is pushed further downstream to the monitoring of the power exchange in the
activation of back-up capacities to reduce the TSO-DSO interconnection and the potential
consumption in selected grid regions. constraints in the network, the DSO requests
the LMO to open the local market. The LMO
The pilot C involves 5 primary substations and receives flexibility bids from CMPs, clears
18 radio base stations in the city of Barcelona, the market, while avoiding the creation of
as shown in Figure 35. Moreover, the scenario additional constraints in the grid and informs
considered in the pilot is looking into a future both the DSO and CMPs about market results.
situation, with a more electrified energy system, Finally, CMPs dispatch the flexibility and the
which may result in congestion problems at DSO checks the actual delivery of the flexibility
distribution level. For this reason, part of the required.
network is virtual, in order to generate such a
new scenario, with an effort made to provide The four participants in this pilot assumed
characteristics, which could reasonably adapt different responsibilities and perform different
to the current grid topology. roles:
The TSO and the DSO agree on a scheduled • VODAFONE has performed the role
profile at the TSO-DSO interconnection. For of DER owner. A party that produces
the purpose of the pilot, such profile is based electricity via a flexible resource. The
• ONE has performed the role of CMP, • For each generator, the optimization model
aggregating local DER resources. Hence, includes constraints on generation limits.
they are responsible for selling the flexibility
of the DER in their portfolio on the local The market performed in the pilot has two
market. major innovations: the time execution and the
use of an OPF to clear the market. The time
• ENDESA has led the pilot and has execution is set in 5 minutes, which is close to
performed different roles; the first role is a real-time operation and, thus, it may provide
the TSO, this role simulates the creation of more accuracy to balancing and to control
the TSO-DSO interconnection scheduled activations. Using an OPF to clear the market
profile. Second role is the DSO, operates allows the LMO to evaluate the technical
the distribution network in the pilot and restrictions and, at the same time, dispatch the
monitors the status of the grid, by means flexibility to achieve the balancing objectives.
of the metered data management system.
The third role is CMP, manages some virtual In addition to the innovation on the DSO-LMO
nodes emulating other CMPs participating side, there is an important innovation in the
in the local market. Finally, the last role is CMP’s role to perform the monitoring, bidding
the LMO, plays the local market operator and activation of a portfolio of homogenous
role at the local (distribution) level. (from the flexibility point of view) batteries in
TECNALIA has provided technological radio base-stations.
consultancy to Endesa when designing
and implementing the overall pilot In order to fulfil these duties, the CMP needs
architecture. It also contributed to ensuring to communicate with the rest of the parties.
the consistency of the pilot with the rest of In particular, communications are required
the developments in the SmartNet project with the LMO for bidding and clearing, with
and the complementarity with the other DER for managing and activating flexibility,
two technological pilots. Last, Tecnalia and (indirectly) with the DSO for real-time
assisted ONE to develop new aggregation information of the actual load per asset to
models for the pilot. guarantee the effective provision of the traded
flexibility.
The LMO implements local market clearing
activities and is in charge of gathering and Given the nature of the DERs in this pilot,
delivering information of local market rules. The a number of parameters and real-time
flexible resources are grouped in LAs along the information exchange is required between
distribution network. CMPs consider all these DERs and the CMP, which is performed
resources to offer bids. The LMO, is a modified by means of a communication between
OPF optimization model to include the market Vodafone’s energy data management (EDM)
constrains. The objective is to determine the system and ONE’s asset gate. Furthermore,
optimal activation of bid blocks among all none of the aggregation model developed
CMPs and the clearing price is set as the most in the project are completely applicable to
expensive matched bid (Pay-as-clear). the pilot (neither the one for atomic loads
because batteries will need to be recharged
The objective function of the model is the again after service provision, nor the battery
minimization of the total flexibility activation model because it will only be used for providing
cost, that is, the sum of all matched positive upward balancing).
power bid prices for all nodes. Three main
assumptions have been made: In order to implement the aggregation
algorithm, the Aggregator has to obtain the
• For each node, the model includes an active state of charge of the battery ant the load in
and reactive power balance constraint. real time, also the CMP need other parameters
like the minimum allowed state of charge and
• For each line, active and reactive line power the nominal charging power. The algorithm
developed for this task allows the CMP to number of issues, ranging from regulatory
manage the different data and communication (such as impeding DER to participate in the
interactions, as well as to model the potential markets for ancillary services organized the
behaviour of the different assets. TSO or having different metering requirements
depending on the contracted consumption
The pilot also offered ONE the opportunity power) to technical (such as low mobile phone
to test Vodafone’s machine-to-machine connectivity in remote rural areas or faulty
technology, which aggregates a number of back-up batteries, which, fortunately, never
operational parameters from the assets in had to provide back-up power until the pilot
one single platform. This solution allows the started the testing phase) and even practical
CMP to communicate with an array of assets barriers (e.g. radio base stations are located in
through one single communication channel, the roofs of residential buildings, so replacing
which simplifies the process significantly, their cabinets requires obtaining permission
as most routines and processes are already from landlords but also from municipalities, as
designed. Furthermore, it is worth underlying they must be uploaded by huge cranes located
that the communication protocol and in the streets).
activation have led to real activations in the
physical assets, thereby seriously decreasing However, the three pilots were successfully
the implementation problems and resulting in completed and resulted in a number of very
a significantly high technology readiness level important lessons learnt for the next step to
(TRL) exercise. be taken to deploy the concepts developed
in SmartNet, which is the replication of these
Conclusions pilots in other regulatory environments, with
different flexibility providers and at a larger
Being in the forefront of technology scale.
implementation, these pilots uncovered a
In the same section of the web site, scientific papers (published in open access modality) and
presentations can be downloaded as well.
D 1.1 Ancillary service provision by RES and DSM connected at distribution level in the future
power system
D 6.2 Survey of regulation and stakeholders’ positions on TSO-DSO coordination for ancillary
services acquisition from distributed resources
D 6.3 Policy recommendations to implement and/or overcome barriers and enable TSO-ISO
integration