Professional Documents
Culture Documents
Fire Alarm Method Statement
Fire Alarm Method Statement
Fire Alarm Method Statement
SUBMITTAL
(MSS)
Project: APOLLO-I
Client / Client Consultant: PIVOT / SUDLOWS
CONTENTS
1.0 Purpose
2.0 Scope
3.0 References
4.0 Definitions
5.0 Responsibilities
6.0 Equipment
9.0 Attachments
1. Purpose
This method statement describes the Testing and Commissioning for Fire alarm system
methodology of the Apollo-I Data Centre Project. It is generated to ensure Testing and
Commissioning for Electrical Works procedures are in place and to provide adequate tools
and equipment to carry out the complete installation in a safe manner.
2. Scope
This method statement covers all processes related to Testing & Commissioning of Fire
Alarm System. This procedure is to be read in conjunction with the relevant ITP, outlining
the responsibility and the quality verification to be performed by various parties.
3. References
4. Definitions
5. Responsibilities
Responsibilities for ensuring that the steps in this procedure shall be carried out are
specified at relevant steps in the procedure:
• Project Manager is the overall responsible for the project in terms of work Testing,
safety, planning & quality. The Project Manager will maintain the planning progress
and coordination of works with the main contractor.
• Specific attention is paid to all safety measures and quality control in coordination
with Safety Engineer and QA/QC Engineer and in line with PSP and PQP.
• Coordinating with Engineer, QA/QC Engineer, Supervisor site Team and foremen for
all Testing & Commissioning activities on site.
• Control and check all Test reports before issuing to Consultant approval.
• Shall be responsible for the implementation of this method statement as per the
work plan, methodology and resources.
• Compliance with the project specified requirements.
• Notifying the site manager of the works that require testing.
• Ensure the calibration of all equipment in use.
• Schedule all testing and commissioning activities and ensure that all test required are
conducted.
• The constant coordination with the Safety Engineer to ensure that the works are
carried out in safe working atmosphere.
• Ensure that the works are carried out according to the specification and drawings.
• Ensure Testing and Commissioning are carried out as per MS procedure
• Co ordinate with MEP project manager and project engineer for sequence of works at site.
• Co ordinate with consultant during inspection.
• Ensure that all in process test are carried out as per DCD,NFPA & Project specification
requirement
5.4 Foreman
• The carrying-out of work and the proper distribution of all the available resources in
coordination with the Site Engineer on a daily basis.
• Daily reports of the works are achieved and coordinated with the Site Engineer.
• Incorporate all the QA/QC and Safety requirements as requested by the concerned
Engineer.
• Meeting with any type of unforeseen incident or requirement and reporting the same
to the Site Engineer immediately.
• The Safety Officer will be responsible for implementing and maintaining the Project
HSE Plan in full conformance to the safety requirements.
• Conduct regular tool box talks on site.
• He is responsible to ensure all site activities are covered by Safety Inspections and
will initiate and follow up all required corrective actions.
• Compile all safety records as per the Project HSE Plan.
• Ensure that all equipment used on site have valid registration, insurance and test
Certificates.
• Review method statement, material safety data sheets and handle requirements to
enforce compliance of safety aspects.
• Digital Multi-meter
• Smoke Detector & Heat Detector- Aerosol smoke & Heat dispenser
• Portable Hand tools
• Drilling machine
• Standard Tool Box
• Certified mobile scaffoldings (Tower/Podium) / MEWP
• Portable Drilling Machine/ Grinding Machine
• Hammer Drilling Machines
• Mobile Scaffold / Fixed scaffolding & stepladders.
• Spirit Level / Level Threads
➢ Note: All Power tools shall be suitable for use with 110V & 220V power supply.
7. PPE
All workers involved shall be equipped with adequate PPE as stated below:
➢ Uniform
➢ Hard hat
➢ Goggles
➢ Reflective jacket
➢ Steel toed safety shoes
➢ Ear plug
➢ Nose mask
➢ Hand gloves as per the job
❖ The installer for this project shall be responsible for the testing of all cabling, with an appropriate
calibrated insulation resistance meter for each complete circuit. The results will be logged on the
cable test sheet and will be available for the commissioning engineer and for inclusion into the
Operation and Maintenance manual. When the insulation tests are complete, the Tyco
representative & the client representative will sign the test certificate.
❖ Upon arrival at site the commissioning engineer will familiarize himself with all aspects of the
system .This will include a visual inspection of the installation, i.e. position of panels, heat
detectors, interface units, Manual call points and notification devices in conjunction with all
approved drawings to ensure that the drawings are true reflection of the installation. If any
changes it will converted as RED Mark Up.
❖ The Commissioning Engineer will also ensure that panel as indicated on the drawings is supplied
with appropriate supply voltage individually fused, labelled accordingly. Make sure all applicable
permits are available for starting the commissioning activity. Ensure a 230 V AC supply is
provided to power the Heat gun that will be used for testing the heat detectors.
❖ When the Commissioning Engineer is satisfied that there are no outstanding works associated
with the detection loops and the interfaces to other equipment, then the commissioning can
commence.
Before the devices are tested the various parts need to be set up and checked individually. Ensure
all equipment’s, devices and panels have been installed as per the approved drawings and identified
correctly.
8.2 Commissioning
• The Fire alarm system shall be commissioned in-line with the functional sequence of
the System which is given below.
❖ The FACP LCD will display a custom message programmed for that respective point.
❖ The fire detection notification devices & interfacing modules ( MSFD Dampers, etc)
in the respective area will be activated as per C& E logic
❖ The LFACP LCD will display a custom message programmed for that respective point.
• Function test will annunciate to the FACP, The annunciation includes panel buzzer
and LCD display of location.
• The test will be printed in the printer which is located in main control room.
• Check for cause and effects are functioned according to the approved matrix.
• If the test is successful, moves to the next device and continue the test.
• Check the sounders and flashers are functioning.
• If the test result is successful, move to the next device and continue the test until
all devices are tested in the loop.
• If all devices tested successfully in the one loop, move to the next loop and
continue in same manner.
• If the “Alarm Silence” button is pressed, it will stop all notifications and an
“ALARM SILENCE IN PROGRESS” message will show on the FACP prior to stop the
notification.
• If the “System Reset” button is pressed, “SYSTEM RESET IN PROGRESS” message
will display and reset will take place alarm.
• Will be cleared after a successful reset or the panel will show a massage that
“ALARM PRESENT SYSTEM RESET BOARD”.
• Use the available scaffolding / Ladder to reach the Smoke detector location. Portable
testing tool kit (Aerosol Dispenser) will be used for testing the Smoke Detectors
• Place the testing tool & inject/spray the Aerosol in to Smoke detector.
• The Detector will activate
• Fire led on the panel facia will be “ON”.
• The device details (Loop number, Device number, Panel number etc,) are displayed on
the Fire panel display.
• Device text for the activated device will be displayed.
• Activation of relevant Notification device as per cause and Effect
• FACP configured outputs will be activated
• Move to the next device / Detector
• Repeat the above steps for each Area / System / Building
• Once Tests are completed the respective Fire Alarm panel is reset to bring it to normal
Condition
• All Results will be visually checked verified and recorded in the check sheet.
• Check before activation the Red indicator LED is flashing (Red Light) on the unit.
• Activate individually using the connected device (FM200, Valve etc.).
• Check after activation the red indicator LED is on (Red Light) on the unit.
• Check if the correct message is displayed on the MFACP display with actual
addressed as per approved shop drawings, PC monitor (Graphic Command
Centre) and printer.
NOVEC System
All operations of NOVEC system including operations of solenoid valve shall be
verified as per C & E matrix.
Sprinkler System
Systems operations of alarm check valve and monitoring of all zone control value,
Zone control Flow switches / isolation valves shall be verified as per C & E matrix.
Fire Pumps
Fire pumps operations shall be verified as per C & E matrix.
FAHU
FAHU will turn off during fire at each pod-1 and shall be verified as per C&E Matrix
Testing will be conducted as per approved C & E Matrix to verify the sequence of
operation as per project requirement. Points to be verifying.
• It will be tested by activating any detector or break glass in the loop and verify
the following effects are taken place.
• It will be tested by activating one device in the building also, one manual call
point will be operated in each floor. The testing will be done as follows.
• Mark the new routes as per site condition then this information shall be detailed in the
drawings with Red Lines and shall be part of the documents during the inspection.
• After approval of inspection with changes (RED Lines Drawing). This information will be
incorporated in the As Built drawings.
9.4 Quality
At the start of each activity in each area it should be checked by the foreman that the
latest approved method of statement in hand. All testing arrangement shall be
inspected by QA / QC and once internally approved; the inspection request shall be
raised to the Consultant for the witness. All inspections shall be followed as per
attached ITP.
9.6 Environmental
Any waste generated due to above work shall be segregated and disposed off,
according to the site / and statutory norms and approved EHS plan. For details, refer
Method statement for Construction Environmental Management Plan or Project
Waste Management & Recycling Plan.
10. Attachments