Professional Documents
Culture Documents
Cementation
Cementation
Cementation
DRILLING Page 1 of 44
OPERATIONS CEMENTATION
MANUAL Issue 2
CHAPTER 8
CEMENTATION
TABLE OF CONTENTS
8.3 PREPARATION.................................................................................................................... 6
8.3.1 Supervision ............................................................................................................................ 6
8.3.2 Cementing Programme .......................................................................................................... 6
8.4 CEMENT, ADDITIVES AND SPACERS............................................................................ 7
8.4.1 Cements ................................................................................................................................. 7
8.4.2 Cement Additives .................................................................................................................. 8
8.4.3 Spacers ................................................................................................................................. 12
8.4.4 Testing Requirements........................................................................................................... 15
8.5 PRIMARY CEMENTATION ............................................................................................. 18
8.5.1 General Guidelines .............................................................................................................. 18
8.5.2 30” Casing Sub Sea Method With Stinger........................................................................... 20
8.5.3 Inner String (Stinger) Method.............................................................................................. 20
8.5.4 Single Stage Cementation Procedures ................................................................................. 23
8.5.5 Multiple Stage Cementation Procedure ............................................................................... 26
8.5.6 Liner Cementation Procedure .............................................................................................. 31
8.6 REMEDIAL CEMENTATION ........................................................................................... 35
8.6.1 Squeeze Cementing.............................................................................................................. 35
8.6.2 Cement Grouting.................................................................................................................. 37
8.7 CEMENT PLUGS (ISOLATION AND KICK-OFF).......................................................... 39
DRILLING DEPARTMENT
PETRONAS CARIGALI SDN BHD
DOM 8
DRILLING Page 2 of 44
OPERATIONS CEMENTATION
MANUAL Issue 2
DRILLING DEPARTMENT
PETRONAS CARIGALI SDN BHD
DOM 8
DRILLING Page 3 of 44
OPERATIONS CEMENTATION
MANUAL Issue 2
8.1 INTRODUCTION
No matter how good the cement slurry formulation, and no matter how well the cementing
programme is engineered, the success of the cementing operation will always be critically
dependent on how well the operation is performed on the drilling rig.
The cost of correcting a poor primary cementation can become a very large part of the
overall well cost and, even then, remedial cementing operations may not be entirely
effective. Communication between zones can ruin a well’s performance, reduce its
economic life, and result in a loss of ultimate recovery from the reservoir.
Many cementations have failed to achieve the necessary quality because the additional
effort, or care, was not taken during the job. Every cement job is worthy of the utmost
attention to detail. Jobs which are often regarded as simple, such as setting open hole
cement plugs for abandonment or side-tracking operations, should always be carefully
planned and executed. Whilst a cement plug can usually be reset if it fails, the time
required to repeat a deep set cement plug job (and waiting for it to cure), can run into days.
Cement can not form an effective seal if mud-filled channels are left. The geometry must
therefore allow the cement to adequately displace the previous fluid contents, rheological
properties must be correct, and the turbulence must be maximised during displacement.
This requires that preparation for a cementation should begin well in advance of the job.
DRILLING DEPARTMENT
PETRONAS CARIGALI SDN BHD
DOM 8
DRILLING Page 4 of 44
OPERATIONS CEMENTATION
MANUAL Issue 2
DRILLING DEPARTMENT
PETRONAS CARIGALI SDN BHD
DOM 8
DRILLING Page 5 of 44
OPERATIONS CEMENTATION
MANUAL Issue 2
DRILLING DEPARTMENT
PETRONAS CARIGALI SDN BHD
DOM 8
DRILLING Page 6 of 44
OPERATIONS CEMENTATION
MANUAL Issue 2
8.3 PREPARATION
8.3.1 Supervision
Two to three days before the job, the cementing contractor shall prepare a cementation
programme at the well site, in consultation with the Drilling Supervisor. The programme
shall be sent to the Drilling Superintendent for verification and approval.
The Drilling Superintendent shall check the cement programme and confirm acceptance, or
request a revision if required. When the programme is finalised, the Drilling Supervisor
shall submit the programme to the Drilling Superintendent.
DRILLING DEPARTMENT
PETRONAS CARIGALI SDN BHD
DOM 8
DRILLING Page 7 of 44
OPERATIONS CEMENTATION
MANUAL Issue 2
The standard cement used in Carigali drilling operations is API Class G oilwell cement.
This grade of cement is the most widely used in the industry, and it is compatible with a
variety of commonly available accelerators and/or retarders, to cover a wide range of well
depths and temperatures up to 230°F. For wells with static bottom hole temperature of
>230°F, silica flour is blended with the cement to prevent cement strength retrogression.
8.4.1.2 Slag Cement
Blast furnace slag is a by-product of the steel manufacturing industry, but has chemical
properties which allow it to be used as a cement. The raw “clinker” (blast furnace slag) is
simply prepared by grinding into a fine white powder.
The chemical reaction that causes the slag cement slurry to set, requires the addition of an
alkaline activator. Portland cement is a good activator, and the slag cement used in Carigali
operations, is therefore a blend containing 35% Portland cement and 65% blast furnace
slag.
Slag cement has advantages in wells where gas migration could be a problem, or when CO2
bearing formations are encountered.
8.4.1.3 Preventing Gas Migration with Slag Cement
Although cement slurry transmits the full hydrostatic pressure to the formation, gel strength
develops in the first phase of the setting process, and the cement enters a “transition state”,
where the cement solids start to form chemical and electrostatic bonds. For conventional
Portland cement, this occurs when the slurry has developed a shear strength of about
21 lbs/100ft2. The slurry becomes a porous, self supporting matrix, and the hydrostatic
head of the slurry reduces to that of the mix water.
As the curing process continues, the cement shrinks by about 5%, causing the pressure of
the mix water remaining in the pore spaces to reduce rapidly, which can allow formation
gas to enter the matrix. If this occurs, the gas will form channels in the semi-cured cement,
which can result in communication and flow to shallower sands.
In comparison to Portland cement, blast furnace slag cement has a much shorter “transition
state”, and rapidly changes from its liquid slurry from into the solid material. This greatly
reduces the time available for formation gas to enter the cement, and has been found to be
very effective in eliminating gas migration.
DRILLING DEPARTMENT
PETRONAS CARIGALI SDN BHD
DOM 8
DRILLING Page 8 of 44
OPERATIONS CEMENTATION
MANUAL Issue 2
The additives to be used, and their concentration, shall be determined by the cementing
service contractor.
The same additives can be used in both conventional API Class G cement, and slag cement,
and they have the same action in both types of slurry. In general, the action of the additives
is slightly greater in slag cement than it is in API Class G cement.
The following information illustrates the function of the various classes of cement
additives, and highlights which chemicals are used for what purpose. It is provided as an
aid to understanding the formulation and preparation of the cement slurry, and should be
used by Carigali personnel to assist in the verification of the cementing service contractor’s
recommendations. No deviation from the agreed recipe shall be permitted, unless specific
written instructions have been issued by the Drilling Superintendent.
8.4.2.1 Accelerators
Accelerators may be added to the mix water to reduce the thickening and setting times of
the slurry, with the purpose of avoiding unnecessary time spent waiting on cement.
8.4.2.1.1 Salt
Salt (sodium chloride) is the most commonly used accelerator. It produces moderate
acceleration at concentrations between 10 lbs/bbl and 20 lbs/bbl, but causes slight
retardation at concentrations greater than about 25 lbs/bbl. Sea water contains sodium
chloride in the correct concentration range to act as an accelerator, and is often used as mix
water for shallow cementing operations offshore, particularly when large volumes are
required.
8.4.2.1.2 Calcium Chloride
Calcium chloride produces a cement slurry with high early compressive strength. It
produces considerable acceleration, and heat output. Flash setting may occur at
concentrations above 3%, and it also increases the viscosity of the slurry.
DRILLING DEPARTMENT
PETRONAS CARIGALI SDN BHD
DOM 8
DRILLING Page 9 of 44
OPERATIONS CEMENTATION
MANUAL Issue 2
As temperature increases, the chemical reaction between cement and water is accelerated
which, in turn, reduces the time, for which the slurry remains pumpable. Increased depths
and formation temperatures may require the use of retarders in order to extend the
pumpable time of the cement. Thixotropic slurries may require retarders at shallow depths
and low temperatures.
Most retarders affect the viscosity of the cement as follows:
DRILLING DEPARTMENT
PETRONAS CARIGALI SDN BHD
DOM 8
DRILLING Page 10 of 44
OPERATIONS CEMENTATION
MANUAL Issue 2
There are two main methods of increasing the gradient of the cement slurry as outlined
below.
a. Reducing the water / cement ratio.
This is the preferred method for increasing cement gradient, particularly when cementing
across gas zones. A maximum gradient of approximately 15.7 ppg can be attained by this
method.
b. Addition of weighting material.
The preferred material is hematite (iron oxide) but barite may also be used. It is preferable
to batch mix the cement and the weighting material, rather than to use pre-blended cement,
since the weighting material in pre-blended high weight cement, may segregate (settle out)
during storage in the cement silos. Handling different blends of cement on the rig also
increases the risk of operational mistakes.
Note: If a well requires the use of a mud gradient above 15 ppg, a batch mixing
unit and sufficient sacks of weight material, should be kept on the rig as a
contingency.
Low gradient slurries are used for cementing weak formations or when there is a possibility
that the casing could collapse or float if a heavier slurry was used.
Generally, a low gradient slurry is prepared by adding extra mix water. Bentonite is usually
premixed at a concentration of 1 - 2% w/w of dry cement in the mix water to reduce free
water separation of the resultant slurry.
The bentonite must be fully hydrated before any other additives are added to the mix water.
To achieve this, the premix may be cut back using drill water, or dry bentonite may be
hydrated in drill water. In the latter case, the minimum hydration period is six hours, but
may need to be longer, depending on the quality of bentonite used. The addition of caustic
soda to the bentonite premix is also necessary.
Notes:
1. The bentonite content must be checked using the methylene blue test.
DRILLING DEPARTMENT
PETRONAS CARIGALI SDN BHD
DOM 8
DRILLING Page 11 of 44
OPERATIONS CEMENTATION
MANUAL Issue 2
Friction reducers (or thinners) are dispersing agents which can be added to the slurry to
reduce its viscosity (and thus the frictional pressure losses in the system) while displacing
the cement. As a result, higher pumping rates are possible and higher displacement
efficiencies may be achieved.
Fluid loss control additives are added to cement slurries for the following reasons:
Most fluid loss additives tend to viscosify the slurry and consequently, dispersants are often
added at the same time.
8.4.2.7 Additives for Thixotropic Slurries
The main application for thixotropic slurries is cementing lost circulation zones.
Thixotropic slurries behave like normal slurries whilst being pumped, but rapidly develop a
gel structure when static. The major disadvantage of thixotropic slurries however, is their
relatively high viscosities, which may adversely affect displacement efficiency.
8.4.2.8 Defoamers and Antifoams
While mixing cement, and/or when preparing mix water, containing retarders, salts, fluid
loss additives and/or Bentonite, foaming is often experienced. To control such problems
antifoams and defoamers are available.
In practice, such distinction may be difficult to ensure and therefore both antifoams as well
as defoamers should be added in advance.
DRILLING DEPARTMENT
PETRONAS CARIGALI SDN BHD
DOM 8
DRILLING Page 12 of 44
OPERATIONS CEMENTATION
MANUAL Issue 2
The use of blast furnace slag cement in Carigali operations has largely superseded the use
of gas blocking additives in combination with conventional (Portland) oil well cement. The
following types of additives have been developed for cements used across gas bearing
formations:
• Surfactants added to the slurry will form a stable foam with the gas bubbles
preventing their transport through the cement slurry.
• Additives may be incorporated into the slurry which act to block the gelled cement
pore structure, preventing gas migration.
Fine silica, or silica flour is commonly blended with cement to help prevent loss of strength
at high temperatures. When temperatures exceed 230o F, all common cements lose much of
their strength. This strength retrogression is accompanied by an increase in permeability
from 0.02 mD for typical neat retarded cement at 230o F, to a maximum of about 8 mD
after 8 days at 320o F.
The optimum amount of silica for controlling strength loss is 30 – 40%, and this will not
only control the problem, but reduce permeability to less than 0.001 mD, and produce a
cement with a compressive strength far in excess of that of neat cement.
8.4.2.11 Fibre
Synthetic fibrous materials have been used successfully for many years to improve the
shear, impact and tensile strength of cement. Nylon or polypropylene fibres up to 1” long
are normally used, but must be added carefully to batch mixed slurry to avoid local
concentrations that could plug tools and equipment.
The fibres transmit localised stresses more evenly throughout the cement, and are
particularly effective at reducing the effects of impact loads from drilling assemblies, and
can also act as a bridging material when lost circulation zones are to be shut off with
cement.
8.4.3 Spacers
Spacers are defined as any fluids other than cement slurry or mud, pumped ahead
(pre-flush) or behind the cement slurry (after-flush). After-flush should, in general have the
same formulation as the pre-flush.
Spacers can fulfil a number of different roles, but must be individually designed for each
specific cementation.
DRILLING DEPARTMENT
PETRONAS CARIGALI SDN BHD
DOM 8
DRILLING Page 13 of 44
OPERATIONS CEMENTATION
MANUAL Issue 2
Scavenger slurries are dilute mixes of cement and water which are used to remove gelled
mud and filter cakes. Their gradient should be mid-way between mud gradient and the
main cement slurry gradient. To prevent fast setting of the scavenger slurry, a cement
retarder is added to the mix water at a concentration of 0.2% by weight of cement.
8.4.3.3 Spacers for Use With Water Based Drilling Fluids
8.4.3.3.1 High Annular Velocity Displacements
DRILLING DEPARTMENT
PETRONAS CARIGALI SDN BHD
DOM 8
DRILLING Page 14 of 44
OPERATIONS CEMENTATION
MANUAL Issue 2
Since cement will only bond to water-wet surfaces, spacers containing appropriate
surfactants must be used to separate the cement slurry from the synthetic based drilling
fluids.
8.4.3.3.4 For High Annular Velocity Displacements
DRILLING DEPARTMENT
PETRONAS CARIGALI SDN BHD
DOM 8
DRILLING Page 15 of 44
OPERATIONS CEMENTATION
MANUAL Issue 2
The after-flushes listed in the table below should be used in all cementations.
This section highlights the general guidelines to be followed for cement testing
requirements.
8.4.4.1 Samples for Laboratory Testing
8.4.4.1.1 Cement QC
The common oil well cements, such as API Class G, are manufactured at the same factories
that produce cement for the civil construction industry. By far the greatest volume of
cement is made for the construction industry, and since oil well cement only represents a
very small proportion of the total factory production, the “clinker” is usually made in
batches. Starting and stopping the process can lead to quality problems, and variations
between batches.
It is therefore essential that the cement supplier (often the cementing service contractor)
maintains full details of factory batch numbers and API certificates, and that consignments
are kept segregated. If unexpected results are obtained either during testing, or the actual
job, cement quality should always be checked by performing a detailed analysis of the
compounds it contains. This should always be conducted in an independent laboratory,
using the appropriate equipment.
DRILLING DEPARTMENT
PETRONAS CARIGALI SDN BHD
DOM 8
DRILLING Page 16 of 44
OPERATIONS CEMENTATION
MANUAL Issue 2
Some of the symptoms which have been found to be associated with inconsistent cement
quality are unexpectedly poor bond quality, and excessive requirement for slurry additives
to obtain suitable rheological properties. Cement quality problems are often readily blamed
on hole condition, casing centraliser programmes or the execution of the job, and it is
important that potential cement quality problems are not neglected as a possible cause.
8.4.4.1.2 Sampling Requirements
The formulation, testing and mixing of the slurry must be very closely controlled if it is to
have the precise rheological properties required, and the slurry is to remain pumpable
throughout the time period required for the job. Small differences in cement, chemicals and
mix water can cause large differences in the slurry properties, and it is essential that truly
representative samples are used for testing the formulations.
All sampling shall be carried out by the cementing contractor. The following general
guidelines shall be followed.
a. Whilst offloading cement, take a sample directly from the supply line or the silo. It is
essential that the cement sampled is representative of the cement to be used in the
forthcoming cementing operation.
b. Additives shall only be sampled when specifically requested by the laboratory.
Samples must be from the batch to be used in the forthcoming cementing operation.
c. A portion of all samples must be retained for use in the standard bench tests. The
remainder (along with separate samples of the mix water) shall be despatched by the
Drilling Supervisor to the Contractor's laboratory in air-tight containers as detailed
below. Containers must be clean.
Bench testing of samples shall also be carried out at the well site by the Cementing
Contractor.
a. Bench testing must be carried out at the well site for quality control on the mix water
before adding the chemicals. It provides a comparison with the onshore laboratory
results to confirm that the mix water is not contaminated and properly prepared.
DRILLING DEPARTMENT
PETRONAS CARIGALI SDN BHD
DOM 8
DRILLING Page 17 of 44
OPERATIONS CEMENTATION
MANUAL Issue 2
b. Testing should be completed well in advance of the job, so that time is left to make
new mix water and to repeat the bench tests if necessary.
c. Bench tests must also be carried out with samples of the mixed slurry (“surface
samples”) to give an indication of when the cement downhole has hardened
sufficiently to proceed with operations.
8.4.4.2.1 Procedures for Bench Tests
a. Testing of drill water for contamination
To test drill water for chloride contamination, the same procedure used to test mud
shall be applied, ie, titration method with silver nitrate solution. The chlorides should
be less than 500 ppm.
b. Testing of Mix Water
1. Mix 500 grams of properly sampled cement with enough mix water to achieve
the planned water/cement ratio, using the bench mixer for 5 minutes at high
speed.
2. Place the slurry in a plastic bag in a water bath controlled at the expected static
bottom hole temperature (SBHT). Check every 15 minutes for thickening time
and hardening time.
Note:
i. Make sure that the mix water/additive mixture is homogeneous before
sampling.
ii. If the cement job is delayed by a substantial amount of time after the mix
water has been prepared, check carefully that the additives have neither
settled out nor deteriorated.
c. Testing of Pumped Cement Slurry
The procedure for this test is identical to the above with samples of the pumped
slurry taken during the cement job.
8.4.4.2.2 Interpretation of Bench Tests
a. The chloride content in drill water must not exceed 500 ppm.
b. Thickening and hardening times obtained from well site bench tests on mix water
should coincide with the laboratory data, to within ± 30 minutes. Minor differences
can be attributed to differences in cement and additives concentration, temperature
differences and other test conditions. The bench test times should not be related to
pumpable and thickening times determined under dynamic conditions.
c. If the results differ by more than 30 minutes, the concentration of additives is
questionable and the cementing contractor’s laboratory shall be consulted.
DRILLING DEPARTMENT
PETRONAS CARIGALI SDN BHD
DOM 8
DRILLING Page 18 of 44
OPERATIONS CEMENTATION
MANUAL Issue 2
The quality of the cementation critically depends on the effectiveness of mud displacement,
and its replacement by cement slurry. Cement is a non-Newtonian fluid which, in either
turbulent or plug flow, has a flatter velocity profile across the area of flow than when it is
in lamina flow. In lamina flow, the cement has a parabolic velocity profile across the area
of flow, and it is likely to “telescope” through the mud, leaving by-passed channels.
Cement slurry requires impractically high displacement rates to achieve the fully-developed
turbulent flow that would ensure good mud removal, even in gauge hole with well
centralised casing. Experience has shown however, that the following rates can be achieved
in practice, and that they produce sufficient turbulence in the cement slurry to allow good
cementation:
• 13-3/8” casing : 920 gpm
• 9-5/8” casing : 840 gpm.
• 7” casing : 500 gpm.
Displacement of the mud by cement during primary cementation, critically depends on the
geometry of the hole and casing. If there are washouts, or the casing is eccentric in the hole,
there will be places where the cement slurry will by-pass the mud, leaving channels. These
problems can be reduced by utilising an adequate centraliser programme, and moving the
casing by reciprocation or rotation during the job.
DRILLING DEPARTMENT
PETRONAS CARIGALI SDN BHD
DOM 8
DRILLING Page 19 of 44
OPERATIONS CEMENTATION
MANUAL Issue 2
If reciprocation is used, care is required to ensure that both the cement and the casing are in
the correct place and condition when the job is completed. Hook load must be carefully
monitored throughout the job. The effect of increasing buoyancy on string weight (as the
cement fills the annulus) should be pre-calculated so that it can be continuously accounted
for. Reciprocation should be stopped, and the casing string returned to the correct shoe
depth, if casing string drag or resistance increase.
If casing string rotation is used, torque must be carefully and continuously monitored.
rotation should be stopped if torque exceeds 70% of the minimum connection make up
torque.
8.5.1.3 Circulating Test
Displacing cement slurry at the high rates required to achieve turbulent flow, demands that
particular care is taken to avoid exceeding the maximum ECD that the formation will
allow. The Cementing Contractor should calculate the estimated ECD for a range of
circulating rates for the cement job, and advise any potential losses due to formation
strength limitations. The following procedure is recommended:
1. Ensure the tank level indicators are properly working and physically check the
level in the active tank.
2. Commence circulation at a low rate (50 gpm).
3. Increase circulating rate in increments of 10 gpm. After each increase, wait at
least five minutes to observe for losses and to allow pressures to stabilise.
4. Reduce the pump rate as soon as losses are observed or as soon as the ECD is
reached.
5. Record circulating pressure at the rate that will be used to bump the plug, in
order to allow determination of the final static differential pressure for
estimation of the TOC.
If losses are observed at a rate which is substantially below the optimum displacement rate
(as indicated in item 4 above) consideration should be given to circulating around a lost
circulation material (LCM) pill. This should be carried out at a circulating rate where slight
losses are induced. Once the losses have stopped, the rate may be carefully increased.
8.5.1.4 The Need for Job Continuity
From the commencement of pumping the cement slurry, until the completion of the cement
displacement, the operation must be continued without any interruptions if a high quality
job is to be achieved. Stopping, pausing, then re-starting slurry movement in the casing-
hole annulus can significantly aggravate mud displacement problems which will result in a
poor job. It is particularly important however, not to allow any interruption of the operation
from the commencement of pumping the slurry into the casing, until the mud used for
displacement has “caught up” with the slurry.
DRILLING DEPARTMENT
PETRONAS CARIGALI SDN BHD
DOM 8
DRILLING Page 20 of 44
OPERATIONS CEMENTATION
MANUAL Issue 2
During this phase of the operation, the top of the slurry inside the casing will continue to
move downwards even if the pump is stopped, since the heavy cement slurry will keep
moving until it balances the lighter mud in the annulus. This action (commonly called “U-
tubing”) can be very rapid, and a partial vacuum will be created in the casing above the
slurry if the pumping operation is halted.
The partial vacuum can be sufficient to cause the liquids to boil off from the slurry, which
will lead to de-hydration of the slurry, and may result in localised flash-setting. Whilst this
is not sufficient plug the casing, it is possible that it could be the cause of the cement
stringers that are sometimes found in the casing after the cement job, and poor quality
slurry left around the casing shoe.
The following procedure is used when the 30” sub sea housing has been run on the housing
running tool, and a drill pipe stinger run below the running tool, with the end
approximately 10 ft above the float shoe.
1. Perform the circulation test (see Section 8.5.1.3).
2. Mix and pump the required volume of cement. Observe for returns using an ROV or
guideline-deployed TV camera.
3. Displace cement using the cement pump to leave 6 ft of cement inside the casing.
4. Check for back flow.
5. If back flow is observed, displace the cement from the stinger, then hold pressure
until surface the samples are set.
6. If there is no back flow, release the running tool and POOH.
7. If no returns are noted, a top up job should be performed by running a stinger though
the funnel on the guide base, and into the top of the annulus.
8.5.3 Inner String (Stinger) Method
This method is used in areas or on wells where the presence of shallow gas has been
established or interpreted. Hole volume in surface hole sections is not accurately known,
owing to hole enlargement of the unconsolidated formations. In order to ensure a good
cementation across all sands, the 20” or 18 5/8” surface casing string is usually cemented
using this method since it allows:
• Cementing with actual required, rather than estimated slurry volume.
• Back pressure to be held on drill pipe should the float shoe fail.
• Better control of displacement (by reducing the risk of over displacement past the
shoe, or under displacement with consequent excessive drill-out time).
A schematic of the procedure is illustrated in Figure 1.
DRILLING DEPARTMENT
PETRONAS CARIGALI SDN BHD
DOM 8
DRILLING Page 21 of 44
OPERATIONS CEMENTATION
MANUAL Issue 2
1. Make up stab-in adaptor, and run on drill pipe. Install two centralisers on the first
joint of drill pipe above the stab-in adaptor.
Note: i) The use of a float shoe with a conical entry guide for the stab-in adaptor is
recommended, but always ensure that the stab-in adaptor is the same make
as the float shoe.
ii) HWDP may be run above the stab-in tool to provide sufficient weight to
resist pump-out force.
1. Stab stinger into the float shoe. Circulate and check for leakage at the stab-in adaptor
(by filling annulus if necessary).
Note: If seals are leaking POOH and inspect/re-dress stab-in tool. If seals still leak,
cement using a circulating head.
3. Perform circulation test (see Section 8.5.1.3). Circulate 150% of hole contents.
Closely monitor for losses and adjust flowrate as necessary.
4. Rig up the cementing line and flush surface lines. Pressure test lines to 1500 psi.
5. Pump pre-flush ahead. Mix and pump main slurry until returns are observed at
seafloor, then follow with programmed volume of tail slurry.
6. If the well is not to be cemented to surface, pump the calculated volume.
7. If the well is to be cemented back to surface, continue pumping until returns are
observed at the wellhead/mudline. If returns have not been observed after all the
cement is pumped, carry out top-up cementation after the primary cement is set.
8. Displace cement with mud, using cement pump. Pump drill pipe volume to stab-in
adaptor allowing sufficient under-displacement to leave 10 ft of cement inside
casing. Monitor for losses during displacement and adjust displacement rate as
required.
9. Disconnect cement line. Bleed off pressure and check for back-flow. If there is no
back-flow, pull stinger back one stand, circulate clean and POOH. If back-flow is
observed, displace cement from the drill pipe and maintain pressure. Check for back
flow again after surface samples are set, before pulling stinger.
DRILLING DEPARTMENT
PETRONAS CARIGALI SDN BHD
DOM 8
DRILLING Page 22 of 44
OPERATIONS CEMENTATION
MANUAL Issue 2
Start
Test Seals
Yes
Circulate as per
Section 8.3.2.
Pump Spacer
Pre-Mix/ Recirculate
No
Pump Cement
Yes
Leave 6 m Cement
Inside Casing
DRILLING DEPARTMENT
PETRONAS CARIGALI SDN BHD
DOM 8
DRILLING Page 23 of 44
OPERATIONS CEMENTATION
MANUAL Issue 2
DRILLING Page 24 of 44
OPERATIONS CEMENTATION
MANUAL Issue 2
9. Bump plug and record bump pressure. If the plug does not bump at the calculated
total pump strokes continue displacing until either the plug is bumped, or the
calculated volume, based on 93% pump efficiency, has been pumped.
10. Pressure test casing.
11. Release pressure and check for back-flow. If back-flow is observed hold pressure
until the surface cement samples have set.
Note: Do not re-displace any volume of mud that was bled off during back flow
check, since this may result in mud contaminated cement being pumped
around the shoe.
DRILLING DEPARTMENT
PETRONAS CARIGALI SDN BHD
DOM 8
DRILLING Page 25 of 44
OPERATIONS CEMENTATION
MANUAL Issue 2
Pump scavenger
Yes
Yes
Circulate Out
Cement
Solvable in
Problem? Yes
time?
No
No
Pump spacer
No
Severe loss
Yes Lower pump rate
returns?
No
Continue displacing
with mud pumps
No
Continue with
WOC
programme
DRILLING DEPARTMENT
PETRONAS CARIGALI SDN BHD
DOM 8
DRILLING Page 26 of 44
OPERATIONS CEMENTATION
MANUAL Issue 2
There are two widely used multi-stage cementing techniques, the free fall and the
continuous displacement type. A comparison of the two techniques is tabulated below:
DRILLING DEPARTMENT
PETRONAS CARIGALI SDN BHD
DOM 8
DRILLING Page 27 of 44
OPERATIONS CEMENTATION
MANUAL Issue 2
6. Displace at pre-determined maximum loss-free rate using the rig pumps. Reduce the
circulating rate to that used in Section 8.5.1.3 (e.g. 30 SPM).
7. Bump plug and record bump pressure. If the plug does not bump, do not
over-displace by more than ½ of the shoetrack volume. If the plug bumps, pressure
test casing.
8. Release pressure and check for back-flow.
9. If back-flow is observed, shut the well in, wait for 30 minutes and check again. If
back-flow continues, shut the well in and wait on cement.
10. Release free-fall stage cementing collar opening plug and wait 2 minutes/1000ft
depth.
11. Increase pressure to open multi-stage cementing collar as per manufacturer's
instructions. If collar fails to open, release pressure and wait for another
5-10 minutes.
Note: If further attempts at opening the cementing collar fail, consider running
drill pipe, and opening collar by applying weight on the plug.
12. Establish circulation and circulate minimum of 120% of annular contents. Check for
spacer-cement and for losses.
13. Switch over to the cement line, pressure test line.
14. Pump pre-flush.
15. Pre-mix and re-circulate slurry until gradient is within specification tolerance.
16. Mix and pump cement. If a problem occurs before programmed volume of cement
has been pumped, determine the optimum course of action based on Table 16.
DRILLING DEPARTMENT
PETRONAS CARIGALI SDN BHD
DOM 8
DRILLING Page 28 of 44
OPERATIONS CEMENTATION
MANUAL Issue 2
Pump scavenger
S.G. within
No Re-circ./Dump
tolerance?
Yes
Yes
Time To Solve
Problem? Yes
Problem?
No
No
Pump spacer
No
DRILLING DEPARTMENT
PETRONAS CARIGALI SDN BHD
DOM 8
DRILLING Page 29 of 44
OPERATIONS CEMENTATION
MANUAL Issue 2
No
Backflow? Yes Apply pressure Yes
Wait 30 minutes
Apply pressure to
open collar
Circulate 120%
contents of
annulus
Circulate
Fixed in < 20
Problem? Yes No out
mins?
preflush
No
Pre-mix /
Re-circulate
S.G. within
Re-circulate
safe No
/ Dump
tolerance? Circulate out
cement
Yes
Yes
Pump cement Solve Problem
Yes
No
Yes
Continue
No
with Part 3
DRILLING DEPARTMENT
PETRONAS CARIGALI SDN BHD
DOM 8
DRILLING Page 30 of 44
OPERATIONS CEMENTATION
MANUAL Issue 2
Continued
from Part 2
Pump spacer
Chase cement
No Bump?
Yes
Hold pressure
Bleed Off
Continue with
programme
DRILLING DEPARTMENT
PETRONAS CARIGALI SDN BHD
DOM 8
DRILLING Page 31 of 44
OPERATIONS CEMENTATION
MANUAL Issue 2
Because the capacities involved are generally smaller than those used in casing
cementations, close control is critical to the success of liner cementations. Job continuity
(see Section 8.5.1.4) must be assured. Surface lines must be rigged up so that no changes
are required which could interrupt pumping or displacing the cement. All personnel
involved must be fully briefed on the sequence of operations, and the details of their duties
before the job commences.
A schematic of the procedure is illustrated in Figure 4. Guidelines are as follows:
1. Circulate and perform circulation test (see Section 8.5.1.3). Rig up cementing lines,
flush and pressure test surface lines.
2. Batch-mix slurry to ensure correct density and homogeneity.
3. Pump spacer and cement. If a problem occurs before the programmed volume of
cement has been pumped, determine the optimum course of action to be taken using
the guide lines provided in Table 17.
Case 1 Case 2
There is enough time to solve the problem There is insufficient time to solve the
problem
Solve problem and continue pumping Circulate out the slurry and preflush.
slurry
Table 17, Course of Action
4. Drop drill pipe wiper plug and displace at pre-determined maximum loss free rate
using the cement unit. Look for pressure indication of shearing liner wiper plug.
5. Before bumping the plugs, reduce the pump rate to that used is Section 8.5.1.3 (e.g.
30 SPM).
Note:
i. Keep pumping until bump is observed, or until a maximum excess of 50% of
the shoe track volume has been pumped.
ii. Rotate the liner at approximately 20 - 40 RPM during displacement to improve
the cement bond. Do not exceed liner make-up torque.
6. After bump, pressurise liner to 500 psi over differential. Immediately bleed off and
check for back-flow. If back-flow is observed, pull out the stinger and circulate the
hole clean using the mud pumps until there are no further cement returns. A remedial
cement job will then be necessary using a packer set above the shoe.
7. Pick up liner running string sufficiently to activate tie-back packer setting dogs, and
set the integral tie-back packer.
DRILLING DEPARTMENT
PETRONAS CARIGALI SDN BHD
DOM 8
DRILLING Page 32 of 44
OPERATIONS CEMENTATION
MANUAL Issue 2
8. Apply 200 psi to liner running string, and pull stinger free of the cementing pack-off
bushing. As soon as pressure drop indicates that stinger is free, circulate out excess
cement at high rate. Rotate and reciprocate the liner running string whilst circulating,
to assist cement removal from casing. Continue circulation until returns are clear of
all cement indications.
DRILLING DEPARTMENT
PETRONAS CARIGALI SDN BHD
DOM 8
DRILLING Page 33 of 44
OPERATIONS CEMENTATION
MANUAL Issue 2
RIH liner
Condition mud
Pump spacer(s)
Pre-mix/Re-circulate Re-circ/Dump
No
Yes
Yes
Pump cement
Yes
Circulate out
Solvable in
Problems? Yes No cement &
time?
spacer(s)
No
Continued with
Part 2
DRILLING DEPARTMENT
PETRONAS CARIGALI SDN BHD
DOM 8
DRILLING Page 34 of 44
OPERATIONS CEMENTATION
MANUAL Issue 2
Continued
From Part 1
Plug sheared?
Yes
No Bump? Yes
No
Pull out stinger &
Overdisplace by a
circulate hole
maximum of 50% of Backflow? Yes
the shoe track volume clean using
mudpumps
No
Pull stinger
100m above liner Yes Losses? Contac
hanger t base
No
Continue With
Programme
DRILLING DEPARTMENT
PETRONAS CARIGALI SDN BHD
DOM 8
DRILLING Page 35 of 44
OPERATIONS CEMENTATION
MANUAL Issue 2
1. RIH with approximately 500 ft of tubing stinger on drill pipe to the bridge plug. If no
bridge plug has been set, the stinger should be run to approximately 200 ft below the
bottom perforations and a weighted, high-viscosity pill spotted to hold the slurry in
place during the job.
2. Set a balanced cement plug.
3. Pull back to 3 stands above theoretical TOC and circulate drill pipe clean. Pull up 10
stands and circulate bottoms up.
4. Pull back one single, close the annular BOP and apply maximum allowable surface
pressure until the cement surface samples are hard or until all of the cement has been
displaced.
Note: A minimum of 50ft of cement should be left above the perforations. Spot
more cement, if required.
5. Pull out of hole with the stinger.
8.6.1.2 Straight Squeeze
1. Set a cement retainer on drill pipe approximately 20ft above the perforations to be
squeezed off.
2. Pull out of cement retainer.
3. Pump the pre-flush, followed by the required volume of cement, and displace until
pre-flush reaches the end of the stinger.
DRILLING DEPARTMENT
PETRONAS CARIGALI SDN BHD
DOM 8
DRILLING Page 36 of 44
OPERATIONS CEMENTATION
MANUAL Issue 2
1. Perforate the casing at the top and bottom of the required interval.
2. Set a retrievable packer between the perforations.
3. RIH with drill pipe and establish circulation carefully, preferably using a solids-free
fluid. Circulate at increasing rates until the pressure at the perforations is equal to the
leak-off pressure. If circulation is very restricted, or not possible, follow the course of
action below.
i. Spot 10 bbls of 15% HCl and allow to soak for 10 mins.
ii. Attempt to circulate the acid through the perforations.
iii. If it is not possible to circulate, re-perforate at a point between the two sets of
perforations.
iv. If circulation is not improved, POOH with retrievable packer and carry out
block squeeze.
DRILLING DEPARTMENT
PETRONAS CARIGALI SDN BHD
DOM 8
DRILLING Page 37 of 44
OPERATIONS CEMENTATION
MANUAL Issue 2
If good returns were obtained at surface during the primary cement job, the casing to the
drive pipe annulus should be topped up as follows:
1. Run a 2 3/8” tubing stringer down to the annulus as far as possible.
2. Slowly pump the cement slurry (Class G cement mixed with 3% CaCl2 mix water)
until the annulus until good cement returns are obtained at surface.
Note: Stop pumping if there are no returns after pumping 50 bbl of grout cement.
3. Wait on cement for 2 hours.
4. Repeat the above procedure as required.
8.6.2.2 Procedure With Lost Returns
If good returns were not obtained at surface during the primary cement job, the casing to
the drive pipe annulus should be topped up as follows:
1. Run a 2 3/8” tubing stringer down the annulus.
2. Mix and pump the 300 sacks of extended cement slurry (Class G cement with no
retarder) down the annulus.
DRILLING DEPARTMENT
PETRONAS CARIGALI SDN BHD
DOM 8
DRILLING Page 38 of 44
OPERATIONS CEMENTATION
MANUAL Issue 2
DRILLING DEPARTMENT
PETRONAS CARIGALI SDN BHD
DOM 8
DRILLING Page 39 of 44
OPERATIONS CEMENTATION
MANUAL Issue 2
DRILLING DEPARTMENT
PETRONAS CARIGALI SDN BHD
DOM 8
DRILLING Page 40 of 44
OPERATIONS CEMENTATION
MANUAL Issue 2
iii. Hole stability, caving and string plugging for shale zones.
7. If excess cement does not have to be circulated out, pull back to 3 stands above
theoretical TOC and circulate drill pipe clean. Pull up 10 stands and circulate
bottoms up.
8. If the plug is to be tagged after the cement has set, keep the stinger moving while
WOC (reciprocate and rotate). Commence circulating before tagging the cement
plug.
9. Set the next plug or POOH.
DRILLING DEPARTMENT
PETRONAS CARIGALI SDN BHD
DOM 8
DRILLING Page 41 of 44
OPERATIONS CEMENTATION
MANUAL Issue 2
The setting of cement involves an exothermic (heat producing) reaction, which can be
detected by a temperature which is higher that that of the formation temperature gradient.
A temperature survey can therefore be used to indicate both the presence of cement and its
TOC during setting.
8.8.1.1 Application
a. The temperature survey can be used to determine TOC when a CBL is not planned,
or unreliable due to size of casing.
b. The optimum time to run the survey is between 6 - 12 hours after cementation.
c. For best results, the fluid inside the casing must be left undisturbed following
completion of the cementation until the survey is made.
d. The log should be recorded while running in the hole.
8.8.1.2 Interpretation
a. The log should follow the formation temperature gradient until an increase in
temperature indicates the TOC.
b. Below the TOC, the temperature is dependent upon the mass of cement in the
annulus; the greater the mass of cement, the greater the temperature.
c. The log should correlate with the calliper. If there is no correlation, it is probably an
indication of channelling.
d. Temperature anomalies can also be related to fluid movement behind the casing,
resulting from poor zonal isolation.
8.8.2 Cement Bond Logs
8.8.2.1 CBL
The CBL gives a continuous measurement of the amplitude of the first casing arrival at a
receiver spaced 3 ft from an acoustic transmitter. The absolute reading is a function of
various elements (e.g. casing size and wall thickness, cement bond quality, wellbore fluid,
tool type and tool centralisation). Because most of these parameters are constant, only
cement bond quality can be directly related to the amplitude measured. The amplitude is at
a maximum in unsupported pipe and at a minimum for well cemented casing.
Comparing log readings when run in pressurised and unpressurised casing may give
indications of the existence of a microannulus, as the readings will show an improved
casing to cement bond under pressure if a microannulus is present.
DRILLING DEPARTMENT
PETRONAS CARIGALI SDN BHD
DOM 8
DRILLING Page 42 of 44
OPERATIONS CEMENTATION
MANUAL Issue 2
The CBL is correlated to the open hole logs, and is usually run in combination with a
gamma ray (GR) and casing collar locator (CCL), to provide a correlation for any
subsequent operations.
8.8.2.2 VDL
The variable density log (VDL) provides a graphical representation of the actual sonic
waveform recorded at a 5 ft transmitter/receiver spacing. The extra spacing gives more
time for transit time differences to develop. In addition, information from the sonic
waveform beyond the first arrival is provided.
In VDL, a poor bond is noted by strong parallel black and white vertical stripes, while a
good one is noted by a dull grey featureless response where the casing signal is expected.
8.8.2.3 CET
The CET generally provides better cement bond evaluation than CBL/VDL and is largely
unaffected by micro-annuli. The determination of the cement quality can however be
unclear, and the tool is therefore usually run in combination with the CBL, to provide
additional cement quality information.
8.8.2.4 CBL/VDL Quality Control
The following guidelines shall be followed to ensure quality of the CBL/VDL log:
a. The log is normally run in casing sizes of 9 5/8” or less.
b. The tool shall be well centralised using at least 3 centralisers. It is essential that the
transmitter and receiver are within 1/8” of the pipe centre for results to be
meaningful.
Transit time measurements can give an indication of tool eccentricity. Table 18 lists the
expected transit times for a 3ft transmitter/receiver spacing in various casing sizes.
DRILLING DEPARTMENT
PETRONAS CARIGALI SDN BHD
DOM 8
DRILLING Page 43 of 44
OPERATIONS CEMENTATION
MANUAL Issue 2
The following guidelines shall be followed to ensure quality of the CET log.
a. The CET tool shall be calibrated downhole in free pipe to determine tool constants in
the specific environment of the well to be logged. The calibration plot produced shall
be presented on the log.
b. The tool eccentricity shall be less than 1/4”.
c. In general, the cement quality should agree with the CBL.
d. The 4 callipers should read within 1/8” of each other, and the ovality shall be less
than 1/8”.
e. There shall be no more than one black flag (indicating unreliable results) per foot.
f. Free pipe will show as white.
g. This tool should be run at least 36 hours after the cement has been displaced.
CBL/VDL CET
High CBL readings White on map
Parallel lines on VDL versus Depth CSMX* & CSMN* are zero
Weak formation signals
VDL shows clear “w” pattern at collars
No change in transit time with depth
White
*CSMX & CSMN are the Maximum and Minimum Cement Strength respectively.
Table 79, Free Pipe Characteristics
CBL/VDL CET
Low CBL readings Black on map
Casing signals very weak High CSMX & CSMN
Strong formation arrivals on VDL provided formation
attenuation is not too high
Formation arrivals change pattern with depth.
Casing arrivals show as parallel lines
May be a correlation between GR and VDL in shales
Table 20, The Characteristics of a Good Bond
DRILLING DEPARTMENT
PETRONAS CARIGALI SDN BHD
DOM 8
DRILLING Page 44 of 44
OPERATIONS CEMENTATION
MANUAL Issue 2
Table 21 lists the characteristics of hard formations (anhydrite/dense limestone) behind the
casing.
CBL/VDL CET
Formation arrivals precede the casing May show as free pipe but they may be
arrivals flagged
Can be identified on the VDL
In the following two cases, the CBL/VDL shows up as poor cement. The CET shall be used
to differentiate between the cases. This is important since channelling would be considered
a failure whereas the existence of a micro-annulus is unlikely to cause problems.
Table 22 lists the characteristics of a micro-annulus, which shall not be considered a failure
in the primary cement job.
CBL/VDL CET
Shown as poor cement Shown as good cement
Decrease in formation signal and increase in casing signal
Apply pressure to casing and re-run log. A micro-annulus
should now show up as good cement-unless hydraulic seal
prevents closing of the gap
Table 22, Characteristics of a Micro-annulus
CBL/VDL CET
Shown as poor cement Channels are easily seen
Decrease in formation signal and increase in casing signal since whole
circumference is scanned
Table 23, Characteristics of Cement Channelling
DRILLING DEPARTMENT
PETRONAS CARIGALI SDN BHD