Professional Documents
Culture Documents
Schedule Phase One - Eagt Church
Schedule Phase One - Eagt Church
Schedule Phase One - Eagt Church
1 1 1 21.80
10.80 235.44
-1 0 2 3.75
3.57 0.00
-1 0 1 1.20
3.30 0.00
-1 0 1 2.40
3.30 0.00
-1 0 1 5.30
3.20 0.00
-1 0 1 6.18
0.76 0.00
-1 0 1 1.17
2.23 0.00
-1 0 1 4.90
3.00 0.00
Pit excavation
1 1 12 1.80
1.80
2.00 77.76 F05 & F06
1 1 3 2.50
2.50
2.00 37.50 F01
0 1 1 1.00
1.00
2.00 0.00 F03
115.26 Total volume
163.49
&
25.00
138.49 Backfill
1 1 12 1.80
1.80 38.88 F05 & F06
1 1 3 2.50
2.50 18.75 F01
0 1 1 1.00 F03
1.00 0.00
84.43
84
1 1 3 2.50
2.50
0.50 9.38 F01
0 1 1 1.00
1.00
0.35 0.00 F03
28.82
29
Concrete to column
1 1 6 0.23
0.45
2.00 1.24 C05 &C06
1 1 6 0.23
0.30
2.00 0.83 C04
1 1 3 0.25
0.60
2.00 0.90 C01
2.97
2.97
concrete bed
1 1 1 17.21
12.46 214.37
0 1 1 8.00
1.46 0.00
0 1 1 8.00
0.96 0.00
0 1 1 3.65
0.60 0.00
0 1 1 2.05
3.65 0.00
0 1 1 4.45
2.75 0.00
0 1 1 5.15
3.50 0.00
0 1 1 5.95
0.75 0.00
214.37 sqm
Concrete to steps/Ramp
0 4 0.5 0.30
0.15
2.50 0.00 total volume
Formworks
Fwk to vertical sides of columns
1 1 6 1.36
2.00 16.32 C05 & C06
1 1 6 1.06
2.00 12.72 C04
1 1 3 1.70
2.00 10.20 C01
1 3 4 2.50
0.50 15.00 F01
0 3 2 2.16
0.35 0.00 F02A
0 3 2 1.10
0.35 0.00 F02B
0.00 lm
0 1 1 32.37
0.20 0.00
20.33 sqm
Reinforcement
Reinforcement for column bases
16mm diameter
1 12 20 1.90 456.00 F05, F04, F06
1 3 27 2.60 210.60 F01
0 3 14 2.26 0.00
0 3 24 1.20 0.00
666.60
1052.56 kgs
518.29 kgs
193.82 kgs
1 1 2 0.23
0.45
8.70 1.80 C05
1 1 4 0.23
0.45
4.80 1.99 C06
1 1 3 0.25
0.60
8.70 3.92
11.30 M3
Conrete to beam
1 1 1 30.92 tie beam & ring beam
0.23
0.45 3.20 MFB 01, MFB 11
1 1 1 34.41
0.25
0.50 4.30 MFB 07
1 1 1 16.71
0.25
0.70 2.92 MFB 02
1 1 1 34.41
0.25
0.50 4.30 FB 07
1 1 1 16.71
0.25
0.70 2.92 FB 02
8.09 m3
Concrete to suspended slab
0 1 1 5.42
4.27 0.00 FF & SF & MR
0 1 1 5.10
2.55 0.00
0 1 1 8.98
5.77 0.00
0.00
0 2 1 3.77
1.77 0.00
0 2 1 3.77
5.77 0.00
0.00
0 2 2 3.77
2.45 0.00
0 2 2 3.77
4.57 0.00
0 2 2 2.97
3.77 0.00
0 2 1 3.77
1.23 0.00
0 2 1 0.89
10.45 0.00
0 1 1 1.50 Landing
2.75 0.00
0 1 2 2.69
3.70 0.00
Concrete to gutter
0 1 1 8.74
0.89 0.00 total volume (soffits)
0 1 1 6.08
0.89 0.00 total volume for sides
0 1 1 12.47
0.89 0.00
0 1 1 4.10
0.89 0.00
Concrete to stair
0 21 0.5 1.28 Flight 01 & 02
0.30
0.15 0.00
0 14 0.5 0.90
0.30
0.15 0.00
0 1 2 1.28 Waist
6.20
0.15 0.00
0.00 Total cubic metre
1 1 2 1.36
8.70 23.66 C05
1 1 4 1.36 C06
4.80 26.11
1 1 3 1.70 C01
8.70 44.37
149.48 Total
1 1 2 34.41
1.25 86.03 MFB 07
1 1 2 16.71
1.65 55.14 MFB 02
1 1 1 12.46
0.83 10.34 FB 01
0 1 4 5.49
0.83 0.00
0 3 15 0.95
0.83 0.00
0 1 2 3.90
2.72 0.00
0 1 2 4.20
1.27 0.00
0 1 1 9.00
2.08 0.00
0 1 3 3.97
1.75 0.00
0 1 1 2.30
1.50 0.00
0.00 Total
Formwork to stair
0 1 2 6.20 Soffities
1.28 0.00
WALLING (230mm)
External wall
1 1 2 17.11 34.21
1 1 1 13.66 13.66
0 1 1 4.00 0.00
0 1 1 7.76 0.00
0 1 1 7.73 0.00
0 1 1 17.66 0.00
0 1 1 29.33 0.00
0 1 1 2.75 0.00
0 1 1 5.65 0.00
0 1 1 4.73 0.00
0 1 1 3.83 0.00
0 1 2 1.50 0.00
0 1 1 14.24 0.00
0 1 1 3.50 0.00
0 1 1 0.84 0.00
47.87
10.21
488.75 total area (sqm)
488.75 Total sqm
ddt: openings
1 1 10 1.20
2.45 29.40
1 1 6 3.00
1.50 27.00
1 1 1 0.90
3.00 2.70
0 1 3 1.00
2.45 0.00
0 1 5.00 1.20
2.45 0.00
0 1 3.00 0.80
1.00 0.00
0 1 2.00 1.70
2.45 0.00
0 1 1.00 1.20
3.00 0.00
0 1 1.00 2.00
3.00 0.00
0 1 1.00 0.90
3.00 0.00
0 1 2.00 2.40
2.00 0.00
59.10
0.00
4.35
0.00 total area
ddt: openings
0 1 6.00 0.75
3.00 0.00
0 1 1.00 0.60
3.00 0.00
0 1 4 0.90 429.65
3.00 0.00
0.00
4.35
0.00 total area
ddt: openings
0 1 6.00 1.24
2.40 0.00
0 1 13.00 0.70
2.40 0.00
0 1 7 0.90 0.00
2.70 0.00
20.66 Total
6.10
126.03 total area
1 1 3.00 0.80
1.00 2.40
1 1 1.00 1.30
4.10 5.33
16.06
109.97 total area for externally
12.27
4.15
50.92
ddt;
1 1 3.00 0.90
3.00 8.10
1 1 1.00 0.75
3.00 2.25
1 1 1.00 12.46
14.55 181.29
0 1 1 14.32
3.20 0.00
0 1 1.00 0.76
8.05 0.00
221.54 total area (sqm)
Bottom chord
0 34 2 12.82 0.00 TI
1 1 4 22.47 89.90 T2
0 2 4 5.37 0.00
0 1 11 4.23 0.00
89.90 total lm
Top chord
0 34 2 16.17 0.00 T1
1 1 4 10.70 42.80 T2
0 1 4 10.66 0.00
0 1 11 4.20 0.00
42.80 total lm
STRUTS
1 1 1.00 25.63 25.63 Total lm
PURLINS
1 2 6 14.40 172.80
0 1 5 6.25 0.00
0 2 7 3.60 0.00
0 1 6 11.90 0.00
172.80 Total lm
Finishing
Floor finish
1 1 1 14.10
12.00 169.14 Ground floor
1 1 1 4.80
3.00 14.40
1 1 1 3.00
3.00 9.00
1 1 1 1.92
1.20 2.30
1 1 1 1.08
1.35 1.46
1 1 1 1.20
3.00 3.60
0 1 1 1.64
4.00 0.00
Internal plastering
1 1 2 14.10 28.19 Ground
1 1 2 12.00 24.00
0 1 3 4.00 0.00
0 1 2 1.64 0.00
0 1 3 5.50 0.00
0 1 2 5.64 0.00
0 1 1 2.93 0.00
0 1 1 3.18 0.00
0 1 1 9.75 0.00
0 1 1 7.42 0.00
52.19 total length
10.21
532.86 sqm
Height 2
1 1 1 7.20 7.20
1 1 1 10.80 10.80
1 1 1 9.00 9.00
1 1 1 5.94 5.94
1 1 1 11.10 11.10
0 1 1 1.31 0.00
0 1 4 5.28 0.00
0 1 1 3.54 0.00
44.04 total
5.71
251.47
1 1 6 3.00
1.45 26.10
1 1 2 1.70
2.45 8.33
0 1 3 0.90
2.45 0.00
1 1 3.00 0.80
1.00 2.40
1 1 8.00 0.90
3.00 21.60
1 1 2.00 0.75
3.00 4.50
0 1 1 0.60
3.00 0.00
0 1 6 3.20
2.30 0.00
0 1 3 1.24
2.30 0.00
0 1 1 2.40
1.70 0.00
0 1 1 1.80
2.30 0.00
0 1 6 2.50
3.10 0.00
0 1 16 1.24
3.00 0.00
0 1 29 0.80
3.10 0.00
86.45
697.88 total internal plastering (sqm)
Externally plastering
1 1 2 14.10 28.20 Height 01
0 1 1 21.57 0.00
0 1 1 4.23 0.00
0 1 1 7.99 0.00
0 1 1 7.96 0.00
0 1 1 4.05 0.00
0 1 1 6.55 0.00
0 1 1 3.03 0.00
0 1 1 6.46 0.00
0 1 1 8.49 0.00
0 1 1 31.96 0.00
0 1 1 14.31 0.00
28.20
10.21
287.92 total area
Height 02
1 1 2 3.00 6.00
1 1 2 1.80 3.60
1 1 1 13.22 13.22
0 1 1 4.80 0.00
0 1 2 5.69 0.00
22.82 total length
6.16
140.57 total area
ddt:
1 1 8 1.20
2.45 23.52
0 1 3 1.00
2.45 0.00
0 1 5.00 1.20
2.45 0.00
1 1 3.00 0.80
1.00 2.40
1 1 2.00 1.70
2.45 8.33
1 1 1.00 1.30
3.50 4.55
0 1 1.00 2.00
3.00 0.00
0 1 10 0.87
1.00 0.00
38.80
389.69 Total external plastering (sqm)
Skirting
96.23 total lm
0.00 1.00 1.00 28.80 0.00
96.23
ddt:
1.00 1.00 2.00 0.75 1.50
1.00 1.00 8.00 0.90 7.20
0 1 12 0.70 0.00
0 1 3 1.27 0.00
87.53 total skirting (lm)
Brandering
1 1 6 1.20 7.20
1 1 3 3.00 9.00
1 1 6 4.80 28.80
1 1 9 3.00 27.00
1 1 6 3.00 18.00
1 1 6 3.00 18.00
1 1 4 1.20 4.80
1 1 3 1.77 5.31
1 1 3 3.00 9.00
1 1 6 1.20 7.20
1 1 3 1.35 4.05
1 1 3 1.08 3.24
4,187.00
4,187
4,187.00
&
-1 1 1 1.50
5.65 (8.48)
-1 1 1 4.00
8.65 (34.60)
-1 1 2 3.50
5.65 (39.55)
-1 1 2 10.00
8.65 (173.00)
-1 1 1 2.57
5.33 (13.70)
-1 1 1 4.00
9.16 (36.64)
-1 1 1 3.50
5.33 (18.66)
-1 1 1 3.50
9.16 (32.06)
-1 1 1 10.00
9.16 (91.60)
633.00
253
C/L of fdn trench
1 1 3 28.82 86.46
1 1 1 3.83 3.83 GRID D
1 1 1 3.00 3.00 GRID D
1 1 2 9.16 18.32 GRID E
1 1 1 3.83 3.83 GRID H
1 1 1 3.00 3.00 GRID H
1 1 1 37.50 37.50
1 1 1 3.43 3.43
1 1 3 6.00 18.00
1 1 1 4.50 4.50
1 1 2 3.50 7.00
1 1 2 10.50 21.00
1 1 2 3.50 7.00
216.87
216.87
PITS
1 1 51 2.90
2.90
1.50 643.37 F1
644
214.46
214
Plinth beam
1 1 3 28.82 86.46
1 1 1 3.83 3.83 GRID D
1 1 1 3.00 3.00 GRID D
1 1 2 9.16 18.32 GRID E
1 1 1 3.83 3.83 GRID H
1 1 1 3.00 3.00 GRID H
1 1 1 37.50 37.50
1 1 1 3.43 3.43
1 1 3 6.00 18.00
1 1 1 4.50 4.50
1 1 2 3.50 7.00
1 1 2 10.50 21.00
1 1 2 3.50 7.00
Manual
1 1 1 216.87 216.87 length of plinth beam
217.0
63 Backfill
269.79
270
16
104
104
75.74
76.00
164
164
262
262
reinforcement column bases
1 24 51 2.70 3,304.80 Y16
1 1 1 275.40 275.40
3,580.20
3,580
1,259.70
1,260
8 to columns
1 9 51 1.40 643.00 y8
182
16
141
Reinforcement to beams
1 1 4 217.00 868.00
1 1 1 72.33 72.33
940.33
940
floor bed
1 1 1 37.50
28.82 1,080.75 clear site
-1 1 1 1.50
5.65 (8.48)
-1 1 1 4.00
8.65 (34.60)
-1 1 2 3.50
5.65 (39.55)
-1 1 2 10.00
8.65 (173.00)
-1 1 1 2.57
5.33 (13.70)
-1 1 1 4.00
9.16 (36.64)
-1 1 1 3.50
5.33 (18.66)
-1 1 1 3.50
9.16 (32.06)
-1 1 1 10.00
9.16 (91.60)
632
632
632
632.47 H/core
less 49.88 583
583
217.00
217
158
total excavation
63.00 trench
644.00 colum base
253.00 reduce level
960.00
960
207.79
208
208 disposal from trench excavation
752
146
315
26.30
27
355
Y16mm columns
3,508.80
3,509
11,368.73
11,369
0 4 6 3.00 -
- Y12mm diameter
1 51 32 1.40 2,285.00 y8
2,971
Beam
concrete to beam
1 1 1 217.00
0.23
0.35 17.47
34.94
35
1 1 1 217.00
0.93
1.00 201.81
403.62
404
16mm to BEAMS
1 1 8 217.00
1.00
1.00 1,736.00
3,038.00 253.17
0.23
3,798
3,607.69 300.64
0.18
3,608
reinforcement to slab
1 2 10 271 5,420.00
5,420.00
-1 1 1 1.50
5.65 (8.48)
-1 1 1 1.50
11.01 (16.52)
-1 1 1 5.33
2.57 (13.70)
270.22
271
FLOOR FINISH
1 1 1 10.73 GROUND FLOOR SLAB
7.00 37.56
1 1 1 17.27
3.20 55.26
1 1 1 24.13
10.27 247.82
1 1 1 17.27
3.20 55.26
1 1 1 6.00
4.50 27.00 ALTAR
1 1 1 3.87
4.50 17.42
1 1 1 5.65
7.26 41.02 URINALS
1 1 1 2.77
6.23 17.26
1 1 1 3.37
4.09 13.77
1 1 1 3.91
4.27 16.67 OFFICES
1 1 1 1.20
2.73 3.28
1 1 1 5.14
5.17 26.59 RESTAURANT
1 1 1 5.60
5.77 32.31 KITCHEN/ STORE
1 1 1 5.33
2.32 12.37 WC
1 1 1 5.60 VERRANDAH
1.32 7.39
1 1 1 2.00
10.80 21.60 ENTRY VERR
1 1 1 10.73
2.73 29.29 ENTRY VERRANDAH
1 1 5 10.73 STAIRS-GOING/STEPS
0.30 8.05
1 2 5 4.23
0.30 12.69
1 1 5 10.73 RISER
0.15 4.02
1 2 5 4.23
0.15 6.35
2 1 5 11.00 STAIRS-GOING/STEPS
0.30 16.50
2 2 5 2.50
0.30 15.00
2 1 5 11.00 RISER
0.15 8.25
2 2 5 2.50
0.15 7.50
1 1 6 8.65 WC2
0.15 3.89 RISER
1 1 4 17.23 ALTAR
0.15 5.17 RISER
783.00
STAIRCASE
2.75
2.74
10
27
28
22 1 1 2.75 12MM
1.50 91
2 2 1 4.03
1.38 22
113 M
100 KG
WALLING
External wall
ext wall CL
1 2 1 37.73 75
1 2 1 29.05 116
1 4 1 9.16 73
264.94
1,722.11
Gable wall
1 1 3 12.13 36
1 1 1 12.64 13
49
1 1 0.5 49.03
9.12 223.45
48
1 1 1 47.91
3.20 153.31
ddt ditto
1 1 2 3.20 ground floor
2.12 13.57 w1
1 1 2 3.50
2.12 14.84 w2
1 1 2 3.27
2.12 13.86 w3
1 1 2 3.27
2.12 13.86 w4
1 1 2 3.20
2.12 13.57 w5
1 1 2 1.50
2.12 6.36 w6
1 1 2 1.50
2.12 6.36 w7
1 1 2 3.20
2.12 13.57 w8
1 1 2 3.20
2.12 13.57 w9
1 1 2 3.20
2.12 13.57 w10
1 1 11 0.90
0.90 8.91 w11
1 1 3 1.50
1.80 8.10 w12
1 1 1 1.20
0.90 1.08 w13
1 1 6 2.50
3.10 46.50 door
1 1 4 1.80
3.10 22.32
1 1 2 1.20
0.90 2.16 w2
1 1 2 2.40
1.80 8.64 w3
1 1 1 1.20
3.10 3.72 D
237.52
1,862
internal wall;
ground floor
1 1 8 1.93 15.44 Internal wall150mm Thick gf
1 1 1 4.72 4.72
1 1 1 6.00 6.00
1 1 3 4.00 12.00
1 1 1 4.73 4.73
1 1 1 3.10 3.10
1 1 1 5.65 5.65 wc
1 1 1 5.33 5.33 wc
1 1 1 9.24 9.24
1 1 1 11.57 11.57
77.78
1 1 1 77.78
3.20 248.88
ddt
1 11 0.80 3.1 27.28 doors
1 2 0.90 3.1 5.58
1 2 1.20 3.1 7.44
40
209
first floor
1 1 2 6.00 12.00 Internal wall150mm Thick gf
1 1 1 4.69 4.69
1 1 1 14.88 14.88
31.57
1 1 1 31.57
3.20 101.02
ddt
1 2 0.80 3.1 4.96 doors
1 3 1.20 3.1 11.16
16
85 net 230mm thick first floor internal wall
Louvre block
1 1 1 18.22
10.05 183.09
deduct
-1 1 1 5.00
3.35 (16.73)
ROOFING
50x150mm top chord black pipe
1 7 2 12.68 177.52 T24
177.52
178
50 X 150mm bottom chord
1 7 2 11.91 166.78 T24
166.78
167
struts
100 X50mm
1 7 2 36.45 510.34 T24
510.34
561
- 231.00
231
340.60
426
TIMBER STRUCTURE
Rafters
1 6.00 2 5.71 68 T01
1 5.00 1 3.37 17 T26
1 4 2 3.37 27 T10
2 3 2 2.88 35 T2
1 1 1 -
191
Struts
1 6 1 25.18 151 T01
1 5 1 6.60 33 T26
1 4 1 11.28 45 T10
2 3 1 9.10 55 T02
284
Tie beam
1 6 1 12.83 77 T01
1 5 1 2.77 14 T26
1 4 1 5.51 22 T10
2 3 1 4.71 28 T02
141
PURLINS
1 2 5.75 8.67 100 at T1
1 2 4.93 1.83 18 at T2
1 2 5.59 5.56 62 at T7
1 1 5.60 6.83 38 at T10
273
wall plate
1 1 2 3.50 14
1 1 1 1.56 3
1 1 1 7.72 15
1 1 1 9.88 20
-
52
1 1 2 6.24
6.49 114.45
1 1 1 6.26
8.02 71.04
1 1 2 3.50
1.49 14.70
1 1 1 6.43
5.61 51.05
761
0 1 2 12.78 - valley
0 1 2 7.08 -
RAINWATER DISPOSAL
46
1 1 8 1 8 Roof outlet
1 1 8 1 8 swanneck
1 1 8 1 8 shoe
1 1 10 1 10 stop end
10
1 1 10 1 10 outer angle
10
1 1 10 1 10 inner angle
10
BILL No.3 - MEASURED WORKS
Item Description Unit Qty Rate Amount
ELEMENT No. 1
SUBSTRUCTURES
Hardcore
150mm Thick bed levelled, compacted and blinded to
A sm 207
receive polythene membrane (measured separately)
Soil sterilization
Concrete Work
Plain concrete grade "10" nominal mix (1:4:8)
H Column cm 3
cement bags 24 17,000 403,920
Sand cm 2 25,000 50,000
agregates cm 3 100,000 300,000
Item Description Unit Qty Rate Amount
To Collection 19,083,088
3/1/1
A Plinth beam cm 6
cement bags 60 17,000 1,014,727
Sand cm 4 25,000 100,000
agregates cm 5 100,000 537,208
B Ramp/STEPS cm 2 -
Cement bags 12 17,000 204,000
sand cm 2 25,000 50,000
Agregates cm 1.8 100,000 180,000
Reinforcement
Bars; high tensile; hot rolled deformed steel
reinforcement to B.S 4449:1969
Fabric; BS 4483
To Collection 88,670,112
3/1/2
Walling
Block work
Solid concrete blocks to B.S 2028 type 'A' bedded and
jointed in cement and sand mortar (1:3)
A 230mm wall sm 90.27
450x230x150mm blocks No 1263.724 1,500 1,895,586
Sand cm 18 25,000 450,000
Cement bags 21 17,000 357,000
C DPC lm 50.84
Damp proof Course Roll - 85,000 -
To Collection 3,206,962
COLLECTION
3/1/3
Item Description Unit Qty Rate Amount
ELEMENT No. 2
REINFORCED CONCRETE SUPERSTRUCTURE
Reinforced Concrete grade "25" nominal mix (1:1.5:3)
including vibrating around reinforcement
A Columns cm 11
Cement bags 90 17,000 1,537,466
Sand cm 9 25,000 225,000
agregates cm 10 100,000 1,000,000
C Beams cm 8
Cement bags 65 17,000 1,099,593
Sand cm 6 25,000 154,630
agregates cm 7 100,000 727,672
Reinforcement
Bars; high tensile; hot rolled deformed steel
reinforcement to B.S 4449:1969
ELEMENT No. 3
SUPERSTRUCTURE (WALLING )
Solid concrete blocks; to B.S 6073; type "A" 5.0N per
square milimetre bedded and jointed in cement and
sand (1:4) mortar
A External walling
230mm Thick walling sm 540
450x230x150mm No 7555 1,400 10,576,527
Sand cm 27 25,000 675,000
cement bags 151 17,000 2,567,000
Internal walling
B 150mm Thick walling sm 41
450x230x150mm No 365 1,400 511,188
Sand cm 24 25,000 600,000
cement bags 9 17,000 153,000
3/3/1
ELEMENT NO. 4 - ROOFING
J Struts m 25.63
7 mm x 37.5 mm diameter tubular pipes pcs 4.00 15,000 60,000
K Z-Purlins m 172.80
126 mm x4 mm pcs 29.00 65,000 1,885,000
Item Description Unit Qty Rate Amount
To collection 10,611,164
3/4/1
Tie Beams ; m 26
A 150 x 50mm treated timber pcs 7 12,000.00 84,000.00
Struts m 39
B 150 x 50mm treated timber struts pcs 11 12,000.00 132,000.00
Purlins m 58
D 50 x 75 mm treated timber pcs 16 12,000.00 192,000.00
Rafters; m 26
E 150 x 50mm treated Timber pcs 7 12,000.00 84,000.00
Wall plates m 13
F 50 x 100mm pcs 4 12,000.00 48,000.00
To Collection 540,000
COLLECTION
3/5/1
ELEMENT No.6
DOORS
Ironmongery
To Collection 4,844,000
3/6/1
A Clear varnish -
Clear varnish ltr 45 8,000 360,000
sanding sealer ltr 20 9,000 180,000
Thinner ltr 10 5,000 50,000
B Solvent ltr 15 6,000 90,000
C Brushes 4'' no 10 4,500 45,000
D sand paper m 25 3,500 87,500
-
-
E 5mm Thick Clear Glass Pcs 5 45,000 225,000
F Nails 1/2'' kg 1 5,000 5,000
To Collection 1,042,500
COLLECTION
3/6/2
ELEMENT No. 7- FINISHING
C 15 mm to beams m2 32
Cement bags 6 17,000 102,000
Sand m3 2 25,000 50,000
F 15 mm to walls m2 390
Cement bags 78 17,000 1,326,000
Sand m3 22 25,000 545,570
To collection 10,359,000
3/7/1
Ceramic floor tiles s to BS 1282 non- slippery
fixed to backing with adhesive and pointed m2 6
with coloured grouts
B 15 x100 mm skirting m 88
Grouts pkt 9 4,000 36,000
To Collection 1,005,500
Item Description Unit Qty Rate Amount
COLLECTION
MATERIALS SCHEDULES
CLIENT:
JULY,2021
BILL No.2 - PROVISIONAL AND P.C SUMS
PROVISIONAL AND P.C SUMS
VII/2/1/1
PRELIMINARIES AND GENERAL MATTERS
Item Description Amount
A The contractor shall provide at his own risk and cost all materials
scaffolding, tools , plants transport and workmen required for the works
except in so far as may be stated otherwise herein. No timber used for
scaffolding, formwork , or similar purposes shall be used afterwards in
the permanent works. 5,000,000.00
D The contractor shall pay rates of wages and observe hours and
conditions of labour not less than favourable than those laid down in
the Regulationsof wages and conditions of employment Act of the
Building and Construction Industry issued by the government.
F The contractor shall provide at his own expenses all watching , lighting
and protection of the works , materials and public through fares as may
be necessary for the safety of the works and for the public and his own
employees. 1,000,000.00
To collection 7,000,000.00
Item Description Amount
1/1/1
B The Contractor shall provide at his own risk and cost all water for the
use in connection with the works including Sub- contractor's work ,
make arrangement for the connection to the main and provision of a
meter for all water used by him throughout the construction and pay all
costs , fee and charges in connection herewith. He shall provide all
necessary storage, cisterns, tubing and the like and remove on
completion. All water used in the works shall be fresh, clean and pure;
free from organic matters and alkaline substances in solution or in
suspension. 1,000,000.00
C The Contrator shall arrange for a temporary meter and supply to the
site and shall provide all temporary wiring power and lighting points for
the whole of the works and clear away when no longer required. He
shall pay all charges for the same and for current consumed.
Disturbance or nuisance
E The contractor shall make every effort to avoid and in any event shall
be liable for any undue disturbance amounting to nuisance to the
occupiers of the contigous properties by reasons of noise, dust, traffic
and the like or by negligence in controlling his workmen or materials.
F The contractor shall, at his own cost, supply and erect all temporary
buildings, sheds, messrooms and stores with floors at least 150mm
above ground level. No office, stores or other temporary building shall
be erected on the site without first obtaining the consent of the
architect as to the type of temporary building to be supplied and the
position on which they are to be erected. 300,000.00
Item Description Amount
To collection 1,300,000.00
1/1/2
Protection of the works
A Cover-up and effectively protected works from injury by weather ,traffic
or otherwise and case up and protect cells, stops, joinery and all other
work as may be necessary. 200,000.00
Testing:
Sign boards
F The contractor shall remove all rubbish and superfluous materials from
the site of the works with all reasonable speed from time to time and at
completion. 450,000.00
Item Description Amount
To collection 1,950,000.00
1/1/3
A The contractor shall also properly cleanse floors, woodwork, steps,
paving, roads, hard standings, glass (inside and outside), cisterns,
flushing cisterns, all finishing and leave the whole of the works in a
sound and perfect condition free from all defects whatsoever, and to
the satisfaction of the Architect.
Collection
1/1/4
GENERAL SUMMARY