Professional Documents
Culture Documents
Saep 79
Saep 79
Saep 79
Contents
1 Scope ................................................................ 2
2 Conflicts and Deviations .................................... 2
3 References ........................................................ 2
4 Definitions .......................................................... 4
5 General Requirements ....................................... 5
6 Pipeline Section Replacement ........................... 7
7 Repair Methods and Requirements ................... 8
8 Hyperbaric Welding Procedure Qualification ... 18
9 Subsea Flexibles ............................................. 19
10 Pressure Testing .............................................. 20
11 Coatings........................................................... 21
12 Cathodic Protection ......................................... 21
Revision Summary ............................................... 222
1 Scope
1.1 This SAEP describes the procedures to be followed for the repair of rigid subsea
pipelines.
1.2 The requirements are primarily for rigid pipelines, however, repair of subsea
flexibles is also discussed in Section 9.
1.3 The repair of offshore platform piping is not within the scope of this procedure
and is covered in SAEP-310.
1.4 The repair method for subsea pipeline shall be based on the most economical
and the most practical method/solution.
1.5 The repair methods and procedures set forth herein are the minimum
requirements and are not a release from the responsibility for prudent action that
circumstances make advisable.
1.6 The repair procedures shall comply with safety management processes outlined
in Company Safety Management System (SMS), Element #5, Asset Integrity.
2.1 Any conflicts between this document and other applicable Mandatory Saudi
Aramco Engineering Requirements (MSAERs) shall be addressed to the
Engineering Support Department (ESD) Manager.
2.2 Any deviation from the requirements herein shall follow internal company
procedure SAEP-302, Waiver of a Saudi Aramco Engineering Requirement.
3 References
The requirements contained in the following documents apply to the extent specified in
this procedure.
Industry Practices
IMCA D 014 IMCA International Code of Practice for Offshore
Diving
4 Definitions
Demarcation Point: A point along the onshore portion of the line, established in the
Project Proposal, to mark the location at which the submarine pipeline ends as
referenced in the installation contract.
Free Span: A pipe segment which is not supported by the seabed due to uneven
seabed, pipeline crossings, tie-in to subsea structures, soil scouring, etc.
Pipeline Stabilization: The measures required to stabilize the pipeline on the seabed
during its design life.
Subsea Pipelines: All lines used for the transportation of fluids and/or gases, installed
on or below the sea bed between an offshore facility and the demarcation point onshore
or another offshore facility.
5 General Requirements
5.1 Any repair methods that are not addressed in this procedure shall be reviewed and
approved by the Offshore Engineering Group of Consulting Services Department.
5.2 The adopted procedure shall ensure safe repair of subsea pipelines.
5.3 Prior to commencing any repair activities, subsea pipeline damage shall be
investigated and assessed considering that the extent of damage can vary from
insignificant to a fully buckled, ruptured or parted pipeline. The extent of
damage shall be classified as per following damage categories:
a) Minor Damage (D1): Damage not resulting in release of hydrocarbons or
water and not requiring repair.
b) Moderate Damage (D2): Damage not resulting in release of hydrocarbons
or water but requiring repair.
c) Major Damage (D3): Damage resulting in release of hydrocarbons or water.
5.4 Defect assessment for metal loss shall be conducted in accordance with
SAEP-306. The severity of internal anomalies originating from in line
inspection shall be determined to establish the appropriate damage category.
Similar approach shall be used for wall thickness metal loss resulting from
external corrosion.
5.5 When the pipeline defects are not acceptable as per SAEP-306, pipeline pressure
derating shall be considered. Calculations shall be reviewed by the Offshore
Engineering Group of Consulting Services Department.
Commentary Note:
5.6 Damage types falling under either moderate or major damage categories shall be
repaired as per the requirements of this procedure.
5.7 Subsea pipeline repair methods should be according to Table A-1, Appendix A.
Selection of the repair method should be evaluated based on the economics and
the practicality of the repair methods.
5.8 Pipeline damage/defects that are not addressed in Table A-1 should be reviewed
by the Offshore Engineering Group of Consulting Services Department.
5.9 A risk assessment shall be carried out by the proponent organization. It should
include but not limited to the assessment of defect types and location, design and
operating conditions, geometry, effect of impact and environmental loading.
5.11 Prior to commencing any repair work, a written procedure meeting all the
requirements outlined in Appendix B shall be developed. The procedure shall
be reviewed by the Offshore Engineering Group of Consulting Services
Department and approved by all parties involved in the repair activities.
5.11.1 The procedure shall comply with GI-0002.100, “Work Permit System,”
GI-0006.012, “Isolation, Lockout, and Use of Hold Tags,” and
GI-0002.711 “Fire and Safety Watch.”
5.11.2 The procedure shall include detailed requirements for safe working
conditions.
5.11.4 The procedure shall detail the safety measures associated with all
mechanized repair equipment.
5.11.5 The procedure shall include all required data such as pipe diameter, wall
thickness, grade, etc.
Saudi Aramco: Company General Use
©Saudi Aramco 2019. All rights reserved Page 6 of 24
5.12 Seabed preparation shall be performed either by jetting out the damaged area or
by excavation in case of hard seabed to locate the damage and to provide
sufficient access at the bottom of the pipeline during repair.
5.13 Concrete weight coating shall be removed from the subsea pipeline by water
blaster, sledge hammer or hydraulic jack hammer. Concrete coating removal
process shall be carefully controlled to avoid gouging on the pipeline.
5.14 External corrosion coating such as FBE shall be removed with grit blaster,
3M pads or wire wheel. Grinder shall not be used for the removal of corrosion
protection coating.
6.1 Pipeline sections with cracks, rupture, severe damage (e.g., caused by dropped
objects) or with defects that cannot be repaired shall be removed or replaced.
6.2 Pipeline section replacement can be performed using any of the following
methods as appropriate:
a) Mechanical connectors
b) Pipeline lifting
c) Hyperbaric dry welding
6.4 Pipeline cutting shall be performed with mechanical cutters such as diamond
wire, guillotine saw or travel cutter.
6.5 The new replacement section shall meet the requirements of SAES-L-850 and
01-SAMSS-012.
6.8 For leaking girth welds, pipeline section replacement shall be performed as use
of alternative repair methods is not allowed.
7.1.1 Offshore repair sleeve may be used for leaks, severe internal corrosion
defects and for externally damaged pipeline resulting from external
corrosion or mechanical damage such as dents.
7.1.2 The suitability of repair sleeve for a given application shall be assured by
considering all relevant parameters.
7.1.2.1 The design strength (SMYS) of the repair sleeve shall be the
same or greater than the pipeline.
7.1.2.4 The sleeve design shall allow easier and faster installation
which will reduce the offshore repair time.
7.1.3.2 Marine epoxy coating (paint), plated studs and nuts and
sacrificial anodes shall also be provided to protect against
external corrosion.
7.1.4 Repair sleeve shall not be used for leaking girth welds of subsea
pipelines.
7.2.1 Mechanical connectors can be used for pipeline section replacement and
shall be considered as the most preferable option.
7.2.4 Swivel ring flanges shall be installed on spool piece (if needed) which
enables the diver to easily align the bolt holes of the swivel flange to the
other fixed flange on the mechanical connector.
7.2.5 Mechanical connectors shall have test ports which can be used to check
main seal integrity.
7.3.1 Pipeline section replacement can be carried out by lifting the pipeline to
the vessel provided that there are no severe/excessive defects in the
pipeline. This shall be confirmed based on the findings of the latest
in-line inspection (ILI) and external subsea inspection reports.
7.3.2 Lifting strategy shall be established taking into consideration the pipeline
data, extent of the damage and the pipeline condition during lifting,
e.g., empty or flooded.
7.3.2.1 Lifting the pipeline above sea level and performing the cutting
and repair on the vessel shall be the preferred option, if feasible.
7.3.2.2 Cutting the damaged pipeline section subsea and lifting each of
the pipeline end separately for subsequent repair activities can
also be performed.
7.3.2.3 After cutting the damaged pipeline section, bevel the pipe ends
and perform MPI and measure wall thickness prior to welding.
7.3.2.5 Install external clamps for fine tuning the alignment to achieve
the required alignment.
7.3.2.6 Preheat the pipe using propane flame or heating blankets until
temperatures reaches the minimum preheat temperature
specified in the welding procedure specification.
7.3.2.11 The flanged pipeline end shall be lowered back to the seabed.
Saudi Aramco: Company General Use
©Saudi Aramco 2019. All rights reserved Page 10 of 24
7.3.2.12 The sections 7.3.2.3 to 7.3.2.10 above shall be repeated for the
other end of the pipeline.
7.3.3 For internally coated pipelines, repair by section replacement shall only
be performed by flanged connections.
7.3.4.1 The capacity and location of lifting davits from stern of the
proposed vessel to be used for pipeline lifting shall be provided.
7.3.4.4 Local buckling checks as per API RP 1111 and DNV OS F101
shall be performed to confirm that buckling of the pipeline will
not occur for the chosen lifting curve configuration.
7.3.4.5 The loads on the lifting davits shall be within the capacity of
lift davits.
7.4.2 With the bevels completed and accepted, install welding plugs into the
pipeline ends to a distance of at least 500 mm and inflate plug seal.
7.4.3 On the vessel deck, prepare a pup piece with suitable length that will fit
between the pipeline ends, bevel both ends. NDT shall be carried out
on the pup piece prior to cutting and after beveling to ensure the bevel
ends are free of defects.
7.4.4 Install rigging on the pup piece and lower the pup pieces until it is
aligned with both ends of the beveled pipeline subsea. During
alignment, of the two ends, extreme caution should be used to ensure
bevel ends do not touch; which could results in damage to the bevels.
Once alignment is achieved, install temporary bevel protector such as
half shells over the ends.
7.4.5 Deploy habitat onto position over the welding ends, in accordance
with the approved habitat deployment procedures and lifting plan.
Extreme care must be taken to avoid contacting the pipes during
installation and risk damaging the pipe and bevels.
7.4.6 Perform additional dredging for habitat (if required). Do not over
dredge as excessive dredging will require concrete matrasses/sandbag
installation to raise the height of the habitat.
7.4.7 Once habitat is in position, displace (blowdown) water from the habitat.
Install welding and preheat umbilicals according to the habitat system
standard operating procedures.
7.4.8 The temporary bevel protection shall be removed and the welding plugs
shall be inflated. Final alignment shall be made by moving the pipe
ends, until root gap is within welding specification tolerances.
7.4.9 Install external clamps for fine tuning the alignment to achieve the
required alignment.
7.4.10 Install preheat blankets onto pipeline ends and pup piece and install
clamps over blankets to ensure full contact with underlying pipe.
7.4.16 Perform free span rectification, if any, in accordance with Section 7.7
and recover pipe handling frames (if applicable) to vessel deck.
7.4.17 Deflate welding plug seal then pressurize pipeline to send the welding
plugs to a plug receiving facility such as scraper receiver.
7.5.1 Composite repair of subsea applications for both internal and external
corrosion is allowed as temporary repair only. The repair lifetime shall
be specified by the end user.
Saudi Aramco: Company General Use
©Saudi Aramco 2019. All rights reserved Page 13 of 24
The lifetime of the repair shall not exceed more than 1 year and
the minimum design lifetime of the repair shall be 2 years.
7.5.2.2 For pipe fittings, such as, tees, reducers and flanges,
composite repair is not allowed. Composite system can be
used to repair bends where the service provider needs to
demonstrate previous track record.
7.5.3.3 Repairing of pipe fittings, such as, tees, reducers, bends, and
flanges are not allowed.
7.5.4 For pipelines with pinhole leak, composite repairs to live piping systems
are not allowed.
7.5.6 Composite repair system shall be compatible with internal fluids and
external environments.
7.5.8 The service provider shall utilize the similar surface preparation as it
was used during the qualification and it should extend at least over the
whole surface onto which the repair laminate is to be applied.
7.5.10 Design of the repair laminate shall be based on two design cases,
i.e., Type A: pipeline not leaking but requires structural reinforcement
only or Type B: pipeline leaking and requires structural reinforcement.
A pipeline shall be considered to be leaking if the wall thickness at any
7.5.11 Design temperature limit of the repair system shall follow the values
stated in Table 1, where Tg denotes to glass transition temperature and
HDT denotes to heat distortion temperature.
7.5.12 For repairs of leaking pipeline, the service provider shall demonstrate
that the repair system is capable of withstanding a low velocity 5 Joule
(44.3 inch-lb) impact. Under high probability of third party damage,
composite repair system shall be safeguarded by using additional wraps
or other methods recommended by the service provider.
Since the curing time is not long and it varies service provider to
provider, the diver must be properly trained to ensure on-time
completion of the job.
7.5.16 Upon completion of repair, the line shall be tested based on new MAOP
meeting the requirements of Section 10.
7.5.17 The repair system shall not impose any barrier to the internal inspection
of steel pipeline. This inspection issue shall be addressed in the design
phase especially in the repairing of the leaks.
7.6.3 The number and spacing of concrete mattresses along the pipeline
length shall be reviewed by Offshore Engineering Group of Consulting
Services Department. Concrete mattresses shall not be installed until
approved by Consulting Services Department.
7.6.5 Concrete mattresses shall be installed between the subsea cable, flexible
or umbilical crossing the pipeline and found in contact.
7.7.1 Free spans exceeding the allowable free span length shall be evaluated
prior to being corrected by installing subsea supports such as grout bags.
7.7.2 Local free span assessment shall be performed for each exceeding span
taking into consideration the applicable environmental (wave and
current), soil and effective axial force data at the span location in
accordance with DNV RP F105.
7.8 Repair couplings shall not be used for subsea pipeline repair due to
misalignment issues and the associated impact on seal performance.
7.9 The use of patches and partial encirclement half sleeves is prohibited for repair
of subsea pipelines.
8.1 Welding procedure qualification shall be carried out under simulated hyperbaric
conditions using equipment and operating procedures similar to those to be used
during production welding.
8.3 Prior to welding, the test-pieces shall be inspected visually to ensure the beveled
edges and joint geometry conforms to the requirements of relevant welding
procedure specification.
8.4 During the welding procedure qualification test, the data in SAES-W-012 and
the following additional data shall be recorded or logged using the appropriate
data sheet, and shall form the basis of the welding procedure qualification
record:
a) Water depth
b) Habitat atmosphere (gas composition – argon, heliox, air or nitrox)
c) Habitat humidity and temperature
d) Joint fit-up and bevel geometry measurements
8.5 The power source and the technical specification for the welding system shall be
equivalent to the one used for production.
8.6 With increasing pressure (e.g., with increasing water depth), the voltage gradient
will increase. Small changes in arc length or operating depth result in
considerable changes in the monitored values of arc voltage. For calculations of
the heat input, the arc voltage shall be recorded at the position/point of welding
during qualification of the welding procedure and the difference between the
values and remote monitored values for use during production welding.
8.9 Mechanical testing for weld procedure qualification shall be carried out in
accordance with ASME SEC IX. Such tests shall be carried out in approved
laboratory.
8.10 Welds within 19 mm or 3 times the wall thickness of the pipe from an existing
girth weld shall be inspected by radiography.
9 Subsea Flexibles
9.1 Damaged subsea flexibles shall not be replaced for their entire length instead
only the damaged section of the flexible shall be repaired. However, damage
spread over a long length or multiple damage location may require full
replacement.
9.2.1 Subsea flexible with moderate damage, i.e., without leak and with
localized deterioration (lighter cut) of the outer plastic sheath will not
require shutdown or isolation of the line.
9.2.2 If the extent of the damage is of an order of magnitude greater than the
OD of the flexible, then repair by means of offshore sleeve shall be
performed by the divers.
9.2.4 Seabed preparation and coatings removal are not required for subsea
flexibles resulting in faster installation of repair sleeves.
9.3.3 Depending on the extent of the damage and the successful control of
leak provided by the repair sleeve, production can be restored.
9.3.4 For permanent repair and if the repair sleeve will not hold the leak
completely, the damaged section of the flexible shall be replaced by the
specific flexible vendor. The replaced section shall also be obtained
from the same vendor.
9.3.5 The damaged section of the flexible can be cut subsea and each end can
be lifted separately to the vessel. End fittings can then be installed at
each end and connected with the newly replaced section prior to
lowering it back into the position.
10 Pressure Testing
10.1 Pressure testing is not required when subsea pipeline repairs are made for the
following scenarios:
a) Offshore repair sleeves installed for severe corrosion anomalies without any
leak.
b) Composite repair made for wall thickness metal loss due to corrosion
without any leak.
c) Concrete mattresses installed to compensate for weight coating loss.
d) Subsea supports installed either for free span corrections or at crossings.
10.2 When offshore repair sleeve/composite repair is used to fix subsea pipeline leak,
the hydrotest shall be according to SAES-A-004 and SAES-L-150.
10.4 When the pipeline system with replacement section is to be hydrotested, the test
shall be in full compliance with SAES-A-004 and SAES-L-150.
10.5 When the hydrotest is not practical, full compliance of SAES-A-004 shall be
adhered to along with the following requirements:
a) Verification of the pipe mechanical prosperities through the mill certificate.
b) Visually inspect all mill applied welds of the spiral or longitudinally welded
joint(s) of new pipe prior to installation in the pipeline.
c) Radiograph or ultrasonically check all suspect areas of the manufacturers'
welds found to be defective by visual inspection.
d) Repair all manufacturers weld defects and radiograph repairs to assure
defects are removed.
e) Visually inspect the pipe ends for proper bevel and evidence of no
laminations. Repair as required.
f) Radiograph all butt welds required to install the new pipeline section and
repair defects as required.
g) Provide and approve NDE In-Lieu-of Pressure Test.
11 Coatings
11.1 The selection and application of internal and external coating systems for subsea
pipelines shall be as per SAES-H-002 and SAES-H-004.
12 Cathodic Protection
12.1 When repairs are made due to external corrosion, the proponent cathodic
protection unit within the operating organization shall determine when and
where supplemental “Hot Spot” cathodic protection will be provided.
12.2 The design contractor shall collect/use details from previous diver/ROV surveys
about the pipeline to be replaced, including whether the corrosion is external or
internal, the length of the segment to be replaced, condition of the coating, age
of the pipeline, age of the anodes, remaining weight/life of the anodes, design
life of the pipeline and design life of the anodes.
12.3 Based on the data gathered, the operations/design contractor shall prepare a
CP anode replacement/upgrade proposal using ISO 15589-2 as a guideline to be
reviewed and approved by CSD on a case-by-case basis.
Revision Summary
17 January 2017 New Saudi Aramco Engineering Procedure that describes the procedures to be followed for
subsea pipeline repairs.
8 May 2019 Editorial revision as part of content confirmation assessment.
30 October 2019 Editorial revision to revise the Next Planned Update .
Operations/Contractor shall develop a plan for subsea pipeline repair which shall be reviewed
by the Offshore Engineering Group of Consulting Services Department and approved by all
parties involved in the repair activities. The plan shall include the followings as minimum
where applicable:
1. Description of pipeline/s to be repaired.
2. Damage category based on subsea survey.
3. Safety considerations/ requirements such as risk assessment, LOTO, JSA, work permits,
use of specialized PPE, etc.
4. Engineering Calculations.
5. Selected repair method along with its justification.
6. Pipeline lifting analysis (applicable for pipeline repair by lifting only).
7. Seabed preparations.
8. Coatings removal method.
9. Pipeline isolation and cleaning procedure.
10. Cutting method (applicable for pipeline section replacement only).
11. Repair fittings.
12. Post-repair testing.