BOQ - Retaining Wall0001

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

BOQ FOR PROPOSED EXTERNAL RETAINING WALL AT PLOT 1018 CADASTRAL ZONE B11

KAURA DISTRICT, F.C.T ABUJA.

DESCRIPTION QTY UNIT RATE AMOUNT


EXCAVATION
per m run of Wall

Labour for excavation 1 m 4,500 ₦4,500.00


TOTAL ₦4,500.00

S/NO DESCRIPTION QTY UNIT RATE AMOUNT


CONCRETE WORK
2m3 per m run of Wall

Cement 12 bag 3,600.00 ₦43,200.00


Stone dust 2 ton 4,500.00 ₦9,000.00
Granite 4 ton 4,500.00 ₦18,000.00
Labour for casting Concrete 12 bag 800.00 ₦9,600.00
TOTAL ₦79,800.00

S/NO DESCRIPTION QTY UNIT RATE AMOUNT


REINFORCEMENT

10mm diameter 5 len 3,600 ₦18,000.00


12mm diameter 10 pcs 4200 ₦42,000.00
Binding wire 0.5 bag 10,0000 ₦5,000.00
Iron-bender on reinforcement 144 kg 50.00 ₦7,200.00
TOTAL ₦72,200.00

S/NO DESCRIPTION QTY UNIT RATE AMOUNT


FORM WORK
10m2 per m run of Wall

Marine Boards 4 pcs 12,000 ₦42,000.00


2” x 3” x 3.6 11 pcs 550 ₦6,060.00
Nail various Sizes (3", 4" & 5" Sizes) 1 bag 9,000 ₦9,000.00
Carpenter on formwork 10 m2 700.00 ₦7,000.00
TOTAL ₦64,060.00
BOQ FOR PROPOSED EXTERNAL RETAINING WALL AT PLOT 1018 CADASTRAL ZONE B11
KAURA DISTRICT, F.C.T ABUJA.

DESCRIPTION QTY UNIT RATE AMOUNT


DRAIN PIPE
per m run of Wall

6” drain pipe 1 m 3,500 ₦2,500.00


TOTAL ₦2,500.00

TOTAL COST OF RETAINING WALL per m run ₦223,060.00