This document is a bill of quantities (BOQ) for the proposed construction of an external retaining wall at a plot in Abuja, Nigeria. It provides details of the materials and labor needed, including quantities, units, rates, and total amounts for excavation, concrete work, reinforcement, formwork, and drain pipes. The total estimated cost to construct 1 meter of the retaining wall is ₦223,060.00.
This document is a bill of quantities (BOQ) for the proposed construction of an external retaining wall at a plot in Abuja, Nigeria. It provides details of the materials and labor needed, including quantities, units, rates, and total amounts for excavation, concrete work, reinforcement, formwork, and drain pipes. The total estimated cost to construct 1 meter of the retaining wall is ₦223,060.00.
This document is a bill of quantities (BOQ) for the proposed construction of an external retaining wall at a plot in Abuja, Nigeria. It provides details of the materials and labor needed, including quantities, units, rates, and total amounts for excavation, concrete work, reinforcement, formwork, and drain pipes. The total estimated cost to construct 1 meter of the retaining wall is ₦223,060.00.
This document is a bill of quantities (BOQ) for the proposed construction of an external retaining wall at a plot in Abuja, Nigeria. It provides details of the materials and labor needed, including quantities, units, rates, and total amounts for excavation, concrete work, reinforcement, formwork, and drain pipes. The total estimated cost to construct 1 meter of the retaining wall is ₦223,060.00.
BOQ FOR PROPOSED EXTERNAL RETAINING WALL AT PLOT 1018 CADASTRAL ZONE B11
KAURA DISTRICT, F.C.T ABUJA.
DESCRIPTION QTY UNIT RATE AMOUNT
EXCAVATION per m run of Wall
Labour for excavation 1 m 4,500 ₦4,500.00
TOTAL ₦4,500.00
S/NO DESCRIPTION QTY UNIT RATE AMOUNT
CONCRETE WORK 2m3 per m run of Wall
Cement 12 bag 3,600.00 ₦43,200.00
Stone dust 2 ton 4,500.00 ₦9,000.00 Granite 4 ton 4,500.00 ₦18,000.00 Labour for casting Concrete 12 bag 800.00 ₦9,600.00 TOTAL ₦79,800.00
S/NO DESCRIPTION QTY UNIT RATE AMOUNT
REINFORCEMENT
10mm diameter 5 len 3,600 ₦18,000.00
12mm diameter 10 pcs 4200 ₦42,000.00 Binding wire 0.5 bag 10,0000 ₦5,000.00 Iron-bender on reinforcement 144 kg 50.00 ₦7,200.00 TOTAL ₦72,200.00
S/NO DESCRIPTION QTY UNIT RATE AMOUNT
FORM WORK 10m2 per m run of Wall
Marine Boards 4 pcs 12,000 ₦42,000.00
2” x 3” x 3.6 11 pcs 550 ₦6,060.00 Nail various Sizes (3", 4" & 5" Sizes) 1 bag 9,000 ₦9,000.00 Carpenter on formwork 10 m2 700.00 ₦7,000.00 TOTAL ₦64,060.00 BOQ FOR PROPOSED EXTERNAL RETAINING WALL AT PLOT 1018 CADASTRAL ZONE B11 KAURA DISTRICT, F.C.T ABUJA.
DESCRIPTION QTY UNIT RATE AMOUNT
DRAIN PIPE per m run of Wall
6” drain pipe 1 m 3,500 ₦2,500.00
TOTAL ₦2,500.00
TOTAL COST OF RETAINING WALL per m run ₦223,060.00