Epoxy Jointing of Concrete Bridge Segments

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 8

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/245558838

Epoxy Jointing of Concrete Bridge Segments

Article  in  Transportation Research Record Journal of the Transportation Research Board · January 1999
DOI: 10.3141/1654-14

CITATION READS
1 5,265

3 authors, including:

Nur Yazdani
University of Texas at Arlington
135 PUBLICATIONS   1,298 CITATIONS   

SEE PROFILE

Some of the authors of this publication are also working on these related projects:

Hydrocarbon Pool Fire Performance of Fiber Reinforced Polymer Retrofitted and Thermally Insulated Bridges View project

Load Test Evaluation and Theoretical Modeling of In-Service FRP Strengthened Bridges View project

All content following this page was uploaded by Nur Yazdani on 24 January 2017.

The user has requested enhancement of the downloaded file.


TRANSPORTATION RESEARCH RECORD 1654 Paper No. 99-1422 121

Epoxy Jointing of Concrete Bridge Segments


NUR YAZDANI, MOUSSA ISSA, AND CLAYTON WOLFE

Epoxy is used between precast bridge segments to fill voids on the faces, the internal tendons. In 1985, the Ynys-y-Gwas Bridge in South
keep water and contaminants from seeping into joints, prevent grout from Wales collapsed because of corrosion and fracture of the postten-
bleeding into joints from posttensioning ducts, and act as a lubricant sioning tendons (4). This bridge contained 25-mm mortar joints,
between the segments during assembly. To create a good seal at the joint
which had permeabilities of 100 to 1,000 times that of the concrete
faces, two experimental epoxy applications were tested: a top strip recess
at the joint formed in the concrete during precasting, and a recessed annu- (5). This occurrence demonstrates the catastrophic effects of outside
lus groove around the duct that provides a distinct guide for epoxy appli- contaminants on segmental joint performance.
cation. Eight beams were fabricated with various combinations of epoxy Posttensioning ducts typically are grouted to bond the tendons
face applications, top strip, and annulus. Six segments were cast by using and protect them from corrosion. If the joint is not sealed properly,
match casting. After curing, the beams were posttensioned with the grout may leak out of these ducts into the joint and adjacent ducts
minimum required prestress force. Tanks above the joints were used to
(6 ). This cross grouting decreases the bond between the steel and
measure the seepage of water and joint permeability comparisons. Pres-
surized water was used to test the cross grouting between ducts. The top the concrete, increasing the possibility of further corrosion from out-
strip provided slightly more resistance than did the current one face side contaminants. Studies and tests by FHWA show that corrosion
epoxy application technique and improved alignment problems, segment of tendons is more prevalent at these joints (7 ). Techniques have
defects, and epoxy application procedures. The annulus created a water- been devised to grout all the ducts at once and to flush the grout out
tight seal around the ducts and assisted in aligning the segments and cou- if problems arise (8). If problems arise later because of the defi-
pling the ducts. The existing practice of one face application performed ciency of the joints, costly repairs may be needed or catastrophic
well in both tests, but problems occurred in epoxy thickness and clear-
ances. The top strip and annulus features eliminated the approximation structural failure may result.
of edge and duct clearances. Both performed well together and helped Guidelines have been established for the amount of epoxy, area
the epoxy application process produce a more reliable joint without where epoxy should be applied, and removal of excess epoxy from
additional work in casting or erection of the segments. the edges and ducts. Because of the popularity of segmental bridges
in Florida, the guidelines for epoxy application set by the Florida
Department of Transportation (FDOT) generally are accepted as the
The use of precast concrete members in bridge construction is
standard. The current FDOT guidelines for epoxy jointing include
increasing in popularity because of many factors, including ease
provisions whose success heavily depends on the workmanship and
in erection and control of casting quality. The segmental bridge
judgment of the contractor (8,9). The quality of this bond is essen-
method uses precast concrete, typically box girders, to create large
tial to the success of the epoxy, but it is undetectable after the joint
spans while reducing the complex construction problems. A chem-
is closed. Currently, the epoxy typically is applied to one face of
ical epoxy adhesive normally is applied to the segment joints before
the segments. The area around the posttensioning duct cannot be
posttensioning. AASHTO specifies that epoxied joints be used for
inspected after posttensioning. The 1989 FDOT Segmental Manual
all bridges having internal tendons and for all bridges exposed to
identifies soft epoxy as a frequently occurring problem in segmen-
severe climatic conditions in which freeze-thaw cycles are encoun-
tal construction (10).The current solution to these problems is to
tered or deicing chemicals are used (1). The primary functions of the
separate the joint and repeat the process. The effect of this technique
epoxy are to provide a watertight seal at the joint to prevent the
has not been investigated yet.
intrusion of water and deicing salts and to prevent the grout from
The study reported herein was developed to investigate the per-
bleeding across the joint. The epoxy can be manipulated, in con-
formance of the current epoxy jointing technique for segmental con-
junction with other materials, to change the alignment of the struc-
struction and to compare it with two new epoxy features. These
ture (2). Although significant research has been performed to
features are intended to improve the performance of segmental joints
verify the strength characteristics of the epoxy bond, this additional
against water seepage and cross grouting, assist in proper alignment
strength seldom is considered in design calculations. The joints
of segments, and provide distinct and convenient locations of epoxy
between precast units are vulnerable where ducts are not continuous
application.
and a relatively easy passage for water exists (3). Water penetrating
the joints and ducts may freeze and expand. Other problems include
improper alignment (which may occur during the joining of the seg- EXPERIMENTAL PROCEDURE
ments), improper epoxy curing, and match cast segments that do not
fit because of excessive sandblasting. The penetrating water may Experimental Matrix
contain substances such as salt, automobile fluids, and deicing
chemicals (3). All these additives can increase the corrosion rate of The experimental portion of this study involved the use of a top strip
and an annulus feature with a typical model segmental structure. The
N. Yazdani, Civil Engineering Department, Florida A&M University, 2525 experimental task was divided into three phases:
Pottsdamer St., Room 129, Tallahassee, FL 32310-6046. M. Issa, Florida
Department of Transportation, Structures Design Office, 609 Suwannee St.,
Tallahassee, FL 32399. C. Wolfe, The LPA Group, 4904 Professional Court, 1. Segment production phase: construction of necessary formwork
Suite 201, Raleigh, NC 27609. and the casting of the precast concrete beam segments.
122 Paper No. 99-1422 TRANSPORTATION RESEARCH RECORD 1654

2. Beam erection phase: assembly and erection of the beams, Material Properties
including epoxy application and posttensioning operations.
3. Experimentation phase: testing of the beams for seepage quality The concrete specified by FDOT standards for most segmental bridge
and cross-grouting resistance. projects is typically a Class IV mix design (11). Twenty-six gauge gal-
vanized metal pipes 100 mm in diameter were used for the 610-mm-
A test segment representing the top flange section of a typical seg- long post tensioning ducts. The casting cells were coated with a
mental box girder was selected, as shown in Figure 1. The model test common form release liquid before the concrete was poured. The
segment was 610 mm long with a cross section 813 mm wide and Burke Clean Lift 90 was used as a bond breaker for the match casting
254 mm deep. Three ducts were equally spaced across the cross sec- operation. Bearing grease was used in the grooved areas for bond
tion of the segment at 200-mm spacing. These ducts had a diameter breaking. Kure & Seal curing compound was applied to the concrete
of 100 mm and were centered 150 mm below the top surface of segments after the forms were removed. The Sikadur 31 segmental
the segment. bridge adhesive used in this study is a high-modulus, high-strength,
Three annuli were provided on the face of some of the segments, moisture-insensitive epoxy with an open time of 60 min. Eight pieces
corresponding to one annulus for each duct. The male component of of 25-mm-diameter grade 150 threaded DYWIDAG bars were used
the annulus was a half-torus-shaped ring and the female component for posttensioning. The steel bars were anchored by plates 152 ×
was a groove in the concrete with the same shape as the ring. The 178 × 37 mm and held by 25-mm anchor nuts, as shown in Figure 2.
shape of the annulus design was based on the epoxy clearance dis-
tance and the duct size. The annulus had an inside diameter of 134 mm Preparation, Setup, and Casting
and an outside diameter of 172 mm with a width of 19 mm and a
45° chamfer. Wood forms were used in which the female groove was routed and
To evaluate the effectiveness of the top strip, the annulus, and the male ring was attached. To construct the top strip, a piece of
the face epoxy application, various combinations of these features wood was cut to dimensions that are half that of the top strip and
were tested. The four different types of segments tested were plain attached to the respective bulkheads. The actual casting cells, shown
face, with annulus only, with top strip only, and with annulus and in Figure 3, consisted of three boards and one bulkhead bolted
top strip. Six segments were cast for each beam following the together and screwed to a single sheet of plywood for the first pour.
short-line casting method. These segments were assembled, epox- The match cast segment replaced the second bulkhead. To eliminate
ied, and posttensioned into eight separate beams, as shown in the possibility of cracking from transportation or thermal effects, a
Table 1. Beams 1 through 4 had no face epoxy application and layer of welded wire mesh was placed in the upper section of the
Beams 5 through 8 had one face epoxy application. The beam with cells. PVC pipes 25 mm in diameter were attached vertically to the
plain faces had no epoxy on any of the joints and served as the con- end of the posttensioning ducts in the first and last segments in each
trol in each group. Beams 1 through 4 were used to isolate the top beam to simulate grout inlet-outlet pipes. The segments were con-
strip and annulus features and test their individual effects, and structed during November and December 1996. The compressive
Beam 5 represented the current method used in typical segmental strength of concrete varied between 41 and 56 MPa with an average
construction. of 47.8 MPa for the various segments.

FIGURE 1 Dimensions of test segments with features (mm).


Yazdani et al. Paper No. 99-1422 123

TABLE 1 Summary of Segment Features and Epoxy Application

Epoxy Jointing Following manufacturer instructions, approximately 1 to 2 min


was needed to apply the epoxy for each joint. The thick consistency
The segment assembly method used here resembled the span-by- of the epoxy made it difficult to fill the grooves perfectly, but a sat-
span technique of using a support truss to assemble the segments of isfactory application was made. The interlocking of the annulus was
the span, including epoxy application and post-tensioning. The seg- very helpful in aligning the segments in their proper positions. After
ments were spaced at 300 mm to allow access to the faces for the the beam was posttensioned, the ducts were swabbed to remove any
application of epoxy, as shown in Figure 4. excess epoxy.

FIGURE 2 Detail of posttensioning anchorage.


124 Paper No. 99-1422 TRANSPORTATION RESEARCH RECORD 1654

FIGURE 3 Layout of casting cells in yard. FIGURE 5 Epoxy application on annulus and one face.

To simulate field conditions, the joint faces of Beam 5 were leaving them accessible for swabbing. The erected beam and support
coated with epoxy at an estimated average thickness of 2 mm, with conditions are shown in Figure 7.
12-mm edge clearance and 25-mm duct clearance. A large amount
of extruded epoxy was observed on the edges and inside the ducts
in Beam 6 after posttensioning. Figures 5 and 6 show the applica- Joint Seepage Test
tion of epoxy on the face and annuli and on the top strip, respec-
tively. Even with the presence of the annuli, top strip, and epoxy The joint seepage test was undertaken to evaluate the seepage
face application (Beam 8), only a few minutes for epoxy application resistance of the eight beams with various combinations of epoxy
in each joint and 25 min for the entire process were needed. The key- application. Plastic tanks filled with water were positioned above
like action of the annuli made it easier for the matching of segments each joint to determine the extent of water seepage through the
in the beams with annuli.
joints, as shown in Figure 8. The inner dimensions of each tank
were 102 mm wide, 762 mm long, and 102 mm high. Plastic rulers
Posttensioning were fastened to the sides of the tanks for water drop measure-
ments. An additional tank was placed on one of the segments in
The posttensioning force was designed to provide a minimum com- Beam 1 to act as the control tank for the first group of Beams 1
pressive pressure of 0.3 N/mm2 across all joints to set the epoxy through 4. This control tank was used to account for water loss due
(11). Simple support conditions were assumed because of the eccen- to evaporation and the porosity of the concrete. For the second
tric tendons and expected camber. The actual section moduli for the group of beams (5 through 8), a separate control tank was placed
beam section were found to be adequate with respect to American on Beam 5. The tanks were filled with dyed water to a depth of
Concrete Institute allowable tensile and compressive stresses (12). roughly 50 mm. The tanks were covered with polythene sheets
It was determined that a minimum effective prestress force of 120 to minimize water loss due to evaporation. Readings of the water
kN was needed to achieve the minimum compressive pressure depth in the tanks were taken daily over a 2-week period. The
needed at the critical location (bottom of midspan joint) for epoxy ducts were swabbed near each joint to check for seepage of
setting. Only one bar was used in the middle duct, leaving the other the dyed water. After sufficient data were recorded, the tanks were
two ducts accessible for examination. In practice, the temporary removed and the cross-grouting part of the experiment was
posttensioning steel is located outside of the main internal ducts, performed.

FIGURE 4 Assembly setup for model segment beams. FIGURE 6 Epoxy application in typical top strip.
Yazdani et al. Paper No. 99-1422 125

FIGURE 7 Erected beam with simple supports. FIGURE 9 Gauge-valve apparatus for cross-grouting test.

Cross-Grouting Test capability of the annulus feature. As shown in Figure 10, the aver-
age seepage rate of 600 mm3/s in Beam 2 was considerably less than
The cross-grouting test consisted of filling the ducts with water and that of 7532 mm3/s for Beam 1. It was evident from the amount and
pressurizing the ducts to force the water through any openings at the location of the excess squeezed epoxy in Beam 2 that the joint faces
joints. Because water has a lower density than grout, the pressurized were only partially covered, as expected. The average seepage for
water test provided a more critical evaluation of the joints. Using PVC Beam 2 was well above the control seepage rate of 2.46 mm3/s. The
pipe fittings, an apparatus containing a one-way air valve and an air swabbing of the ducts for Beam 2 produced no traces of dyed water.
gauge connected to the inlet pipes was devised, as shown in Figure 9. The effectiveness of the top strip feature was tested through its
The two side ducts were capped with sewer test plugs epoxied at the exclusive use in Beam 3. No water was visible below the joints and
edges. The inlet pipes were then filled with air to an initial pressure of no stains were found from swabbing the ducts throughout the test-
0.2 N/mm2 and the loss of pressure with time was recorded. The ing period for this beam. The average seepage rate for Beam 3 was
amount of pressure maintained after 1.5 hours, when actual grout gen- 2.49 mm3/s, only 1.26 percent more than the control tank seepage
erally begins setting, was the focus of this test. The joints were also rate of 2.46 mm3/s.
examined for water leakage during this time. On completion of these Beam 4 was a combination of Beams 2 and 3. Figure 10 shows an
tests, the ducts were pressurized to more than 0.4 N/mm2 air pressure, average seepage of 1.75 mm3/s for Beam 4, 29 percent less than the
the maximum reading on the gauge, or until the plugs failed. control rate of 2.46 mm3/s. This demonstrates that the joint was vir-
tually impenetrable to water and that the effects of the concrete
porosity were reduced by the epoxy in the top strip.
RESULTS AND ANALYSIS As mentioned, Beam 5 represents the current practice of epoxy
application on one face of the joint with proper clearance. During
Joint Seepage Test the epoxy application process, the required excess epoxy bead lines
formed at all joints, which indicated that the epoxy squeezed out
The seepage rate is defined herein as the volume of water lost per evenly at all edges. It is observed in Figure 10 that the average rate
second (mm3/s). Beam 1 provided a demonstration on the perfor- of seepage for Beam 5 was 3.41 mm3/s and only 1 percent higher
mance of dry joints in a beam. In Figure 10, the high seepage in than the control seepage of 3.38 mm3/s. Swabbing of the ducts in
Beam 1 is clearly demonstrated. The swabbing of each duct pro- Beam 5 produced no traces of dyed water seepage from the tanks.
duced evidence of a significant amount of dyed water in the ducts. Beam 6 included the annulus feature with one face application of
Only the annuli in Beam 2 were epoxied to isolate and test the epoxy. From Figure 10 it is observed that the average seepage for
Beam 6 was 3.80 mm3/s, 12.6 percent greater than the control seep-
age. No water was detected inside the ducts or around the joint edges
for Beam 6. It is obvious that the addition of the annulus did not
demonstrate any improvements to the duct protection in this group
of beams (5 through 8).
Beam 7 included the top strip along with one face application of
epoxy. Theoretically, if the top strip performed as expected, that
face application of epoxy would be redundant. The average seepage
rate for Beam 7 was 3.55 mm3/s, only 5.3 percent higher than the
control seepage of 3.38 mm3/s. In Beam 7, no water was detected
inside the ducts or around the joint edges.
In Beam 8, the annulus was added to the top strip and one face
epoxy application. As seen in Figure 10, the average seepage for this
beam was 3.24 mm3/s, 4.1 percent lower than the control seepage of
3.38 mm3/s. No water was found in the ducts or around the joint
edges for Beam 8. Following the same reasoning as for Beam 6, the
FIGURE 8 Joint seepage test in progress. presence of the annulus did not improve the protection of the ducts.
126 Paper No. 99-1422 TRANSPORTATION RESEARCH RECORD 1654

FIGURE 10 Average joint seepage in all beams and controls.

Cross-Grouting Test CONCLUSIONS

The absence of epoxy on the joint faces of Beams 1 and 3 prevented 1. Careful and immediate attention is needed with the swabbing
the ducts from maintaining any amount of pressure. For both of ducts after joint closure. Blockage in the ducts due to epoxy may
beams, the air pressure applied to the ducts resulted in a significant be as harmful as blockage due to cross grouting.
volume of water flowing from one outer duct to the other outer duct 2. The current practice of one-face epoxy application performed
due to cross grouting. The water appeared to be transported mainly well in this study when done properly.
across the bottom area of the joints where the stresses were lower. 3. Creating the annulus in a segment is simple and may be
The average pressure drops in the beams, except for Beams 1 and achieved by the match cast process. It requires no significant extra
3, are illustrated in Figure 11. The pressure drop lines for the beams time during the epoxy application procedure. However, it is diffi-
are fairly linear, indicating constant pressure losses with time. It was cult to manually apply epoxy with uniform thickness in the annulus
mentioned previously that grout typically begins setting after about feature.
1.5 hours. All the beams, except for Beam 5, maintained more than 4. The annulus provides a duct coupling that resembles the func-
75 percent of initial pressure after 1.5 hours and more than 50 per- tion of a rubber gasket but that eliminated the complication of adding
cent after 3 hours. The data for Beam 5, the current typical epoxy a foreign object. The coupling effect of the annulus is beneficial in
application, demonstrated that the ducts maintained 50 percent of providing continuity across the joints.
the initial pressure for at least 1 hour. The water pressure in Beam 6 5. The annulus eliminates the need for the approximate clearance
remained at 0.21 N/mm2 for the entire 3-hour test period. This result around the duct, which is difficult to maintain in actual practice.
indicated that the use of annuli with one face application created a 6. The beams with epoxy only in the annuli protected the ducts
watertight seal across all the joints. from water penetration as well as in the beams with face application
Excluding Beams 1 and 3, no water leakage from the joint edges only. The annulus feature may not provide a noticeable joint seep-
of any beams was detected during the cross-grouting test. As men- age improvement as compared with the typical face application, but
tioned, water was used instead of actual grout for convenience and it will provide an auxiliary resistance.
practicality in the testing. Because water is lighter than grout, the 7. The use of epoxied annuli in the joints created a completely
performance of the tested joints would be more efficient for actual watertight seal for more than 4 hours. In practice, the denser grout
grouted ducts. Even with this conservative approach, no cross water- material is unlikely to flow between the ducts because the initial
ing was evident for the beams with epoxied faces or epoxied annuli. grout set usually begins after 12 hours.
Yazdani et al. Paper No. 99-1422 127

FIGURE 11 Pressure variations in beams.

8. The application of epoxy only in the top strip was more effec- Engineering Group deserves appreciation for initiating the research
tive in resisting water penetration than the typical one face applica- idea and for providing technical assistance during the study.
tion. This demonstrates that the epoxy needs only to act as a fill in
the top strip to prevent water penetration.
REFERENCES

RECOMMENDATIONS 1. Guide Specifications for Design and Construction of Segmental Con-


crete Bridges. AASHTO, 1989.
1. Proper swabbing of the ducts after joint closure should be 2. Moreton, A. J. Tests of Epoxy Glued Joints for a Segmental Bridge
practiced to remove excess epoxy squeezed out into the ducts. Deck. Journal of Adhesion and Adhesives, 1981.
3. Durable Bonded Post-Tensioned Concrete Bridges, Vol. 2, TR 47.
2. The current practice of one face epoxy application should be Concrete Society/Concrete Bridge Development Group, Slough, Berk-
continued. Total epoxy coverage is needed in the joint to prevent shire, U.K., 1996, pp. 642–656.
penetration of water that may pass through the concrete. 4. Woodward, R. J., and D. L. Wilson. Deformation of Segmental Post-
3. It is recommended that the circular annulus feature for epoxy Tensioned Precast Bridges as a Result of Corrosion of the Tendons.
application in segmental construction be used by state highway Proc., Institution of Civil Engineers—Structures and Buildings, Part I,
departments. Vol. 90, London, U.K. 1991, pp. 397– 419.
5. Clark, L. A. Performance in Service of Post-Tensioned Concrete
4. The application of the top strip feature may not be practical Bridges. British Cement Association, Crowthorne, U.K., 1992.
because of maintenance problems. While this study was underway, 6. Gerwick, B. C. Construction of Prestressed Concrete Structures. John
grinding of the segments was initiated by FDOT, which may cause Wiley and Sons, Inc., New York, 1993.
damage to the top strip feature. 7. Standard Specifications for Construction of Roads and Bridges on Fed-
5. A reliable and simple mechanical applicator should be eral Highway Projects. FHWA, U.S. Department of Transportation,
adopted for convenient application of epoxy in the annulus feature. 1992.
8. Post-Tensioning. Florida Department of Transportation, Tallahassee,
6. Further investigation of other more efficient annulus shapes is Fla., 1989.
needed. The investigation may include rectangular shapes and com- 9. Epoxy Jointing of Precast Segments. Florida Department of Transporta-
bined annulus around several ducts. The proper shape and configu- tion, Tallahassee, Fla., 1990.
ration may eliminate the need for epoxy application around the ducts 10. Segmental Manual, A Guide to the Construction of Segmental Bridges.
on both faces. Florida Department of Transportation Tallahassee, Fla., 1989.
11. Standard Specifications of Road and Bridge Construction. Florida
Department of Transportation, Tallahassee, Fla., 1991.
12. Building Code Requirements for Structural Concrete and Commentary.
ACKNOWLEDGMENTS American Concrete Institute, Farmington Hills, Mich, 1995.

The study reported herein was performed under a research grant


funded by FDOT. The authors thank the staff of the FDOT/Structural Publication of this paper sponsored by Committee on Construction of
Research Center for their help in this project. Alan Moreton of Figg Bridges and Structures.

View publication stats

You might also like