Professional Documents
Culture Documents
Project Planning (Marked)
Project Planning (Marked)
Project Planning (Marked)
Chapter 5-4
Composite Plan
Chapter 5-5
Project Plan
Chapter 5-6
Project Plan Elements
The process of developing the project plan varies
among organizations, but any project plan must
contain the following elements:
Overview - a short summary of the objectives and
scope of the project (directed to top management and contains a
statement of the goals of the project, a brief explanation of their relationship to the
firm’s objectives, a list of the major milestones in the project schedule.)
Chapter 5-10
Project Planning in Action
Concept evaluation
Requirements identification
Design
Implementation
Test Chapter 5-11
Project Planning in Action
Chapter 5-12
Systems Integration
Systems Integration (sometimes called systems engineering or
Chapter 5-13
Systems Integration
[Added design cost may lead to decreased component cost, leaving performance and effectiveness otherwise
unchanged. Added design cost may yield decreased production costs, and production cost may be traded off against
unit cost for materials. It can be used in any project where the relevant cost trade-offs can be estimated. It is simply
the consistent and thorough use of cost/effectiveness analysis]
The Action Plan (Hierarchical Planning
System)
If a large project is to come in on time and within cost, a great many things must happen when and how they are
supposed to happen. Yet each of these details is uncertain and thus each must be subjected to risk management.
Chapter 5-15
Sorting Out the Project
Strategic planning lays out the long-term, broad goals that a business or individual wants to
achieve. And tactical planning outlines the short-term steps and actions that should be taken to
achieve the goals described in the strategic plan.
Chapter 5-16
Sorting Out the Project
Strategic Success Factors:
Project Mission - spell out clearly defined and agreed-
upon objectives in the project plan
Top Management Support - it is necessary for top
management to get behind the project at the outset, and
make clear to all personnel involved that they support
successful completion
Project’s Action Plan - detailed plan of the required
steps in the implementation process needs to be
developed including all resource requirements
Chapter 5-17
Tactical Factors
Tactical Factors
Competent project manager: the
importance of initial selection of a skilled
(interpersonally, technically, and
administratively) project leader
Competent project team members: the
importance of selecting and, if necessary of
training project team members
Tactical Factors
Items 1-5 focus on the WBS as a planning tool but it may also
be used to monitor and control the project
Chapter 5-21
The Work Breakdown Structure
Items 6 and 7 focus on the WBS as an aid to monitor
and control a project:
6. The project manager can examine actual resource use,
by work element, work package, task, up to the full
project level. The project manager can identify
problems, harden the estimates of final cost, and make
sure that relevant corrections have been designed and
are ready to implement
7. The project schedule may be subjected to the same
comparisons as the project budget. Actual progress is
compared to scheduled and corrective action can be
taken
Chapter 5-22
Interface Coordination through
Integration Management
The most difficult aspect of
implementing a project is the
coordination and integration of
the various elements of the
project
The intricate process of
coordinating the work and
timing of all inputs is called
integration management
Interface coordination is used to
denote the process of managing
this work across multiple groups
Chapter 5-23
Approaches to Interface
Management
Recent work on managing the interface
focuses on the use of multifunctional
teams (MT)
There is general agreement that MT has a
favorable impact on product/service design
and delivery
Successfully involving cross-functional teams
in project planning requires that some
structure be imposed on the planning process
Chapter 5-24
Approaches to Interface
Management
Chapter 5-25
Summary
Chapter 5-28
Project Planning
Questions?
Chapter 5-29
Project Planning
Picture Files
Project Planning
Figure 5-1
Project Planning
Figure 5-2
Project Planning
Figure 5-4
Project Planning
Figure 5-6
Project Planning
Figure 5-11
Project Planning
Figure 5-12
Project Planning
Table Files
Project Planning
Project Planning
Copyright © 2000 John Wiley & Sons, Inc. All rights
reserved. Reproduction or translation of this work
beyond that permitted in Section 117 of the 1976 United
States Copyright Act without the express written
permission of the copyright owner is unlawful. Request
for further information should be addressed to the
Permissions Department, John Wiley & Sons, Inc. The
purchaser may make back-up copies for his/her own use
only and not for distribution or resale. The Publisher
assumes no responsibility for errors, omissions, or
damages, caused by the use of these programs or from
the use of the information contained herein.