Professional Documents
Culture Documents
Pier Foundation
Pier Foundation
Pier Foundation
Or
Drilled Shafts
Prepared by:
Avishek Shrestha
M.Eng in Geotechnical Engineering 1
| Kathmandu University|
Introduction
2
| Avishek Shrestha, M.Eng, M.A|
| Kathmandu University|
3
| Avishek Shrestha, M.Eng, M.A|
| Kathmandu University|
4
| Avishek Shrestha, M.Eng, M.A|
| Kathmandu University|
5
| Avishek Shrestha, M.Eng, M.A|
| Kathmandu University|
• As for piles, while calculating the effective vertical pressure at the base, the
limits imposed by the concept of critical depth should be considered, if
applicable.
• The value of k is approximately equal to the coefficient of earth pressure at
rest (Ko). Thus, 𝑘 = 𝑘𝑜 = 1 − 𝑠𝑖𝑛𝜑
6
| Avishek Shrestha, M.Eng, M.A|
| Kathmandu University|
7
| Avishek Shrestha, M.Eng, M.A|
| Kathmandu University|
𝑄𝑠
𝑄𝑛𝑒𝑡(𝑎𝑙𝑙) = 𝑄𝑝−𝑛𝑒𝑡 𝑎𝑙𝑙 +
𝐹𝑆
8
| Avishek Shrestha, M.Eng, M.A|
| Kathmandu University|
9
| Avishek Shrestha, M.Eng, M.A|
| Kathmandu University|
11
| Avishek Shrestha, M.Eng, M.A|
| Kathmandu University|
12
| Avishek Shrestha, M.Eng, M.A|
| Kathmandu University|
𝑄𝑢(𝑛𝑒𝑡) = 𝑓𝑖 𝑝∆𝐿𝑖 + 𝑞𝑝 𝐴𝑝
𝑖=1
13
| Avishek Shrestha, M.Eng, M.A|
| Kathmandu University|
14
| Avishek Shrestha, M.Eng, M.A|
| Kathmandu University|
15
| Avishek Shrestha, M.Eng, M.A|
| Kathmandu University|
16
| Avishek Shrestha, M.Eng, M.A|
| Kathmandu University|
Construction Procedures
• Can be divided into 3 stages:
• Excavation of piers
• Providing supports
• Concreting of piers
• Excavation or piers:
• Generally excavated using an auger drill or some other
type of drilling equipment
• For formation of a bell, the auger is replaced by an
under-reaming tool. The cutting blades are in the folded
position when the under-reamer is lowered into the
hole. On reaching the bottom of the hole, the blades are
spread outward. As the bell is formed and the loose soil
falls inside the cylinder, it is raised and emptied. The dia.
of bell is kept two to three times the dia. of the shaft.
• This method is suitable for hard clays where the hole can
be left open for a few hours without support. In
cohesionless soils the hole is prevented from collapsing
by providing casing or drilling in slurry.
17
| Avishek Shrestha, M.Eng, M.A|
| Kathmandu University|
Construction Procedures
• Providing supports
• A) Chicago method:
• a circular hole is excavated upto the depth at
which the soil will stand unsupported (about
0.5m for soft clays and 2m for stiff clay)
• Vertical boards known as laggings, are then set
in position around the excavated face and are
held tightly against the soil by steel rings.
• The shaft is then excavated further for 1 to 2m
and another setting of boards and rings is
made.
• The process is repeated until the desired level
is reached. The base of the shaft is then belled
out.
• B) Gow Method:
• Telescopic steel shells are used to support the
soil.
• The telescopic shells are extended as the hole
is deepened.
• The shells are removed as the concreting
progresses.
• The minimum diameter of the hole in this
method is about 1.25m.
18
| Avishek Shrestha, M.Eng, M.A|
| Kathmandu University|
Construction Procedures
• Concreting of piers:
• After the hole has been drilled to the required depth, the shaft is dewatered
• The casing, if used, is removed before the concreting is done.
• The reinforcement cage is then inserted and concreting is done.
• As far as possible, concreting should be done in dry. However, if dewatering is
not possible or slurry is used to support the shaft sides, concrete is placed
using a tremie.
19
| Avishek Shrestha, M.Eng, M.A|
| Kathmandu University|
𝑄𝑤 𝑄𝑤
𝑓𝑐 = 0.25𝑓𝑐 ′ = =𝜋 2
𝐴𝑔𝑠 𝐷
4 𝑠
𝑄𝑤
𝐷𝑠 = 2.257
𝑓𝑐 ′
Where, Ds = diameter of the shaft
f’c = 28-day concrete strength
Qw = working load of the drilled shaft
Ags = gross cross-sectional area of the shaft
20
| Avishek Shrestha, M.Eng, M.A|
| Kathmandu University|
21
| Avishek Shrestha, M.Eng, M.A|
Thank You
☺
22