CHK008 - Building Certification Checklist

Project
Building # Unit #

Item ✓ Close-out Date Relevant Supervisor


1 ESSENTIAL FIRE SERVICES CHECK: Fire contractor
Hydrants commissioned & operational ☐ Name: …………………………………..
Sprinklers commissioned & operational ☐
Dry Fire commissioned & operational ☐ Signed: ………………………………….

2 FINAL TESTING & REPORTING: Fire contractor


Hydrant test - Results: …………………………… ☐ Name: …………………………………..
Sprinkler test - Results: …………………………… ☐
Stair pressurisation - Results: …………………………… ☐ Signed: ………………………………….

3 FINAL INSPECTION: Private Certifier Auth.


Certifier witness min req. of ESSENTIAL fire services operations ☐ Name: …………………………………..
Fire Engineer
Fire Eng. witness min req. of ESSENTIAL fire services operations ☐ Signed: ………………………………….

4 PERFORMANCE SOLUTION/S: (if required) Fire Engineer


Fire Engineer to finalise performance solution ☐ Name: …………………………………..
Private Certifier Auth.
Updated FER Lodgement ☐ Signed: ………………………………….
(Guide: Allow 4 weeks for approval)
5 FIRE BRIGADE INSPECTION APPLICATION: Karimbla PM
Lodgement Date by PCA
To include: Name: …………………………………..
a) Application for Occupation Certificate ☐
b) Overall Fire Safety Certificate by the owner ☐ Signed: ………………………………….
c) Compliance Statement by the Fire Engineer ☐
d) Installation Certificates (fire safety measures) ☐
e) Commissioning test reports for hydrants, sprinklers & ☐
stair pressurisation
(Guide: Allow 2-3 weeks for Brigade Inspection)
Inspection Booking Date
FIRE BRIGADE INSPECTION: Name: …………………………………..
Fire Brigade Inspection - Results: ………………………
(Attach formal letter of results, if fire brigade refused the Signed: ………………………………….
inspection invite provide email correspondence.)
6 ITEM RECTIFICATION: Site PM /
General Site Supervisor
Items from Inspection/s rectified (if required) ☐ Name: …………………………………..

Signed: ………………………………….

7 OCCUPATION CERTIFICATE: Karimbla PM


Occupancy Certificate Received ☐ Name: …………………………………..
(Guide: Allow 3 to 8 weeks from time of fire brigade / certifier
approval inspection, attach OC cover page.) Signed: ………………………………….
Approval of all works complete (Scan & upload all supporting documents to Buildtools)

Building Manager Date: Name: ………………………………………………. Signed: ………..………………………………….