DB 52 46 VILLA DAMAC HILLS SILVER SPRING 3 Date: 20-09-22

Complete
Work Work d Villa No. of
Total IR
S.no Description Villas
done up to done on Names Balance On going Progress status
approvals
18-09-22 19-09-22 on 19-09- villas
22

Structural Works
1 Excavation 46 46 0 0 0

2 Foundation & Neck Columns 46 46 0 0 0


3 Tie Beam 46 46 0 0 0
4 SOG 46 46 0 0 0
5 Walls & Columns (GF-1st) 46 46 0 0 0

6 1st Floor Slab 46 44 2 0 0 Formwork and Reinforcement at G2 Zone-01


7 Walls & Columns (1st-Roof) 46 44 0 0 2
8 Roof Slab 46 34 0 0 12 Formwork at G10 Zone-01

Finishing Works
1 Blockwork - Ground Floor 46 13 0 0 33 Blockwork at G5 & G6 Zone- 02
2 MEP 1st fix in wall - Ground floor 46 6 0 0 40 Marking at G13 Zone-01

3 MEP 1st fix in high level - Ground floor 46 0 0 0 46 G13 at Zone-01


4 Internal Plaster - Ground floor 46 0 0 0 46 Surface preparation for Plaster at G13 Zone-01
5 Blockwork - 1st Floor 46 13 0 0 33 Blockwork at G5 & G6 Zone- 02

6 MEP 1st fix in wall - 1st floor 46 6 0 0 40 G13 at Zone-01


7 MEP 1st fix high level - 1st floor 46 0 0 0 46 G13 at Zone-01

8 Internal Plaster - 1st Floor 46 0 0 0 46 Surface preparation for Plaster at G13 Zone-01

Actual Manpower Open NCR Work affecting issues


S.no Category Sub-Cont Delta Total NCR No Description Date of issue S.no Description

1 CHARGE HAND 2 1 3 Non Compliance of Wearing mandatory PPE at the sit 6/10/2022

2 CARPENTER 20 9 29 6/10/2022
3 STEEL FIXER 15 6 21 Unsafe Working at Height Activity 6/17/2022
4 MASON 15 7 22 Poor House Keeping & Material Management 7/17/2022
5 PAINTER( Bitumen ) 0 0 0
6 HELPER 20 25 45
7 OTHERS 0 8 8
TOTAL 128