Professional Documents
Culture Documents
Optimizing The Project
Optimizing The Project
project's overall time and cost. By breaking down large, complex projects into smaller, more
manageable tasks, allocating resources, and controlling the project's circles, project managers always
use the Project Evaluation Review Technique (PERT) and the Critical Path Method (CPM) to reduce the
project's overall cost and duration. PERT and CPM are hence operational research tools that are used to
increase project effectiveness and efficiency. These methodologies can be employed in a variety of fields
or sectors, including construction, aviation, the military, education, and civil administration.
The methods are essentially network-oriented techniques using the same principle. PERT and CPM are
basically time-oriented methods in the sense that they both lead to determination of a time schedule for
the project. The significant difference between two approaches is that the time estimates for the
different activities in CPM were assumed to be deterministic while in PERT these are described
probabilistically. These techniques are referred as project scheduling techniques.
PERT
The Project Evaluation and Review Technique (PERT) is a method for representing project activities in
the right order and at the right time. It is a method of organizing, scheduling, and integrating work inside
a project. PERT is essentially a management planning and control system that offers a project's
blueprint. The PERT has successfully identified all of a project's key components or events.
This method involves creating a PERT Chart that serves as a timetable for all the project's stated tasks.
The reporting levels of the tasks or events in the PERT Charts are largely the same as those specified in
the WBS (WBS).
In PERT activities are shown as a network of precedence relationships using activity-onarrow network
construction
Characteristics of PERT:
The main characteristics of PERT are as following:
1. It serves as a base for obtaining the important facts for implementing
the decision-making.
2. It forms the basis for all the planning activities.
3. PERT helps management in deciding the best possible resource
utilization method.
4. PERT take advantage by using time network analysis technique.
5. PERT presents the structure for reporting information.
6. It helps the management in identifying the essential elements for the
completion of the project within time.
Advantages of PERT:
It has the following advantages:
1. Estimation of completion time of project is given by the PERT.
2. It supports the identification of the activities with slack time.
3. The start and dates of the activities of a specific project is determined.
4. It helps project manager in identifying the critical path activities.
5. PERT makes well organized diagram for the representation of large
amount of data.
Disadvantages of PERT:
It has the following disadvantages:
1. The complexity of PERT is more which leads to the problem in
implementation.
2. The estimation of activity time is subjective in PERT which is a major
disadvantage.
3. Maintenance of PERT is also expensive and complex.
4. The actual distribution of may be different from the PERT beta
distribution which causes wrong assumptions.
5. It under estimates the expected project completion time as there is
chances that other paths can become the critical path if their related
activities are deferred.
The Project Management Body of Knowledge's (PMBOK) definition of the Critical Path Method is as
follows:
“The Critical Path Method is the order of planned activities that establishes the project's duration.”
For instance, if building a house, would have the following work sequences:
Each task takes a different amount of time and resources. It takes more time to build walls and
lay the roof than to install faucets and fixtures.
If to figure out the project’s ‘Critical Path’, look at the sequence that takes the most amount of
time, like this:
The total time taken to complete the sequence along this critical path gives an idea of the
project’s minimum duration. Undertake several task sequences simultaneously, but if there are
any delays in the critical path sequence, the project will suffer delays as well.
Suppose you have a list of tasks as shown below. Columns C and D list the tasks that must be
accomplished for the activity to begin, and the duration of the activity, respectively.
Since the project manager's goal is to complete the project as quickly as possible (without
compromising on quality, of course), we'll try to find the earliest finish time for each activity.
To do this, organize all tasks into a flowchart and note their durations next to the task ID. The
arrows indicate the sequence of activities. We'll mark the Earliest Start (ES) time to the left of
the activity, and the Earliest Finish (EF) time to the right.:
Mark the Start Time (S) to the left and right of the first activity. Usually, this would be 0.
Now mark the Earliest Start (ES) time of each activity. This is given by the largest number to the
right of the activity's immediate predecessor (i.e., its Earliest Finish time, or EF).
If the activity has two predecessors, the one with the later EF time would give you the ES of the
activity.
The EF of an activity is given by its Earliest Start time (ES) and its duration (t), i.e. ES + t.
Thus, if an activity's ES is 20 and will last for 10 days, its EF will be 30.
The final figure to the right of the last task in the sequence will give you the minimum time the
project will take to finish.
In this method, the critical path of the project is established by identifying the critical activities of the
project. Critical activities are the activities whose total float value is ‘0’.
In CPM activities are shown as a network of precedence relationships using activity-on node network
construction
1) Early start (ES) is the earliest time it takes for an activity to begin. The
assumption is that all preceding activities begin at their earliest possible
start time; otherwise, a late start to the preceding activity will result in a
late start to its succeeding activity. The ES of an activity is the sum of the
time of all preceding activities on that path. When an activity has more
than one preceding activity, the early start of that activity depends on the
early finish of the longest duration or the activity with the longest ES
time, t.
2) A late start (LS) is a delay in the start of an activity. The latest time an
activity can begin without delaying the project completion time.
3) Early finish (EF) is an early start of an activity that will lead to an early
finish. The assumption is that the activity begins with ES and ends with t.
EF = ES + t. The precedence relationship shows that the early start of
activity depends upon the early finish of its immediately preceding
activity. That is, ES + t = EF (Forward induction/movement).
4) Late finish (LF)—A late start to an activity will lead to a late finish. The
delay in the late start of an activity resulting in the late finish of that
activity should be such as not to delay the project completion time. We
assume that for the last activity in the critical path, EF = LF and then LF −
t = LS indicates a reverse process called Backward induction/movement.
The LS of an activity is determined by the LF of the previous activity (ies).
When an activity has more than one preceding activity, that is, if two or
more paths converge on an activity, the path with the shortest total LS
time is taken as the LF of the preceding activity or activities.
USED IN: Production management - for the jobs of repetitive in nature where the activity time estimates
can be predicted with considerable certainty due to the existence of past experience.
It is activity-oriented technique
It is event-oriented technique which which means that network is
means that network is constructed constructed on the basis of
2. on the basis of event activities