FACTORY MESS HALL

Description No L B D Qty

1 Removing old tiled roof


2 35.00 4.00 280.000 M²
TOTAL 280.000
280.00 M² @ 200.00 /-M² 56,000.00
2 Removing old brick work
TOILET door 2 0.9 0.25 2.5 1.125
toilet walll 1 7.96 0.25 2.5 4.975
toilet walll 4 2.54 0.25 2.5 6.350
wash area 1 6 0.6 0.6 2.160
TOTAL 14.610 M³
14.61 m³ @ 1500.00 /- m³ 21,915.00
3 Removing RCC roof
toilet roof 1 9 3 0.1 2.700
lintel 1 7.96 0.24 0.15 0.287
lintel 3 2.54 0.15 0.15 0.171
TOTAL 3.158 M³
3.16 M³ @ 3000.00 /-M³ 9,474.03
4 Removing floor concrete
toilet 1 7.96 2.54 0.075 1.516
floor 1 34.32 3.81 0.075 9.807
TOTAL 46.859 M³
46.86 M³ @ 300.00 /-M³ 14,057.80
5 Removing rr foundation
toilet 1 7.96 0.6 0.6 2.866
TOTAL 2.866 M³
2.87 m³ @ 600.00 /- m³ 1,719.36
6 Removing old plastering
1 34.32 2.50 85.800
1 3.81 2.50 9.525
TOTAL 95.325 M²
95.33 M² @ 70.00 /-M² 6,672.75
EARTH work for toilet wall ₂
7
1 7.96 0.6 0.6 2.866 M²
2.87 M³ @ 450.00 /-M³ 1,289.52

Page 1 of 12 06/01/2023
RR foundation for toilet
8
wall
1 7 0.6 0.6 2.520 M²
2.52 M³ @ 3500.00 /-M³ 8,820.00

9 Brick work
upper wall on lintel 2 34.32 0.15 0.45 4.633
upper wall on lintel 2 3.81 0.15 0.45 0.514
toilet 1 7 0.15 2.6 2.730
TOTAL 5.148 M³
5.15 M³ @ 9000.00 /-M³ 46,327.95
10 RCC lintel
2 34.32 0.24 0.15 2.471
2 3.81 0.24 0.15 0.274
TOTAL 2.745 M³
2.75 M³ @ 14000.00 /-M³ 38,435.04
11 Rainforcement for lintel
2 34.32 4 0.395 108.451
2 3.81 4 0.395 12.040
1 0.7 360 0.222 55.944
1 7 4 0.395 11.060
TOTAL 187.495 kg
187.49 kg @ 96.00 /-kg 17,999.50

CC 1:3:6 using 20mm


12 broken stone including
watering curing etc

mess hall 1 34.32 3.81 0.075 9.807


TOTAL 9.807 M³
9.81 M³ @ 8000.00 /- M³ 78,455.52

Plastering with CM 1:4, 12


13 mm thick 1 coat

4 34.32 1.00 137.280


compound wall 1 70.00 1.50 105.000
4 3.81 1.00 15.240
TOTAL 257.520 m2
257.52 M² @ 400.00 /- M² 103,008.00

Page 2 of 12 06/01/2023
Roofing with GP tubular
roof members and GI
powder coated trafford
14 sand witch sheet including
necessary overlap etc
complete
2 36 4 288.000
TOTAL 288.000 m2
288.00 M² @ 2000.00 /- M² 576.000 576,000.00
Roofing with GP tubular
roof members and GI
15 powder coated trafford
sheet including necessary
overlap etc complete
1 32.3 1.5 48.450
TOTAL 48.450 M²
48.45 M² @ 1500.00 /-M² 72,675.00
16 PVC GUTTERS
east and west side 2 34.00 68.000
TOTAL 68.000 m
68.00 M @ 340.00 /- m 23,120.00
17 Weld mesh for partion
passage 1 35.00 1.50 52.500
TOTAL 52.500 M²
52.50 M² @ 950.00 /- M² 49,875.00
Gate gi tubular members
18 with gi mesh

1 5.7 1.5 8.550

TOTAL 8.550 M²
8.55 M² @ 1600.00 /- M² 13,680.00
Floor finishing
19

mess hall 1 34.32 3.80 130.416


TOTAL 130.416 M²
130.42 M² @ 1100.00 /- M² 143,457.60
Dadoing Walls with
20 glazed tiles

toilet wall tile 1 7.00 2.10 14.700


wash basin 1 6.00 0.60 3.600
TOTAL 18.300 M²
18.30 M² @ 1000.00 /- m² 18,300.00

Page 3 of 12 06/01/2023
BASIN PANNEL WORK FOR
21 ROOM PARTITION

2 3.81 2.40 18.288


TOTAL 18.288 M²
18.29 M² @ 1500.00 /- M² 27,432.00
Aluminium partion work
22

passage 1 3.81 1.20 4.572


fixed 1 1.20 1.50 1.800
TOTAL 6.372 M²
6.37 M² @ 2900.00 /- M² 18,478.80
Aluminium window work
23

mess hall 2 1.50 1.20 3.600


TOTAL 3.600 m²
3.60 m² @ 3500.00 /- m² 12,600.00
Aluminium door work
24
3 0.90 2.10 5.670
TOTAL 5.670 m²
5.67 m² @ 3900.00 /- m² 22,113.00
Pvc door work
25
2 0.90 2.10 3.780
TOTAL 3.780 m²
3.78 m² @ 1450.00 /- m² 5,481.00
26 Stainless steel wash basin
1 2.00 2.000
2.00 @ 15000.00 /- 30,000.00
27 SINK TAP
2 4.00 8.000
8.00 @ 1200.00 /- NOS 9,600.00
28 60 mm pvc went coul
1 2.00 2.000
2.00 @ 200.00 /- NOS 400.00
29 110 mm pvc pipe
1 5.00 5.000
5.00 @ 600.00 /- m 3,000.00
25 dia mm pvc pipe
29
1 25.00 25.000
25.00 @ 200.00 /- M 5,000.00

Page 4 of 12 06/01/2023
30
60 mm pvc pipe

1 25.00 25.000
25.00 @ 400.00 /- m 10,000.00
31 steel graitings
1 2.00 2.000
2.00 @ 200.00 /- m 400.00
32 Paving block
passage 1 35.00 1.10 38.500
1 32.00 1.30 41.600
80.100
80.10 m² @ 800.00 /- m² 64,080.00
33 White cement washing
SAME AS PLASTERING 257.520 m²
257.520 m²
257.52 m² @ 30.00 /- m² 7,725.60
Painting with ready mixed
34 plastic emulsion 2 coat

SAME AS wall 500.000 m²


500.000
500.00 m² @ 90.00 /- m² 45,000.00
35 ENAMAL PAINTING
1 5.7 1.5 8.550
passage 1 35.00 1.5 52.500
TOTAL 61.050 m²
61.05 m² @ 300.00 /-M² 18,315.00
GRAND TOTAL 1,580,974.00

Page 5 of 12 06/01/2023
Page 6 of 12 06/01/2023
72

Page 7 of 12 06/01/2023
Page 8 of 12 06/01/2023
Page 9 of 12 06/01/2023
Page 10 of 12 06/01/2023
.

Page 11 of 12 06/01/2023
Page 12 of 12 06/01/2023