FLEET SHIP MANAGEMENT

PTE. LTD

Y.M WARRANTY

F.O TRANSFER PROCEDURES


FO TRANSFER PROCEDURES
POINTS TO NOTE:
 Before doing any transfer operations check the F.O TRANSFER
LINE FINISHED DIAGRAM of our ship (SHIP NO:S-2622),
DRAWING NO: M2008, SHEET NO:08.
 Inform chief engineer regarding the transfer operation prior
operating any valves.
 We are using three grades of fuel
o ULSFO (< 0.1 % sulphur)
o VLSFO(< 0.5 % sulphur)
o LSMGO(< 0.1% sulphur)
 No.1 ULSFO (P) tank is the designated tank for ULSFO.
 No.1 F.O.T (S), No.2 F.O.T (P), No.2 F.O.T (S), No.3 F.O.T (P),
No.3 F.O.T (S) tanks are designated tank for VLSFO.
 No.1 M.D.O /M.G.O (P) and No.1 M.D.O /M.G.O (S) are
designated tanks for LSMGO.

HYDRAULIC OPERATED BUNKER TANK SUCTION


VALVES:
 074VNP –NO.1 ULSFO TANK (P)
 075VNP – NO.2 F.O.T (P)
 076VNP – NO.3 F.O.T (P)
 071VNP – NO.1 F.O.T (S)
 072VNP – NO.2 F.O.T (S)
 073VNP – NO.3 F.O.T (S)
 077VNP - No.1 M.D.O /M.G.O (P)
 078VNP - No.1 M.D.O /M.G.O (S)
 009VNP – F.O OVERFLOW TANK(S)
These are the hydraulic valves which can be operated either from
ECR valve control panel or from SHIP’S OFFICE valve control
panel.

ENGINE ROOM FUEL OIL TANKS:


 F.O SETTLING TANK
 F.O SERVICE TANK
 ULSFO SETTLING TANK
 ULSFO SERVICE TANK
 NO.1 MDO/MGO SERVICE TANK
 NO.2 MDO/MGO SERVICE TANK

TRANSFER OPERATION FROM VLSFO BUNKER


TANKS TO F.O SETTLING TANK:
 MAINTAIN BUNKER TANK TEMPERATURE 500C.
 WE USE F.O TRANSFER PUMP TO TRANSFER VLSFO
FROM BUNKER TANK TO F.O SETTLING TANK.
To transfer from no.2 (p) & no.3 (p) VLSFO bunker tank to F.O
settling tank
 Open consecutive bunker tank (p) hydraulic valves from
valve control panel.
VALVES TO OPEN VALVES TO CLOSE
003 VPN 001 VPN
006 VPN 007 VPN
009 VPN 060 VPN
011 VPN 014 VPN (BLANK)
013 VPN 063VPN
062 VPN (BLANK)
012 VPN
002 VPN
004VPN
059 VPN
052VPN
053VPN
074VPN
To transfer from no.1 (s), no.2(s) & no.3 (s) VLSFO bunker
tank to F.O settling tank
 Open consecutive bunker tank (s) hydraulic valves from
valve control panel.
VALVES TO OPEN VALVES TO CLOSE
004 VPN 002 VPN
007 VPN 006 VPN
009 VPN 060 VPN
011 VPN 014 VPN (BLANK)
013 VPN 063 VPN
062 VPN (BLANK)
012 VPN
001 VPN
003 VPN
059 VPN
052 VPN
053 VPN
074 VPN

TRANSFER OPERATION FROM ULSFO BUNKER


TANK TO U.L.S.F.O SETTLING TANK:
 WHEN WE ARE ENTERING ECA, WE HAVE TO
COMPLETE THE CHANGE OVER OF ME, AE, BLR
CONSUMPTION TO ULSFO.
 CHANGE OVER TIMINGS CALCULATED BY FOBAS.
 WE WILL FILL ULSFO SETTLING TANK WHEN M/E
CHANGE OVER COMMENCES.
 BEFORE FILLING THE ULSFO SETTLING TANK, WE
HAVE TO FLUSH THE PIPELINES WITH 1.0 M3 OF
ULSFO TO F.O SETTLING TANK, TO AVOID CARRY
OVER OF VLSFO IN ULSFO SETTLING TANK.
 ULSFO SULPHUR CONTENT=0.065 %, VLSFO SULPHUR
CONTENT= 0.45%
 MAINTAIN BUNKER TANK TEMPERATURE 500C.
 WE USE D.O TRANSFER PUMP TO TRANSFER ULSFO
FROM BUNKER TANK 1(P) TO U.L.S.F.O SETTLING
TANK.
 ULSFO TRANSFER OPERATION CARRIED OUT BY D.O
TRANSFER PUMP IN MANUAL MODE.
 AFTER EVERY TRANSFER, WE STRIP THE LINE TO
AVOID CLOGGING OF FILTERS.
FLUSHING PROCEDURES:
 Prior flushing operation, fill the F.O SETTLING TANK up to
90 M3 of VLSFO.
 Run the F.O TRANSFER PUMP by closing the bunker tank
suction valve to strip the F.O transfer line.
 Isolate the F.O TRANSFER PUMP by closing the suction valve
(009VPN) and discharge valve (011VPN).
 Open bunker tank 1(p) hydraulic valves from valve control
panel.
VALVES TO OPEN VALVES TO CLOSE
059 VPN 003 VPN
074 VPN 006 VPN
023 VPN 004 VPN
016 VPN 007 VPN
018 VPN 001VPN
019 VPN 002 VPN
013VPN( After flushing 1.0 m3 060 VPN
change over to 063 VPN)
062 VPN (BLANK)
012 VPN
054 VPN
052 VPN
053 VPN
055 VPN
021 VPN
014 VPN (BLANK)
024 VPN
 After flushing with 1.0 m of VLSFO change over the valve(013
3

VPN) to (063 VPN).


NOTE:
 After ECA EXIT, before putting the VLSFO in transfer
operation make sure we fill the ULSFO settling tank up to 48.0
m3.
 After finish with ULSFO transfer operations, we have to flush
the D.O transfer pump with LSMGO to make it ready for
further D.O transfer operations.
 Flushing oil quantity should be discussed with chief engineer
before handling.

TRANSFER OPERATION FROM LSMGO BUNKER


TANKS TO MGO/MDO SERVICE TANK:
 MAKE SURE D.O TRANSFER PUMP LINES ARE
FLUSHED WITH LSMGO.
To transfer from NO.1 MDO/MDO TK (P) LSMGO bunker
tank to MDO/MGO SERVICE TANK
 Open NO.1 MDO/MDO TK (P) LSMGO bunker tank
hydraulic valve from valve control panel.
VALVES TO OPEN VALVES TO CLOSE
052 VPN 050 VPN
054 VPN 053 VPN
023 VPN 0051 VPN
016 VPN 014 VPN (BLANK)
018 VPN 024 VPN
021 VPN 019 VPN
065VPN FOR NO.1
MDO/MGO SERVICE TANK
066VPN FOR NO.2
MDO/MGO SERVICE TANK

To transfer from NO.1 MDO/MDO TK (S) LSMGO bunker


tank to MDO/MGO SERVICE TANK
 Open NO.1 MDO/MDO TK (S) LSMGO bunker tank
hydraulic valve from valve control panel.
VALVES TO OPEN VALVES TO CLOSE
053 VPN 050 VPN
055 VPN 052 VPN
023 VPN 0051 VPN
016 VPN 014 VPN (BLANK)
018 VPN 024 VPN
021 VPN 019 VPN
065VPN FOR NO.1
MDO/MGO SERVICE TANK
066VPN FOR NO.2
MDO/MGO SERVICE TANK

! CAUTION:
!!! THINK TWICE BEFORE OPERATING ANY
VALVES.
!!! ALWAYS REFER THE F.O TRANSFER LINE
DIAGRAM BEFORE EVERY VALVE OPERATIONS.
!!! INFORM CHIEF ENGINEER BEFORE ANY
VALVE OPERATIONS.
!!! KEEP IN MIND ABOUT THE CONSEQUENCE OF
CONTAMINATION.