Professional Documents
Culture Documents
Edwin Zaaruka Project Proposal 2
Edwin Zaaruka Project Proposal 2
Topic Area: Voltage drop, Distribution line, DigSilent Power Factory, Shunt
Compensation
Abstract
This project will be based on CENORED, Regional Electricity Distribution Company in the
central part of Namibia, which is experiencing a voltage drop on one of the overhead line
feeder (Tschudi quinas 33kv reticulation). High voltage drop might cause damage to
electrical and electronic equipment at consumer premises.
Therefore, in this project simulation of a 33kV reticulation will be done on DigSilent Power
Factory software with all the loads (customers) connected from which analysis will be
made on the voltage profile at different bus bars. Key problem areas will be outlined and
produce three possible suggestions from which the most effective one will be chosen,
recommendations will be made based on the findings.
DG Distributed generation
ii
iii
iv
LIST OF TABLES
1.1 Background
This project will be based on Tschudi quinas 33kv reticulation, a reticulation in Tsumeb
Namibia supplying power to almost 200 customers. For the past few years’ customers
have been raising complains about the voltage drop mostly during peak hours. There exist
assumptions on what the causes are but no amicable solutions have been found.
Therefore, this project will focus on simulating a network on Dig Silent with all the loads
connected, analysis on the voltage profile at different bus bars will be prepared, to identify
the problem area and to produce possible solutions at the end of the report.
The author has been working for CENORED for almost 5 years as technician, mostly
responsible for attending to power outage and connecting new customers on the grid.
Due to high demand for electricity in Namibia, the number of customers requiring electricity
increase on the daily basis thus placing pressure on the utility to try and keep up with the
demand. Utility company like CENORED has been experiencing voltage drop on one of
their reticulation (Tschudi Quinas 33kV) mostly during peak hours. It has been reported
that during peak hours’ voltage level goes below 5% of the nominal voltage and according
to the regulation, the voltage level that the consumer terminal must be within +- 5% of the
nominal voltage. Electrical and Electronics equipment’s are designed to operate on
specific voltage. Any change from the specified voltage values will result in a serious
problem to the power system and equipment.
1
1.3.1. Capacitor Banks
Authors like N.M. Neagle and Dr. Samson
Considered the losses reduction can be achieved by installation of capacitor banks on the
primary feeders. In this method the peak power requirement was minimized, he also
developed some formula calculating loss reduction as offered by a shunt capacitor, Figure
1 show the connection of the capacitor bank in to the distribution network .[1][2]
[3]
According to Carlisle et Al, the author believes that electric energy from the generating
point to the end users (consumers) via the transmission and distribution networks is
escorted by losses. Most of these losses occur on the distribution system. It is widely
recognized that placement of shunt capacitors on the distribution system can lead to a
reduction in power losses.[1][4]
Authors M.A. Yadav, D.s. Reddy and K.S.N. Hitesh, developed an analytical method for
the calculating power losses reduction by applying a number of shunt capacitors of
same
size, to a uniformly loaded feeder for a constant reactive load level. [1]
2
1.3.2. Voltage Regulation on MV feeder using Tap Changing Transformer
The main objective of voltage control in conventional feeders is to minimize losses on the
feeder or to operate the voltage closer to the nominal voltage. Two methods are used to
control the voltage.[5]
3
system, directly to the customer’s facilities, or both. As DG systems generate power locally
to fulfil customer demands, appropriate size and placement of DG can drastically reduce
power losses in the system. DG inclusion improves supply quality and reliability and
reduces greenhouse effects In this work, voltage profile is improved better when DG is
connected with appropriate size and location.[2]
None of the authors from the literatures has analyzed the voltage drop on Tschudi
Quinas
33kV Reticulation, therefore this study stands district in this area.
With the help of NDEEN theory I obtained on Power systems, Power System Simulation
and protection . Tschudi Quinas Reticulation will be Simulated on DigSilent Power
Factory, analyzes will be made on voltage level at each bus bar with all the loads
connected. All possible solutions will be applied to rectify the voltage drop and the best
one will be chosen.
The project will require site visit in order to take voltage readings on the retic, individual
peak current readings of each customer connected to the grid. Currently the system
controller at CENORED is assisting with all the information needed.
No funding has been allocated to this project.
Output
System Voltage Profile
Load profile
Voltage at each bus bar
5
2.4 Technical Specification
2.4.1 Conductors
Tschudi quinas reticulation is constructed using two types of conductors (rabbit and
Goffer). Table 1 below show line parameters of conductors used in this project.
2.4.2 Transformers
On this project different sizes of transformer will be used, Table 2 below contains all the
transformers information that will be required.
Transformer Data
Positive Sequence data
Transformer Size Voltage ratings Vector group Z% XL R
Dyn11 0.09999998 0.00007
25kVA 33/0.42 4
50kVA 33/0.42 Dyn11 4 0.09999998 0.00007
6
Dyn11 0.09999998 0.00007
100kVA 33/0.42 4.2
Dyn11 0.09999998 0.00007
200kVA 33/0.42 4.07
Dyn11 0.09999998 0.00007
315kVA 33/0.42 4.25
Dyn11 0.09999998 0.00007
2.5MVA 66/0.42 4.27
7
3. Methodology & Theoretical Backgroung
3.1.1 Theory
The following Theory will be used for this project
Power flow
Gauss Seidel Method
Newton –Raphson Method
Power System Power Factory DigSilent Software
Simulation Will be used for Simulation of the network
8
capacitor bank designs
Table 3: Theory
Deliverable:
Read what other authors have written about the topic (Voltage drop on distribution
network).
Contact CENORED’S systems controllers for information on the problem.
Gather technical specification and useful information for the network.
Consult my supervisor
Compile proposal (Draft)
Consult my Supervisor
Edit Proposal
Consult my Supervisor
Final proposal (Submit)
Deliverable:
Deliverable:
Determine the voltages and angles at each bus bar using Gauss Seidel and newton
–Raphson Method.
Compare the calculated value with the simulated results.
Deliverable:
Deliverable:
Step 6:
4. Outcomes
4.1 Results
The result will contain the Power Factory Simulated voltage profile, load Flow.
10
4.2 Findings
From the possible solutions, the preferred method (solution) must be able to reduce
the voltage drop during peak hours.
4.3 Recommendations
4.4 Benefits
The project expected benefits are
This project will benefit Cenored, NamPower and other utilities that experiencing similar
problem.
Figure 3 : Work Breakdown Structure
12
5.2 Gantt chart:
Gantt chart attached on Appendix c
5.3 Tracking
Once done with Literature review and other missing information in the report. I will use MS
Excel to then track this project in terms of expectation and actual timelines which will be
contained in the final thesis.
DigSilent Power Factory is available on my Laptop, if fails, there is one at work that I can
use. It won’t be easy to get all information that I might need from the company therefore
from time to time; the author will be force to travel to Namibia.
5.5 Budget
Total 29,325.00
Table 4 : Budget
13
5.5.2 Project Financing
Table 5 show estimated budget for the project.
LABOUR
TRANSPORT
Total 32,727.12
15% VAT 1 4,909.07
TOTAL N$37,636.19
Figure 4: budget
6. References
[3] N. M. Neagle and D. R. Samson, “on Primary,” no. October, pp. 950–959, 1956.
[4] J. C. C. A. A. El-keib and D. B. K. Nolan, “A Review of Capacitor Placement
Techniques on Distribution Feeders,” no. 1, pp. 359–365, 1997.
[5] F. A. Viawan, A. Sannino, and J. Daalder, “Voltage control with on-load tap changers
in medium voltage feeders in presence of distributed generation,” Electr. Power
Syst. Res., vol. 77, no. 10, pp. 1314–1322, 2007.
7. Appendices
Appendix A
15
16
EDWIN ZAARUKA PROJECT PROPOSAL
Tschudi Quinas Reciculation
17
18
Gantt chart
Manually Consult my
1 day Thu Thu 6
Scheduled supervisor 27/4/23 27/4/23
Manually Mon
Draft a Proposal 7 days Fri 28/4/23 7
Scheduled 8/5/23
Manually
Final Proposal 9 days Wed Mon 9
Scheduled 10/5/23 22/5/23
Manually Power Point
1 day Tue Tue 10
Scheduled Presentation 23/5/23 23/5/23
Manually DigSilent Power Tue
10 days Wed 2
Scheduled Factory 24/5/23 6/6/23
20
EDWIN ZAARUKA PROJECT PROPOSAL
Manually Choose the best Thu
5 days Fri 11/8/23 20
Scheduled solution 17/8/23
Manually
Final Report 1 day Wed Wed 31
Scheduled 20/9/23 20/09/23
21
EDWIN ZAARUKA PROJECT PROPOSAL