4.2 Org Chart & Manpower Planning
4.2 Org Chart & Manpower Planning
4.2 Org Chart & Manpower Planning
Zakaria
(Foreman)
Description Pylon 1 Pylon 2 Pylon 3 Pylon 4 Pylon 5 Pylon 6 Pylon 7 Pylon 8 Pylon 9 Pylon 10 Pylon 11 Pylon 12 Pylon 13 Clearing works
Manpower Team 1 Team 2 Team 1 Team 2 Team 1 Team 2 Team 1 & 2
Duration 2 days 2 days 2 days 2 days 2 days 2 days 2 days
Frequency Bi-yearly
Machineries and specification