Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

PROJECT: STEEL CAGE PLATFORM (HOISTING BEAM)

Work Schedule for Preparation, Fabrication and Installation of Steel Cage Platform (Hoisting Beam)

ITEM PROJECTS NAME DUR 2023


May-23 Jun-23 Jul-23
(LIFTING BEAM) W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4
1 PROCUREMENT WORKS
Preparing & Submission of Drawing DONE
Purchasing & Delivery Process of Materials 7 days
2 FABRICATION WORKS
Cut & Weld 7 days
Sand blast & Painting 7 days
3 INSTALLATION WORKS
Lifting Beam Installation 8 days
4 FINAL INSPECTION
Final Joint Inspection & Final As-built Joint Survey 1 day
(STEEL CAGE) W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4
1 PROCUREMENT WORKS
Preparing & Submission of Drawing DONE
Purchasing & Delivery Process of Materials 7 days
2 FABRICATION WORKS
Cut & Weld 7 days
Powder Coat 14 days
4 FINAL INSPECTION
Final Joint Inspection & Final As-built Joint Survey 1 day

Issue Date : 19 May 2023

You might also like