Professional Documents
Culture Documents
Action Plan
Action Plan
Expected Date of
Sl.No DEPARTMENT DOCUMENT NAME
Completion
SOPs 31.03.2023
SMF 31.05.2023
VMP 31.05.2023
1 QA
QMS Completed
Internal Audit Shedule 15.04.2023
Log books related to SOP 31.03.2023
SOPs
Method validation
Instrument Qualification
Temperature Mapping
Calibration Schedule
Job Discription,Analyst Qualification &
Training Record
Control Sample+ Storage+Distruction
2 QC Reference / Working Standard
(List,Qualification,Reconciliation)
Temperature and Humidity Record
Availability/Stand-by/Calibration of
Standard weight Box
Calibration of Measuring Equipments
Column Usage/Performance Log
Data Back-up
List Authorized Persons to enter QC
Log books related to SOP
SOPs
Reactors volumetric calibration
Process Validation
Equipment Hold time Study
(dirty-hold time, clean-hold time)
Filter bag Change Record
3 Production Equipmment Status Board
Production Weighing Balance check
(Daily, Fortnightly, Quartterly, half
yearly and Yearly)
Job Discription.
Training Record of Individual employee
Log books related to SOP
SOPs
Equipment Qualification
Utilities Qualification
Preventive Maintenance shedule
Calibration Shedule
4 Engineering
4 Engineering
Approved Drawings
Light fittings number
SAG, RAG Number
Under ground water tank Number
Log books related to SOP
SOPs
Training shedule
Training Calender
Training Need identification
Individule Personnel File
Pest Control and Lay out
(Gum Pad and Rodent bite station)
Insectocutor/ Fly catcher lay out
Job Discription of Individuals,
5 HR Possition wise & Key Personnels
HR Poloicies
Induction Program
Organogram
Exit Interview
Distribution of Uniforms and Aprons
record
Master Role
Specimen Signature
Log books related to SOP
SOPs
Fire Hydrant Layout Drawing
Fire Extinguisher Layout drawing
Emergency evaccuation Plan
Fire Hydrant Challenging Test
6 Safety Smoke detector & Foam dispenser
Numbering
Numbering And Layout drawing for
fire extinguisher
Hose reel Box Number
Safety Instructions for material Hoist
Log books related to SOP
SOPs
Gum pads and Rodent Bite Station
7 Warehouse
Temperature Mapping
Log books related to SOP
Name of the
S. No. Equipment / Code
Instrument
Equipments
1 Reactor R
2 Dosing tank DT
3 Vacuum tray drier VTD
Roto cone vacuum
4 RCVD
drier
5 Centrifuge CF
6 Storage tank ST
7 Holding Tank HT
8 Nutsche filter NF
9 Blender BL
10 Multi mill MM
11 Sifter SFT
12 Microniser MN
13 Sparkler Filter SPF
14 Dome Filter DF
15 Micron Filter MF
Equipment code
16 Vacuum trap
with VT
Equipment code
17 Vacuum Pump
with VP
Equipment code
18 Receiver
with RE
Equipment code
19 Condenser
with HE
20 Air curtain PR/ACR
Environmental
21 EVM
monitor
22 Lights PRLT
23 Smoke detector PRSD
24 Fire siren PRFS
25 Isolator module PRISM
26 Camera PRCAM
27 Safety shower PRSS
28 Light switch PRLTS
29 Single phase PR 1Ø
30 Three phase PR 3Ø
Breathing
31 PRBA
apparatus
32 Push button PRPB
33 Compound gauge CG
34 Temperature gauge TG
Temperature
35 TS
sensor
Temperature
36 TI
indicator
37 Vacuum gauge VG
38 Pressure gauge PG
EQUIPMENT QUALIFICATION
Manjunath
6 Blender
7 Multi mill
8 Sifter
9 Microniser
10 Sparkler Filter
11 Dome Filter
12 Micron Filter
UTILITY QUALIFICATION
ATION