UNIT COST
ITEM DESCRIPTION MODEL QTY. UNIT AMOUNT
Materials Labor/Others Total Unit Cost
GENERAL REQUIREMNETS
Mobilization/Demobilization/Temp. Facilities 1.00 lot - 29,700.00 29,700.00 29,700.00
Site Management/Engineering and Technical Supervision 1.00 lot - 32,400.00 32,400.00 32,400.00
Testing and Commissioning 1.00 lot - 19,800.00 19,800.00 19,800.00
Quality Standard and Control/As Built Plans/Shop Drawings 1.00 lot - 35,100.00 35,100.00 35,100.00
Safety & PPE 1.00 lot - 18,000.00 18,000.00 18,000.00
K MECHANICAL WORKS
K1 AC Equipment (DAIKIN VRF/VRV)
Outdoor Unit
ACCU-GF-01, 12.1kw, 230/1/60 RXMQ4AVE 1.00 set 165,800.00 7,000.00 172,800.00 172,800.00
ACCU-GF-02, 12.0kw, 230/1/60 RXMQ4AVE 1.00 set 165,800.00 7,000.00 172,800.00 172,800.00
ACCU-GF-03, 16.0kw, 230/1/60 RXMQ4AVE 1.00 set 165,800.00 7,000.00 172,800.00 172,800.00
ACCU-GF-04, 12.1kw, 230/1/60 RXMQ5BVM 1.00 set 191,600.00 7,000.00 198,600.00 198,600.00
ACCU-GF-05, 12.1kw, 230/1/60 RXMQ4AVE 1.00 set 165,800.00 7,000.00 172,800.00 172,800.00
Indoor Unit
FCU-GF-01, 4-Way Ceiling Cassette, 3.95kw, 230/1/60, GF Lobby FXFQ50AVM 1.00 set 69,500.00 2,500.00 72,000.00 72,000.00
FCU-GF-02, 4-Way Ceiling Cassette, 4.69kw, 230/1/60, GF Corridor FXFQ50AVM 1.00 set 69,500.00 2,500.00 72,000.00 72,000.00
FCU-GF-03, 4-Way Ceiling Cassette, 4.69kw, 230/1/60, GF Corridor FXFQ50AVM 1.00 set 69,500.00 2,500.00 72,000.00 72,000.00
FCU-GF-04, 2-Way Ceiling Cassette, 1.95kw, 230/1/60, GF Meeting Room 1 FXCQ25AVM 1.00 set 99,800.00 2,500.00 102,300.00 102,300.00
FCU-GF-05, 2-Way Ceiling Cassette, 1.95kw, 230/1/60, GF Meeting Room 2 FXCQ25AVM 1.00 set 99,800.00 2,500.00 102,300.00 102,300.00
FCU-2F-01, 4-Way Ceiling Cassette, 3.32kw, 230/1/60, 2F Conference Room FXFQ40AVM 1.00 set 67,600.00 2,500.00 70,100.00 70,100.00
FCU-2F-02, 4-Way Ceiling Cassette, 7.03kw, 230/1/60, 2F Work Station FXFQ80AVM 1.00 set 78,500.00 2,500.00 81,000.00 81,000.00
FCU-2F-03, 4-Way Ceiling Cassette, 7.03kw, 230/1/60, 2F Work Station FXFQ80AVM 1.00 set 78,500.00 2,500.00 81,000.00 81,000.00
FCU-2F-04, 4-Way Ceiling Cassette, 3.77kw, 230/1/60, 2F Lobby FXFQ40AVM 1.00 set 67,600.00 2,500.00 70,100.00 70,100.00
FCU-2F-05, 4-Way Ceiling Cassette, 3.77kw, 230/1/60, 2F Lobby FXFQ40AVM 1.00 set 67,600.00 2,500.00 70,100.00 70,100.00
Refrigerant Piping
7/8" diameter copper pipe type L, hard drawn - m - -
5/8" diameter copper pipe type L, hard drawn 184.00 m 433.88 130.17 564.05 103,785.05
1/2" diameter copper pipe type L, hard drawn 73.00 m 304.36 91.31 395.66 28,883.38
3/8" diameter copper pipe type L, hard drawn 184.00 m 193.13 57.94 251.07 46,196.22
1/4" diameter copper pipe type L, hard drawn 73.00 m 123.83 37.15 160.98 11,751.28
Copper Elbows
7/8" diameter - pcs - - -
5/8" diameter 154.00 pcs 38.40 11.52 49.92 7,687.68
1/2" diameter 61.00 pcs 27.60 8.28 35.88 2,188.68
3/8" diameter 154.00 pcs 24.00 7.20 31.20 4,804.80
1/4" diameter 61.00 pcs 25.20 7.56 32.76 1,998.36
Copper Couplings
7/8" diameter - pcs - - -
5/8" diameter 123.00 pcs 40.80 12.24 53.04 6,523.92
1/2" diameter 49.00 pcs 26.40 7.92 34.32 1,681.68
3/8" diameter 123.00 pcs 24.00 7.20 31.20 3,837.60
1/4" diameter 49.00 pcs 28.80 8.64 37.44 1,834.56
Refrigerant Pipe hangers / supports / Platforms (ACCU) -VRF SYSTEM 1.00 lot 90,704.80 38,873.48 129,578.28 129,578.28
Consumable items for refrigerant piping installation - VRF System 1.00 lot 189,243.09 81,104.18 270,347.27 270,347.27
Chipping Works & Sealant Apllication 1.00 lot 12,600.00 5,400.00 18,000.00 18,000.00
Grilles
200 x 100 mm Exhaust Air Grille 2.00 pcs 1,428.57 450.00 1,878.57 3,757.14
150 x 100 mm Toilet Exhaust Air Grille 4.00 pcs 1,428.57 450.00 1,878.57 7,514.29
Others
Electrical Works 1.00 lot 4,327.61 1,854.69 6,182.30 6,182.30
Prepared by