Sand/ Aggregate
Lime,Moorum, Manure or Excavated Aggregates 40mm &
Lead Building rubbish. Earth Sludge Rock below 40 mm Above Soling/Stone Bricks Brick Tiles
in Kms cum cum cum cum cum cum cum per 1000 No per 1000 No
NOTE :- THE RATES WILL BE APPLICABLE TO NET QUANTITIES AFTER DEDUCTION OF PRESCRIBED PERCENTAGE OF VOIDS MENTIONED IN
SPECIFICATION UNDER SUBHEAD "CARRIAGE OF MATERIALS".
Carriage of Materials by MeChaniCal transport
Cement, stone
blocks,
G.I. C.I., A.C.,
Stainless
Steel & C.C.
pipes
below 100 mm
dia and
other heavy Steel/CGI Tar
Lead materials Crates sheets Timber Bitumen Solvent Steam Coal
in Kms tonne tonne tonne cum tonne qtls tonne
NOTE :- THE RATES WILL BE APPLICABLE TO NET QUANTITIES AFTER DEDUCTION OF PRESCRIBED PERCENTAGE OF VOIDS
MENTIONED IN SPECIFICATION UNDER SUBHEAD "CARRIAGE OF MATERIALS".
Carriage of Materials by MeChaniCal transport
S.W. PIPES
Lead 100 mm dia 150 mm dia 200 mm dia 230 mm dia 250 mm dia 300 mm dia 350 mm dia 400 mm dia 450 mm dia 500 mm dia 600 mm dia empty cement bags
in Kms per 100 m per 100 m per 100 m per 100 m per 100 m per 100 m per 100 m per 100 m per 100 m per 100 m per 100 m per 1000 No's
1 171.66 343.32 572.2 817.44 980.92 1226.15 1716.61 2452.31 3121.12 3433.23 4291.53 51.5
2 196.59 393.17 655.29 936.12 1123.35 1404.18 1965.86 2808.36 3574.28 3931.71 4914.64 58.98
3 221.11 442.23 737.05 1052.93 1263.51 1579.39 2211.15 3158.78 4020.27 4422.29 5527.87 66.33
4 244.78 489.56 815.93 1165.62 1398.74 1748.43 2447.8 3496.85 4450.54 4895.6 6119.49 73.43
5 267.65 535.3 892.17 1274.53 1529.43 1911.79 2676.51 3823.58 4866.38 5353.02 6691.27 80.3
6 288.54 577.07 961.79 1373.99 1648.78 2060.97 2885.37 4121.95 5246.12 5770.74 7213.41 86.57
7 309.43 618.84 1031.41 1473.45 1768.13 2210.15 3094.23 4420.32 5625.86 6188.46 7735.55 92.84
8 330.32 660.61 1101.03 1572.91 1887.48 2359.33 3303.09 4718.69 6005.6 6606.18 8257.69 99.11
9 351.21 702.38 1170.65 1672.37 2006.83 2508.51 3511.95 5017.06 6385.34 7023.9 8779.83 105.38
10 372.1 744.15 1240.27 1771.83 2126.18 2657.69 3720.81 5315.43 6765.08 7441.62 9301.97 111.65
11 389.55 779.05 1298.44 1854.92 2225.89 2782.33 3895.31 5564.71 7082.35 7790.62 9738.22 116.88
12 407 813.95 1356.61 1938.01 2325.6 2906.97 4069.81 5813.99 7399.62 8139.62 10174.47 122.11
13 424.45 848.85 1414.78 2021.1 2425.31 3031.61 4244.31 6063.27 7716.89 8488.62 10610.72 127.34
14 441.9 883.75 1472.95 2104.19 2525.02 3156.25 4418.81 6312.55 8034.16 8837.62 11046.97 132.57
15 459.35 918.65 1531.12 2187.28 2624.73 3280.89 4593.31 6561.83 8351.43 9186.62 11483.22 137.8
16 476.8 953.55 1589.29 2270.37 2724.44 3405.53 4767.81 6811.11 8668.7 9535.62 11919.47 143.03
17 494.25 988.45 1647.46 2353.46 2824.15 3530.17 4942.31 7060.39 8985.97 9884.62 12355.72 148.26
18 511.7 1023.35 1705.63 2436.55 2923.86 3654.81 5116.81 7309.67 9303.24 10233.62 12791.97 153.49
19 529.15 1058.25 1763.8 2519.64 3023.57 3779.45 5291.31 7558.95 9620.51 10582.62 13228.22 158.72
20 546.6 1093.15 1821.97 2602.73 3123.28 3904.09 5465.81 7808.23 9937.78 10931.62 13664.47 163.95
21 561.32 1122.58 1871.02 2672.81 3207.37 4009.2 5612.97 8018.46 10205.34 11225.94 14032.37 168.36
22 576.04 1152.01 1920.07 2742.89 3291.46 4114.31 5760.13 8228.69 10472.9 11520.26 14400.27 172.77
23 590.76 1181.44 1969.12 2812.97 3375.55 4219.42 5907.29 8438.92 10740.46 11814.58 14768.17 177.18
24 605.48 1210.87 2018.17 2883.05 3459.64 4324.53 6054.45 8649.15 11008.02 12108.9 15136.07 181.59
25 620.2 1240.3 2067.22 2953.13 3543.73 4429.64 6201.61 8859.38 11275.58 12403.22 15503.97 186
26 634.92 1269.73 2116.27 3023.21 3627.82 4534.75 6348.77 9069.61 11543.14 12697.54 15871.87 190.41
27 649.64 1299.16 2165.32 3093.29 3711.91 4639.86 6495.93 9279.84 11810.7 12991.86 16239.77 194.82
28 664.36 1328.59 2214.37 3163.37 3796 4744.97 6643.09 9490.07 12078.26 13286.18 16607.67 199.23
29 679.08 1358.02 2263.42 3233.45 3880.09 4850.08 6790.25 9700.3 12345.82 13580.5 16975.57 203.64
30 693.8 1387.45 2312.47 3303.53 3964.18 4955.19 6937.41 9910.53 12613.38 13874.82 17343.47 208.05
31 708.52 1416.88 2361.52 3373.61 4048.27 5060.3 7084.57 10120.76 12880.94 14169.14 17711.37 212.46
32 723.24 1446.31 2410.57 3443.69 4132.36 5165.41 7231.73 10330.99 13148.5 14463.46 18079.27 216.87
33 737.96 1475.74 2459.62 3513.77 4216.45 5270.52 7378.89 10541.22 13416.06 14757.78 18447.17 221.28
34 752.68 1505.17 2508.67 3583.85 4300.54 5375.63 7526.05 10751.45 13683.62 15052.1 18815.07 225.69
35 767.4 1534.6 2557.72 3653.93 4384.63 5480.74 7673.21 10961.68 13951.18 15346.42 19182.97 230.1
36 782.12 1564.03 2606.77 3724.01 4468.72 5585.85 7820.37 11171.91 14218.74 15640.74 19550.87 234.51
37 796.84 1593.46 2655.82 3794.09 4552.81 5690.96 7967.53 11382.14 14486.3 15935.06 19918.77 238.92
38 811.56 1622.89 2704.87 3864.17 4636.9 5796.07 8114.69 11592.37 14753.86 16229.38 20286.67 243.33
39 826.28 1652.32 2753.92 3934.25 4720.99 5901.18 8261.85 11802.6 15021.42 16523.7 20654.57 247.74
40 841 1681.75 2802.97 4004.33 4805.08 6006.29 8409.01 12012.83 15288.98 16818.02 21022.47 252.15
PER KM ADD 14.72 29.43 49.05 70.08 84.09 105.11 147.16 210.23 267.56 294.32 367.9 4.41
NOTE :- THE LENGTH OF S.W. PIPES WILL BE MEASURED EXCLUSIVE OF INTERNAL DEPTH OF SOCKETS.
Carriage of Materials by MeChaniCal transport
R.C.C. PIPE,AC PIPES,STEEL CYLINDER,R.C PIPES,G.I. PIPES,D.I. PIPES,C.I. PIPES AND UNREINFORCED CEMENT PIPES
NOTE:- THE LENGTH OF THE FLANGED OR PLAIN ENDED CONCRETE R.C.C. PIPES,STEEL CYLINDERS,R.C. PIPES & C.I. PIPES SHALL BE MEASURED OVERALL.
THE LENGTH OF SOCKETED PIPES SHALL BE MEASURED EXCLUSIVE OF INTERNAL DEPTH OF SOCKETS.
Carriage of Materials by Manual labour
100.00 336.32 552.82 773.61 990.83 1288.07 1840.1 2576.15 3220.18 3903.26 4770.64 5854.88 45.62
150.00 379.36 623.56 872.6 1117.62 1452.89 2075.56 2905.8 3632.24 4402.73 5381.1 6604.08 53.78
200.00 422.4 694.3 971.59 1244.41 1617.71 2311.02 3235.45 4044.3 4902.2 5991.56 7353.28 61.94
250.00 465.44 765.04 1070.58 1371.2 1782.53 2546.48 3565.1 4456.36 5401.67 6602.02 8102.48 70.1
300.00 508.48 835.78 1169.57 1497.99 1947.35 2781.94 3894.75 4868.42 5901.14 7212.48 8851.68 78.26
350.00 551.52 906.52 1268.56 1624.78 2112.17 3017.4 4224.4 5280.48 6400.61 7822.94 9600.88 86.42
400.00 594.56 977.26 1367.55 1751.57 2276.99 3252.86 4554.05 5692.54 6900.08 8433.4 10350.08 94.58
450.00 637.6 1048 1466.54 1878.36 2441.81 3488.32 4883.7 6104.6 7399.55 9043.86 11099.28 102.74
500.00 680.64 1118.74 1565.53 2005.15 2606.63 3723.78 5213.35 6516.66 7899.02 9654.32 11848.48 110.9
550.00 723.68 1189.48 1664.52 2131.94 2771.45 3959.24 5543 6928.72 8398.49 10264.78 12597.68 119.06
600.00 766.72 1260.22 1763.51 2258.73 2936.27 4194.7 5872.65 7340.78 8897.96 10875.24 13346.88 127.22
650.00 809.76 1330.96 1862.5 2385.52 3101.09 4430.16 6202.3 7752.84 9397.43 11485.7 14096.08 135.38
700.00 852.8 1401.7 1961.49 2512.31 3265.91 4665.62 6531.95 8164.9 9896.9 12096.16 14845.28 143.54
750.00 895.84 1472.44 2060.48 2639.1 3430.73 4901.08 6861.6 8576.96 10396.37 12706.62 15594.48 151.7
800.00 938.88 1543.18 2159.47 2765.89 3595.55 5136.54 7191.25 8989.02 10895.84 13317.08 16343.68 159.86
850.00 981.92 1613.92 2258.46 2892.68 3760.37 5372 7520.9 9401.08 11395.31 13927.54 17092.88 168.02
900.00 1024.96 1684.66 2357.45 3019.47 3925.19 5607.46 7850.55 9813.14 11894.78 14538 17842.08 176.18
950.00 1068 1755.4 2456.44 3146.26 4090.01 5842.92 8180.2 10225.2 12394.25 15148.46 18591.28 184.34
1000.00 1111.04 1826.14 2555.43 3273.05 4254.83 6078.38 8509.85 10637.26 12893.72 15758.92 19340.48 192.5
Per 50m add 43.04 70.74 98.99 126.79 164.82 235.46 329.65 412.06 499.47 610.46 749.2 8.16
NOTE :- THE LENGTH OF S.W. PIPES WILL BE MEASURED EXCLUSIVE OF INTERNAL DEPTH OF SOCKETS.
Carriage of Materials by Manual labour
R.C.C. PIPE,AC PIPES,STEEL CYLINDER,R.C PIPES,G.I. PIPES,D.I. PIPES,C.I. PIPES AND UNREINFORCED CEMENT PIPES
NOTE:- THE LENGTH OF THE FLANGED OR PLAIN ENDED CONCRETE R.C.C. PIPES,STEEL CYLINDERS,R.C. PIPES & C.I. PIPES SHALL BE MEASURED OVERALL.
THE LENGTH OF SOCKETED PIPES SHALL BE MEASURED EXCLUSIVE OF INTERNAL DEPTH OF SOCKETS.
Carriage of Materials by Manual labour
Asbestos Cement Pipes