Doc.

Code FM-ESH-01-43
Rev. No. 0
.
Daily Observation report Eff. Date 01 Aug 2014

Sta. Clara International Corp. Page No. 1 of 1

SC-OTVIlijan
Consortium
Project / Location:
LNG Import Facility Project Control No.
Inspection Date: April 28, 2022 Reporting Date: April 28, 2022

AREA FINDINGS PHOTOS

Sea water intake

Instructed Mr. Armando Torres


Poor housekeeping to conduct housekeeping to
avoid incident.

Inspected by: Approved by:

Armando Torres Ronald De Leon


ESH TEAM Project Manager