Earthworks

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 7

Earthworks

Earthworks
The Process of earthworks is to excavate the existing land to a suitable level so that road construction may begin. The
earthworks can take the form of either excavation in the form of cuts or the construction of embankments to carry an
elevated highway. Normally in a road design project, both will be necessary and movement of earth from one part of
the site to the next will be necessary. This should be done with as little waste created or as little extra material required
as disposal or collection is expensive.

Also included under the topic of earthworks is the compaction of the road materials to the appropriate level. This
however is not covered as it is more concerned with the actual construction of the road than the design of it.

This page is concerned solely with the design of the earthworks and not with the actual design of the embankments or
cuts. If you wish to learn more about this then links to relevant pages are contained in the geotechnical section of the
links page. A link to this can be found opposite.

Of the topics covered in this page, they can be split up into the design of the earthworks and the plant used in the
construction.

Excavation
The most important feature of the excavation is the material you are working with. This will be known from the Site
Investigation. Poor information can lead to technical problems and to cost overruns.

There are many ways of classifying the soil in terms of it's ease of excavation including seismic techniques. The most
common in the United Kingdom at present however is the Ease of Digging scale or diggability. This classifies the soil
in one of four categories:

E
Easy digging - Loose free running soils eg sands, fine gravels.
M
Medium - Denser cohesive soils eg clayey gravel, low PI clays
M-H

https://community.dur.ac.uk/~des0www4/cal/roads/earthwk/earthwk.html[2017-09-26 11:02:32 AM]


Earthworks

Medium to Hard - eg broken rock, wet heavy clay, gravel with boulders
H
Hard - material requiring blasting and hard high PI clays

Typical diggability factors can be seen in Table 1 below.

Another important feature of rock is the amount of fissuring. There are two methods of assessing this, the percentage
Rock Quality Data method and the Spacing of joints method. Each of these leads directly to an estimate of the uniaxial
compressive strength and thus an indication of the excavation method. Both these can be found in the Manual of
contracts document, Series 6001.

Excavation increases the volume of material. It is therefore necessary to use a bulking factor to determine the volume of
material that will be created by excavation. Bulking factor is defined as:

/
Bulking Factor = Volume after Excavation Volume before Excavation

Similarly a shrinkage factor is defined for the compaction of a soil at it's final destination.:

/
Shrinkage Factor = Volume after Compaction Volume before Excavation

Typical values can be found in Table 1 below.

Table 1 - Soil Properties


Bulk Density Bulking Shrinkage
Material Diggability
Mg/m3 Factor Factor
Clay (Low PI) 1.65 1.30 - M
Clay (High PI) 2.10 1.40 0.90 M-H
Clay and Gravel 1.80 1.35 - M-H
Sand 2.00 1.05 0.89 E
Sand & Gravel 1.95 1.15 - E
Gravel 2.10 1.05 0.97 E
Chalk 1.85 1.50 0.97 E
Shales 2.35 1.50 1.33 M-H
Limestone 2.60 1.63 1.36 M-H
Sandstone (Porous) 2.50 1.60 - M
Sandstone (cemented) 2.65 1.61 1.34 M-H
Basalt 2.95 1.64 1.36 H
Granite 2.41 1.72 1.33 H

In addition to the above properties, it is important to have some idea about the trafficability of the soils. This is because
the excavation plant will need to drive over the soils without becoming bogged down. The trafficability of the soils is
related to their drainage properties.

Sands/Gravels
Free Draining. Tend to have few problems.
High PI Clays
Low permeability will prevent water ingress so the surface becomes dangerous but not in the long term.

https://community.dur.ac.uk/~des0www4/cal/roads/earthwk/earthwk.html[2017-09-26 11:02:32 AM]


Earthworks

Silts/Low PI Clays
These cause the most problems. Permeability allows ingress which softens the soils thus weakening them.

Earthworks Balance
In order to minimise material waste or borrow, it is necessary to produce what is called a Mass Haul diagram. This is
essentially a plot of cumulative volume of soil against distance along the road, often called the chainage. Cut volumes
are taken to be positive and fill volumes to be negative.

Calculation of Cross Sectional Area

The first stage in the production of the Mass Haul Diagram is the calculation of the cross sectional areas of cut or fill at
different points along the road.

For a cut or fill on horizontal ground.

Figure 1 - Typical Cut Cross Section

Assuming a cut such as the one above, the cross sectional area is given by:

Area = h.2b + 2nh²/2 = h(2b + nh)

For a cut or fill on sloping ground

Figure 2 - Typical Sloping Cut Cross Section

Assuming a cut such as the one above, the cross sectional area is found firstly by calculating WL and WG:

https://community.dur.ac.uk/~des0www4/cal/roads/earthwk/earthwk.html[2017-09-26 11:02:32 AM]


Earthworks


WL = S(b+nh)/(S+n)

WG = S(b+nh)/(S-n)

Thus Area = ½(h + b/n)(WL + WG) - b²/n

For more complicated cross sections, simply combine the above. It should be noted that this is NOT part of the design
process for the slope stability.

Cumulative Volumes

Once the cross sectional areas are known at various points along the road, it is possible to calculate the cumulative
volume along the cut by interpolating between the different points.

The simplest way of doing this is to assume a straight line variation and use the prismatic rule. Other slightly more
complicated methods involve using Simpsons rule or similar. Do not forget to take account of the bulking factor or
shrinkage factor although care should be taken not to use them both as this will produce incorrect results. If you are
using the shrinkage factor then changes in volume due to excavation is accounted for automatically. The same is true
for the bulking factor.

Mass Haul Diagram

The mass haul diagram is now simply a plot of cumulative volume against chainage. Areas below the line represent net
fill and areas above the line represent net waste. The following points are worth noting:

A rising curve indicates an increasing volume (cut).


A maximum point on the curve represents the end of a cut.
A falling curve represents a decreasing volume (fill).
A minimum point represents the end of a fill.
Areas at the end of the diagram represent a waste or a deficit.

Earthmoving Equipment
This section will highlight some of the principal earthmoving equipment and their areas of application.

Bulldozer - This is used primarily for pushing soil. Vehicles are generally tracked and require large amounts of
traction. Many bulldozers incorporate hydraulic attachments at the rear for breaking up soil and rock. The best
known of the vehicles.

Drag Line - This vehicle allows excavation below it's own level. It is essentially a bucket on the end of a jib and is
used solely for bulk excavation as it is relatively uncontrolled.

Dump Truck - These are wheeled vehicles and as such are able to move much faster. This is offset by a lack of
traction and dump trucks are always the first to get stuck. They are used for transferring material from one part of
the site to another.

https://community.dur.ac.uk/~des0www4/cal/roads/earthwk/earthwk.html[2017-09-26 11:02:32 AM]


Earthworks

Shovels - These again are normally wheeled vehicles and are used to fill up the dump trucks. Typically they take
2-3 loads to fill an average dump truck.

Hydraulic Excavators - These can be either wheeled or tracked and are used again to excavate below truck level.
They have a very small capacity and are extremely flexible.

Grader - Used to level out deposited fill, ready for compaction.

Rollers - There are many different types of roller and they are used for compaction. Different types include
vibratory, sheepsfoot and grid. Vibratory are the most common as they have effectively double the effect.

https://community.dur.ac.uk/~des0www4/cal/roads/earthwk/earthwk.html[2017-09-26 11:02:32 AM]


Earthworks

Problems
Question 1

The table below shows ground levels and formation levels for a proposed road construction. Embankments are to be
built with side slopes of 1:2.5 and cuttings with slopes of 1:3.0. The embankment crest width and cutting base width is
13m. It may be assumed that the ground is horizontal across the section.

Formation Formation
Ground Level Ground Level
Chainage Level Chainage Level
(mAD) (mAD)
(mAD) (mAD)
0 28 35 800 4 11
100 29 32 900 3 8
200 32 29 1000 2 5
300 35 26 1100 -5 2
400 30 23 1200 -5 2
500 19 20 1300 10 5
600 11 17 1400 15 8
700 7 14 1500 23 11

a. Construct a Mass haul diagram for the project given the following
Bulking Factor = 1.1
Shrinkage Factor = 0.8
b. A River breaks up the project at chainage 1160m. Calculate the volumes of waste material and borrow for two
scenarios:
i. Material Cannot be moved across the river
ii. A Bailey bridge is constructed allowing material to be transported across the river.

ANSWERS

i. Borrow=68,000 m3 Waste=89,500m3
ii. Borrow=0m3 Waste=21,500m3

https://community.dur.ac.uk/~des0www4/cal/roads/earthwk/earthwk.html[2017-09-26 11:02:32 AM]


Earthworks

Worked Solution

References
1) Department of Transport, Manual of Contract Documents for Highway Works, Volume 1, Specification of Highway Works, Series 600 -
Earthworks. 1993


Return to top of page.

e-mail: D.G.Toll@Durham.ac.uk.

Last Updated:25 February 1997

https://community.dur.ac.uk/~des0www4/cal/roads/earthwk/earthwk.html[2017-09-26 11:02:32 AM]

You might also like