Date :April 29, 2023

Attention :
Thru :
Project : Proposed Sewage Treatment Plant
Location : Quezon Province, Philippines
Owner :
Subject : Proposed Design and Build of Sewage Treatment Plant 100 CmD

A. SCOPE OF WORKS
UNIT RATE
ITEM NO. ITEM DESCRIPTION UNIT QTY TOTAL AMOUNT
MATERIAL LABOR OTHERS TOTAL
I PRELIMINARIES
Mobilization/Demobilization 1.00 ITEM 80,000.00
Temporary Facilities 1.00 ITEM 70,000.00
Supervision 1.00 ITEM 100,000.00
sub-total I 250,000.00
II Civi Works

Supply and Installation (STP Tank 5.00 x 9.00 x 4.00m) 1.00 LOT 1,750,502.00 525,150.60 78,772.59 2,354,425.19 2,354,425.19
Earthworks
• Excavation
• Backfill
• Layout/Site Clearing
Masonry works
• Rebar works
• ChB laying
• Plastering
• Concrete pouring
• Formworks
• Waterproofing
2,354,425.19
SUB-TOTAL PROJECT COST 2,604,425.19

GENERAL REQUIREMENTS / PRELIMENARIES (I) 250,000.00


INDIRECT COST (II-IV) 2,354,425.19
VAT 12% 312,531.02
TOTAL PROJECT COST 2,916,956.21

B. TOTAL AMOUNT OF THIS OFFER: PHP 2,916,956.21


C. AMOUNT IN WORDS: Two million, nine hundred sixteen thousand, nine hundred fifty-six pesos and 21/100 only.
D. TERMS OF PAYMENT: 40% DOWN-PAYMENT , BALANCE SHALL BE PAID IN PROGRESS BILLING BASED ON ACCOMPLISHMENT.
E. WORK COMPLETION: Thirty (30) - Sixty (60) calendar days.
F. VALIDITY OF QUOTATION: THIRTY (30) CALENDAR DAYS FROM THE DATE OF THIS QUOTATION
Note:
1 Client should provide area / facility for materials and equipment storage area.
2 Electricity and water consumption shoulder by the client.
3 The Contractor will provide Municipal Health Certificate only (if needed), For antigen/Swab test
the client will shoulder the payment.
4 Permits / Entry pass fees shoulder by the client (if needed)
5 The client will shoulder the payment of the processing / filing fee of ther discharge permit application.

Prepared by : Conformed by :

John Axl Lajom - 091558310767

STP Civil Works 100CmD Page 1 of 1 5/4/2023