This daily report summary provides updates on construction supervision works for the rehabilitation of the Uaiaca (Quelicai) - Ossu road section from May 2023. Over the reporting period:
1) Excavation works were carried out between Sta. 5+400 to 5+500 and Sta. 7+200. Meetings were held to review monthly reports.
2) Site clearing, grubbing and excavation works continued between Sta. 8+000 to 10+000, with some delays due to heavy rainfall.
3) Other works included a foundation for a quarry being laid with concrete and rebar installed between Sta. 3+500. Site clearing was also undertaken between Sta.
This daily report summary provides updates on construction supervision works for the rehabilitation of the Uaiaca (Quelicai) - Ossu road section from May 2023. Over the reporting period:
1) Excavation works were carried out between Sta. 5+400 to 5+500 and Sta. 7+200. Meetings were held to review monthly reports.
2) Site clearing, grubbing and excavation works continued between Sta. 8+000 to 10+000, with some delays due to heavy rainfall.
3) Other works included a foundation for a quarry being laid with concrete and rebar installed between Sta. 3+500. Site clearing was also undertaken between Sta.
This daily report summary provides updates on construction supervision works for the rehabilitation of the Uaiaca (Quelicai) - Ossu road section from May 2023. Over the reporting period:
1) Excavation works were carried out between Sta. 5+400 to 5+500 and Sta. 7+200. Meetings were held to review monthly reports.
2) Site clearing, grubbing and excavation works continued between Sta. 8+000 to 10+000, with some delays due to heavy rainfall.
3) Other works included a foundation for a quarry being laid with concrete and rebar installed between Sta. 3+500. Site clearing was also undertaken between Sta.
CONSULTING SERVICES FOR CONSTRUCTION SUPERVISION OF REHABILITATION WORKS OF
THE EXISTING UAIACA (QUELICAI) – OSSU ROAD SECTION FROM STA 0+000 TO STA 22+700 ( RFP/068/MOP-2022 )
Daily Report Summary No. 4
MAY 2023 DAT WORK DESCRIPTION REMARKS E 1 No activity. Labour Day 2 Excavation works at Sta. 5+400 – Sta. 5+500 LHS 3 Excavation works at Sta. 5+400 – Sta. 5+500 LHS continue. Mobilised to Sta. 7+200. 4 Meeting at Raikotu on engineer’s facilities together with contractor. Submission Attended by Ms. of monthly report for review by contractor. Submission of monthly reports for Serena from PYKP LDA consultant and contractor to HQ before official submission to DNCVR. headquarters. 5 Weekly Meeting No. 6 at Temporary Site Office at Abafala. Site monitoring by Meeting at 3.00pm. DNCVR team lead by Mr Crispin at noon. 6 Site clearing/grubbing and excavation at Sta. 8+000. 7 No activity. Sunday 8 No activity due to heavy down pour. 9 No activity due to heavy down pour. 10 No activity due to heavy down pour. 11 Site clearing/grubbing and excavation at Sta. 8+100 continue works. 12 Weekly Meeting No.7 at Temporary Site Office at Abafala. 13 Site clearing/grubbing and excavation at Sta. 8+200 continue works. 14 No activity. Sunday 15 Slab concreting for quarry foundation. 16 Installation of rebar for quarry foundation at Sta. 3+500. 17 Site clearing/grubbing at Sta.11+900 to Sta. 12+000. 18 Weekly Meeting No.8 at Temporary Site Office at Abafala. 19 Site clearing/grubbing at Sta.12+000 to Sta. 12+600. Public Holiday 20 No activity. Public Holiday 21 No activity. Election Day 22 No Activity. Public Holiday 23 Site clearing/grubbing and excavation at Sta. 8+600. 24 Site clearing/grubbing and excavation at Sta. 8+900. 25 Site clearing/grubbing and excavation at Sta. 9+100. 26 Weekly Meeting No.9 at Temporary Site Office at Abafala. 27 Site clearing/grubbing and excavation at Sta. 9+250. 28 Site clearing/grubbing and excavation at Sta. 9+350. Sunday 29 Site clearing/grubbing and excavation at Sta. 9+500. 30 Site clearing/grubbing and excavation at Sta. 10+000. 31 Site clearing/grubbing at Sta. 16+700.