Professional Documents
Culture Documents
MEXICO '13 NB3 Q-Support For Tunnels and Caverns 86 Screens
MEXICO '13 NB3 Q-Support For Tunnels and Caverns 86 Screens
NB #3
ORIGINAL DATA BASE
UNSUPPORTED TUNNEL CHARACTERISTICS
NMT CONCEPTS OF TUNNEL SUPPORT
UPDATING Q-SUPPORT WITH S(fr) SHOTCRETE
STRENGTH-DEFORMATION CHARACTER OF S(fr)
STRENGTH-DEFORMATION CHARACTER OF BOLTING
WATER CONTROL WITH FREE-STANDING LINERS
RRS FOR TUNNELLING IN BAD GROUND
‘NOMINALLY UNLINED’ HEADRACE TUNNELS
NMT (SINGLE-SHELL) COST ESTIMATION
1
212 case records, mostly B+S(mr) (from Barton, Lien and Lunde, 1974)
2
SUPPORT PRESSURE GUIDELINES (FROM 1974) - used for checking bolt and
anchor capacity needs 3
APPROXIMATE GUIDE-LINES FOR TEMPORARY SUPPORT
AND FOR (PERMANENT) WALL SUPPORT
4
5
6
UPDATED SUPPORT CHART PRINCIPLES, FOR 1989 TO 1993 INCORPORATION
OF NEW B+ S(fr) CASE RECORDS. Grimstad, 1989
7
8
In 1992 (Barton et al. 1992) coined the phrase NMT –
the Norwegian Method of Tunnelling – to differentiate
it from NATM, which was soon to get so bad publicity
from high-profile collapses around the world
(Heathrow, Munich, São Paulo).
9
10
11
12
Some details concerning NMT. Tunnels are dry, drained, and PC-element
cladded if required for road or rail use . (‘Pigging’ = scaling)
13
Some of the key differences between NMT and (the
sometimes misused term) NATM that were more obvious
10 years ago than today, following technology
improvements. More NATM tunnel operations use S(fr)
today than 10 years ago.
14
After Grimstad and Barton, 1993 (Norway) and Barton and Grimstad, 1994 (Austria).
15
UPDATED ESR RATINGS
(TUNNEL-USE-and-SAFETY rating for adjusting EQUIVALENT SPAN)
(Barton and Grimstad, 1994) 16
Grimstad’s new case records 17
18
19
20
21
22
Cycle-time recordings (drilling the next round, blasting, waiting for gasses
to clear, mucking, logging, bolting-if needed, shotcreting-if needed) as a
function of Q-value. (Grimstad, NGI: pers com.1998).
23
SOME IMPROVED TECHNOLOGY ASPECTS OF NMT
24
B+S (better still B+Sfr) gives by far the best tunnel-stabilizing result
according to 5 years of deformation monitoring at an experimental
tunnel in mudstone.
25
Ward et al. 1983 (left), and Barton 1994. (right).
THE POTENTIAL (ACTUAL)
INEFFECTIVENESS OF
STEEL SETS, UNTIL (IF?)
THEY ARE PUT IN
CONTACT WITH THE
TUNNEL ARCH.
27
28
Typical S(fr) mix design for C45 to C55 (MPa) shotcrete.
Note operator location close to nozzle, where rebounds of 4 to 6%
(and almost dust-free air) make quality control very easy.
29
Large-scale testing of S(fr) by Robocon in the mid-eighties. Fracture
energy (area under load-deformation curves) was 60 to 80 times that of
unreinforced shotcrete, depending on fibre dosage 40 or 60 kg/m3.
30
31
32
SLAB TEST LOAD-DEFORMATION BEHAVIOUR WITH S(fr)
Torsteinsen and Kompen, 1983.
33
Conceptual comparison of S(mr) and S(fr)
35
ONE OF THE FIVE MAIN PROBLEMS, same tunnel.
36
The advantages of S(fr) compared to S(mr). There is today the additional
advantage of alkali-free accelerator, allowing thick layers of S(fr) to be
built up rapidly, without the previous loss of long-term strength when 37
using ‘too much’ accelerator.
LOAD-DERORMATION COMPARISON OF S (mr) and S (fr)
38
POLYPROPOLENE FIBRE….gaining ground!
39
40
Comparison of load (= kraft) versus deformation behaviour for various
Dramix-steel, and Barchip-polypropylene fiber-reinforced shotcretes.
NFF lecture, Grimstad, 2010.
Note energy absorption classes E1000J, E700J (and remainder E500J). In
boxes: dimensions of RRS (rib reinforced shotcrete arches) with thickness
(cm), number of reinforcing bars, and c/c spacing of the ribs.
From Grimstad et al., 2002.
(See Fig. 3.16 for original correct bolt lengths: small errors in present figure).
42
(From Grimstad, 2010. NFF lecture.)
43
EXAMPLES OF POOR PRACTICE USING
THIN MESH, HAND-HELD EQUIPMENT
44
POOR PRACTICE….INCOMPLETE SHOTCRETING
MAKE THE MESH APPEAR STRONG !
(Shadow effect, and later corrosion likely)
45
Wrong distance, poor-practice shotcreting.
A strange choice for an NATM advertisement of….S(mr) ?
AMV (Andersons Mekaniske Verksted – Andersons
Mechanical Workshop) road-licensed, deisel/electric
shotcrete robot: 20-25 m3/hr shotcreting capacity.
Relevant bolting technology (corrosion protected)
• Because NMT uses S(fr)+B as the final support of tunnels and caverns
(Barton et al. 1992, Barton and Grimstad, 1994), it is important that also
the bolts are of good quality, with suitable long-life corrosion
protection.
• The widespread use of NMT principles in Norway for the last 25 years
(35 years if S(mr) is included) has meant excellent development of
corrosion protected bolts in this country.
57
An unstable wedge
in the cavern wall.
in relation to
the critically inclined
discontinuity.
The optimal bolt
installation angle
(and resulting
capacity) will vary
with the shear
displacement that
has already
occurred.
The critical
discontinuity/joint
might be at post-
peak strength.
59
Relevant water control
60
An example of one of the most expensive tunnelling solutions, like
conventional NATM, with B+S(mr) for primary support, and final cast concrete
liner with membrane and drainage fleece, for secondary support. This high-
speed rail tunnel through jointed chalk in Southern England, had final (year
2000) costs of US$ 128M /3.2 km, or $ 40,000 per metre. This was three to
four times higher than a typical NMT tunnel, with similar Q-value rock, using
B+S(fr) as permanent rock support, and a PC-element+membrane liner, for a
61
drained-but-dry solution.
NMT concepts in diagram form
Note: stage No. 6 must precede stage No.
2 if stability /stand-up time is very poor.
64
9 tons
ARCH
elements
being lifted
up ready for
fixing
(bolting) in
220 km/hr
double-track
rail tunnel.
NMT (B+Sfr)
then PC-
element liner
with outer
membrane
PC-elements stacked at rail tunnel portal ready for mounting with outer
membrane sheet – at rates of 900m/month (after learning curve)
66
THE PRE-INJECTION OPTION
FOR WHEN INFLOW AND
GROUNDWATER DRAWDOWN
ARE UNACCEPTABLE
67
RRS (rib-reinforced shotcrete arches)
68
RRS philosophy
• When Q-values are below approx. 0.1 (i.e. extremely poor),
it can be expected that there will be the possibility of large
over-break, low stand-up time, and significant early
deformations.
3D
effect
becaus
e of
S(fr)
arches.
72
AN IMPORTANT CONTRIBUTION
OF THE Q-SYSTEM:
‘NOMINALLY UNLINED’
HEADRACE TUNNELS FOR
HYDROPOWER
(economic, rapidly constructed)
73
Hydropower tunnels in
Norway. 3,500 km total
length.
‘Rocks in the
turbines’? Never?
Why? Parabolic flow
velocity.
Thidemann and Bruland, 1992, Broch 2011.
Two options: concrete
lined, or larger DRILL-
AND-BLASTED section
with S(fr) + B where
needed.
USE FRACTURE-FLOW ANALOGY TO FLOW
ALONG
ROUGH-WALLED HYDROPOWER TUNNEL
‘BED-LOAD’
TRANSPORT
NOT EASY
WITH ZERO
VELOCITY.
With occasional HEADRACE TUNNEL collapse/blockage/break-
through trauma, large blocks can be transported, due to ultra-
high velocities. (Sources: NB and confidential)
Debris reach 400m from collapse * Coarse material upstream * Stones collected from 4km
CONTENTS OF A ‘ROCK-
TRAP’. THE STONES ARE
PUMICE THAT CAME
FLOATING.
NO SIGNIFICANT SIZE OF BED
TRANSPORT….DUE TO
VELOCITY non-ISOTROPY
(9 km TBM + 1 km D+B)
HJULSTRÖM DIAGRAM
from 1937 Ph.D. river studies.
REALITY IN A
‘NOMINALLY UNLINED’
HEADRACE’ TUNNEL:
1.5, 2.5 AND EVEN 3.5
m/s WATER FLOW
VELOCITIES DO NOT
MOVE PARTICLES EVEN
AS BIG AS
10X10X10 mm.
FINALLY:
COST ESTIMATION
IN
RELATION TO
THE
Q-VALUE
82
Historic cost
differences:
concrete
lined/ ‘nominally
unlined’