Commissioning Check Sheet For Fan Coil Unit
Commissioning Check Sheet For Fan Coil Unit
SITE NO.:
SUBCONTRACTOR:
Checked
ITEM POINTS TO BE CHECKED by REMARKS
1 Areas being fed by FCU are clean.
2 Filter is clean.
3 Condensate drain tray is clean and connected to
waste line.
4 Three speed switch and DP switch are connected.
5 Thermostat is installed.
6 Fan impeller rotates freely.
7 DRV and GV are adjusted for design flow rate.
8 Check fan bearings.
9 Check flow of condensate drain and P-trap.
THE ABOVE POINTS HAVE BEEN CHECKED AND FOUND TO COMPLY WITH
CONTRACT SPECIFICATIONS.