PROJECT: PROJECT NAME

SITE NO.:

COMMISSIONING CHECK SHEET FOR FAN COIL UNIT Sheet No.

SUBCONTRACTOR:

EQUIPMENT NO. : SEQUENCE NO. :


SERIAL NO. : DATE :
LOCATION : COMMISSIONED ON :

Checked
ITEM POINTS TO BE CHECKED by REMARKS
1 Areas being fed by FCU are clean.
2 Filter is clean.
3 Condensate drain tray is clean and connected to
waste line.
4 Three speed switch and DP switch are connected.
5 Thermostat is installed.
6 Fan impeller rotates freely.
7 DRV and GV are adjusted for design flow rate.
8 Check fan bearings.
9 Check flow of condensate drain and P-trap.

THE ABOVE POINTS HAVE BEEN CHECKED AND FOUND TO COMPLY WITH
CONTRACT SPECIFICATIONS.

CHECKED BY SUBCONTRACTOR: _____________________


Signature

WITNESSED BY CLIENT: ______________________


Signature

WITNESSED / ACCEPTED BY CONSULTANT: ____________________


Signature