Watermeter For Standpipe-Hydrants - Rev.

You might also like

Download as xls, pdf, or txt
Download as xls, pdf, or txt
You are on page 1of 72

Republic of the Philippines

ZAMBOANGA CITY WATER DISTRICT


Pilar Street, Zamboanga City

PROPOSED INSTALLATION OF FLOWMETER AT FIRE HYDRANT/STANDPIPE

Zamboanga City

BREAKDOWN OF EXPENDITURES % OF TOTAL AMOUNT


I - ESTIMATED COST
A. DIRECT COST:
1. Mobilization/Demobilization . . . . . . . . . . . . . . . . . . . . . #REF! #REF!
2. Materials . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . #REF! #REF!
3. Labor (including fringe benefits) . . . . . . . . . . . . . . . . . . #REF! #REF!
4. Equipment Expenses . . . . . . . . . . . . . . . . . . . . . . . . . #REF! #REF!

B. INDIRECT COST:
1. Overhead contingency Miscellaneous . . . . . . . . . . . . . . #REF! #REF!
2. Profit . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . #REF! -
3. Comprehensive All Risk Insurance . . . . . . . . . . . . . . . .
4. Value Added Tax (5% of EDC, OCM and Profit) . . . . . #REF! -
5. Materials Testing 7% of 1% of OCM . . . . . . . . . . . . . .

C. ENVIRONMENTAL COMPLIANCE AND PERMITS


Concrete Cutting and Excavation Permit #REF!
S U B - T O T A L (CONTRACT COST) #REF! #REF!

II - ESTIMATED GOVERNMENT EXPENDITURES


1. Engineering & Administrative Overhead
2. POW/Site Acquisition/Pre-Engineering
3. Materials to be furnished by the government
4. Materials Quality Control & Hydrology (MQCH)
5. Retention for RO & C.O.

SUB-TOTAL 0.00 0.00

III - CONTINGENCIES/RESERVED:
1. Physical (up to 5% of the Estimated Contract Cost) . . . . . . #REF! #REF!
2. Price Escalation (up to 12% of the Estimated #REF!
Contract Cost) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
3. Preliminary Engineering . . . . . . . . . . . . . . . . . . . . . . . . . .

SUB-TOTAL #REF! #REF!


TOTAL ESTIMATED PROJECT COST #REF! #REF!

PREPARED BY: CHECKED & REVIEWED BY:

FELIXBERTO R. CAARE, JR. RMP MARK BENEDICT C. REYES


Engineering Assistant B (J.O.) Officer-In-Charge
NRWMD - PAMD NRWMD - PAMD

SUBMITTED BY: RECOMMENDING PROJECT IMPLEMENTATION:

VALERIE GAY Y. GUITIERREZ ALEJO S. ROJAS, JR.


Dept. Manager A - PAMD AGM - Operations Group

APPROVED FOR PROJECT IMPLEMENTATION:

LEONARDO REY D. VASQUEZ


General Manager
Republic of the Philippines
ZAMBOANGA CITY WATER DISTRICT
Pilar Street, Zamboanga City

INDIVIDUAL PROGRAM OF WORK


14-Dec-20
(Date)
PROJECT TITLE: APPROPRIATE: Php #REF!
SOURCE OF FUNDS:
PROPOSED INSTALLATION OF FLOWMETER AT FIRE ISSUED OBLIGATED:
HYDRANT/STANDPIPE AUTHORITY RELEASED:
LOCATIONS:
CALENDAR DAYS TO COMPLETE: FIFTY-FOUR (54) WORKING DAYS
Zamboanga City

PROJECT CATEGORY: DESIRABLE STARTING DATE: UPON APPROVAL

REHABILITATION OF WATER SERVICE CONNECTIONS


CONTRACT / / ADMINISTRATION / X /

PROJECT DESCRIPTION:
LENGTH:

MININUM EQUIPMENT REQUIRED TECHNICAL PERSONNEL REQUIRED


Description No. Description No. Description No. Description No.
Dump Truck (10 cu.m.) 1 Boom Truck 1 #REF! 1
Water Pump 1 1-Bagger Concrete Mixer 1
Hydro Machine 1 Concrete Cutter 1
Air Compressor w/ Jackhammer 1 ### 6
Service Vehicle 1 ### 2
Tamper Rammer Machine 1
Plate Compactor 1
Concrete Vibrator 1
ESTIMATED COST OF PROPOSED PROJECTS
ITEM % OF DIRECT COST ADJUSTED
DESCRIPTION UNIT QTY.
NO. TOTAL TOTAL UNIT COST UNIT COST
SPL-1 MOBILIZATION/DEMOBILIZATION #REF! LOT 1.00 #REF! #REF! #REF!
SPL-2 HAULING OF MATERIALS #REF! LOT 1.00 85,430.00 85,430.00 93,973.00
SPL-1 INSTALLATION OF 75mmØ MECHANICAL TYPE METER FOR #REF! Unit 1.00 64,717.00 64,717.00 71,188.70
FIRE HYDRANTS / STANDPIPES
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Total Percent #REF! Total Direct Cost #REF!

PREPARED BY: CHECKED & REVIEWED BY: SUBMITTED BY:

FELIXBERTO R. CAARE, JR. RMP MARK BENEDICT C. REYES VALERIE GAY Y. GUITIERREZ
Engineering Assistant B (J.O.) Officer-In-Charge Dept. Manager A - PAMD
NRWMD - PAMD NRWMD - PAMD

RECOMMENDING PROJECT IMPLEMENTATION: APPROVED FOR PROJECT IMPLEMENTATION:

ALEJO S. ROJAS, JR. LEONARDO REY D. VASQUEZ


AGM - Operations Group General Manager
Republic of the Philippines
ZAMBOANGA CITY WATER DISTRICT
Pilar St., Zamboanga City

PERT/CPM

ESTIMATED
ACTIVITY ACTIVITY DESCRIPTION PREDECESSOR
DURATION
A #REF! 3
B MOBILIZATION 2 A
C #REF! 3 B
D HAULING OF MATERIALS 3 B
E #REF! 2 C, D
F #REF! 1 E
G #REF! 31 C, D
H #REF! 23 G
I #REF! 1 F, H
J #REF! 1 I
K #REF! 7 I
L #REF! 0.5 K, J
M #REF! 0.5 L
N #REF! 1 J, M
O DEMOBILIZATION 2 N

CRITICAL PATH
74 = A-B-D-G-H-I-K-L-M-N-O
68 = A-B-C-G-H-I-J-L-M-N-O
16 = A-B-C-E-F-I-J-N-O
3 2 1 1

C E F J
0 3 2 1 1 2 0

START A B I N O FINISH

0 3 5 3 31 23 7 0.5 0.5 72 74 0
63
D G H K L M
8 39 62 70 70.5 71

PREPARED BY: CHECKED & SUBMITTED BY: RECOMMENDING PROJECT IMPLEMENTATION: APPROVED FOR PROJECT IMPLEMENTATION:

FELIXBERTO R. CAARE, JR. RMP MARK BENEDICT C. REYES ALEJO S. ROJAS, JR. LEONARDO REY D. VASQUEZ
Engineering Assistant B (J.O.) Officer-In-Charge AGM-OPERATIONS GROUP General Manager
NRWM DIVISION - PAMD NRWM DIVISION - PAMD
Republic of the Philippines
ZAMBOANGA CITY WATER DISTRICT
Pilar St., Zamboanga City

GANTT CHART
Project : PROPOSED INSTALLATION OF FLOWMETER AT FIRE HYDRANT/STANDPIPE
Location : Zamboanga City
Total Estimated Project Cost : #REF!
Project Duration : FIFTY-FOUR (54) WORKING DAYS

FIFTY-FOUR (54) WORKING DAYS (Sundays not included)


Particulars Amounts % Perfected
14 28 42 54

SPL-1 MOBILIZATION/DEMOBILIZATION #REF! #REF! ###### ###

SPL-2 HAULING OF MATERIALS Php 93,973.00 #REF! ##########################################################################################################################################

SPL-1 INSTALLATION OF 75mmØ MECHANICAL TYPE METER FOR FIRE HYDRANTSPhp 71,188.70 #REF! ###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
#REF! #REF! #REF! #REF!
#REF! ### #REF! #REF! ###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
#REF! #REF! #REF! #REF! ###
###
###
###
###
###
###
###
###
TOTAL CONTRACT COST #REF! #REF!
CASH OUTLAY REQUIREMENT #REF! Php40,465.26 #REF! #REF!
TARGETED COMPLETION THIS PERIOD #REF! #REF! #REF! #REF!
COMMULATIVE COMPLETION TO DATE #REF! #REF! #REF! #REF!

PREPARED BY: CHECKED & REVIEWED BY: SUBMITTED BY: RECOMMENDING PROJECT IMPLEMENTATION:

FELIXBERTO R. CAARE, JR. RMP MARK BENEDICT C. REYES VALERIE GAY Y. GUITIERREZ ALEJO S. ROJAS, JR.
Engineering Assistant B (J.O.) Officer-In-Charge Dept. Manager A - PAMD AGM - Operations Group
NRWMD - PAMD NRWMD - PAMD

APPROVED FOR PROJECT IMPLEMENTATION:

LEONARDO REY D. VASQUEZ


General Manager
Republic of the Philippines
ZAMBOANGA CITY WATER DISTRICT
Pilar Street, Zamboanga City

Standard Form Number: SF-INFR-01 Contract Reference Number


Revised on: July 28, 2004 Name of the Contract
Location of the Contract
APPROVED BUDGET FOR THE CONTRACT

PROPOSED INSTALLATION OF FLOWMETER AT FIRE HYDRANT/STANDPIPE


Zamboanga City

Length: 0
Contract Duration: 360 Calendar Days
MARK-UPS
TOTAL MARK-UP
ITEM ESTIMATED IN PERCENT TOTAL UNIT
DESCRIPTION QUANTITY UNIT VAT TOTAL COST
NO. DIRECT COST INDIRECT COST COST
OCM PROFIT % VALUE
(9) (10) (11) (12) (13)
(1) (2) (3) (4) (5) (6) (7) (8)
(5)X(8) 5%((5)+(9)) (9)+(10) (5)+(11) (12)/(3)
SPL-1 MOBILIZATION/DEMOBILIZATION 1.00 LOT #REF! 0% 0% 0% #REF! #REF! #REF! #REF! #REF!
SPL-2 HAULING OF MATERIALS 1.00 LOT 85,430.00 10% 0% 10% 8,543.00 0.00 8,543.00 93,973.00 93,973.00
SPL-1 INSTALLATION OF 75mmØ MECHANICAL TYPE 1.00 Unit 64,717.00 10% 0% 10% 6,471.70 0.00 6,471.70 71,188.70 71,188.70
METER FOR FIRE HYDRANTS / STANDPIPES
#REF! #REF! #REF! #REF! #REF! 10% 0% 10% #REF! #REF! #REF! #REF! #REF!
TOTAL #REF! #REF!

PREPARED BY: CHECKED & REVIEWED BY: SUBMITTED BY:

FELIXBERTO R. CAARE, JR. RMP MARK BENEDICT C. REYES VALERIE GAY Y. GUITIERREZ
Engineering Assistant B (J.O.) Officer-In-Charge Dept. Manager A - PAMD
NRWMD - PAMD NRWMD - PAMD

RECOMMENDING PROJECT IMPLEMENTATION: APPROVED FOR PROJECT IMPLEMENTATION:

ALEJO S. ROJAS, JR. LEONARDO REY D. VASQUEZ


AGM - Operations Group General Manager
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME: PROPOSED INSTALLATION OF FLOWMETER AT FIRE HYDRANT/STANDPIPE


#REF! Zamboanga City

Item No./Description: SPL-1 MOBILIZATION/DEMOBILIZATION


Unit of Measurement: LOT
Output per day: N/A
Quantity: 1.00 LOT

Designation No. Person No. of Days Daily Rate Amount

A. Labor
N/A

Sub-Total for A P -

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment
N/A

Sub-Total for B P
C. Total (A+B) -
D. Output per day = N/A

Name and Specifications Quantity Unit Unit Cost Amount

E. Mobilization/Demobilization

Note: Per D.O. 22 series 2015, Mobilization/Demobilization


should not exceed 1% of estimated Direct Cost
Estimated Direct Cost #REF!
Mob./Demo (1.0% of E.D.C.) #REF!

Sub-Total for E P #REF!


F. Direct Cost (C+E) #REF!
G. Overhead, Contingencies & Miscellaneous 0% per D.O. 22 s 2015 #REF!
H. Contractor's Profit (CP) 0% per D.O. 22 s 2015 #REF!
I. Value Added Tax (VAT) 0% per D.O. 22 s 2015 #REF!
J. Total Cost #REF!
k. Total Unit Cost #REF!
Republic of the Philippines
ZAMBOANGA CITY WATER DISTRICT
Pilar Street, Zamboanga City

BILL OF QUANTITIES
Project Title: PROPOSED INSTALLATION OF FLOWMETER AT FIRE HYDRANT/STANDPIPE
Approved Budget Cost: #REF!
Project Duration: TWO HUNDRED NINETY EIGHT (298) CALENDAR DAYS
P.R. No.

WORK ITEM/DESCRIPTION UNIT UNIT PRICE


ESTIMATED (Taxes Total Prize (Including
QUANTITY Included) Taxes)
#REF! 1.00 LOT
SPL-1 MOBILIZATION/DEMOBILIZATION 1.00 LOT
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF!
#REF! #REF!

#REF! #REF!
#REF! #REF!

#REF! #REF! #REF! #REF!


#REF! #REF! #REF! #REF!
#REF! #REF!
#REF! #REF!

#REF! #REF!
#REF! #REF!

#REF! #REF!
#REF! #REF!

#REF! #REF! #REF! #REF!

#REF! #REF! #REF!


#REF!
#REF!
#REF! #REF!
#REF!
EQUIPMENT REQUIREMENTS

PARTICULARS QTY UNIT AVAILABLE H.P./PLATE NO.


#REF! #REF! UNITS
Dump Truck (10 cu.m.) 1.00 UNITS
Water Pump 1.00 UNITS
Hydro Machine 1.00 UNITS
Air Compressor w/ Jackhammer 1.00 UNITS
Service Vehicle 1.00 UNITS
Plate Compactor 1.00 UNITS
Concrete Vibrator 1.00 UNITS
#REF! #REF! UNITS
#REF! #REF! UNITS
#REF! #REF! UNITS
#REF! #REF! UNITS
#REF! #REF! UNITS
#REF! #REF! UNITS
Boom Truck 1.00 UNITS
1-Bagger Concrete Mixer 1.00 UNITS
Concrete Cutter
1.00 UNITS

Php - 0.00 UNITS


Php - 0.00 UNITS
Php - 0.00 UNITS

PREPARED BY: CHECKED AND SUBMITTED BY:

REX D. SALE JR. EDITO M. BAUTISTA JR.


Senior Eng'r A (J.O.), CE Officer-In-Charge
DESIGN DIVISION DESIGN DIVISION

APPROVED BY: RECOMMENDING PROJECT IMPLEMENTATION:

MARLI ACOSTA - DE FIESTA ARNULFO A. ALFONSO


Officer-In-Charge AGM-Technical Services Group
ENGINEERING & CONSTRUCTION DEPARTMENT

APPROVED FOR PROJECT IMPLEMENTATION:

LEONARDO REY D. VASQUEZ


General Manager
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME: #REF!

#REF! ###
Item No./Description: SPL-4 FINAL STAKING/LAY-OUTING/LINE AND GRADE
Unit of Measurement: LN.M.
Output per day: 363.10 LN.M./DAY
Quantity: 726.20 LN.M.

Designation No. Person No. of Days Daily Rate Amount

A. Labor
a. Construction Foreman 1 2 524.00 1,048.00
b. Laborers 1 2 317.00 634.00
c. Skilled Worker 1 2 366.00 732.00

Sub-Total for A P 2,414.00

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment
N/A

Sub-Total for B P
C. Total (A+B) 2,414.00
D. Output per day = 363.10 LN.M./DAY

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials
N/A

Sub-Total for E P
F. Direct Cost (C+E) 2,414.00
G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011 144.84
H. Contractor's Profit (CP) 8% per D.O. 29 s 2011 193.12
I. Value Added Tax (VAT) 12% per D.O. 29 s 2011 330.24
J. Total Cost 3,082.20
k. Total Unit Cost 4.24
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME: ###


#REF! ###
Item No./Description: HAULING OF MATERIALS (Sand)
Unit of Measurement: CU.M.
Output per day: 24.00 CU.M./DAY
Quantity: #REF! CU.M.

Designation No. Person No. of Days Daily Rate Amount

A. Labor
a. Laborers 8 #REF! 317.00 #REF!

Sub-Total for A P #REF!

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment
a. Dump Truck (3 cu.m.) 2 #REF! 10,816.00 #REF!
Minor Tools (10%) #REF!

Sub-Total for B P #REF!


C. Total (A+B) #REF!
D. Output per day = 24.00 CU.M./DAY

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials
N/A

Sub-Total for E P
F. Direct Cost (C+E) #REF!
G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011 #REF!
H. Contractor's Profit (CP) 0% per D.O. 29 s 2011 #REF!
I. Value Added Tax (VAT) 0% per D.O. 29 s 2011 #REF!
J. Total Cost #REF!
k. Total Unit Cost #REF!
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME: ###


#REF! ###
Item No./Description: HAULING OF MATERIALS (Item 200)
Unit of Measurement: CU.M.
Output per day: 24.00 CU.M./DAY
Quantity: #REF! CU.M.

Designation No. Person No. of Days Daily Rate Amount

A. Labor
a. Laborers 8 #REF! 317.00 #REF!

Sub-Total for A P #REF!

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment
a. Dump Truck (3 cu.m.) 2 #REF! 10,816.00 #REF!
Minor Tools (10%) #REF!

Sub-Total for B P #REF!


C. Total (A+B) #REF!
D. Output per day = 24.00 CU.M./DAY

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials
N/A

Sub-Total for E P
F. Direct Cost (C+E) #REF!
G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011 #REF!
H. Contractor's Profit (CP) 0% per D.O. 29 s 2011 #REF!
I. Value Added Tax (VAT) 0% per D.O. 29 s 2011 #REF!
J. Total Cost #REF!
k. Total Unit Cost #REF!
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME: ###


#REF! ###
Item No./Description: HAULING OF MATERIALS (Item 201)
Unit of Measurement: CU.M.
Output per day: 24.00 CU.M./DAY
Quantity: #REF! CU.M.

Designation No. Person No. of Days Daily Rate Amount

A. Labor
a. Laborers 8 #REF! 317.00 #REF!

Sub-Total for A P #REF!

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment
a. Dump Truck (3 cu.m.) 2 #REF! 10,816.00 #REF!
Minor Tools (10%) #REF!

Sub-Total for B P #REF!


C. Total (A+B) #REF!
D. Output per day = 24.00 CU.M./DAY

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials
N/A

Sub-Total for E P
F. Direct Cost (C+E) #REF!
G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011 #REF!
H. Contractor's Profit (CP) 0% per D.O. 29 s 2011 #REF!
I. Value Added Tax (VAT) 0% per D.O. 29 s 2011 #REF!
J. Total Cost #REF!
k. Total Unit Cost #REF!
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME: ###


#REF! ###
Item No./Description: HAULING OF MATERIALS (PVC Pipes, Valves, Fittings and Accessories)
Unit of Measurement: LOT
Output per day: N/A
Quantity: 1.00 LOT

Designation No. Person No. of Days Daily Rate Amount

A. Labor
a. Laborers 8 2 317.00 5,072.00

Sub-Total for A P 5,072.00

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment
a. Boom Truck 1 2 7,698.00 15,396.00
Minor Tools (10%) 507.00

Sub-Total for B P 15,903.00


C. Total (A+B) 20,975.00
D. Output per day = N/A

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials
N/A

Sub-Total for E P
F. Direct Cost (C+E) 20,975.00
G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011 1,258.50
H. Contractor's Profit (CP) 0% per D.O. 29 s 2011 -
I. Value Added Tax (VAT) 0% per D.O. 29 s 2011 -
J. Total Cost 22,233.50
k. Total Unit Cost 22,233.50
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME: ###


#REF! ###
Item No./Description: HAULING OF MATERIALS (Cement, Sand and Gravel for Restoration)
Unit of Measurement: LOT
Output per day: N/A
Quantity: 1.00 LOT

Designation No. Person No. of Days Daily Rate Amount

A. Labor
a. Laborers 8 12 317.00 30,432.00

Sub-Total for A P 30,432.00

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment
a. Dump Truck (3 cu.m.) 2 12 10,816.00 259,584.00
Minor Tools (10%) 3,043.00

Sub-Total for B P 262,627.00


C. Total (A+B) 293,059.00
D. Output per day = N/A

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials
N/A

Sub-Total for E P
F. Direct Cost (C+E) 293,059.00
G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011 17,583.54
H. Contractor's Profit (CP) 0% per D.O. 29 s 2011 -
I. Value Added Tax (VAT) 0% per D.O. 29 s 2011 -
J. Total Cost 310,642.54
k. Total Unit Cost 310,642.54
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME: #REF!

#REF! ###
Item No./Description: SPL-5 POTHOLING
Unit of Measurement: CU.M.
Output per day: 5.40 CU.M./DAY
Quantity: 3.21 CU.M.

Designation No. Person No. of Days Daily Rate Amount

A. Labor
a. Construction Foreman 1 0.59 524.00 311.49
b. Laborers 6 0.59 317.00 1,130.63
c. Skilled Worker 1 0.59 366.00 217.57

Sub-Total for A P 1,659.69

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment
N/A

Sub-Total for B P
C. Total (A+B) 1,659.69
D. Output per day = 5.40 CU.M./DAY

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials
N/A

Sub-Total for E P
F. Direct Cost (C+E) 1,659.69
G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011 99.58
H. Contractor's Profit (CP) 8% per D.O. 29 s 2011 132.78
I. Value Added Tax (VAT) 12% per D.O. 29 s 2011 227.05
J. Total Cost 2,119.09
k. Total Unit Cost 660.15
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME: #REF!

#REF! #REF!

Item No./Description: SPL-4 ASPHALT CUTTING


Unit of Measurement: LN.M.
Output per day: 75.00 LN.M./day
Quantity: 0.00 LN.M.

Designation No. Person No. of Days Daily Rate Amount

A. Labor
a. Construction Foreman 1 0.00 524.00 -
b. Light Equipment Operator 2 0.00 394.00 -

Sub-Total for A P -

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment
a. Concrete Cutter 1 0.00 1,758.00 -
Minor Tools (10%) -

Sub-Total for B P -
C. Total (A+B) -
D. Output per hour = LN.M./day

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials
N.A.

Sub-Total for E P
F. Direct Cost (C+E) -
G. Overhead, Contingencies & Miscellaneous 9% per D.O. 22 s 2015 -
H. Contractor's Profit (CP) 8% per D.O. 22 s 2015 -
I. Value Added Tax (VAT) 5% per D.O. 22 s 2015 -
J. Total Cost -
k. Total Unit Cost #DIV/0!
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME: #REF!

#REF! #REF!

Item No./Description: 101(4)b REMOVAL OF EXISTING ASPHALT PAVEMENT


Unit of Measurement: SQ.M.
Output per day: 480.00 SQ.M./DAY
Quantity: 0.00 SQ.M.

Designation No. Person No. of Days Daily Rate Amount

A. Labor
a. Construction Foreman 1 0.00 524.00 -
b. Laborers 2 0.00 317.00 -

Sub-Total for A P -

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment
a. Backhoe w/ Pavement Breaker (0.80 cu.m.) 1 0.00 12,296.00 -
b. Payloader (1.50 cu.m.), LX80-2C 1 0.00 13,864.00 -
c. Dump Truck (10 cu.m.) 1 0.00 9,016.00 -
Minor Tools (10%) -

Sub-Total for B P -
C. Total (A+B) -
D. Output per hour = 480.00 SQ.M./DAY

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials
N.A.

Sub-Total for E P
F. Direct Cost (C+E) -
G. Overhead, Contingencies & Miscellaneous 9% per D.O. 22 s 2015 -
H. Contractor's Profit (CP) 8% per D.O. 22 s 2015 -
I. Value Added Tax (VAT) 5% per D.O. 22 s 2015 -
J. Total Cost -
k. Total Unit Cost #DIV/0!
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME: #REF!

#REF! #REF!

Item No./Description: SPL-6 PIPELINE EXCAVATION (MANUAL EXCAVATION)


Unit of Measurement: CU.M.
Output per day: 28.50 CU.M./DAY
Quantity: 6,285.72 CU.M.

Note: PIPELINE EXCAVATION IS BY MANUAL EXCAVATION TO AVOID THE USAGE OF HEAVY EQUIPMENT AND THE FORMATION OF SLOW
MOVING TRAFFIC IN THE PROJECT SITE.

Designation No. Person No. of Days Daily Rate Amount

A. Labor
a. Construction Foreman 1 221 524.00 115,569.07
b. Laborers 30 221 317.00 2,097,446.36

Sub-Total for A P 2,213,015.43

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment
N.A.

Sub-Total for B P -
C. Total (A+B) 2,213,015.43
D. Output per day = 28.50 CU.M./DAY

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials

Sub-Total for E P
F. Direct Cost (C+E) 2,213,015.43
G. Overhead, Contingencies & Miscellaneous 9% per D.O. 22 s 2015 199,171.39
H. Contractor's Profit (CP) 8% per D.O. 22 s 2015 177,041.23
I. Value Added Tax (VAT) 5% per D.O. 22 s 2015 129,461.40
J. Total Cost 2,718,689.46
k. Total Unit Cost 432.52
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME: #REF!

#REF! ###
Item No./Description: SPL-9 LAYING OF 363.10 LN.M. OF 100mm.Ø PVC PIPELINE w/ PARTIAL BACKFILLING
Unit of Measurement: PCS
Output per day: 4 PCS./DAY
Quantity: 122.03 PCS.

Designation No. Person No. of Days Daily Rate Amount

A. Labor
a. Construction Foreman 1 28 524.00 14,426.10
b. Laborers 15 28 317.00 130,908.57
c. Pipefitter 1 28 341.00 9,387.98

Sub-Total for A P 154,722.65

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment
N.A.

Sub-Total for B P -
C. Total (A+B) 154,722.65
D. Output per day = 4.43 PCS./DAY

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials
a. Polyethelyne Warning Tape, "Attention Water Main", 3"W x 1000ft/roll 2.38 rolls 1,400 3,334.71
b. 150mmØ x 6.00m D.I. Push-on Pipe in Accordance with ISO 2531, Class K9 122.03 pcs. 9,988.85 1,218,972.66
c. 150mmØ x 45° D.I. Bend, Push-On in Accordance with ISO 2531, Class K12 2 pcs. 1756.32 3,512.65
d. Plain Margarine 3.39 kgs. 70 237.29
e. 150mmØ D.I. Sleeve Type Flexible Coupling, (D.I.) 2.18 pcs. 2,730.00 5,947.58

Sub-Total for E P 1,232,004.89


F. Direct Cost (C+E) 1,386,727.53
G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011 83,203.65
H. Contractor's Profit (CP) 8% per D.O. 29 s 2011 110,938.20
I. Value Added Tax (VAT) 12% per D.O. 29 s 2011 189,704.33
J. Total Cost 1,770,573.71
k. Total Unit Cost 14,508.94
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME: #REF!

PROJECT LOCATION: #REF!

Item No./Description: SPL-8 BRIDGE CROSSING (200mmØ D.I. PIPELINE)


Unit of Measurement: LN.M.
Output per day: 3.00 LN.M./DAY
Quantity: #REF! LN.M.

Length of Bridge
Location
(Ln.m.)
Aplaya Compound 0.00
### #REF!
### #REF!
### #REF!
### #REF!
Total Length #REF!

Designation No. Person No. of Days Daily Rate Amount

A. Labor
a. Construction Foreman 1 #REF! 524.00 #REF!
b. Pipefitter 1 #REF! 341.00 #REF!
c. Skilled Worker 3 #REF! 366.00 #REF!
d. Laborers 6 #REF! 317.00 #REF!

Sub-Total for A P #REF!

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment
a. Generator Set/ Welding Machine w/ complete accessories (w/ fuel) 1 #REF! 2,160.00 #REF!
b. ICS Ductile Iron Pipe-Cutting Gas Chain Saw 1 #REF! 1,600.00 #REF!

Sub-Total for B P #REF!


C. Total (A+B) #REF!
D. Output per day = 3.00 LN.M./DAY

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials
#REF!
a. 200mmØ x 6.00m D.I. Pipe, F/F 2.00 pcs. 13,633.93 27,267.86
b. 6mm Thk x 50mm x 6.0m MS Flat Bar 0.95 pc. 865.20 821.94
c. 12mmØ x 25mmØ MS Bolt with Nut and Washer 12.00 pcs. 36.75 441.00
d. 20mmØ x 70mm Hex Head Stainless Bolt w/ Nut & Washer 96.00 pcs. 62.76 6,024.96
e. 12mmØ x 6.0m MS Plain Round Bar 0.69 pc. 260.00 179.70
f. 200mmØ x 45° D.I. Bend, F/F 4.00 pcs. 4,729.83 18,919.32
g. 200mmØ D.I. Adapter, F/P 2.00 pcs. 5,287.91 10,575.82
h. 200mmØ D.I. Sleeve Type Flexible Coupling, (D.I.) 5.00 pcs. 4,308.00 21,540.00
i. Red Oxide Metal Primer 0.16 gal. 427.00 68.63
j. Quick Dry Enamel (Blue) 0.16 gal. 655.20 105.30

Page 21 of 72
k. Paint Thinner 0.16 gal. 332.00 53.36
l. 3" Paint Brush 2.00 pcs. 65.00 130.00
m. 4" Paint Brush 2.00 pcs. 95.00 190.00
n. 6mm thk Rubber Gasket 8.00 kgs. 140.00 1,120.00

Concrete Thrust Block


a. Portland Cement 1.56 bags 265.00 413.40
b. Washed Sand 0.06 cu.m. 1,000.00 62.40
c. Gravel (G1) 0.12 cu.m. 1,000.00 124.80

Sub-Total for E P 88,038.49


F. Direct Cost (C+E) #REF!
G. Overhead, Contingencies & Miscellaneous 9% per D.O. 22 s 2015 #REF!
H. Contractor's Profit (CP) 8% per D.O. 22 s 2015 #REF!
I. Value Added Tax (VAT) 5% per D.O. 22 s 2015 #REF!
J. Total Cost #REF!
k. Total Unit Cost #REF!

Page 22 of 72
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME: #REF!

#REF! #REF!

Item No./Description: SPL-9a DRAINAGE CROSSING WITH CONCRETE ENCASEMENT (150mmØ D.I. PIPELINE)
Unit of Measurement: LN.M.
Output per day: #REF! LN.M./DAY
Quantity: #REF! LN.M.

Length of Drainage Crossing Pipe Size


Location
(Ln.m.) (mm)
Aplaya Compound 0.00 150
#REF! 21.10 150
#REF! #REF! 150
#REF! #REF! 150
Total Length #REF!

Designation No. Person No. of Days Daily Rate Amount

A. Labor
a. Construction Foreman 1 #REF! 524.00 #REF!
b. Pipefitter 1 #REF! 394.00 #REF!
c. Skilled Worker 6 #REF! 366.00 #REF!
d. Laborer 12 #REF! 317.00 #REF!

Sub-Total for A P #REF!

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment
a. One Bagger Mixer 1 0.42 1,376.00 577.92
b. Concrete Vibrator 1 0.42 1,191.04 500.24
c. Water Truck (1000 gal.) 1 0.04 8,520.00 357.84
d Bar Cutter 1 0.21 1,758.00 369.18
e. Bar Bender 1 0.21 2,812.00 590.52
f. Cargo Truck (10T, 270 Hp) 1 0.06 8,816.00 555.41

Sub-Total for B P 2,951.10


C. Total (A+B) #REF!
D. Output per day = #REF! LN.M./DAY

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials
#REF!
a. 150mmØ x 11.25° D.I. Bend, Push-on Double Socket w/ Rubber Gasket 32.00 pcs. 933.06 29,857.92

b. 150mm Ø D.I. Sleeve Type Flexible Coupling, (D.I.) 16.00 pcs. 2,730.00 43,680.00
c. Lumber, Good - 4 uses 326.20 bd.ft 20.00 6,524.00
d. Plywood (1/2" x 4' x 8") - 4 uses 7.46 pcs. 950.00 7,083.20
e. Assorted CWN (1kg./100 bdft. Of Lumber) 3.26 kgs. 80.00 260.96
f. Cement 44.27 bags 265.00 11,731.55
g. Sand 2.33 cu.m. 1,000.00 2,330.00
h. Gravel 4.66 cu.m. 1,000.00 4,660.00
i. #16 Tie Wire (2% of RSB) 6.31 kgs. 70.00 441.98
j. Reinforcing Steel Bar 315.70 kgs. 36.00 11,365.33
(w/ 5% Wastage)

Page 23 of 72
#REF!
a. 150mmØ x 11.25° D.I. Bend, Push-on Double Socket w/ Rubber Gasket 0.00 pcs. 933.06 -

b. 150mm Ø D.I. Sleeve Type Flexible Coupling, (D.I.) 0.00 pcs. 2,730.00 -
c. Lumber, Good - 4 uses 0.00 bd.ft 20.00 -
d. Plywood (1/2" x 4' x 8") - 4 uses 0.00 pcs. 950.00 -
e. Assorted CWN (1kg./100 bdft. Of Lumber) 0.00 kgs. 80.00 -
f. Cement 0.00 bags 265.00 -
g. Sand 0.00 cu.m. 1,000.00 -
h. Gravel 0.00 cu.m. 1,000.00 -
i. #16 Tie Wire (2% of RSB) 0.00 kgs. 70.00 -
j. Reinforcing Steel Bar 0.00 kgs. 36.00 -
(w/ 5% Wastage)

#REF!
a. 150mmØ x 11.25° D.I. Bend, Push-on Double Socket w/ Rubber Gasket 0.00 pcs. 933.06 -

b. 150mm Ø D.I. Sleeve Type Flexible Coupling, (D.I.) 0.00 pcs. 2,730.00 -
c. Lumber, Good - 4 uses 0.00 bd.ft 20.00 -
d. Plywood (1/2" x 4' x 8") - 4 uses 0.00 pcs. 950.00 -
e. Assorted CWN (1kg./100 bdft. Of Lumber) 0.00 kgs. 80.00 -
f. Cement 0.00 bags 265.00 -
g. Sand 0.00 cu.m. 1,000.00 -
h. Gravel 0.00 cu.m. 1,000.00 -
i. #16 Tie Wire (2% of RSB) 0.00 kgs. 70.00 -
j. Reinforcing Steel Bar 0.00 kgs. 36.00 -
(w/ 5% Wastage)

Note: Quantities for D.I. Pipes are already included in SPL-7


Sub-Total for E P 117,934.94
F. Direct Cost (C+E) #REF!
G. Overhead, Contingencies & Miscellaneous 9% per D.O. 22 s 2015 #REF!
H. Contractor's Profit (CP) 8% per D.O. 22 s 2015 #REF!
I. Value Added Tax (VAT) 5% per D.O. 22 s 2015 #REF!
J. Total Cost #REF!
k. Total Unit Cost #REF!

Page 24 of 72
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME: #REF!

#REF! #REF!

Item No./Description: SPL-9b DRAINAGE CROSSING WITH CONCRETE ENCASEMENT (200mmØ D.I. PIPELINE)
Unit of Measurement: LN.M.
Output per day: #REF! LN.M./DAY
Quantity: #REF! LN.M.

Length of Drainage Crossing Pipe Size


Location
(Ln.m.) (mm)
#REF! #REF! 200
Total Length #REF!

Designation No. Person No. of Days Daily Rate Amount

A. Labor
a. Construction Foreman 1 #REF! 524.00 #REF!
b. Pipefitter 1 #REF! 394.00 #REF!
c. Skilled Worker 6 #REF! 366.00 #REF!
d. Laborer 12 #REF! 317.00 #REF!

Sub-Total for A P #REF!

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment
a. One Bagger Mixer 1 #REF! 1,376.00 #REF!
b. Concrete Vibrator 1 #REF! 1,191.04 #REF!
c. Water Truck (1000 gal.) 1 #REF! 8,520.00 #REF!
d Bar Cutter 1 #REF! 1,758.00 #REF!
e. Bar Bender 1 #REF! 2,812.00 #REF!
f. Cargo Truck (10T, 270 Hp) 1 #REF! 8,816.00 #REF!

Sub-Total for B P #REF!


C. Total (A+B) #REF!
D. Output per day = #REF! LN.M./DAY

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials
#REF!
a. 200mmØ x 11.25° D.I. Bend, Push-on Double Socket w/ Rubber Gasket 0.00 pcs. 1,386.98 -

b. 200mm Ø D.I. Sleeve Type Flexible Coupling, (D.I.) 0.00 pcs. 4,308.00 -
c. Lumber, Good - 4 uses 0.00 bd.ft 20.00 -
d. Plywood (1/2" x 4' x 8") - 4 uses 0.00 pc. 950.00 -
e. Assorted CWN (1kg./100 bdft. Of Lumber) 0.00 kg. 80.00 -
f. Cement 0.00 bags 265.00 -
g. Sand 0.00 cu.m. 1,000.00 -
h. Gravel 0.00 cu.m. 1,000.00 -
i. #16 Tie Wire (2% of RSB) 0.00 kgs. 70.00 -
j. Reinforcing Steel Bar 0.00 kgs. 36.00 -
(w/ 5% Wastage)

Note: Quantities for D.I. Pipes are already included in SPL-7


Sub-Total for E P -
F. Direct Cost (C+E) #REF!
G. Overhead, Contingencies & Miscellaneous 9% per D.O. 22 s 2015 #REF!
H. Contractor's Profit (CP) 8% per D.O. 22 s 2015 #REF!
I. Value Added Tax (VAT) 5% per D.O. 22 s 2015 #REF!
J. Total Cost #REF!
Page 25 of 72
k. Total Unit Cost #REF!

Page 26 of 72
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME: #REF!

PROJECT LOCATION: #REF!

Item No./Description: SPL-13 INSTALLATION OF 100mmØ BLOW-OFF ASSEMBLY


Unit of Measurement: UNIT
Output per day: 0.50 UNIT/DAY
Quantity: #REF! UNIT

Location No. of Blow-off


Aplaya Compound 0.00
#REF! #REF!
#REF! #REF!
#REF! #REF!
#REF! #REF!
Total No. #REF!

Designation No. Person No. of Days Daily Rate Amount

A. Labor
a. Pipefitter 1 #REF! 524.00 #REF!
b. Skilled Worker 3 #REF! 366.00 #REF!
c. Laborer 6 #REF! 317.00 #REF!

Sub-Total for A P #REF!

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment
a. ICS Ductile Iron Pipe-Cutting Gas Chain Saw 1 #REF! 1,600.00 #REF!

Sub-Total for B P #REF!


C. Total (A+B) #REF!
D. Output per day = 0.50 UNIT/DAY

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials
#REF!
a. 200mmØ x 100mmØ D.I. Tee, F/F 1 pc. 10,758.00 10,758.00
b. 200mmØ D.I. Adapter, F/P 2 pcs. 5,287.91 10,575.82
c. 200mmØ D.I. Sleeve Type Flexible Coupling, (D.I.) 2 pcs. 4,308.00 8,616.00
d. 100mmØ D.I. Gate Valve, F/F, PN16 1 pc. 7,447.00 7,447.00
e. 100mmØ x 90º D.I. Bend, F/F 2 pcs. 4,000.00 8,000.00
f. 100mmØ D.I. Adapter, F/P 3 pcs. 2,643.95 7,931.85
g. 100mmØ D.I. Sleeve Type Flexible Coupling, (D.I.) 3 pcs. 1,939.00 5,817.00
h. 100mmØ x 6.00m D.I. Push-on Socket and Spigot with Rubber Gasket 1 pc. 5,962.58 5,962.58
i. 150mmØ D.I. Valve Box Cover 1 pc. 1,402.00 1,402.00
j. 150mmØ x 6.0m PVC Pipe, Class 150 B/S w/ R.R. 0.13 pc. 4,340.00 549.73
k. 16mmØ x 65mm Stainless Steel Hex. Bolt w/ Nut & Washer 32 pcs. 50.21 1,606.66
l. 20mmØ x 70mm Stainless Steel Hex. Bolt w/ Nut & Washer 24 pcs. 62.76 1,506.24
m. 6mm Thk Rubber Gasket 6.00 kgs. 140.00 840.00
n. 12mmØ x 6.00m Deformed Rein. Steel Bar 0.30 pc. 192.00 56.64
o. Portland Cement 1.30 bags 265.00 344.50
p. Washed Sand 0.05 cu.m. 1,000.00 52.00
q. Gravel 0.10 cu.m. 1,000.00 104.00

Sub-Total for E P 71,570.02


F. Direct Cost (C+E) #REF!
G. Overhead, Contingencies & Miscellaneous 9% per D.O. 22 s 2015 #REF!
H. Contractor's Profit (CP) 8% per D.O. 22 s 2015 #REF!
I. Value Added Tax (VAT) 5% per D.O. 22 s 2015 #REF!
J. Total Cost #REF!
k. Total Unit Cost #REF!
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME: #REF!

#REF! #REF!
Item No./Description: SPL-14 TRANSFER OF INDIVIDUAL SERVICELINE CONNECTION
Unit of Measurement: UNIT
Output per day: 8.00 UNIT/DAY
Quantity: 50.00 UNITS

Location Number of Serviceline


(unit)
Aplaya Compound 50.00
#REF! #REF!
#REF! #REF!
#REF! #REF!
#REF! #REF!
Total no. #REF!

Designation No. Person No. of Days Daily Rate Amount

A. Labor
a. Construction Foreman 1 6.25 524.00 3,275.00
b. Skilled Worker 4 6.25 366.00 9,150.00
c. Plumber 4 6.25 394.00 9,850.00
d. Laborers 16 6.25 317.00 31,700.00

Sub-Total for A P 53,975.00

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment
N.A.

Sub-Total for B P -
C. Total (A+B) 53,975.00
D. Output per day = 8.00 UNIT/DAY

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials
Aplaya Compound
a. 150mmØ x 19mmØ C.I Saddle Clamp with Stainless Steel Bolt Head, Nuts & Washers 50.0 pcs. 629.00 31,450.00
b. 19mmØ Brass Corporation Cock (ISO) 50.0 pcs. 237.00 11,850.00
c. 19mmØ x 150m / Roll PE Tubing SDR-11 3.3 rolls. 2,423.00 8,076.67
d. 19mmØ Brass Single Adaptor 50.0 pcs. 105.00 5,250.00
e. 19mmØ x 12mmØ GI Reducer, ANSI B16.3 Class 150 50.0 pcs. 32.00 1,600.00
f. 12mmØ x 900 GI Elbow, ANSI B16.3 Class 150 200.0 pcs. 23.00 4,600.00
g. 12mmØ x 406mm GI Nipple, Sch. 40 100.0 pcs. 90.30 9,030.00
h. 12mmØ x 152mm GI Nipple, Sch. 40 100.0 pcs. 40.95 4,095.00
i. 12mmØ x 101mm GI Nipple, Sch. 40 100.0 pcs. 26.25 2,625.00
j. Water Meter Sealing Wire 50.0 sets 5.00 250.00
k. 12mm Ø Water Meter (Specs will refer to Metering Section) 50.0 sets 1,300.00 65,000.00
l. 12mmØ Brass Tail Piece 100.0 pcs. 437.85 43,785.00
m. 12mmØ Safety Valve (Key Type) 50.0 pcs. 360.00 18,000.00
n. 12mmØ Brass Ball Valve 50.0 pcs. 250.00 12,500.00
o. 25mm Thread Seal Tape 100.0 rolls. 28.00 2,800.00
p. 10mmØ x 6.00m Reinf. Steel Def Bar 9.1 pcs. 130.00 1,180.83

Page 29 of 72
q. #16 G.I. Tie Wire 1.2 kg. 70.00 84.00
r. Portland Cement 2.3 bags. 265.00 602.10

Page 30 of 72
s. Washed Sand 0.1 cu.m. 1,000.00 90.88
t. Gravel (G-1) 0.2 cu.m. 1,000.00 181.77
u. 12mm Thk x 1.20m x 2.40m Ordinary Plywood 4.7 shts. 950.00 4,440.30
v. 1-1/2" C.W. Nail 6.3 kgs. 80.00 500.00
w. 50 pcs.-1" x 3" x 8' Coco Lumber 100.0 bd.ft. 20.00 2,000.00

#REF!
a. 150mmØ x 19mmØ C.I Saddle Clamp with Stainless Steel Bolt Head, Nuts & Washers #REF! pcs. 629.00 #REF!
b. 19mmØ Brass Corporation Cock (ISO) #REF! pcs. 237.00 #REF!
c. 19mmØ x 150m / Roll PE Tubing SDR-11 #REF! rolls. 2,423.00 #REF!
d. 19mmØ Brass Single Adaptor #REF! pcs. 105.00 #REF!
e. 19mmØ x 12mmØ GI Reducer, ANSI B16.3 Class 150 #REF! pcs. 32.00 #REF!
f. 12mmØ x 900 GI Elbow, ANSI B16.3 Class 150 #REF! pcs. 23.00 #REF!
g. 12mmØ x 406mm GI Nipple, Sch. 40 #REF! pcs. 90.30 #REF!
h. 12mmØ x 152mm GI Nipple, Sch. 40 #REF! pcs. 40.95 #REF!
i. 12mmØ x 101mm GI Nipple, Sch. 40 #REF! pcs. 26.25 #REF!
j. Water Meter Sealing Wire #REF! sets 5.00 #REF!
k. 12mm Ø Water Meter (Specs will refer to Metering Section) #REF! sets 1,300.00 #REF!
l. 12mmØ Brass Tail Piece #REF! pcs. 437.85 #REF!
m. 12mmØ Safety Valve (Key Type) #REF! pcs. 360.00 #REF!
n. 12mmØ Brass Ball Valve #REF! pcs. 250.00 #REF!
o. 25mm Thread Seal Tape #REF! rolls. 28.00 #REF!
p. 10mmØ x 6.00m Reinf. Steel Def Bar #REF! pcs. 130.00 #REF!
q. #16 G.I. Tie Wire #REF! kg. 70.00 #REF!
r. Portland Cement #REF! bags. 265.00 #REF!
s. Washed Sand #REF! cu.m. 1,000.00 #REF!
t. Gravel (G-1) #REF! cu.m. 1,000.00 #REF!
u. 12mm Thk x 1.20m x 2.40m Ordinary Plywood #REF! shts. 950.00 #REF!
v. 1-1/2" C.W. Nail #REF! kgs. 80.00 #REF!
w. 42 pcs.-1" x 3" x 8' Coco Lumber 84.00 bd.ft. 20.00 1,680.00

#REF!
a. 200mmØ x 19mmØ C.I Saddle Clamp with Stainless Steel Bolt Head, Nuts & Washers 26 pcs. 642.00 16,692.00
b. 19mmØ Brass Corporation Cock (ISO) 26 pcs. 237.00 6,162.00
c. 19mmØ x 150m / Roll PE Tubing SDR-11 1.73 rolls. 2,423.00 4,199.87
d. 19mmØ Brass Single Adaptor 26 pcs. 105.00 2,730.00
e. 19mmØ x 12mmØ GI Reducer, ANSI B16.3 Class 150 26 pcs. 32.00 832.00
f. 12mmØ x 900 GI Elbow, ANSI B16.3 Class 150 104 pcs. 23.00 2,392.00
g. 12mmØ x 406mm GI Nipple, Sch. 40 52 pcs. 90.30 4,695.60
h. 12mmØ x 152mm GI Nipple, Sch. 40 52 pcs. 40.95 2,129.40
i. 12mmØ x 101mm GI Nipple, Sch. 40 52 pcs. 26.25 1,365.00
j. Water Meter Sealing Wire 26 sets 5.00 130.00
k. 12mm Ø Water Meter (Specs will refer to Metering Section) 26 sets 1,300.00 33,800.00
l. 12mmØ Brass Tail Piece 52 pcs. 437.85 22,768.20
m. 12mmØ Safety Valve (Key Type) 26 pcs. 360.00 9,360.00
n. 12mmØ Brass Ball Valve 26 pcs. 250.00 6,500.00
o. 25mm Thread Seal Tape 52 rolls. 28.00 1,456.00
p. 10mmØ x 6.00m Reinf. Steel Def Bar 5 pcs. 130.00 614.03
q. #16 G.I. Tie Wire 1 kg. 70.00 43.68
r. Portland Cement 1 bags. 265.00 313.09
s. Washed Sand 0 cu.m. 1,000.00 47.26
t. Gravel (G-1) 0 cu.m. 1,000.00 94.52
u. 12mm Thk x 1.20m x 2.40m Ordinary Plywood 2 shts. 950.00 2,308.96
v. 1-1/2" C.W. Nail 3 kgs. 80.00 260.00
w. 26 pcs.-1" x 3" x 8' Coco Lumber 52.00 bd.ft. 20.00 1,040.00

Page 31 of 72
#REF!
a. 150mmØ x 19mmØ C.I Saddle Clamp with Stainless Steel Bolt Head, Nuts & Washers #REF! pcs. 629.00 #REF!
b. 19mmØ Brass Corporation Cock (ISO) #REF! pcs. 237.00 #REF!
c. 19mmØ x 150m / Roll PE Tubing SDR-11 #REF! rolls. 2,423.00 #REF!
d. 19mmØ Brass Single Adaptor #REF! pcs. 105.00 #REF!
e. 19mmØ x 12mmØ GI Reducer, ANSI B16.3 Class 150 #REF! pcs. 32.00 #REF!
f. 12mmØ x 900 GI Elbow, ANSI B16.3 Class 150 #REF! pcs. 23.00 #REF!
g. 12mmØ x 406mm GI Nipple, Sch. 40 #REF! pcs. 90.30 #REF!
h. 12mmØ x 152mm GI Nipple, Sch. 40 #REF! pcs. 40.95 #REF!
i. 12mmØ x 101mm GI Nipple, Sch. 40 #REF! pcs. 26.25 #REF!
j. Water Meter Sealing Wire #REF! sets 5.00 #REF!
k. 12mm Ø Water Meter (Specs will refer to Metering Section) #REF! sets 1,300.00 #REF!
l. 12mmØ Brass Tail Piece #REF! pcs. 437.85 #REF!
m. 12mmØ Safety Valve (Key Type) #REF! pcs. 360.00 #REF!
n. 12mmØ Brass Ball Valve #REF! pcs. 250.00 #REF!
o. 25mm Thread Seal Tape #REF! rolls. 28.00 #REF!
p. 10mmØ x 6.00m Reinf. Steel Def Bar #REF! pcs. 130.00 #REF!
q. #16 G.I. Tie Wire #REF! kg. 70.00 #REF!
r. Portland Cement #REF! bags. 265.00 #REF!
s. Washed Sand #REF! cu.m. 1,000.00 #REF!
t. Gravel (G-1) #REF! cu.m. 1,000.00 #REF!
u. 12mm Thk x 1.20m x 2.40m Ordinary Plywood #REF! shts. 950.00 #REF!
v. 1-1/2" C.W. Nail #REF! kgs. 80.00 #REF!
w. 18 pcs.-1" x 3" x 8' Coco Lumber 36.00 bd.ft. 20.00 720.00

#REF!
a. 150mmØ x 19mmØ C.I Saddle Clamp with Stainless Steel Bolt Head, Nuts & Washers 7.00 pcs. 629.00 4,403.00
b. 19mmØ Brass Corporation Cock (ISO) 7.00 pcs. 237.00 1,659.00
c. 19mmØ x 150m / Roll PE Tubing SDR-11 0.47 rolls. 2,423.00 1,130.73
d. 19mmØ Brass Single Adaptor 7.00 pcs. 105.00 735.00
e. 19mmØ x 12mmØ GI Reducer, ANSI B16.3 Class 150 7.00 pcs. 32.00 224.00
f. 12mmØ x 900 GI Elbow, ANSI B16.3 Class 150 28.00 pcs. 23.00 644.00
g. 12mmØ x 406mm GI Nipple, Sch. 40 14.00 pcs. 90.30 1,264.20
h. 12mmØ x 152mm GI Nipple, Sch. 40 14.00 pcs. 40.95 573.30
i. 12mmØ x 101mm GI Nipple, Sch. 40 14.00 pcs. 26.25 367.50
j. Water Meter Sealing Wire 7.00 sets 5.00 35.00
k. 12mm Ø Water Meter (Specs will refer to Metering Section) 7.00 sets 1,300.00 9,100.00
l. 12mmØ Brass Tail Piece 14.00 pcs. 437.85 6,129.90
m. 12mmØ Safety Valve (Key Type) 7.00 pcs. 360.00 2,520.00
n. 12mmØ Brass Ball Valve 7.00 pcs. 250.00 1,750.00
o. 25mm Thread Seal Tape 14.00 rolls. 28.00 392.00
p. 10mmØ x 6.00m Reinf. Steel Def Bar 1.27 pcs. 130.00 165.32
q. #16 G.I. Tie Wire 0.17 kg. 70.00 11.76
r. Portland Cement 0.32 bags. 265.00 84.29
s. Washed Sand 0.01 cu.m. 1,000.00 12.72
t. Gravel (G-1) 0.03 cu.m. 1,000.00 25.45
u. 12mm Thk x 1.20m x 2.40m Ordinary Plywood 0.65 shts. 950.00 621.64
v. 1-1/2" C.W. Nail 0.88 kgs. 80.00 70.00
w. 7 pcs.-1" x 3" x 8' Coco Lumber 14.00 bd.ft. 20.00 280.00

Sub-Total for E P #REF!


F. Direct Cost (C+E) #REF!
G. Overhead, Contingencies & Miscellaneous 9% per D.O. 22 s 2015 #REF!
H. Contractor's Profit (CP) 8% per D.O. 22 s 2015 #REF!
I. Value Added Tax (VAT) 5% per D.O. 22 s 2015 #REF!
J. Total Cost #REF!
k. Total Unit Cost #REF!

Page 32 of 72
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME: #REF!

PROJECT LOCATION: #REF!

Item No./Description: SPL-15 CONSTRUCTION OF CLUSTER CONNECTION (10 WATERMETER PER CLUSTER CON.)
Unit of Measurement: UNIT
Output per day: 0.50 UNIT/DAY
Quantity: 2.00 UNITS

Number of Water Meter per Cluster


Location No. of Valve Box
First Cluster (units) Second Cluster (units)
Aplaya Compound 0
### 2 7 10
### 0
### 0
### 0
Total no. 2

Designation No. Person No. of Days Daily Rate Amount

A. Labor
a. Construction Foreman 1 4.00 524.00 2,096.00
a. Skilled Worker 6 4.00 366.00 8,784.00
b. Laborer 8 4.00 317.00 10,144.00

Sub-Total for A P 21,024.00

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment
a. One Bagger Mixer 1 4.00 1,248.00 4,992.00
b. Concrete Vibrator 1 4.00 800.00 3,200.00
c. Welding Machine 1 4.00 2,160.00 8,640.00

Sub-Total for B P 16,832.00


C. Total (A+B) 37,856.00
D. Output per day = 0.50 UNIT/DAY

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials
#REF!
a. 50mm.Ø D. I. Body Gate Valve, PN16, NRS, F/F, with 2-Units Steel Ring Flange in 2 pcs. 7,130.00 14,260.00
accordance w/ ANSI B16.5 Class 150 Standard w/ 8 pcs.- 16mm.Ø x 75mm
Stainless Steel Bolt Head, Nut & Washer

b. 150mm.Ø x 50mm.Ø D. I. Tee, M/M 2 pcs. 5,455.00 10,910.00


c. 150mm.Ø CI Valve Box Cover 2 pcs. 1,402.00 2,804.00
d. 150mm.Ø x 6.00m. PVC Pipe, Class 150, B/S, 1 pc. 4,340.00 4,340.00
e. 150mmØ D.I. Sleeve Type Flexible Coupling, (D.I.) 2 pcs. 1,600.00 3,200.00
f. 50mm.Ø Brass Single Adaptor 2 pcs. 520.00 1,040.00
g. 50mm.Ø x 60.00m. P. E. Tubing, SDR 11 1 roll 7,300.00 7,300.00
h. 50mm Ø x 2000mm. Sch. 40 G. I. Nipple (Standard BSP Thread, Both Ends) 2 pcs. 548.00 1,096.00
i. 50mm.Ø x 625mm. Sch. 40 G. I. Nipple (Standard BSP Thread, Both Ends) 2 pcs. 249.00 498.00
j. 50mm.Ø x 430mm. Sch. 40 G. I. Nipple (Standard BSP Thread, Both Ends) 2 pcs. 198.00 396.00
k. 50mm.Ø x 330mm. Sch. 40 G. I. Nipple (Standard BSP Thread, Both Ends) 2 pcs. 176.00 352.00
l. 50mm.Ø x 200mm. Sch. 40 G. I. Nipple (Standard BSP Thread, One End) 2 pcs. 155.00 310.00

Page 33 of 72
m. 50mm.Ø x 150mm. Sch. 40 G. I. Nipple (Standard BSP Thread, Both Ends) 2 pcs. 136.00 272.00
n. 50mm.Ø x 100mm. Sch. 40 G. I. Nipple (Standard BSP Thread, Both Ends) 22 pcs. 124.00 2,728.00

Page 34 of 72
o. 50mm.Ø Sch. 40 G. I. Tee 26 pcs. 104.00 2,704.00
p. 50mm.Ø x 90o G. I. Elbow, Sch. 40 4 pcs. 72.00 288.00
q. 50mm.Ø G. I. Union Patent 2 pcs. 83.00 166.00
r. 50mm.Ø x 12mm.Ø G. I. Bushing 24 pcs. 52.00 1,248.00
s. 12mm.Ø G. I. Plug 8 pcs. 12.00 96.00
t. 6mm. thk. Rubber Gasket 4 kgs 140.00 560.00
u. Thread Seal Tape 34 rolls. 28.00 952.00
v. 12mmØ x 900 GI Elbow, Sch. 40 34 pcs. 23.00 782.00
w. 12mmØ x 560mm GI Nipple, Sch. 40 17 pcs. 85.00 1,445.00
x. 12mmØ x 150mm GI Nipple, Sch. 40 17 pcs. 60.00 1,020.00
y. 12mmØ x 63mm GI Nipple, Sch. 40 17 pcs. 57.00 969.00
z. 12mm Ø Water Meter (Specs will refer to Metering Section) 17 units 1,300.00 22,100.00
a.a. Water Sealing Wire 17 pcs. 5.00 85.00
a.b. 12mmØ Brass Tail Piece 17 pcs. 437.85 7,443.45
a.c. 12mmØ Safety Valve (Key Type) 17 pcs. 360.00 6,120.00
a.d. 12mmØ Brass Ball Valve 17 pcs. 250.00 4,250.00
a.e. 12mmØ x 6.00m Reinf. Steel Def Bar 8 pcs. 192.00 1,536.00
a.f. Portland Cement 8 bags. 265.00 2,120.00
a.g. Washed Sand 0.16 cu.m. 1,000.00 160.00
a.h. Gravel (G-1) 0.32 cu.m. 1,000.00 320.00
a.i. Hacksaw Blade 10 pcs. 65.00 650.00
a.j. 4" C.W. Nail 1 kg. 80.00 80.00
a.k. 3" C.W. Nail 1 kg. 80.00 80.00
a.l. 2" C.W. Nail 2 kgs. 80.00 160.00
a.m. 1-1/2" C.W.Nail 1 kg. 80.00 80.00
a.n. 1" C.W. Nail 2 kgs. 80.00 160.00
a.o. 6mm. thk. x 38mm. x 38mm. x 6.00m. MS Angle Bar 6 pcs. 852.00 5,112.00
a.p. # 4 x 50mm. x 50mm. x 1.20m. x 2.40m. Steel Matting 4 shts. 1,500.00 6,000.00
a.q. 10mm. Ø x 20mm. SS Triangular Head Bolt w/ Nut 8 pcs. 65.00 520.00
a.r. Welding Rod (6011) 4 kgs. 160.00 640.00
a.s. Welding Glass # 12 1 pc. 25.00 25.00
a.t. 10mmØ x 6.00m Deformed Reinforced Steel Bar 8 pcs. 130.00 1,040.00
a.u. # 16 G. I. Tie Wire 5 kgs. 70.00 350.00
a.v. 12mm. thk. x 1.20m. x 2.40m. Ordinary Plywood 4 shts. 950.00 3,800.00
a.w. 20 pcs. -2" x 2" x 10' Coco Lumber 67.00 bd.ft. 20.00 1,340.00
a.x. 20 pcs. -2" x 3" x 10' Coco Lumber 100 bd.ft. 20.00 2,000.00
a.y. Zinc Chromate Epoxy Primer (Yellow) 2 gals. 937.65 1,875.30
a.z. Quick Dry Enamel (Royal Blue) 2 gals. 792.00 1,584.00
b.a. Rust Converter 2 gals. 260.00 520.00
b.b. Paint Thinner 2 gals. 332.00 664.00
b.c. 2" Paint Brush 2 pcs. 35.00 70.00
b.d. 2" Steel Brush 2 pcs. 20.00 40.00

Sub-Total for E P 130,660.75


F. Direct Cost (C+E) 168,516.75
G. Overhead, Contingencies & Miscellaneous 9% per D.O. 22 s 2015 15,166.51
H. Contractor's Profit (CP) 8% per D.O. 22 s 2015 13,481.34
I. Value Added Tax (VAT) 5% per D.O. 22 s 2015 9,858.23
J. Total Cost 207,022.83
k. Total Unit Cost 103,511.41

Page 35 of 72
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME: #REF!

### #REF!

Item No./Description: SPL-16 CONSTRUCTION OF 1.00M X 1.50M CONCRETE VALVE BOX W/ PREFAB DI COVER
Unit of Measurement: UNIT
Output per day: 0.60 UNIT/DAY
Quantity: #REF! UNITS

Location No. of Valve Box


Aplaya Compound #REF!
### #REF!
### #REF!
### #REF!
### #REF!
Total no. #REF!

Designation No. Person No. of Days Daily Rate Amount

A. Labor
a. Construction Foreman 1 #REF! 524.00 #REF!
b. Skilled Worker 12 #REF! 366.00 #REF!
c. Laborer 12 #REF! 317.00 #REF!

Sub-Total for A P #REF!

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment
a. One Bagger Mixer 3 #REF! 1,248.00 #REF!
b. Concrete Vibrator 3 #REF! 800.00 #REF!
c. Welding Machine 3 #REF! 2,160.00 #REF!

Sub-Total for B P #REF!


C. Total (A+B) #REF!
D. Output per day = 0.60 UNIT/DAY

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials
Aplaya Compound
a. Cement #REF! bags 265.00 #REF!
b. Sand #REF! cu.m 1,000.00 #REF!
c. Gravel #REF! cu.m 1,000.00 #REF!
d. Reinforcing Steel Bar #REF! kgs. 36.00 #REF!
e. #16 GI Tie wire (2% of RSB) #REF! kgs. 70.00 #REF!
f. 50mm x 50mm x 6mm x 6.00m MS Angle Bar #REF! kgs. 48.00 #REF!
g. 16mmØ x 6.00m Stainless Steel Rod #REF! kgs. 1,318.57 #REF!
h. 150mmØ x 6.00m PVC Pipe, Class 150, w/ B/S & R.R. #REF! pcs. 4,340.00 #REF!
i. 1m x 1.50m D.I. Rectangular Manhole Frame Double Cover, #REF! pcs. 71,500.00 #REF!
Light Series

j. Welding Rod (1kg./2000kg. of steel) #REF! kg. 145.00 #REF!


k. 1/2" Ordinary Plywood - 2 uses #REF! shts. 950.00 #REF!
l. Coco Lumber - 2 uses #REF! bd.ft. 20.00 #REF!
m. Assorted CWN (1kg/100 bd.ft of lumber) #REF! kgs. 68.00 #REF!
n. Stainless Welding Rod #REF! kg. 396.00 #REF!

Page 36 of 72
o. Hacksaw Blade #REF! pcs. 65.00 #REF!

Page 37 of 72
#REF!
a. Cement #REF! bags 265.00 #REF!
b. Sand #REF! cu.m 1,000.00 #REF!
c. Gravel #REF! cu.m 1,000.00 #REF!
d. Reinforcing Steel Bar #REF! kgs. 36.00 #REF!
e. #16 GI Tie wire (2% of RSB) #REF! kgs. 70.00 #REF!
f. 50mm x 50mm x 6mm x 6.00m MS Angle Bar #REF! kgs. 48.00 #REF!
g. 16mmØ x 6.00m Stainless Steel Rod #REF! kgs. 1,318.57 #REF!
h. 150mmØ x 6.00m PVC Pipe, Class 150, w/ B/S & R.R. #REF! pcs. 4,340.00 #REF!
i. 1m x 1.50m D.I. Rectangular Manhole Frame Double Cover, #REF! pcs. 71,500.00 #REF!
Light Series

j. Welding Rod (1kg./2000kg. of steel) #REF! kg. 145.00 #REF!


k. 1/2" Ordinary Plywood - 2 uses #REF! shts. 950.00 #REF!
l. Coco Lumber - 2 uses #REF! bd.ft. 20.00 #REF!
m. Assorted CWN (1kg/100 bd.ft of lumber) #REF! kgs. 68.00 #REF!
n. Stainless Welding Rod #REF! kgs. 396.00 #REF!
o. Hacksaw Blade #REF! pcs. 65.00 #REF!

#REF!
a. Cement #REF! bags 265.00 #REF!
b. Sand #REF! cu.m 1,000.00 #REF!
c. Gravel #REF! cu.m 1,000.00 #REF!
d. Reinforcing Steel Bar #REF! kgs. 36.00 #REF!
e. #16 GI Tie wire (2% of RSB) #REF! kgs. 70.00 #REF!
f. 50mm x 50mm x 6mm x 6.00m MS Angle Bar #REF! kgs. 48.00 #REF!
g. 16mmØ x 6.00m Stainless Steel Rod #REF! kgs. 1,318.57 #REF!
h. 150mmØ x 6.00m PVC Pipe, Class 150, w/ B/S & R.R. #REF! pc. 4,340.00 #REF!
i. 1m x 1.50m D.I. Rectangular Manhole Frame Double Cover, #REF! pcs. 71,500.00 #REF!
Light Series
j. Welding Rod (1kg./2000kg. of steel) #REF! kg. 145.00 #REF!
k. 1/2" Ordinary Plywood - 2 uses #REF! shts. 950.00 #REF!
l. Coco Lumber - 2 uses #REF! bd.ft. 20.00 #REF!
m. Assorted CWN (1kg/100 bd.ft of lumber) #REF! kgs. 68.00 #REF!
n. Stainless Welding Rod #REF! kg. 396.00 #REF!
o. Hacksaw Blade #REF! pcs. 65.00 #REF!

#REF!
a. Cement #REF! bags 265.00 #REF!
b. Sand #REF! cu.m 1,000.00 #REF!
c. Gravel #REF! cu.m 1,000.00 #REF!
d. Reinforcing Steel Bar #REF! kgs. 36.00 #REF!
e. #16 GI Tie wire (2% of RSB) #REF! kgs. 70.00 #REF!
f. 50mm x 50mm x 6mm x 6.00m MS Angle Bar #REF! kgs. 48.00 #REF!
g. 16mmØ x 6.00m Stainless Steel Rod #REF! kgs. 1,318.57 #REF!
h. 150mmØ x 6.00m PVC Pipe, Class 150, w/ B/S & R.R. #REF! pc. 4,340.00 #REF!
i. 1m x 1.50m D.I. Rectangular Manhole Frame Double Cover, #REF! pcs. 71,500.00 #REF!
Light Series
j. Welding Rod (1kg./2000kg. of steel) #REF! kg. 145.00 #REF!
k. 1/2" Ordinary Plywood - 2 uses #REF! shts. 950.00 #REF!
l. Coco Lumber - 2 uses #REF! bd.ft. 20.00 #REF!
m. Assorted CWN (1kg/100 bd.ft of lumber) #REF! kgs. 68.00 #REF!
n. Stainless Welding Rod #REF! kg. 396.00 #REF!
o. Hacksaw Blade #REF! pcs. 65.00 #REF!

Page 38 of 72
#REF!
a. Cement #REF! bags 265.00 #REF!
b. Sand #REF! cu.m 1,000.00 #REF!
c. Gravel #REF! cu.m 1,000.00 #REF!
d. Reinforcing Steel Bar #REF! kgs. 36.00 #REF!
e. #16 GI Tie wire (2% of RSB) #REF! kgs. 70.00 #REF!
f. 50mm x 50mm x 6mm x 6.00m MS Angle Bar #REF! kgs. 48.00 #REF!
g. 16mmØ x 6.00m Stainless Steel Rod #REF! kgs. 1,318.57 #REF!
h. 150mmØ x 6.00m PVC Pipe, Class 150, w/ B/S & R.R. #REF! pcs. 4,340.00 #REF!
i. 1m x 1.50m D.I. Rectangular Manhole Frame Double Cover, #REF! pcs. 71,500.00 #REF!
Light Series
j. Welding Rod (1kg./2000kg. of steel) #REF! kg. 145.00 #REF!
k. 1/2" Ordinary Plywood - 2 uses #REF! shts. 950.00 #REF!
l. Coco Lumber - 2 uses #REF! bd.ft. 20.00 #REF!
m. Assorted CWN (1kg/100 bd.ft of lumber) #REF! kgs. 68.00 #REF!
n. Stainless Welding Rod #REF! kg. 396.00 #REF!
o. Hacksaw Blade #REF! pcs. 65.00 #REF!

Sub-Total for E P #REF!


F. Direct Cost (C+E) #REF!
G. Overhead, Contingencies & Miscellaneous 9% per D.O. 22 s 2015 #REF!
H. Contractor's Profit (CP) 8% per D.O. 22 s 2015 #REF!
I. Value Added Tax (VAT) 5% per D.O. 22 s 2015 #REF!
J. Total Cost #REF!
k. Total Unit Cost #REF!

Page 39 of 72
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME: #REF!


PROJECT LOCATION: #REF!

Item No./Description: SPL-10 INSTALLATION OF Twelve(12) UNITS - 25mm Ø AIR RELEASE ASSEMBLY WITH CONCRETE BARRICADE
Unit of Measurement: UNITS
Output per day: 1.00 UNIT/DAY
Quantity: 13 UNITS

Location Qty (Unit)


Aplaya Compound 2
Ayer Village 1
Christian-Muslim UPAI 2
Evangelista Subd. 1
Islamic Village 1
Lustre Rehabilitation 2
Paniran Resettlement 1
Tulungatung 3
Total no. 13

Designation No. Person No. of Days Daily Rate Amount

A. Labor
a. Construction Foreman/Engineering Assistant 1 13 524.00 6,812.00
b. Pipefitter 2 13 341.00 8,866.00
c. Laborers 8 13 317.00 32,968.00
d. Skilled Worker 4 13 366.00 19,032.00

Sub-Total for A P 67,678.00

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment
a. Generator Set/ Welding Machine w/ complete accessories (w/ fuel) 2 2 2,160.00 8,640.00

Sub-Total for B P 8,640.00


C. Total (A+B) 76,318.00
D. Output per day = 1.00 UNIT/DAY

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials
Aplaya Compound
a. 100mmØ x 25mmØ C.I. Saddle Clamp w/ Hex. Head Stainless Steel bolts w/ nut and 2.00 pcs. 414.00 828.00
washer
b. 25mmØ x 90° G.I. Elbow, ANSI B16.3 Class 150 - Standard 4.00 pcs. 72.00 288.00
c. 25mmØ x 6.0m ASTM 53A-90A Heavy Gauge G.I. Pipe 1.37 pcs. 1,312.00 1,793.07
d. 100mmØ x 6.0m G.I. Pipe, ASTM A53-90A Heavy Gauge, Threaded End Finish 0.37 pc. 9,877.00 3,621.57

e. 150mmØ x 100mmØ G.I. Bell Reducer, (ANSI B16.3 Class 150 - Standard) 2.00 pcs. 2,325.00 4,650.00
f. 25mmØ ANSI B16-3 Class 150 G.I. Coupling 2.00 pcs. 55.00 110.00
g. 25mm Teflon Tape 10.00 rolls 38.00 380.00
h. 25mmØ Automatic Air Release Pressure Valve 2.00 pcs. 21,350.00 42,700.00
i. 150mmØ x 6m ASTM 53A-90A Heavy Gauge G.I. Pipe 0.17 pc. 22,713.00 3,785.50
j. 6011 Welding Rod 1.00 kgs. 165.00 165.00
k. Hacksaw Blade 0.50 pcs. 66.00 33.00
l. 25mm Masking Tape 6.00 rolls 32.00 192.00
m. Portland Cement 5.30 bags 260.00 1,378.52
n. Washed Sand 0.21 cu.m. 1,000.00 212.08

Page 40 of 72
o. Gravel 0.32 cu.m. 1,000.00 318.12
p. 16mmØ x 6.00m Deformed Rein. Steel Bar 8.00 pcs. 335.00 2,680.00
q. 10mmØ x 6.00m Deformed Rein. Steel Bar 4.27 pcs. 175.00 747.25
r. Concrete Neutralizer 0.001 gal. 396.00 0.48
s. Flat Latex Paint (Primer) 0.003 gal. 550.00 1.41
t. Gloss Latex Paint (Caterpillar Yellow) 0.003 gal. 937.75 2.41
u. Gloss Latex Paint (Black) 0.003 gal. 683.55 1.76
v. Red Oxide Metal Primer 0.03 gal. 427.00 12.26
w. Quick Dry Enamel (Blue) 0.03 gal. 606.00 17.41
x. Paint Thinner 0.03 gal. 332.00 9.54
y. #16 G.I. Tie-wire 4.00 kgs. 75.00 300.00
z. 12mm thk x 1.20m x 2.40m Ordinary Plywood 2.00 shts. 950.00 1,900.00
aa. 6 pcs. 2" x 2" x 10' Coco Lumber 40.00 bd.ft. 20.00 800.00
ab. 1½" C.W. Nail 0.70 kgs. 80.00 56.00
ac. 2" C.W. Nail 0.70 kgs. 80.00 56.00
ad. 3" C.W. Nail 0.70 kgs. 80.00 56.00
ae. 2" Paint Brush 1.00 pcs. 65.00 65.00
af. 4" Paint Brush 1.00 pcs. 95.00 95.00

Ayer Village
a. 100mmØ x 25mmØ C.I. Saddle Clamp w/ Hex. Head Stainless Steel bolts w/ nut and 1.00 pcs. 414.00 414.00
washer
b. 25mmØ x 90° G.I. Elbow, ANSI B16.3 Class 150 - Standard 2.00 pcs. 72.00 144.00
c. 25mmØ x 6.0m ASTM 53A-90A Heavy Gauge G.I. Pipe 0.68 pcs. 1,312.00 896.53
d. 100mmØ x 6.0m G.I. Pipe, ASTM A53-90A Heavy Gauge, Threaded End Finish 0.18 pc. 9,877.00 1,810.78

e. 150mmØ x 100mmØ G.I. Bell Reducer, (ANSI B16.3 Class 150 - Standard) 1.00 pcs. 2,325.00 2,325.00
f. 25mmØ ANSI B16-3 Class 150 G.I. Coupling 1.00 pcs. 55.00 55.00
g. 25mm Teflon Tape 5.00 rolls 38.00 190.00
h. 25mmØ Automatic Air Release Pressure Valve 1.00 pcs. 21,350.00 21,350.00
i. 150mmØ x 6m ASTM 53A-90A Heavy Gauge G.I. Pipe 0.08 pc. 22,713.00 1,892.75
j. 6011 Welding Rod 0.50 kgs. 165.00 82.50
k. Hacksaw Blade 0.25 pcs. 66.00 16.50
l. 25mm Masking Tape 3.00 rolls 32.00 96.00
m. Portland Cement 2.65 bags 260.00 689.26
n. Washed Sand 0.11 cu.m. 1,000.00 106.04
o. Gravel 0.16 cu.m. 1,000.00 159.06
p. 16mmØ x 6.00m Deformed Rein. Steel Bar 4.00 pcs. 335.00 1,340.00
q. 10mmØ x 6.00m Deformed Rein. Steel Bar 2.27 pcs. 175.00 397.25
r. Concrete Neutralizer 0.001 gal. 396.00 0.24
s. Flat Latex Paint (Primer) 0.001 gal. 550.00 0.71
t. Gloss Latex Paint (Caterpillar Yellow) 0.001 gal. 937.75 1.21
u. Gloss Latex Paint (Black) 0.001 gal. 683.55 0.44
v. Red Oxide Metal Primer 0.01 gal. 427.00 6.13
w. Quick Dry Enamel (Blue) 0.01 gal. 606.00 8.70
x. Paint Thinner 0.01 gal. 332.00 4.77
y. #16 G.I. Tie-wire 2.00 kgs. 75.00 150.00
z. 12mm thk x 1.20m x 2.40m Ordinary Plywood 1.00 shts. 950.00 950.00
aa. 6 pcs. 2" x 2" x 10' Coco Lumber 20.00 bd.ft. 20.00 400.00
ab. 1½" C.W. Nail 0.35 kgs. 80.00 28.00
ac. 2" C.W. Nail 0.35 kgs. 80.00 28.00
ad. 3" C.W. Nail 0.35 kgs. 80.00 28.00
ae. 2" Paint Brush 1.00 pcs. 65.00 65.00
af. 4" Paint Brush 1.00 pcs. 95.00 95.00

Christian-Muslim UPAI
a. 100mmØ x 25mmØ C.I. Saddle Clamp w/ Hex. Head Stainless Steel bolts w/ nut and 2.00 pcs. 414.00 828.00
washer

Page 41 of 72
b. 25mmØ x 90° G.I. Elbow, ANSI B16.3 Class 150 - Standard 4.00 pcs. 72.00 288.00
c. 25mmØ x 6.0m ASTM 53A-90A Heavy Gauge G.I. Pipe 1.37 pcs. 1,312.00 1,793.07
d. 100mmØ x 6.0m G.I. Pipe, ASTM A53-90A Heavy Gauge, Threaded End Finish 0.37 pc. 9,877.00 3,621.57

e. 150mmØ x 100mmØ G.I. Bell Reducer, (ANSI B16.3 Class 150 - Standard) 2.00 pcs. 2,325.00 4,650.00
f. 25mmØ ANSI B16-3 Class 150 G.I. Coupling 2.00 pcs. 55.00 110.00
g. 25mm Teflon Tape 10.00 rolls 38.00 380.00
h. 25mmØ Automatic Air Release Pressure Valve 2.00 pcs. 21,350.00 42,700.00
i. 150mmØ x 6m ASTM 53A-90A Heavy Gauge G.I. Pipe 0.17 pc. 22,713.00 3,785.50
j. 6011 Welding Rod 1.00 kgs. 165.00 165.00
k. Hacksaw Blade 0.50 pcs. 66.00 33.00
l. 25mm Masking Tape 6.00 rolls 32.00 192.00
m. Portland Cement 5.30 bags 260.00 1,378.52
n. Washed Sand 0.21 cu.m. 1,000.00 212.08
o. Gravel 0.32 cu.m. 1,000.00 318.12
p. 16mmØ x 6.00m Deformed Rein. Steel Bar 8.00 pcs. 335.00 2,680.00
q. 10mmØ x 6.00m Deformed Rein. Steel Bar 4.27 pcs. 175.00 747.25
r. Concrete Neutralizer 0.001 gal. 396.00 0.48
s. Flat Latex Paint (Primer) 0.003 gal. 550.00 1.41
t. Gloss Latex Paint (Caterpillar Yellow) 0.003 gal. 937.75 2.41
u. Gloss Latex Paint (Black) 0.003 gal. 683.55 1.76
v. Red Oxide Metal Primer 0.03 gal. 427.00 12.26
w. Quick Dry Enamel (Blue) 0.03 gal. 606.00 17.41
x. Paint Thinner 0.03 gal. 332.00 9.54
y. #16 G.I. Tie-wire 4.00 kgs. 75.00 300.00
z. 12mm thk x 1.20m x 2.40m Ordinary Plywood 2.00 shts. 950.00 1,900.00
aa. 6 pcs. 2" x 2" x 10' Coco Lumber 40.00 bd.ft. 20.00 800.00
ab. 1½" C.W. Nail 0.70 kgs. 80.00 56.00
ac. 2" C.W. Nail 0.70 kgs. 80.00 56.00
ad. 3" C.W. Nail 0.70 kgs. 80.00 56.00
ae. 2" Paint Brush 1.00 pcs. 65.00 65.00
af. 4" Paint Brush 1.00 pcs. 95.00 95.00

Evangelista Subd.
a. 100mmØ x 25mmØ C.I. Saddle Clamp w/ Hex. Head Stainless Steel bolts w/ nut and 1.00 pcs. 414.00 414.00
washer
b. 25mmØ x 90° G.I. Elbow, ANSI B16.3 Class 150 - Standard 2.00 pcs. 72.00 144.00
c. 25mmØ x 6.0m ASTM 53A-90A Heavy Gauge G.I. Pipe 0.68 pcs. 1,312.00 896.53
d. 100mmØ x 6.0m G.I. Pipe, ASTM A53-90A Heavy Gauge, Threaded End Finish 0.18 pc. 9,877.00 1,810.78

e. 150mmØ x 100mmØ G.I. Bell Reducer, (ANSI B16.3 Class 150 - Standard) 1.00 pcs. 2,325.00 2,325.00
f. 25mmØ ANSI B16-3 Class 150 G.I. Coupling 1.00 pcs. 55.00 55.00
g. 25mm Teflon Tape 5.00 rolls 38.00 190.00
h. 25mmØ Automatic Air Release Pressure Valve 1.00 pcs. 21,350.00 21,350.00
i. 150mmØ x 6m ASTM 53A-90A Heavy Gauge G.I. Pipe 0.08 pc. 22,713.00 1,892.75
j. 6011 Welding Rod 0.50 kgs. 165.00 82.50
k. Hacksaw Blade 0.25 pcs. 66.00 16.50
l. 25mm Masking Tape 3.00 rolls 32.00 96.00
m. Portland Cement 2.65 bags 260.00 689.26
n. Washed Sand 0.11 cu.m. 1,000.00 106.04
o. Gravel 0.16 cu.m. 1,000.00 159.06
p. 16mmØ x 6.00m Deformed Rein. Steel Bar 4.00 pcs. 335.00 1,340.00
q. 10mmØ x 6.00m Deformed Rein. Steel Bar 2.27 pcs. 175.00 397.25
r. Concrete Neutralizer 0.001 gal. 396.00 0.24
s. Flat Latex Paint (Primer) 0.001 gal. 550.00 0.71
t. Gloss Latex Paint (Caterpillar Yellow) 0.001 gal. 937.75 1.21
u. Gloss Latex Paint (Black) 0.001 gal. 683.55 0.44
v. Red Oxide Metal Primer 0.01 gal. 427.00 6.13

Page 42 of 72
w. Quick Dry Enamel (Blue) 0.01 gal. 606.00 8.70
x. Paint Thinner 0.01 gal. 332.00 4.77
y. #16 G.I. Tie-wire 2.00 kgs. 75.00 150.00
z. 12mm thk x 1.20m x 2.40m Ordinary Plywood 1.00 shts. 950.00 950.00
aa. 6 pcs. 2" x 2" x 10' Coco Lumber 20.00 bd.ft. 20.00 400.00
ab. 1½" C.W. Nail 0.35 kgs. 80.00 28.00
ac. 2" C.W. Nail 0.35 kgs. 80.00 28.00
ad. 3" C.W. Nail 0.35 kgs. 80.00 28.00
ae. 2" Paint Brush 1.00 pcs. 65.00 65.00
af. 4" Paint Brush 1.00 pcs. 95.00 95.00
Islamic Village
a. 100mmØ x 25mmØ C.I. Saddle Clamp w/ Hex. Head Stainless Steel bolts w/ nut and 1.00 pcs. 414.00 414.00
washer
b. 25mmØ x 90° G.I. Elbow, ANSI B16.3 Class 150 - Standard 2.00 pcs. 72.00 144.00
c. 25mmØ x 6.0m ASTM 53A-90A Heavy Gauge G.I. Pipe 0.68 pcs. 1,312.00 896.53
d. 100mmØ x 6.0m G.I. Pipe, ASTM A53-90A Heavy Gauge, Threaded End Finish 0.18 pc. 9,877.00 1,810.78

e. 150mmØ x 100mmØ G.I. Bell Reducer, (ANSI B16.3 Class 150 - Standard) 1.00 pcs. 2,325.00 2,325.00
f. 25mmØ ANSI B16-3 Class 150 G.I. Coupling 1.00 pcs. 55.00 55.00
g. 25mm Teflon Tape 5.00 rolls 38.00 190.00
h. 25mmØ Automatic Air Release Pressure Valve 1.00 pcs. 21,350.00 21,350.00
i. 150mmØ x 6m ASTM 53A-90A Heavy Gauge G.I. Pipe 0.08 pc. 22,713.00 1,892.75
j. 6011 Welding Rod 0.50 kgs. 165.00 82.50
k. Hacksaw Blade 0.25 pcs. 66.00 16.50
l. 25mm Masking Tape 3.00 rolls 32.00 96.00
m. Portland Cement 2.65 bags 260.00 689.26
n. Washed Sand 0.11 cu.m. 1,000.00 106.04
o. Gravel 0.16 cu.m. 1,000.00 159.06
p. 16mmØ x 6.00m Deformed Rein. Steel Bar 4.00 pcs. 335.00 1,340.00
q. 10mmØ x 6.00m Deformed Rein. Steel Bar 2.27 pcs. 175.00 397.25
r. Concrete Neutralizer 0.001 gal. 396.00 0.24
s. Flat Latex Paint (Primer) 0.001 gal. 550.00 0.71
t. Gloss Latex Paint (Caterpillar Yellow) 0.001 gal. 937.75 1.21
u. Gloss Latex Paint (Black) 0.001 gal. 683.55 0.44
v. Red Oxide Metal Primer 0.01 gal. 427.00 6.13
w. Quick Dry Enamel (Blue) 0.01 gal. 606.00 8.70
x. Paint Thinner 0.01 gal. 332.00 4.77
y. #16 G.I. Tie-wire 2.00 kgs. 75.00 150.00
z. 12mm thk x 1.20m x 2.40m Ordinary Plywood 1.00 shts. 950.00 950.00
aa. 6 pcs. 2" x 2" x 10' Coco Lumber 20.00 bd.ft. 20.00 400.00
ab. 1½" C.W. Nail 0.35 kgs. 80.00 28.00
ac. 2" C.W. Nail 0.35 kgs. 80.00 28.00
ad. 3" C.W. Nail 0.35 kgs. 80.00 28.00
ae. 2" Paint Brush 1.00 pcs. 65.00 65.00
af. 4" Paint Brush 1.00 pcs. 95.00 95.00

Lustre Rehabilitation
a. 100mmØ x 25mmØ C.I. Saddle Clamp w/ Hex. Head Stainless Steel bolts w/ nut and 2.00 pcs. 414.00 828.00
washer
b. 25mmØ x 90° G.I. Elbow, ANSI B16.3 Class 150 - Standard 4.00 pcs. 72.00 288.00
c. 25mmØ x 6.0m ASTM 53A-90A Heavy Gauge G.I. Pipe 1.37 pcs. 1,312.00 1,793.07
d. 100mmØ x 6.0m G.I. Pipe, ASTM A53-90A Heavy Gauge, Threaded End Finish 0.37 pc. 9,877.00 3,621.57

e. 150mmØ x 100mmØ G.I. Bell Reducer, (ANSI B16.3 Class 150 - Standard) 2.00 pcs. 2,325.00 4,650.00
f. 25mmØ ANSI B16-3 Class 150 G.I. Coupling 2.00 pcs. 55.00 110.00
g. 25mm Teflon Tape 10.00 rolls 38.00 380.00
h. 25mmØ Automatic Air Release Pressure Valve 2.00 pcs. 21,350.00 42,700.00
i. 150mmØ x 6m ASTM 53A-90A Heavy Gauge G.I. Pipe 0.17 pc. 22,713.00 3,785.50

Page 43 of 72
j. 6011 Welding Rod 1.00 kgs. 165.00 165.00
k. Hacksaw Blade 0.50 pcs. 66.00 33.00
l. 25mm Masking Tape 6.00 rolls 32.00 192.00
m. Portland Cement 5.30 bags 260.00 1,378.52
n. Washed Sand 0.21 cu.m. 1,000.00 212.08
o. Gravel 0.32 cu.m. 1,000.00 318.12
p. 16mmØ x 6.00m Deformed Rein. Steel Bar 8.00 pcs. 335.00 2,680.00
q. 10mmØ x 6.00m Deformed Rein. Steel Bar 4.27 pcs. 175.00 747.25
r. Concrete Neutralizer 0.001 gal. 396.00 0.48
s. Flat Latex Paint (Primer) 0.003 gal. 550.00 1.41
t. Gloss Latex Paint (Caterpillar Yellow) 0.003 gal. 937.75 2.41
u. Gloss Latex Paint (Black) 0.003 gal. 683.55 1.76
v. Red Oxide Metal Primer 0.03 gal. 427.00 12.26
w. Quick Dry Enamel (Blue) 0.03 gal. 606.00 17.41
x. Paint Thinner 0.03 gal. 332.00 9.54
y. #16 G.I. Tie-wire 4.00 kgs. 75.00 300.00
z. 12mm thk x 1.20m x 2.40m Ordinary Plywood 2.00 shts. 950.00 1,900.00
aa. 6 pcs. 2" x 2" x 10' Coco Lumber 40.00 bd.ft. 20.00 800.00
ab. 1½" C.W. Nail 0.70 kgs. 80.00 56.00
ac. 2" C.W. Nail 0.70 kgs. 80.00 56.00
ad. 3" C.W. Nail 0.70 kgs. 80.00 56.00
ae. 2" Paint Brush 1.00 pcs. 65.00 65.00
af. 4" Paint Brush 1.00 pcs. 95.00 95.00

Paniran Resettlement
a. 100mmØ x 25mmØ C.I. Saddle Clamp w/ Hex. Head Stainless Steel bolts w/ nut and 1.00 pcs. 414.00 414.00
washer
b. 25mmØ x 90° G.I. Elbow, ANSI B16.3 Class 150 - Standard 2.00 pcs. 72.00 144.00
c. 25mmØ x 6.0m ASTM 53A-90A Heavy Gauge G.I. Pipe 0.68 pcs. 1,312.00 896.53
d. 100mmØ x 6.0m G.I. Pipe, ASTM A53-90A Heavy Gauge, Threaded End Finish 0.18 pc. 9,877.00 1,810.78

e. 150mmØ x 100mmØ G.I. Bell Reducer, (ANSI B16.3 Class 150 - Standard) 1.00 pcs. 2,325.00 2,325.00
f. 25mmØ ANSI B16-3 Class 150 G.I. Coupling 1.00 pcs. 55.00 55.00
g. 25mm Teflon Tape 5.00 rolls 38.00 190.00
h. 25mmØ Automatic Air Release Pressure Valve 1.00 pcs. 21,350.00 21,350.00
i. 150mmØ x 6m ASTM 53A-90A Heavy Gauge G.I. Pipe 0.08 pc. 22,713.00 1,892.75
j. 6011 Welding Rod 0.50 kgs. 165.00 82.50
k. Hacksaw Blade 0.25 pcs. 66.00 16.50
l. 25mm Masking Tape 3.00 rolls 32.00 96.00
m. Portland Cement 2.65 bags 260.00 689.26
n. Washed Sand 0.11 cu.m. 1,000.00 106.04
o. Gravel 0.16 cu.m. 1,000.00 159.06
p. 16mmØ x 6.00m Deformed Rein. Steel Bar 4.00 pcs. 335.00 1,340.00
q. 10mmØ x 6.00m Deformed Rein. Steel Bar 2.27 pcs. 175.00 397.25
r. Concrete Neutralizer 0.001 gal. 396.00 0.24
s. Flat Latex Paint (Primer) 0.001 gal. 550.00 0.71
t. Gloss Latex Paint (Caterpillar Yellow) 0.001 gal. 937.75 1.21
u. Gloss Latex Paint (Black) 0.001 gal. 683.55 0.44
v. Red Oxide Metal Primer 0.01 gal. 427.00 6.13
w. Quick Dry Enamel (Blue) 0.01 gal. 606.00 8.70
x. Paint Thinner 0.01 gal. 332.00 4.77
y. #16 G.I. Tie-wire 2.00 kgs. 75.00 150.00
z. 12mm thk x 1.20m x 2.40m Ordinary Plywood 1.00 shts. 950.00 950.00
aa. 6 pcs. 2" x 2" x 10' Coco Lumber 20.00 bd.ft. 20.00 400.00
ab. 1½" C.W. Nail 0.35 kgs. 80.00 28.00
ac. 2" C.W. Nail 0.35 kgs. 80.00 28.00
ad. 3" C.W. Nail 0.35 kgs. 80.00 28.00
ae. 2" Paint Brush 2.00 pcs. 65.00 130.00

Page 44 of 72
af. 4" Paint Brush 2.00 pcs. 95.00 190.00

Tulungatung
a. 75mmØ x 25mmØ C.I. Saddle Clamp w/ Hex. Head Stainless Steel bolts w/ nut and washer 3.00 pcs. 332.00 996.00

b. 25mmØ x 90° G.I. Elbow, ANSI B16.3 Class 150 - Standard 6.00 pcs. 72.00 432.00
c. 25mmØ x 6.0m ASTM 53A-90A Heavy Gauge G.I. Pipe 2.05 pcs. 1,312.00 2,689.60
d. 100mmØ x 6.0m G.I. Pipe, ASTM A53-90A Heavy Gauge, Threaded End Finish 0.55 pc. 9,877.00 5,432.35

e. 150mmØ x 100mmØ G.I. Bell Reducer, (ANSI B16.3 Class 150 - Standard) 3.00 pcs. 2,325.00 6,975.00
f. 25mmØ ANSI B16-3 Class 150 G.I. Coupling 3.00 pcs. 55.00 165.00
g. 25mm Teflon Tape 15.00 rolls 38.00 570.00
h. 25mmØ Automatic Air Release Pressure Valve 3.00 pcs. 21,350.00 64,050.00
i. 150mmØ x 6m ASTM 53A-90A Heavy Gauge G.I. Pipe 0.25 pc. 22,713.00 5,678.25
j. 6011 Welding Rod 1.50 kgs. 165.00 247.50
k. Hacksaw Blade 0.75 pcs. 66.00 49.50
l. 25mm Masking Tape 9.00 rolls 32.00 288.00
m. Portland Cement 7.95 bags 260.00 2,067.78
n. Washed Sand 0.32 cu.m. 1,000.00 318.12
o. Gravel 0.48 cu.m. 1,000.00 477.18
p. 16mmØ x 6.00m Deformed Rein. Steel Bar 12.00 pcs. 335.00 4,020.00
q. 10mmØ x 6.00m Deformed Rein. Steel Bar 6.27 pcs. 175.00 1,097.25
r. Concrete Neutralizer 0.002 gal. 396.00 0.71
s. Flat Latex Paint (Primer) 0.004 gal. 550.00 2.12
t. Gloss Latex Paint (Caterpillar Yellow) 0.004 gal. 937.75 3.62
u. Gloss Latex Paint (Black) 0.000 gal. 683.55 -
v. Red Oxide Metal Primer 0.04 gal. 427.00 18.40
w. Quick Dry Enamel (Blue) 0.04 gal. 606.00 26.11
x. Paint Thinner 0.04 gal. 332.00 14.30
y. #16 G.I. Tie-wire 6.00 kgs. 75.00 450.00
z. 12mm thk x 1.20m x 2.40m Ordinary Plywood 3.00 shts. 950.00 2,850.00
aa. 6 pcs. 2" x 2" x 10' Coco Lumber 60.00 bd.ft. 20.00 1,200.00
ab. 1½" C.W. Nail 1.05 kgs. 80.00 84.00
ac. 2" C.W. Nail 1.05 kgs. 80.00 84.00
ad. 3" C.W. Nail 1.05 kgs. 80.00 84.00
ae. 2" Paint Brush 3.00 pcs. 65.00 195.00
af. 4" Paint Brush 3.00 pcs. 95.00 285.00
Sub-Total for E P 437,700.38
F. Direct Cost (C+E) 514,018.38
G. Overhead, Contingencies & Miscellaneous 6% per D.O. 22 s 2015 30,841.10
H. Contractor's Profit (CP) 8% per D.O. 22 s 2015 41,121.47
I. Value Added Tax (VAT) 5% per D.O. 22 s 2015 29,299.05
J. Total Cost 615,280.00
k. Total Unit Cost 47,329.23

Page 45 of 72
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME: #REF!


PROJECT LOCATION: #REF!
Item No./Description: SPL-11 CONSTRUCTION OF 1.00M X 1.50M CONCRETE VALVE BOX W/ PREFAB DI COVER
Unit of Measurement: UNITS
Output per day: 0.80 UNIT/DAY
Quantity: 40.00 UNITS

Location No. of Valve Box


Aplaya Compound 6
Ayer Village 1
Christian-Muslim UPAI 6
Evangelista Subd. 7
Islamic Village 7
Lustre Rehabilitation 7
Paniran Resettlement 6
Tulungatung 0
Total no. 40

Designation No. Person No. of Days Daily Rate Amount

A. Labor
a. Construction Foreman/Engineering Assistant 1 50.00 524.00 26,200.00
b. Skilled Worker 16 50.00 366.00 292,800.00
c. Laborer 16 50.00 317.00 253,600.00

Sub-Total for A P 572,600.00

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment
a. One Bagger Mixer 4 2.00 1,248.00 9,984.00
b. Concrete Vibrator 4 2.00 800.00 6,400.00
c. Welding Machine 4 2.00 2,160.00 17,280.00

Sub-Total for B P 33,664.00


C. Total (A+B) 606,264.00
D. Output per day = 0.80 UNIT/DAY

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials
Aplaya Compound
a. Cement 228.00 bags 265.00 60,420.00
b. Sand 12.00 cu.m 1,000.00 12,000.00
c. Gravel 18.00 cu.m 1,000.00 18,000.00
d. Reinforcing Steel Bar 1,430.46 kgs. 36.00 51,496.56
e. #16 GI Tie wire (2% of RSB) 18.00 kgs. 70.00 1,260.00
f. W12 x 26 ASTM A36 Wide Flange (AISC Standard) 417.84 kgs. 60.00 25,070.40
g. 9mm thk. x 0.25m x 0.62m ASTM A36 Steel Plate 261.14 kgs. 60.00 15,668.64
h. 9mm thk. X 0.0795m x 0.296m ASTM A36 Steel Plate 79.32 kgs. 60.00 4,759.20
i. 50mm x 50mm x 6mm x 6.00m MS Angle Bar 159.39 kgs. 48.00 7,650.72
j. 16mmØ x 6.00m Stainless Steel Rod 28.44 kgs. 1,318.57 37,500.13
k. 150mmØ x 6.00m PVC Pipe, Class 150, w/ B/S & R.R. 3.00 pcs. 4,340.00 13,020.00
l. 1m x 1.50m D.I. Rectangular Manhole Frame Double Cover, Light 6.00 pcs. 71,500.00 429,000.00
m. Series
Welding Rod (1kg./2000kg. of steel) 48.78 kg. 145.00 7,073.10
n. 1/2" Ordinary Plywood - 2 uses 36.00 shts. 950.00 34,200.00
o. Coco Lumber - 2 uses 750.00 bd.ft. 20.00 15,000.00
p. Assorted CWN (1kg/100 bd.ft of lumber) 9.00 kgs. 68.00 612.00
q. Stainless Welding Rod 1.50 kgs. 396.00 594.00

Page 46 of 72
r. Hacksaw Blade 18.00 pcs. 65.00 1,170.00

Page 47 of 72
Ayer Village
a. Cement 38.00 bags 265.00 10,070.00
b. Sand 2.00 cu.m 1,000.00 2,000.00
c. Gravel 3.00 cu.m 1,000.00 3,000.00
d. Reinforcing Steel Bar 238.41 kgs. 36.00 8,582.76
e. #16 GI Tie wire (2% of RSB) 3.00 kgs. 70.00 210.00
f. W12 x 26 ASTM A36 Wide Flange (AISC Standard) 69.64 kgs. 60.00 4,178.40
g. 9mm thk. x 0.25m x 0.62m ASTM A36 Steel Plate 43.52 kgs. 60.00 2,611.44
h. 9mm thk. X 0.0795m x 0.296m ASTM A36 Steel Plate 13.22 kgs. 60.00 793.20
i. 50mm x 50mm x 6mm x 6.00m MS Angle Bar 26.57 kgs. 48.00 1,275.12
j. 16mmØ x 6.00m Stainless Steel Rod 4.74 kgs. 1,318.57 6,250.02
k. 150mmØ x 6.00m PVC Pipe, Class 150, w/ B/S & R.R. 0.50 pcs. 4,340.00 2,170.00
l. 1m x 1.50m D.I. Rectangular Manhole Frame Double Cover, Light 1.00 pcs. 71,500.00 71,500.00
m. Series
Welding Rod (1kg./2000kg. of steel) 0.13 kg. 145.00 18.85
n. 1/2" Ordinary Plywood - 2 uses 6.00 shts. 950.00 5,700.00
o. Coco Lumber - 2 uses 125.00 bd.ft. 20.00 2,500.00
p. Assorted CWN (1kg/100 bd.ft of lumber) 1.50 kgs. 68.00 102.00
q. Stainless Welding Rod 0.25 kgs. 396.00 99.00
r. Hacksaw Blade 3.00 pcs. 65.00 195.00

Christian-Muslim UPAI
a. Cement 228.00 bags 265.00 60,420.00
b. Sand 12.00 cu.m 1,000.00 12,000.00
c. Gravel 18.00 cu.m 1,000.00 18,000.00
d. Reinforcing Steel Bar 1,430.46 kgs. 36.00 51,496.56
e. #16 GI Tie wire (2% of RSB) 18.00 kgs. 70.00 1,260.00
f. W12 x 26 ASTM A36 Wide Flange (AISC Standard) 417.84 kgs. 60.00 25,070.40
g. 9mm thk. x 0.25m x 0.62m ASTM A36 Steel Plate 261.14 kgs. 60.00 15,668.64
h. 9mm thk. X 0.0795m x 0.296m ASTM A36 Steel Plate 79.32 kgs. 60.00 4,759.20
i. 50mm x 50mm x 6mm x 6.00m MS Angle Bar 159.39 kgs. 48.00 7,650.72
j. 16mmØ x 6.00m Stainless Steel Rod 28.44 kgs. 1,318.57 37,500.13
k. 150mmØ x 6.00m PVC Pipe, Class 150, w/ B/S & R.R. 3.00 pcs. 4,340.00 13,020.00
l. 1m x 1.50m D.I. Rectangular Manhole Frame Double Cover, Light 6.00 pcs. 71,500.00 429,000.00
m. Series
Welding Rod (1kg./2000kg. of steel) 0.78 kg. 145.00 113.10
n. 1/2" Ordinary Plywood - 2 uses 36.00 shts. 950.00 34,200.00
o. Coco Lumber - 2 uses 750.00 bd.ft. 20.00 15,000.00
p. Assorted CWN (1kg/100 bd.ft of lumber) 9.00 kgs. 68.00 612.00
q. Stainless Welding Rod 1.50 kgs. 396.00 594.00
r. Hacksaw Blade 18.00 pcs. 65.00 1,170.00

Evangelista Subd.
a. Cement 266.00 bags 265.00 70,490.00
b. Sand 14.00 cu.m 1,000.00 14,000.00
c. Gravel 21.00 cu.m 1,000.00 21,000.00
d. Reinforcing Steel Bar 1,668.87 kgs. 36.00 60,079.32
e. #16 GI Tie wire (2% of RSB) 21.00 kgs. 70.00 1,470.00
f. W12 x 26 ASTM A36 Wide Flange (AISC Standard) 487.48 kgs. 60.00 29,248.80
g. 9mm thk. x 0.25m x 0.62m ASTM A36 Steel Plate 304.67 kgs. 60.00 18,280.08
h. 9mm thk. X 0.0795m x 0.296m ASTM A36 Steel Plate 92.54 kgs. 60.00 5,552.40
i. 50mm x 50mm x 6mm x 6.00m MS Angle Bar 185.96 kgs. 48.00 8,925.84
j. 16mmØ x 6.00m Stainless Steel Rod 33.18 kgs. 1,318.57 43,750.15
k. 150mmØ x 6.00m PVC Pipe, Class 150, w/ B/S & R.R. 3.50 pcs. 4,340.00 15,190.00
l. 1m x 1.50m D.I. Rectangular Manhole Frame Double Cover, Light 7.00 pcs. 71,500.00 500,500.00
m. Series
Welding Rod (1kg./2000kg. of steel) 0.91 kg. 145.00 131.95
n. 1/2" Ordinary Plywood - 2 uses 42.00 shts. 950.00 39,900.00
o. Coco Lumber - 2 uses 875.00 bd.ft. 20.00 17,500.00
p. Assorted CWN (1kg/100 bd.ft of lumber) 10.50 kgs. 68.00 714.00
q. Stainless Welding Rod 1.75 kgs. 396.00 693.00
r. Hacksaw Blade 21.00 pcs. 65.00 1,365.00

Page 48 of 72
Islamic Village
a. Cement 266.00 bags 265.00 70,490.00
b. Sand 14.00 cu.m 1,000.00 14,000.00
c. Gravel 21.00 cu.m 1,000.00 21,000.00
d. Reinforcing Steel Bar 1,668.87 kgs. 36.00 60,079.32
e. #16 GI Tie wire (2% of RSB) 21.00 kgs. 70.00 1,470.00
f. W12 x 26 ASTM A36 Wide Flange (AISC Standard) 487.48 kgs. 60.00 29,248.80
g. 9mm thk. x 0.25m x 0.62m ASTM A36 Steel Plate 304.67 kgs. 60.00 18,280.08
h. 9mm thk. X 0.0795m x 0.296m ASTM A36 Steel Plate 92.54 kgs. 60.00 5,552.40
i. 50mm x 50mm x 6mm x 6.00m MS Angle Bar 185.96 kgs. 48.00 8,925.84
j. 16mmØ x 6.00m Stainless Steel Rod 33.18 kgs. 1,318.57 43,750.15
k. 150mmØ x 6.00m PVC Pipe, Class 150, w/ B/S & R.R. 3.50 pcs. 4,340.00 15,190.00
l. 1m x 1.50m D.I. Rectangular Manhole Frame Double Cover, Light 7.00 pcs. 71,500.00 500,500.00
m. Series
Welding Rod (1kg./2000kg. of steel) 0.91 kg. 145.00 131.95
n. 1/2" Ordinary Plywood - 2 uses 42.00 shts. 950.00 39,900.00
o. Coco Lumber - 2 uses 875.00 bd.ft. 20.00 17,500.00
p. Assorted CWN (1kg/100 bd.ft of lumber) 10.50 kgs. 68.00 714.00
q. Stainless Welding Rod 1.75 kgs. 396.00 693.00
r. Hacksaw Blade 21.00 pcs. 65.00 1,365.00

Lustre Rehabilitation
a. Cement 266.00 bags 265.00 70,490.00
b. Sand 14.00 cu.m 1,000.00 14,000.00
c. Gravel 21.00 cu.m 1,000.00 21,000.00
d. Reinforcing Steel Bar 1,668.87 kgs. 36.00 60,079.32
e. #16 GI Tie wire (2% of RSB) 21.00 kgs. 70.00 1,470.00
f. W12 x 26 ASTM A36 Wide Flange (AISC Standard) 487.48 kgs. 60.00 29,248.80
g. 9mm thk. x 0.25m x 0.62m ASTM A36 Steel Plate 304.67 kgs. 60.00 18,280.08
h. 9mm thk. X 0.0795m x 0.296m ASTM A36 Steel Plate 92.54 kgs. 60.00 5,552.40
i. 50mm x 50mm x 6mm x 6.00m MS Angle Bar 185.96 kgs. 48.00 8,925.84
j. 16mmØ x 6.00m Stainless Steel Rod 33.18 kgs. 1,318.57 43,750.15
k. 150mmØ x 6.00m PVC Pipe, Class 150, w/ B/S & R.R. 3.50 pcs. 4,340.00 15,190.00
l. 1m x 1.50m D.I. Rectangular Manhole Frame Double Cover, Light 7.00 pcs. 71,500.00 500,500.00
m. Series
Welding Rod (1kg./2000kg. of steel) 0.91 kg. 145.00 131.95
n. 1/2" Ordinary Plywood - 2 uses 42.00 shts. 950.00 39,900.00
o. Coco Lumber - 2 uses 875.00 bd.ft. 20.00 17,500.00
p. Assorted CWN (1kg/100 bd.ft of lumber) 10.50 kgs. 68.00 714.00
q. Stainless Welding Rod 1.75 kgs. 396.00 693.00
r. Hacksaw Blade 21.00 pcs. 65.00 1,365.00

Paniran Resettlement
a. Cement 228.00 bags 265.00 60,420.00
b. Sand 12.00 cu.m 1,000.00 12,000.00
c. Gravel 18.00 cu.m 1,000.00 18,000.00
d. Reinforcing Steel Bar 1,430.46 kgs. 36.00 51,496.56
e. #16 GI Tie wire (2% of RSB) 18.00 kgs. 70.00 1,260.00
f. W12 x 26 ASTM A36 Wide Flange (AISC Standard) 417.84 kgs. 60.00 25,070.40
g. 9mm thk. x 0.25m x 0.62m ASTM A36 Steel Plate 261.14 kgs. 60.00 15,668.64
h. 9mm thk. X 0.0795m x 0.296m ASTM A36 Steel Plate 79.32 kgs. 60.00 4,759.20
i. 50mm x 50mm x 6mm x 6.00m MS Angle Bar 159.39 kgs. 48.00 7,650.72
j. 16mmØ x 6.00m Stainless Steel Rod 28.44 kgs. 1,318.57 37,500.13
k. 150mmØ x 6.00m PVC Pipe, Class 150, w/ B/S & R.R. 3.00 pcs. 4,340.00 13,020.00
l. 1m x 1.50m D.I. Rectangular Manhole Frame Double Cover, Light 6.00 pcs. 71,500.00 429,000.00
m. Series
Welding Rod (1kg./2000kg. of steel) 0.78 kg. 145.00 113.10
n. 1/2" Ordinary Plywood - 2 uses 36.00 shts. 950.00 34,200.00
o. Coco Lumber - 2 uses 750.00 bd.ft. 20.00 15,000.00
p. Assorted CWN (1kg/100 bd.ft of lumber) 9.00 kgs. 68.00 612.00
q. Stainless Welding Rod 1.50 kgs. 396.00 594.00
r. Hacksaw Blade 18.00 pcs. 65.00 1,170.00

Page 49 of 72
Sub-Total for E P 4,857,191.67
F. Direct Cost (C+E) 5,463,455.67
G. Overhead, Contingencies & Miscellaneous 6% per D.O. 22 s 2015 327,807.34
H. Contractor's Profit (CP) 8% per D.O. 22 s 2015 437,076.45
I. Value Added Tax (VAT) 5% per D.O. 22 s 2015 311,416.97
J. Total Cost 6,539,756.44
k. Total Unit Cost 163,493.91

Page 50 of 72
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME: PROPOSED INSTALLATION OF FLOWMETER AT FIRE HYDRANT/STANDPIPE


PROJECT LOCATION: Zamboanga City

Item No./Description: SPL-2 HAULING OF MATERIALS


Unit of Measurement: LOT
Output per day: 1.00 LOT
Quantity: 1.00 LOT

Designation No. Person No. of Days Daily Rate Amount

A. Labor
a. Construction Foreman/Engineering Assistant 1 10.00 551.00 5,510.00
b. Laborer 2 10.00 380.00 7,600.00

Sub-Total for A P 13,110.00

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment
a. Boom Truck 1 10.00 7,232.00 72,320.00

Sub-Total for B P 72,320.00


C. Total (A+B) 85,430.00
D. Output per hour = 1.00 LOT

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials
N.A.

Sub-Total for E P
F. Direct Cost (C+E) 85,430.00
G. Overhead, Contingencies & Miscellaneous 10% per D.O. 22 s 2015 8,543.00
H. Contractor's Profit (CP) 0% per D.O. 22 s 2015 -
I. Value Added Tax (VAT) 0% per D.O. 22 s 2015 -
J. Total Cost 93,973.00
k. Total Unit Cost 93,973.00
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME : PROPOSED INSTALLATION OF FLOWMETER AT FIRE HYDRANT/STANDPIPE

LOCATION : Zamboanga City


Item No./Description : SPL-1 INSTALLATION OF 75mmØ MECHANICAL TYPE METER FOR FIRE HYDRANTS /
STANDPIPES
Unit of Measurement : Unit
Output per day: 1.00 unit/day
Quantity: 1.00 Unit

Designation No. Person No. of Days Daily Rate Amount

A. Labor
Construction Foreman/Engineering Assistant A 1.00 1.00 551.00 551.00
Welder A 1.00 0.50 551.00 275.50
Plumber A 1.00 1.00 380.00 380.00
Skiiled Worker (Lathe Operator) 1.00 1.00 551.00 551.00
Utility Worker A 1.00 1.00 481.00 481.00
Sub-Total for A P 2,238.50

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment
Lathe Machine 1.00 1.00 5,000.00 5,000.00
Welding Machine 1.00 0.50 3,500.00 1,750.00
Angle Grinder 1.00 0.50 1,500.00 750.00
Air Compressor 1.00 0.50 2,500.00 1,250.00
Sub-Total for B P 3,750.00
C. Total (A+B) P 5,988.50
D. Output per day = 1.00 unit/day

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials
75mmØ Mechanical Meter, WP-Dynamic PN16, Class B, 50 deg, Flange 1.00 unit 38,388.00 38,388.00
Type
5mm Thick Flat Rubber Gasket 2.00 kgs. 85.00 170.00
75mmØ x 90º G. I. Elbow, Sch. 40 (Heavy Gauge) 1.00 unit 550.00 550.00
75mmØ x 75mmØ G.I. Tee, Sch. 40 (Heavy Gauge) 2.00 units 216.00 432.00
75mmØ x 100mm G.I. Nipple, Sch. 40 (Std. BSP Threaded 1.00 unit 250.00 250.00
Both Ends)
75mmØ x 250mm G.I. Nipple, Sch. 40 (Std. BSP Threaded 1.00 unit 450.00 450.00
Both Ends)
75mmØ x 375mm G.I. Nipple, Sch. 40 (Std. BSP Threaded 1.00 unit 515.00 515.00
Both Ends)
75mmØ x 625mm G.I. Nipple, Sch. 40 (Std. BSP Threaded 1.00 unit 845.00 845.00
One End)
75mmØ G.I. End Cap, Sch. 40 1.00 unit 139.00 139.00
75mmØ x 6.00m G.I. Pipe, Sch. 40 1.00 unit 5,267.00 5,267.00
75mmØ D.I. Companion Flange 2.00 units 773.00 1,546.00
0-30 Psi, Pressure Gauge, Oil Filled 1.00 unit 2,500.00 2,500.00
12.5mmØ x 10mmØ G.I. Bushing, Sch. 40 1.00 unit 10.00 10.00
12.5mmØ x 100mm G.I. Nipple, Sch. 40 2.00 units 30.00 60.00
12.5mmØ G.I. Coupling, Sch. 40 2.00 units 42.00 84.00
12.5mmØ Brass Ball Valve 1.00 unit 793.00 793.00
Cutting Disk for Metal, 4" Dia. 2.00 pcs. 55.00 110.00
1" Thread Seal Tape "Tombo" 10.00 rolls 28.00 280.00
1/2" Thread Seal Tape "Tombo" 2.00 rolls 14.00 28.00
Ordinary Welding Rod 1.00 kg. 165.00 165.00
Portland Cement 1.00 bag 324.00 324.00

Washed Sand 2.00 bags 55.00 110.00


Name and Specifications Quantity Unit Unit Cost Amount

Gravel (G1) 4.00 bags 55.00 220.00


10mmØ x 6.00m Deformed Bar 1.00 pc. 170.00 170.00
Ga. 10 Steel Matting 1.00 pc. 1,796.00 1,796.00
Ga. 16 G.I. Tie Wire 0.50 kg. 75.00 37.50
16mmØ x 90mm Stainless Steel Bolts w/ N&W (Full Thread) 12.00 pcs. 75.00 900.00
4mm. Thk. X 50mm. X 3.00m. Flat Bar (Mild Steel) 1.00 pc. 360.00 360.00
4mm. Thk. X 25mm. X 3.00m. Flat Bar (Mild Steel) 1.00 pc. 276.00 276.00
4mm. Thk. X 25mm. X 25mm. X 6.00m. Angle Bar 1.00 pc. 677.00 677.00
10mmØ x 37mm. G.I. Bolt w/ Nut & Washers 8.00 pcs. 62.00 496.00
Yellow Acrylic Paint 4.00 pints 125.00 500.00
Acrilyc Thinner 2.00 bots. 85.00 170.00
#100 Sand Papper Waterproof 2.00 pcs. 55.00 110.00
Sub-Total for E P 58,728.50
F. Direct Cost (C+E) 64,717.00
G. Overhead, Contingencies & Miscellaneous 10% per D.O. 29 s 2011 6,471.70
H. Contractor's Profit (CP) 0% per D.O. 29 s 2011 -
I. Value Added Tax (VAT) 0% per D.O. 29 s 2011 -
J. Total Cost 71,188.70
k. Total Unit Cost 71,188.70

PREPARED BY: CHECKED, REVIEWED & SUBMITTED BY:

FELIXBERTO R. CAARE, JR. RMP VALERIE GAY Y. GUITIERREZ


Engineering Assistant B (J.O.) Dept. Manager A - PAMD
NRWMD - PAMD

RECOMMENDING PROJECT IMPLEMENTATION: APPROVED FOR PROJECT IMPLEMENTATION:

REYNALDO R. CABILIN LEONARDO REY D. VASQUEZ


O.I.C. - Operations Group General Manager
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME : PROPOSED INSTALLATION OF FLOWMETER AT FIRE HYDRANT/STANDPIPE

LOCATION : Zamboanga City


Item No./Description : SPL-1 INSTALLATION OF 100mmØ MECHANICAL TYPE METER FOR FIRE HYDRANTS /
STANDPIPES
Unit of Measurement : Unit
Output per day: 1.00 unit/day
Quantity: 1.00 Unit

Designation No. Person No. of Days Daily Rate Amount

A. Labor
Construction Foreman/Engineering Assistant A 1.00 1.00 551.00 551.00
Welder A 0.50 1.00 551.00 275.50
Plumber A 1.00 1.00 380.00 380.00
Skiiled Worker (Lathe Operator) 1.00 1.00 551.00 551.00
Utility Worker A 1.00 1.00 481.00 481.00
Sub-Total for A P 2,238.50

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment
Lathe Machine 1.00 1.00 5,000.00 5,000.00
Welding Machine 1.00 0.50 3,500.00 1,750.00
Angle Grinder 1.00 0.50 1,500.00 750.00
Air Compressor 1.00 0.50 2,500.00 1,250.00
Sub-Total for B P 3,750.00
C. Total (A+B) P 5,988.50
D. Output per day = 1.00 unit/day

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials
100mmØ Mechanical Meter, with Threaded Mating Flange 1.00 unit 60,095.00 60,095.00
5mm Thick Flat Rubber Gasket 1.00 kg. 85.00 85.00
100mmØ x 90º G. I. Elbow, Sch. 40 (Heavy Gauge) 1.00 unit 750.00 750.00
100mmØ x 100mmØ G.I. Tee, Sch. 40 (Heavy Gauge) 1.00 unit 600.00 600.00
100mmØ x 150mm G.I. Nipple, Sch. 40 (Std. BSP Threaded
Both Ends) 1.00 unit 350.00 350.00
100mmØ x 250mm G.I. Nipple, Sch. 40 (Std. BSP Threaded
Both Ends) 1.00 unit 600.00 600.00
100mmØ x 400mm G.I. Nipple, Sch. 40 (Std. BSP Threaded
Both Ends) 1.00 unit 687.00 687.00
100mmØ x 600mm G.I. Nipple, Sch. 40 (Std. BSP Threaded
One End) 2.00 units 870.00 1,740.00
0-150 Psi, Pressure Gauge, Oil Filled 1.00 unit 2,500.00 2,500.00
12.5mmØ x 10mmØ G.I. Bushing, Sch. 40 1.00 unit 8.00 8.00
12.5mmØ x 100mm G.I. Nipple, Sch. 40 2.00 units 25.00 50.00
12.5mmØ G.I. Coupling, Sch. 40 2.00 units 42.00 84.00
12.5mmØ Brass Ball Valve 1.00 unit 793.00 793.00
Cutting Disk for Metal, 4" Dia. 2.00 pcs. 55.00 110.00
1" Thread Seal Tape "Tombo" 10.00 rolls 28.00 280.00
1/2" Thread Seal Tape "Tombo" 2.00 rolls 14.00 28.00
Ordinary Welding Rod 0.25 kg. 165.00 41.25
Portland Cement 1.00 bag 324.00 324.00

Washed Sand 2.00 bags 55.00 110.00


Name and Specifications Quantity Unit Unit Cost Amount

Gravel (G1) 4.00 bags 55.00 220.00


10mmØ x 6.00m Deformed Bar 1.00 pc. 170.00 170.00
12mmØ x 6.00m Deformed Bar 1.00 pc. 420.00 420.00
Ga. 10 Steel Matting 0.25 pc. 1,796.30 449.08
Ga. 16 G.I. Tie Wire 0.50 kg. 75.00 37.50
16mmØ x 90mm Stainless Steel Bolts w/ N&W (Full Thread) 8.00 pcs. 75.00 600.00
Yellow Acrylic Paint 1.00 pint 125.00 125.00
Acrilyc Thinner 1.00 bot. 85.00 85.00
#100 Sand Papper Waterproof 2.00 pcs. 55.00 110.00
Sub-Total for E P 71,451.83
F. Direct Cost (C+E) 77,440.33
G. Overhead, Contingencies & Miscellaneous 10% per D.O. 29 s 2011 7,744.03
H. Contractor's Profit (CP) 0% per D.O. 29 s 2011 -
I. Value Added Tax (VAT) 0% per D.O. 29 s 2011 -
J. Total Cost 85,184.36
k. Total Unit Cost 85,184.36

PREPARED BY: CHECKED & REVIEWED BY: SUBMITTED BY:

FELIXBERTO R. CAARE, JR. RMP CARLOS L. PEREZ, SR. VALERIE GAY Y. GUITIERREZ
Engineering Assistant B (J.O.) Officer-In-Charge Dept. Manager A - PAMD
NRWMD - PAMD NRWMD - PAMD

RECOMMENDING PROJECT IMPLEMENTATION: APPROVED FOR PROJECT IMPLEMENTATION:

ALEJO S. ROJAS, JR. LEONARDO REY D. VASQUEZ


AGM - Operations Group General Manager
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME : PROPOSED INSTALLATION OF FLOWMETER AT FIRE HYDRANT/STANDPIPE

LOCATION : Zamboanga City


Item No./Description : SPL-1 INSTALLATION OF 100mmØ MECHANICAL TYPE METER FOR FIRE HYDRANTS /
STANDPIPES
Unit of Measurement : Unit
Output per day: 1.00 unit/day
Quantity: 1.00 Unit

Designation No. Person No. of Days Daily Rate Amount

A. Labor
Construction Foreman/Engineering Assistant A 1.00 1.00 551.00 551.00
Welder A 1.00 0.50 551.00 275.50
Plumber A 1.00 1.00 380.00 380.00
Skiiled Worker (Lathe Operator) 1.00 1.00 551.00 551.00
Utility Worker A 1.00 1.00 481.00 481.00
Sub-Total for A P 2,238.50

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment
Lathe Machine 1.00 1.00 5,000.00 5,000.00
Welding Machine 1.00 0.50 3,500.00 1,750.00
Angle Grinder 1.00 0.50 1,500.00 750.00
Air Compressor 1.00 0.50 2,500.00 1,250.00
Sub-Total for B P 3,750.00
C. Total (A+B) P 5,988.50
D. Output per day = 1.00 unit/day

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials
100mmØ Mechanical Meter, WP-Dynamic PN16, Class B, 50 deg, Flange 1.00 unit 50,990.00 50,990.00
Type
5mm Thick Flat Rubber Gasket 4.00 kgs. 85.00 340.00
100mmØ x 90º G. I. Elbow, Sch. 40 (Heavy Gauge) 1.00 unit 809.00 809.00
100mmØ x 100mmØ G.I. Tee, Sch. 40 (Heavy Gauge) 2.00 units 313.00 626.00
100mmØ x 100mm G.I. Nipple, Sch. 40 (Std. BSP Threaded 1.00 unit 464.00 464.00
Both Ends)
100mmØ x 300mm G.I. Nipple, Sch. 40 (Std. BSP Threaded 1.00 unit 688.00 688.00
Both Ends)
100mmØ x 500mm G.I. Nipple, Sch. 40 (Std. BSP Threaded 1.00 unit 1,008.00 1,008.00
Both Ends)
100mmØ x 625mm G.I. Nipple, Sch. 40 (Std. BSP Threaded 1.00 unit 1,297.00 1,297.00
One End)
100mmØ G.I. End Cap, Sch. 40 1.00 unit 185.00 185.00
100mmØ x 6.00m G.I. Pipe, Sch. 40 1.00 unit 9,600.00 9,600.00
100mmØ D.I. Companion Flange 2.00 units 1,237.00 2,474.00
0-30 Psi, Pressure Gauge, Oil Filled 1.00 unit 2,500.00 2,500.00
12.5mmØ x 10mmØ G.I. Bushing, Sch. 40 1.00 unit 10.00 10.00
12.5mmØ x 100mm G.I. Nipple, Sch. 40 2.00 units 30.00 60.00
12.5mmØ G.I. Coupling, Sch. 40 2.00 units 42.00 84.00
12.5mmØ Brass Ball Valve 1.00 unit 793.00 793.00
Cutting Disk for Metal, 4" Dia. 2.00 pcs. 55.00 110.00
1" Thread Seal Tape "Tombo" 10.00 rolls 28.00 280.00
1/2" Thread Seal Tape "Tombo" 2.00 rolls 14.00 28.00
Ordinary Welding Rod 0.25 kg. 165.00 41.25
Portland Cement 1.00 bag 324.00 324.00

Washed Sand 2.00 bags 55.00 110.00


Name and Specifications Quantity Unit Unit Cost Amount

Gravel (G1) 4.00 bags 55.00 220.00


10mmØ x 6.00m Deformed Bar 1.00 pc. 170.00 170.00
Ga. 10 Steel Matting 0.25 pc. 1,796.00 449.00
Ga. 16 G.I. Tie Wire 0.50 kg. 75.00 37.50
16mmØ x 90mm Stainless Steel Bolts w/ N&W (Full Thread) 12.00 pcs. 75.00 900.00
4mm. Thk. X 50mm. X 3.00m. Flat Bar (Mild Steel) 1.00 pc. 360.00 360.00
4mm. Thk. X 25mm. X 3.00m. Flat Bar (Mild Steel) 1.00 pc. 276.00 276.00
4mm. Thk. X 25mm. X 25mm. X 6.00m. Angle Bar 1.00 pc. 677.00 677.00
10mmØ x 37mm. G.I. Bolt w/ Nut & Washers 8.00 pcs. 62.00 496.00
Yellow Acrylic Paint 2.00 pints 125.00 250.00
Acrilyc Thinner 1.00 bot. 85.00 85.00
#100 Sand Papper Waterproof 2.00 pcs. 55.00 110.00
Sub-Total for E P 76,851.75
F. Direct Cost (C+E) 82,840.25
G. Overhead, Contingencies & Miscellaneous 10% per D.O. 29 s 2011 8,284.03
H. Contractor's Profit (CP) 0% per D.O. 29 s 2011 -
I. Value Added Tax (VAT) 0% per D.O. 29 s 2011 -
J. Total Cost 91,124.28
k. Total Unit Cost 91,124.28

PREPARED BY: CHECKED, REVIEWED & SUBMITTED BY:

FELIXBERTO R. CAARE, JR. RMP VALERIE GAY Y. GUITIERREZ


Engineering Assistant B (J.O.) Dept. Manager A - PAMD
NRWMD - PAMD

RECOMMENDING PROJECT IMPLEMENTATION: APPROVED FOR PROJECT IMPLEMENTATION:

REYNALDO R. CABILIN LEONARDO REY D. VASQUEZ


O.I.C. - Operations Group General Manager
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME: #REF!

#REF! ###
Item No./Description: ITEM 310(b) BITUMINOUS CONCRETE SURFACE COURSE (50 mm. Thk.)
Unit of Measurement: SQ.M.
Output per day: 1,370.40 SQ.M./DAY
Quantity: 117.78 SQ.M.

Designation No. Person No. of Days Daily Rate Amount

A. Labor
a. Construction Foreman 1 0.09 524.00 45.03
b. Skilled Worker 6 0.09 366.00 188.73
c. Laborers 12 0.09 317.00 326.93

Sub-Total for A P 560.69

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment
a. Asphalt Paver (80 Hp) 1 0.09 14,664.00 1,260.27
b. Pneumatic Roller (10 m.t.) 1 0.09 4,424.00 380.21
c. Tandem Steel Roller (10.1 m.t.) 1 0.09 13,216.00 1,135.82
d. Dump Truck (10 cu.m.) 2 0.09 10,816.00 1,859.12
e. Asphalt Batch Plant (60-80 TPH) 1 0.09 9,717.84 835.18
f. Water Truck (1000 gal.) 1 0.09 8,520.00 732.24
g. Payloader (1.50 cu.m.) 1 0.09 13,864.00 1,191.51
Minor Tools (10% of Labor) 56.00
Sub-Total for B P 7,450.36
C. Total (A+B) 8,011.05
D. Output per day = 1,370.40 SQ.M./DAY

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials
a. Asphalt Cement (6.5%) 0.96 m.t. 50,775.00 48,976.99
b. Aggregates (93%) 5.75 cu.m. 1,000.00 5,750.43
c. Mineral Filler (7%) 15.58 bag 245.00 3,817.55
(w/ 5% wastage)

Sub-Total for E P 58,544.97


F. Direct Cost (C+E) 66,556.02
G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011 3,993.36
H. Contractor's Profit (CP) 8% per D.O. 29 s 2011 5,324.48
I. Value Added Tax (VAT) 12% per D.O. 29 s 2011 9,104.86
J. Total Cost 84,978.73
k. Total Unit Cost 721.53
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME: #REF!


### #REF!

Item No./Description: 311 (1)b PCC PAVEMENT(PLAIN) - CONVENTIONAL METHOD, 230MM THICK
Unit of Measurement: SQ.M.
Output per day: 1,120.00 SQ.M./DAY
Quantity: #REF! SQ.M.

Location Qty (Sq.m.)


Aplaya Compound #REF!
Ayer Village #REF!
Christian-Muslim UPAI #REF!
Evangelista Subd. #REF!
Islamic Village #REF!
Lustre Rehabilitation #REF!
Paniran Resettlement #REF!
Tulungatung #REF!
Total no. #REF!

Designation No. Person No. of Days Daily Rate Amount

A. Labor
a. Construction Foreman/Engineering Assistant 1 #REF! 524.00 #REF!
b. Skilled Worker 8 #REF! 366.00 #REF!
c. Laborers 24 #REF! 317.00 #REF!

Sub-Total for A P #REF!

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment
a. Transit Mixer (5 cu.m.) 8 #REF! 10,232.00 #REF!
b. Concrete Vibrator 4 #REF! 1,191.04 #REF!
c. Batching Plant (30 cu.m.) 2 #REF! 9,664.24 #REF!
d. Payloader 2 #REF! 13,864.00 #REF!
e. Concrete Screeder (5.5 Hp) 2 #REF! 4,360.00 #REF!
f. Water Truck 2 #REF! 8,520.00 #REF!

Sub-Total for B P #REF!


C. Total (A+B) #REF!
D. Output per day = 1,120.00 SQ.M./DAY

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials
Aplaya Compound
a. Curing Compound #REF! lit. 28.00 #REF!
b. Washed Sand #REF! cu.m. 1,000.00 #REF!
c. Gravel #REF! cu.m. 1,000.00 #REF!
d. Portland Cement #REF! bags 265.00 #REF!

Page 60 of 72
Ayer Village
a. Curing Compound #REF! lit. 28.00 #REF!
b. Washed Sand #REF! cu.m. 1,000.00 #REF!
c. Gravel #REF! cu.m. 1,000.00 #REF!
d. Portland Cement #REF! bags 265.00 #REF!

Christian-Muslim UPAI
a. Curing Compound #REF! lit. 28.00 #REF!
b. Washed Sand #REF! cu.m. 1,000.00 #REF!
c. Gravel #REF! cu.m. 1,000.00 #REF!
d. Portland Cement #REF! bags 265.00 #REF!

Evangelista Subd.
a. Curing Compound #REF! lit. 28.00 #REF!
b. Washed Sand #REF! cu.m. 1,000.00 #REF!
c. Gravel #REF! cu.m. 1,000.00 #REF!
d. Portland Cement #REF! bags 265.00 #REF!

Islamic Village
a. Curing Compound #REF! lit. 28.00 #REF!
b. Washed Sand #REF! cu.m. 1,000.00 #REF!
c. Gravel #REF! cu.m. 1,000.00 #REF!
d. Portland Cement #REF! bags 265.00 #REF!

Lustre Rehabilitation
a. Curing Compound #REF! lit. 28.00 #REF!
b. Washed Sand #REF! cu.m. 1,000.00 #REF!
c. Gravel #REF! cu.m. 1,000.00 #REF!
d. Portland Cement #REF! bags 265.00 #REF!

Paniran Resettlement
a. Curing Compound #REF! lit. 28.00 #REF!
b. Washed Sand #REF! cu.m. 1,000.00 #REF!
c. Gravel #REF! cu.m. 1,000.00 #REF!
d. Portland Cement #REF! bags 265.00 #REF!

Tulungatung
a. Curing Compound #REF! lit. 28.00 #REF!
b. Washed Sand #REF! cu.m. 1,000.00 #REF!
c. Gravel #REF! cu.m. 1,000.00 #REF!
d. Portland Cement #REF! bags 265.00 #REF!

Sub-Total for E P #REF!


F. Direct Cost (C+E) #REF!
G. Overhead, Contingencies & Miscellaneous 6% per D.O. 22 s 2015 #REF!
H. Contractor's Profit (CP) 8% per D.O. 22 s 2015 #REF!
I. Value Added Tax (VAT) 5% per D.O. 22 s 2015 #REF!
J. Total Cost #REF!
k. Total Unit Cost #REF!

Page 61 of 72
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME: #REF!

#REF! #REF!

Item No./Description: 302a BITUMINOUS TACK COAT (Emulsified Asphalt)


Unit of Measurement: M.T.
Output per day: 2.40 M.T./DAY
Quantity: #REF! M.T.

Quantity of Emulsified
Location
Asphalt (M.T.)
Aplaya Compound 0.00
#REF! #REF!
#REF! #REF!
#REF! #REF!
#REF! #REF!
Total #REF!

Designation No. Person No. of Days Daily Rate Amount

A. Labor
a. Construction Foreman 1 #REF! 524.00 #REF!
b. Laborers 3 #REF! 317.00 #REF!

Sub-Total for A P #REF!

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment
a. Asphalt Distributor 1 #REF! 7,488.00 #REF!
b. Power Broom 1 #REF! 1,044.32 #REF!
Minor Tools (10%) #REF!

Sub-Total for B P #REF!


C. Total (A+B) #REF!
D. Output per day = 2.40 M.T./DAY

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials
Aplaya Compound
a. Emulsified Asphalt SS-1 (w/ 5% wastage) 0.00 m.t. 44,000.00 -

#REF!
a. Emulsified Asphalt SS-1 (w/ 5% wastage) #REF! m.t. 44,000.00 #REF!

#REF!
a. Emulsified Asphalt SS-1 (w/ 5% wastage) #REF! m.t. 44,000.00 #REF!

Sub-Total for E P #REF!


F. Direct Cost (C+E) #REF!
G. Overhead, Contingencies & Miscellaneous 9% per D.O. 22 s 2015 #REF!
H. Contractor's Profit (CP) 8% per D.O. 22 s 2015 #REF!
I. Value Added Tax (VAT) 5% per D.O. 22 s 2015 #REF!
J. Total Cost #REF!
k. Total Unit Cost #REF!
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME: #REF!

### #REF!

Item No./Description: 310(b) BITUMINOUS CONCRETE SURFACE COURSE (50 mm. Thk.)
Unit of Measurement: SQ.M.
Output per day: 1,370.40 SQ.M./DAY
Quantity: #REF! SQ.M.

Location Area of 50mm thk. Asphalt


Aplaya Compound 0.00
### #REF!
### #REF!
### #REF!
### #REF!
Total Area #REF!

Designation No. Person No. of Days Daily Rate Amount

A. Labor
a. Construction Foreman 1 #REF! 524.00 #REF!
b. Skilled Worker 6 #REF! 366.00 #REF!
c. Laborers 12 #REF! 317.00 #REF!

Sub-Total for A P #REF!

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment
a. Asphalt Paver (80 Hp) 1 #REF! 14,664.00 #REF!
b. Pneumatic Roller (10 m.t.) 1 #REF! 4,424.00 #REF!
c. Tandem Steel Roller (10.1 m.t.) 1 #REF! 13,216.00 #REF!
d. Dump Truck (10 cu.m.) 2 #REF! 10,816.00 #REF!
e. Asphalt Batch Plant (60-80 TPH) 1 #REF! 9,717.84 #REF!
f. Water Truck (1000 gal.) 1 #REF! 8,520.00 #REF!
g. Payloader (1.50 cu.m.) 1 #REF! 13,864.00 #REF!
Minor Tools (10% of Labor) #REF!
Sub-Total for B P #REF!
C. Total (A+B) #REF!
D. Output per day = 1,370.40 SQ.M./DAY

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials
Aplaya Compound
a. Asphalt Cement (6.5%) 0.00 m.t. 50,775.00 -
b. Aggregates (93%) 0.00 cu.m. 1,000.00 -
c. Mineral Filler (7%) 0.00 bags 245.00 -
(w/ 5% wastage)

Sub-Total for E P -
F. Direct Cost (C+E) #REF!
G. Overhead, Contingencies & Miscellaneous 9% per D.O. 22 s 2015 #REF!
H. Contractor's Profit (CP) 8% per D.O. 22 s 2015 #REF!
I. Value Added Tax (VAT) 5% per D.O. 22 s 2015 #REF!
J. Total Cost #REF!
k. Total Unit Cost #REF!
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME: #REF!

#REF! #REF!

Item No./Description: 310(b) BITUMINOUS CONCRETE SURFACE COURSE (100 mm. Thk.)
Unit of Measurement: SQ.M.
Output per day: 685.20 SQ.M./DAY
Quantity: #REF! SQ.M.

Location
Area of 100mm thk. Asphalt
Aplaya Compound 0.00
#REF! #REF!
#REF! #REF!
#REF! #REF!
#REF! #REF!
Total Area #REF!

Designation No. Person No. of Days Daily Rate Amount

A. Labor
a. Construction Foreman 1 #REF! 524.00 #REF!
b. Skilled Worker 6 #REF! 366.00 #REF!
c. Laborers 12 #REF! 317.00 #REF!

Sub-Total for A P #REF!

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment
a. Asphalt Paver (80 Hp) 1 #REF! 14,664.00 #REF!
b. Pneumatic Roller (10 m.t.) 1 #REF! 4,424.00 #REF!
c. Tandem Steel Roller (10.1 m.t.) 1 #REF! 13,216.00 #REF!
d. Dump Truck (10 cu.m.) 2 #REF! 10,816.00 #REF!
e. Asphalt Batch Plant (60-80 TPH) 1 #REF! 9,717.84 #REF!
f. Water Truck (1000 gal.) 1 #REF! 8,520.00 #REF!
g. Payloader (1.50 cu.m.) 1 #REF! 13,864.00 #REF!
Minor Tools (10% of Labor) #REF!
Sub-Total for B P #REF!
C. Total (A+B) #REF!
D. Output per day = 685.20 SQ.M./DAY

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials
Aplaya Compound
a. Asphalt Cement (6.5%) 0.00 m.t. 50,775.00 -
b. Aggregates (93%) 0.00 cu.m. 1,000.00 -
c. Mineral Filler (7%) 0.00 bags 245.00 -
(w/ 5% wastage)

#REF!
a. Asphalt Cement (6.5%) #REF! m.t. 50,775.00 #REF!
b. Aggregates (93%) #REF! cu.m. 1,000.00 #REF!
c. Mineral Filler (7%) #REF! bags 245.00 #REF!
(w/ 5% wastage)
Sub-Total for E P #REF!
F. Direct Cost (C+E) #REF!
G. Overhead, Contingencies & Miscellaneous 9% per D.O. 22 s 2015 #REF!
H. Contractor's Profit (CP) 8% per D.O. 22 s 2015 #REF!
I. Value Added Tax (VAT) 5% per D.O. 22 s 2015 #REF!
J. Total Cost #REF!
k. Total Unit Cost #REF!
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME: #REF!

### #REF!

Item No./Description: 310(b) BITUMINOUS CONCRETE SURFACE COURSE (150 mm. Thk.)
Unit of Measurement: SQ.M.
Output per day: 456.80 SQ.M./DAY
Quantity: #REF! SQ.M.

Area of 150mm thk.


Location
Asphalt
Aplaya Compound 0.00
### #REF!
### #REF!
### #REF!
### #REF!
Total Area #REF!

Designation No. Person No. of Days Daily Rate Amount

A. Labor
a. Construction Foreman 1 #REF! 524.00 #REF!
b. Skilled Worker 6 #REF! 366.00 #REF!
c. Laborers 12 #REF! 317.00 #REF!

Sub-Total for A P #REF!

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment
a. Asphalt Paver (80 Hp) 1 #REF! 14,664.00 #REF!
b. Pneumatic Roller (10 m.t.) 1 #REF! 4,424.00 #REF!
c. Tandem Steel Roller (10.1 m.t.) 1 #REF! 13,216.00 #REF!
d. Dump Truck (10 cu.m.) 2 #REF! 10,816.00 #REF!
e. Asphalt Batch Plant (60-80 TPH) 1 #REF! 9,717.84 #REF!
f. Water Truck (1000 gal.) 1 #REF! 8,520.00 #REF!
g. Payloader (1.50 cu.m.) 1 #REF! 13,864.00 #REF!
Minor Tools (10% of Labor) #REF!
Sub-Total for B P #REF!
C. Total (A+B) #REF!
D. Output per day = 456.80 SQ.M./DAY

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials
#REF!
a. Asphalt Cement (6.5%) #REF! m.t. 50,775.00 #REF!
b. Aggregates (93%) #REF! cu.m. 1,000.00 #REF!
c. Mineral Filler (7%) #REF! bags 245.00 #REF!
(w/ 5% wastage)

#REF!
a. Asphalt Cement (6.5%) #REF! m.t. 50,775.00 #REF!
b. Aggregates (93%) #REF! cu.m. 1,000.00 #REF!
c. Mineral Filler (7%) #REF! bags 245.00 #REF!
(w/ 5% wastage)

Sub-Total for E P #REF!


F. Direct Cost (C+E) #REF!
G. Overhead, Contingencies & Miscellaneous 9% per D.O. 22 s 2015 #REF!
H. Contractor's Profit (CP) 8% per D.O. 22 s 2015 #REF!
I. Value Added Tax (VAT) 5% per D.O. 22 s 2015 #REF!
J. Total Cost #REF!
k. Total Unit Cost #REF!
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME: #REF!

### #REF!
Item No./Description: 310(b) 8" BITUMINOUS CONCRETE SURFACE COURSE (200 mm. Thk.)
Unit of Measurement: SQ.M.
Output per day: 1,370.40 SQ.M./DAY
Quantity: #REF! SQ.M.

Location Area of 200mm


thk. Asphalt
Aplaya Compound 0.00
### #REF!
### #REF!
### #REF!
Total Area #REF!

Designation No. Person No. of Days Daily Rate Amount

A. Labor
a. Construction Foreman 1 #REF! 524.00 #REF!
b. Skilled Worker 24 #REF! 366.00 #REF!
c. Laborers 48 #REF! 317.00 #REF!

Sub-Total for A P #REF!

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment
a. Asphalt Paver (80 Hp) 4 #REF! 14,664.00 #REF!
b. Pneumatic Roller (10 m.t.) 4 #REF! 4,424.00 #REF!
c. Tandem Steel Roller (10.1 m.t.) 4 #REF! 13,216.00 #REF!
d. Dump Truck (10 cu.m.) 8 #REF! 10,816.00 #REF!
e. Asphalt Batch Plant (60-80 TPH) 4 #REF! 9,717.84 #REF!
f. Water Truck (1000 gal.) 4 #REF! 8,520.00 #REF!
g. Payloader (1.50 cu.m.) 4 #REF! 13,864.00 #REF!
Minor Tools (10% of Labor) #REF!
Sub-Total for B P #REF!
C. Total (A+B) #REF!
D. Output per day = 1,370.40 SQ.M./DAY

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials
Baliwasan Road
a. Asphalt Cement (6.5%) #REF! m.t. 50,775.00 #REF!
b. Aggregates (93%) #REF! cu.m. 1,000.00 #REF!
c. Mineral Filler (7%) #REF! bags 245.00 #REF!
(w/ 5% wastage)

Sub-Total for E P #REF!


F. Direct Cost (C+E) #REF!
G. Overhead, Contingencies & Miscellaneous 9% per D.O. 29 s 2011 #REF!
H. Contractor's Profit (CP) 8% per D.O. 29 s 2011 #REF!
I. Value Added Tax (VAT) 12% per D.O. 29 s 2011 #REF!
J. Total Cost #REF!
k. Total Unit Cost #REF!
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME: #REF!

#REF! ###
Item No./Description: SPL-15 CONSTRUCTION OF VALVE BOX
Unit of Measurement: UNIT
Output per day: 0.40 UNIT/DAY
Quantity: 1.00 UNITS

Designation No. Person No. of Days Daily Rate Amount

A. Labor
a. Construction Foreman 1 2.5 524 1,310.00
b. Skilled Worker 4 2.5 366.00 3,660.00
c. Laborers 4 2.5 317.00 3,170.00

Sub-Total for A P 8,140.00

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment
a. Concrete Mixer 1 2.50 1,376.00 3,440.00
b. Concrete Vibrator 1 2.50 1,192.00 2,980.00
c. Welding Machine 1 2.50 3,128.00 7,820.00
Minor Tools (10% of Labor) 814.00
Sub-Total for B P 15,054.00
C. Total (A+B) 23,194.00
D. Output per day = 0.40 UNIT/DAY

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials
a. Cement 3.00 bags 260.00 780.00
b. Sand 1.50 cu.m. 1,000.00 1,500.00
c. Gravel 2.00 cu.m. 1,000.00 2,000.00
d. *16mmØ x 6.0 Reinforcing Steel Bar 30.00 pcs. 337.00 10,110.00
e. #16 GI Tie Wire 4.00 pcs. 75.00 300.00
f. *4mm thk. X 50mm x 50mm x 6mm MS Angle Bar 1.00 pc. 1,045.00 1,045.00
g. *16mmØ x 6.00m Stainless Steel Rod 2.00 pcs. 2,325.07 4,650.14
h. 150mmØ x 6.00m PVC Pipe, Class 150, w/ B/S & R.R. 1.00 pc. 4,609.50 4,609.50
i. 1m x 1.50m D.I. Rectangular Manhole Frame Double Cover, Light Series 1.00 pc. 71,500.00 71,500.00
j. 6011 Welding Rod 1.00 kg. 144.00 144.00
k. *1/2" Ordinary Plywood - 2 uses 5.00 sheets 950.00 4,750.00
l. 30 pcs. -2" x 3" x 10' Coco Lumber - 2 uses 150.00 bd.ft 20.00 3,000.00
m. 4" C.W. Nail 3.00 kgs. 80.00 240.00
n. Stainless Welding Rod 0.25 kg. 340.00 85.00
o. Hacksaw Blade 3.00 pcs. 56.00 168.00
p. *12mmØ x 6.0 Reinforcing Steel Bar 5.00 pcs. 266.00 1,330.00
q. *10mmØ x 6.0 Reinforcing Steel Bar 17.00 pcs. 130.00 2,210.00
r. *12mmØ x 6.00m MS Plain Round Bar 1.00 pc. 260.00 260.00

* ALL SIZES REFERRED HEREIN SHOULD MEAN COMMERCIALLY AVAILABLE


MEASUREMENTS TOLERANCE OF ± 1mm

Sub-Total for E P 108,681.64


F. Direct Cost (C+E) 131,875.64
G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011 7,912.54
H. Contractor's Profit (CP) 8% per D.O. 29 s 2011 10,550.05
I. Value Added Tax (VAT) 12% per D.O. 29 s 2011 18,040.59
J. Total Cost 168,378.81
k. Total Unit Cost 168,378.81
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME: ###


#REF! ###
Item No./Description: SPL-16 LAYING 50mmØ P.E. TUBING, SDR 11 FEEDERLINE
Unit of Measurement: LN.M.
Output per day: 20.62 LN.M./DAY
Quantity: 120.00 LN.M.

Designation No. Person No. of Days Daily Rate Amount

A. Labor
a. Construction Foreman 1 5.82 366.00 2,130.12
b. Laborers 8 5.82 317.00 14,759.52
c. Pipefitter 1 5.82 341.00 1,984.62

Sub-Total for A P 18,874.26

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment

Sub-Total for B P -
C. Total (A+B) 18,874.26
D. Output per day = 20.62 LN.M./DAY

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials
a. 50mm.Ø x 60m P.E. Tubing, SDR 11 2 rolls 10,713.00 21,426.00

Sub-Total for E P 21,426.00


F. Direct Cost (C+E) 40,300.26
G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011 2,418.02
H. Contractor's Profit (CP) 8% per D.O. 29 s 2011 3,224.02
I. Value Added Tax (VAT) 12% per D.O. 29 s 2011 5,513.08
J. Total Cost 51,455.37
k. Total Unit Cost 428.79
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME: #REF!

#REF! ###
Item No./Description: SPL-10 BRIDGE CROSSING
Unit of Measurement: LN.M.
Output per day: 3.00 LN.M. /day
Quantity: 190.00 LN.M.

Designation No. Person No. of Days Daily Rate Amount

A. Labor
a. Pipefitter 3 63.33 394.00 74,860.00
b. Skilled Worker 9 63.33 366.00 208,620.00
c. Laborer 18 63.33 317.00 361,380.00

Sub-Total for A P 644,860.00

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment
a. Generator Set/ Welding Machine w/ complete accessories (w/ fuel) 3 63.33 2,160.00 410,400.00
b. Boom Truck 3 63.33 9,600.00 1,824,000.00
c. Cut-off Saw 3 63.33 200.00 38,000.00

Sub-Total for B P 2,272,400.00


C. Total (A+B) 2,917,260.00
D. Output per day = 3.00 LN.M. /day

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials
a. 190.00 ln.m. 95,856.00 18,212,640.00
b. 6mm Thk x 50mm x 50mm x 6.00m MS Angle Bar 373.67 pcs. 1,123.00 419,627.67
c. 12mmØ x 6.00m MS Plain Round Bar 76 pcs. 146.00 11,096.00
d. 12mmØ x 75mm S.S. Bolt w/ Nut & Washer 1520 pcs. 65.00 98,800.00
e. 6mm Thk x 50mm x 6.00m MS Flat Bar 95 pcs. 894.00 84,930.00
f. Welding Rod (6011) 28.5 kgs. 145.00 4,132.50
g. Cut-Off Saw Wheel 19 pcs. 200.00 3,800.00
h. Red Oxide Metal Primer 26.6 gals 480.00 12,768.00
i. Quick Dry Enamel (Royal Blue) 26.6 gals 558.80 14,864.08
j. Paint Thinner 13.3 gals 480.00 6,384.00
k. 4" Paint Brush 6.65 pcs. 50.00 332.50
l. Portland Cement 532 bags 240.00 127,680.00
m. Washed Sand 26.01 cu.m. 1,000.00 26,008.89
n. Gravel 52.02 cu.m. 1,000.00 52,017.78
o. 16mmØ x 6.00m Deformed Reinf. Steel Bar 17472.00 kgs. 45.50 794,976.00
p. 12mm Thk x 1.20m x 2.40m Ordinary Plywood 128.00 shts. 750.00 96,000.00
q. 2" x 2" x 8' Coco Lumber 5937.5 bd.ft. 20.00 118,750.00
r. 1-1/2" C.W. Nail 17.81 kg. 65.00 1,157.81
s. 3" C.W. Nail 41.56 kg. 65.00 2,701.56

Sub-Total for E P 20,088,666.79


F. Direct Cost (C+E) 23,005,926.79
G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011 1,380,355.61
H. Contractor's Profit (CP) 8% per D.O. 29 s 2011 1,840,474.14
I. Value Added Tax (VAT) 12% per D.O. 29 s 2011 3,147,210.78
J. Total Cost 29,373,967.32
k. Total Unit Cost 154,599.83

You might also like