WTP WI Stick Diagram R4

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 3

Last Issue: 15-May-21

Rev: 0
FL3B PROJECT Internal

WATER TREATMENT PLANT STICK DIAGRAM

Pipe Sleeper Land Side Start Finish Pipe Sleeper River Side Start Finish
QTY - Pile 900 NOS QTY - Bore Pile D500 16 NOS
WTP & WI
15/Apr/2021 04/May/2021
15/Apr/2021 14/Jul/2021 Bore Piling General Start Finish
Piling 7/Jun/21 20/Jun/21
7/Apr/21 07/Jul/21 30/Apr/2021 15/Jul/2021 NTP - 10/Dec/20
Pipe Sleeper
30/Apr/2021 06/01/2022 15/Nov/21 15/Dec/21 15/04/2021 30/Jul/2021
Pipe Sleeper Piling
4/Jun/21 30/Dec/21 ETA at Site 30/Apr/21 7/Apr/21 27/jul/21
ETA at Site 30/Apr/21 Piping Fabrication & 01/Jun/2021 14/Aug/21 30/Apr/2021 09/Feb/2022
Civil Work
Piping Fabrication & 01/Jun/2021 07/03/2022 Installation 18 /Feb/22 19/Mar/22 4/Jun/21 16/Mar/22
Installation 24/May/21 29/Mar/22 29/Sep/2021 10/Mar/2022
Equipment - Mechanical
15/Sep/21 26/Mar/22
01/06/2021 30/Mar/2022
Piping Fabrication & Installation
24/Jun/21 30/Mar/22
25/11/2021
EIA Work 25/Apr/22
19/Nov/21
27/10/2021 20/04/2021
HVAC
19/Nov/21 20/Apr/22
14/Jan/2022 13/Apr/2022 UHRSCC 1 & 2 Start
Insulation Work EL./ Grid. +94.000
20/Jan/21 19/Apr/22
11/04/2022 09/Jun /2022 QTY - Pile 242 NOS
Check Out
24/Feb/22 20/May/22 15/Apr/2021
11/05/2022 09/07/2022 Piling
Comissioning 26/May/21
21/May/22 9/Jul/22 01/06/2021
Start Up 10/Jun/22 10/Jul/22 Civil Work
30/Jun/21
Main equipment at site Start Finish
ETA at Site
Shipment 1 (Anchor bolts,
embedded plates,Auto 08/07/2021 01/Dec/2021
Backwash 8/Sep/21 Mechanical Start
27/Dec/21
Strainner,Agitator, Media) 19/9/2021
Piping Installation
20/Jan/22
Shipment 2 (Dosing
Pump,Centifugal 07/08/2021 FP (Filter Pak) Start
pump,Tanks,Valves,Piping,I 23/Sep/21 EL./ Grid. +97.120
nstrument) QTY - Pile 144 NOS
06/09/2021 26/May/2021
Shipment 3 (Filter Pack) Piling
25/Oct/21 7/Jul/21
06/09/2021 14/06/2021
Shipment 4 (UHRSCC) Civil Work
9/Nov/21 19/Jul/21

Pump Station (WI Area) Start Finish IFC ETA at Site


MCC Room (WI Area) Start Finish Platform 31/12/2021
QTY - Bore Pile D500 12 NOS QTY - Steel Pile D508 21 NOS
Mechanical Start
17/Jan/22
06/May/2021 22/05/2021 15/Apr/2021 30/Apr/2021 19/9/2021
Piling Piling 30/May/21 Piping Installation
22/May/21 07/Jun/21 14/Jun/21 1/Jul/21 20/Jan/22
29/May/2021 25/Sep/2021 Fender
Civil Work
8/Jun/21 14/Nov/21 QTY - Steel Pile D400 13 NOS
01/May/2021 04/May/2021 FWR (Filter Water
Piling 24/May/21 Start
14/Jun/21 01/Jul/21 Reservoir)
24/May/2021 21/Aug/2021
Civil Work 14/Jun/21 EL./ Grid. +99.480
2/Jul/21 29/Sep/21
18/10/2021 01/11/2021 QTY - Pile 512 NOS
ETA at Site 29/May/2021
26/Nov/21 29/Dec/21 Piling
25/Oct/2021 18/Nov/2021 26/Jun/21
Mechanical Start 14/Jun/2021
13/Dec/21 06/Jan/21
Civil Work
09/Nov/2021 08/Dec/2021 17/Aug/21
Piping Fabrication & Installation
18/feb/22 19/Mar/22
ETA at Site
Mechanical Start
19/9/2021
Piping Installation
20/Jan/22

Pipe Rack (ISBL) S


Spread Footing
Civil Work 15/Se
Module Assembly
Module Erection
Piping Erection
E&I Installation

Checked by: YA, DPK, EDP, SP, JMD


Prepared by: SPS Page 1 of 3 Approved by: ALB
Last Issue: 15-May-21
Rev: 0
FL3B PROJECT Internal

WATER TREATMENT PLANT STICK DIAGRAM

MCC Room (WTP Area) Start Finish IFC


QTY - Pile 20 NOS
08/May/2021 12/May/2021
Piling 30/May/21
8/Jun/21 12/Jun/21
08/Aug/2021 05/12/2021
Civil Work 7/Jun/21
8/Jul/21 4/Nov/21

DEMIN PLANT Pumping Station Start Finish IFC


EL./ Grid.
QTY - Pile
Piling
01/Oct/2021 29/Nov/2021
Civil Work 15/Jul/21
27/Oct/21 25/Dec/21
UHRSCC 1 & 2 Start Finish IFC 06/09/2021
ETA at Site
EL./ Grid. +94.000 29/Nov/21
30/Dec/22 3/01/2022
QTY - Pile 242 NOS Mechanical Start
12/Jan/21 16/Jan/22
15/Apr/2021 22/May/2021 20/Aug/21/ 01/Feb/2022
Piling 21/May/21 Piping Installation
26/May/21 29/Jun/21 31/Dec/21 29/Jan/22
01/06/2021 30/11/2021
Civil Work 30/May/21
Sludge Tank Start Finish IFC
30/Jun/21 26/Dec/21
06/09/2021 EL./ Grid. +94.500
23/Sep/21; QTY - Pile 12 NOS
ETA at Site
25/Oct/21; 27/May/2021 28/May/2021
Piling 8/Jul/21
9/Nov/21 15/Jul/21 16/Jul/21
01/Dec/2021 28/Feb/2022 15/Nov/2021 29/Dec/2021
Mechanical Start Civil Work 18/Jul/21
27/Dec/21 11/Mar/22 28/Nov/21 11/Jan/22
19/9/2021 30/04/2022 06/09/2021
Piping Installation ETA at Site
20/Jan/22 19/Apr/22 1/Jul/21
30/Dec/2021 3/Jan/22
Mechanical Start
26/Jan/22 26/Mar/22
FP (Filter Pak) Start Finish IFC
19/9/2021 30/04/2022
EL./ Grid. +97.120 Piping Installation
20/Jan/22 19/Apr/22
QTY - Pile 144 NOS
26/May/2021 22/Jun/2021
Piling 23/Jun/21 BWCT (Back Wash
7/Jul/21 27/Jul/21 Start Finish IFC
Collection Tank)
14/06/2021 09/Feb/2022
Civil Work 30/Jun/21 EL./ Grid. +89.370
19/Jul/21 16/Mar/22
QTY
07/08/2021
ETA at Site Piling 22/Jul/21 4/Aug/21 25/Jun/21
23/Sep/21
23/Jun/2021 30/Sep/2021
31/12/2021 10/03/2022 Civil Work 5/Jul/21
Mechanical Start 19/Jul/21 26/Oct/21
17/Jan/22 17/Mar/22 6/9/21
19/9/2021 30/04/2022 ETA at Site
Piping Installation 25/Oct/21
20/Jan/22 19/Apr/22 14/01/2021 18/01/2021
Mechanical Start
27/Jan/22 31/Jan/22
19/9/2021 30/04/2022
FWR (Filter Water Piping Installation
20/Jan/22 19/Apr/22
Start Finish IFC
Reservoir)
EL./ Grid. +99.480
Stilling Chamber Start Finish IFC
QTY - Pile 512 NOS EL./ Grid.
29/May/2021 30/Jul/2021 QTY - Pile 9 NOS
Piling 23/Jun/21
26/Jun/21 31/Jul/21 Piling
24/May/2021 26/May/2021
24/May/21
14/Jun/2021 09/Feb/2022 6/Jun/21 7/Jun/21
Civil Work 28/Jun/21 16/Sep/2021 14/Nov/2021
17/Aug/21 13/Apr/22 Civil Work 5/Jun/21
29/Sep/21 27/Nov/21
06/09/2021 06/09/2021
ETA at Site ETA at Site
23/Jul/21 25/Oct/21
Mechanical Start Mechanical Start 15/Nov/21 30/Nov/21
19/9/2021 30/04/2022 19/9/2021 30/04/2022
Piping Installation
Piping Installation 20/Jan/22 19/Apr/22
20/Jan/22 19/Apr/22

Pipe Rack (ISBL) Start Finish Cascade Aerator Start Finish IFC
Spread Footing EL./ Grid. +95.546
Civil Work 15/Sep/21 14/Dec/21 QTY - Pile 12 NOS
24/05/2021 26/May/2021
Module Assembly Piling 25/May/21
8/Jun/21 10/Jun/21
Module Erection
01/Jun/2021 15/Sep/2021
Piping Erection Civil Work 31/May/21
16/Jun/21 28/Sep/21
E&I Installation ETA at Site
Mechanical Start

Pipe Sleeper near Storage Start Finish

QTY - Bore Pile D500 28 NOS


26/05/2021 26/06/2021
Bore Piling
8/Jul/21 21/Jul/21
01/07/2021 30/09/2021
Pipe Sleeper
28/Jul/21 27/Oct/21
Piping Fabrication &
Installation

Checked by: YA, DPK, EDP, SP, JMD


Prepared by: SPS Page 2 of 3 Approved by: ALB
Last Issue: 15-May-21
Rev: 0
FL3B PROJECT Internal

WATER TREATMENT PLANT STICK DIAGRAM

Chemical Dosing Start Finish IFC


EL./ Grid. A-C/7-11
QTY
10/Oct/2021 10/Jan/2022
30/Jul/21
Civil Work 5/Aug/21 5/Nov/21
01/07/2021
ETA at Site 25/Oct/21
11/Jan/2022 17/Feb/2022
Mechanical Start 6/Nov/22 13/Dec/21
Piping Installation

Polymer Dosing Tank 1-2 Start Finish IFC Lime Dosing Tank 1-2 Start Finish IFC
EL./ Grid. A-B/7-9 EL./ Grid. A-B/9-11
QTY 2 NOS QTY 2 NOS
10/Oct/2021 10/Jan/2022 10/Oct/2021 10/Jan/2022
30/Jul/21 30/Jul/21
Eq. Foundation 5/Aug/21 5/Nov/21
Eq. Foundation 5/Aug/21 5/Nov/21
01/07/2021
01/07/2021
ETA at Site 25/Oct/21
11/Jan/2022 17/Feb/2022
ETA at Site 25/Oct/21
11/Jan/2022 17/Feb/2022
Mechanical Start 6/Nov/22 13/Dec/21
Mechanical Start 6/Nov/22 13/Dec/21
Piping Installation
Piping Installation

PAC Dosing Tank Start Finish IFC


NaOH Dosing Tank Start Finish IFC
EL./ Grid. B-C/8-11
EL./ Grid. B-C/7-8
QTY 3 NOS
QTY 1 NOS 10/Oct/2021 10/Jan/2022
10/Oct/2021 10/Jan/2022 30/Jul/21
30/Jul/21 Eq. Foundation 5/Aug/21 5/Nov/21
Eq. Foundation 5/Aug/21 5/Nov/21 01/07/2021
01/07/2021 ETA at Site 25/Oct/21
ETA at Site 25/Oct/21 11/Jan/2022 17/Feb/2022
11/Jan/2022 17/Feb/2022 Mechanical Start 6/Nov/22 13/Dec/21
Mechanical Start 6/Nov/22 13/Dec/21 Piping Installation
Piping Installation

Checked by: YA, DPK, EDP, SP, JMD


Prepared by: SPS Page 3 of 3 Approved by: ALB