LAPORAN HARIAN
DINAS PEKERJAAN UMUM HARI : MINGGU
DAN PENATAAN RUANG TANGGAL : 18 OKTOBER 2020 LEMBARAN
Alamat : Jl. Brigjen (Purn) Abraham O. Ataruri Komplek Kantor Gubernur Papua Barat, Arfai - Manokwari MINGGU KE : 1 KE - 7
BULAN KE : 1
I. ALAT UTAMA
- - - - - - 1 Tanah Timbunan - M3 - -
- - - - - 2 Tanah pilihan - - - -
- - Libur - - - WHELL LOADER - - - 3 Curing membran - Ltr - -
- EXCAVATOR - - - 4 Chipping - M3 - -
- DUMP TRUCK - - - 5 - - - - -
- WATER TANK - - - 6 Aspal - Kg - -
- - MOTOR GRADER - - - 7 Kerosene - Ltr - -
- VIBRO ROLLER - - - 8 Agregat Kasar - M3 - -
- - - - - - P. TYRE ROLLER - - - 9 Agregat Halus - M3 - -
- PULVI MEIXER - - - 10 - - - - -
- - - - - - ASP. DISTRIBUTOR - - - 11 - - - - -
- 3-WHELL ROLLER - - - 12 Baja Tulangan - Kg - -
(Polos) U24
- - - - - - ASP. SPRAYER - - - 13 Kawat Beton - Kg - -
- CONC. MIXER - - - 14 Batu Pondasi - M3 - -
- - - - - - TRUCK. MIXER - - - 15 Pasir Pasang - M3 - -
II. ALAT BANTU
- - - - - 6 Cerek Aspal - - -
- - - - - 7 Kaleng Aspal - - -
- 1 - - - - 8 Linggis - - -
2 - - - - 9 Sekop - - -
- - - - - 3 Sapu - - - 10 Garpu - - -
4 Sikat - - - 11 Gergaji listrik - - -
5 Karung - - -
- - - - - C. PENGGUNAAN DAN KONDISI PERALATAN
C.1 PENGGUNAAN AKTIF C.2 KONDISI PERALATAN
KONDISI
NO. JENIS ALAT AKTIF UNIT LOKASI NO. JENIS ALAT
IDLE RUSAK
- - - - - - - - -
- - - - - - - -
- - - - - - WHELL LOADER - WHELL LOADER
- EXCAVATOR - EXCAVATOR
- - - - - - DUMP TRUCK - DUMP TRUCK
- WATER TANK - WATER TANK
- MOTOR GRADER - MOTOR GRADER
- - - VIBRO ROLLER - VIBRO ROLLER
- P. TYRE ROLLER - P. TYRE ROLLER
- - - - - - PULVI MEIXER - PULVI MEIXER
- ASP. DISTRIBUTOR - ASP. DISTRIBUTOR
- - - - - - 3-WHELL ROLLER - 3-WHELL ROLLER
- ASP. SPRAYER - ASP. SPRAYER
- - - - - - CONC. MIXER - CONC. MIXER
- TRUCK. MIXER - TRUCK. MIXER
08 - 09
09 - 10
10 - 11
11 - 12
12 - 13
13 - 14
14 - 15
15 - 16
16 - 17
17 - 18
NO. KONDISI
- - - - JUMLAH
- - - -
1 - - - - - - - - - - - - - - - - -
2 - - - - - - - - - - - - - - - - -
3 - - - - - - - - - - - - - - - - -
4 - - - - - - - - - - - - - - - - -
5 Pelaksana Lapangan E.2 KEJADIAN PENGHAMBAT PEKERJAAN
6 Logistik
7 Mekanik
8 Pembantu Mekanik
9 Operator
10 Pembantu Operator
11 Sopir
12 Pembantu Sopir
13 Pekerja -
14 Tukang -
14 Mandor -
F. USULAN / SARAN / PENGAJUAN / INSTRUKSI / KESEPAKATAN / PELAPORAN Tanda Tangan dan Nama yang Jelas
PIHAK PENYEDIA :
PIHAK KONSULTAN :
PIHAK DIREKSI :
DRAFT CONTRAC CHANGE ORDER (CCO)
NOMOR PAKET KONTRAK : 080.A
PAKET : PENINGKATAN JALAN AYAMARU - SAUF - WEHALI - BATAS KABUPATEN SORONG SELATAN
KONTRAKTOR PELAKSANA: PT. SINAR MAROS
NOMOR KONTRAK : 080.A/KONTR/07.17-BM/059/600/2018
TANGGAL KONTRAK : 10 SEPTEMBER 2018
NILAI KONTRAK : Rp. 4.639.000.000,-
KONSULTAN SUPERVISI : PT. MISHELLA CHARITAS PRATAMA
MINGGU KE : 03
PERIODE : 1 OKTOBER s/d 7 OKTOBER 2018
87,002,296.14 - - 87,002,296.14
(A) Jumlah Harga Pekerjaan ( termasuk Biaya Umum dan Keuntungan ) 4,217,854,847.11 544,913,030.70 544,913,030.70 4,217,854,847.11
(B) Pajak Pertambahan Nilai ( PPN ) = 10% x (A) 421,785,484.71 54,491,303.07 54,491,303.07 421,785,484.71
(C) JUMLAH TOTAL HARGA PEKERJAAN = (A) + (B) 4,639,640,331.82 599,404,333.77 599,404,333.77 4,639,640,331.82
(D) JUMLAH TOTAL HARGA PEKERJAAN DIBULATKAN = (A) + (B) 4,639,000,000.00 599,000,000.00 599,000,000.00 4,639,000,000.00
DILAPORKAN OLEH,
KONSULTAN SUPERVISI
PT. MISHELLA CHARITAS PRATAMA
BARTJE F. TITALEY, ST
Supervisi Engineer
BULAN : NOPEMBER 2018
LAPORAN BULANAN
PERIODE : 29 Oktober 2018 s/d
PEMERINTAH PROVINSI PAPUA BARAT 11 November 2018
DINAS PEKERJAAN UMUM KONTRAKTOR : PT. SINAR MAROS
RENCANA REALISASI
NO. KONTRAK ADDENDUM I
S/D RENCANA S/D S/D PRESTASI S/D
MATA DEVIASI
URAIAN SAT. BULAN LALU BULAN INI BULAN INI BULAN LALU BULAN INI BULAN INI KET.
PEMBA
YARAN BOBOT BOBOT BOBOT BOBOT BOBOT BOBOT BOBOT BOBOT
VOLUME VOLUME VOLUME VOLUME VOLUME VOLUME VOLUME VOLUME
(%) (%) (%) (%) (%) (%) (%) (%) (%)
DIVISI 1. UMUM
1.2 Mobilisasi Ls 1.00 2.63 1.00 2.63 0.50 1.32 0.20 0.52 0.70 1.84 0.50 1.32 - - 0.50 1.32 (0.52)
DIVISI 7. STRUKTUR
7.1(7)(a) Beton Mutu Sedang fc'20 Mpa M3 6.75 0.45 6.75 0.45 6.75 0.45 - - 6.75 0.45 6.75 0.45 - - 6.75 0.45 -
7.3(1) Baja Tulangan U 24 Polos Kg 742.50 0.33 742.50 0.33 742.50 0.33 - - 742.50 0.33 742.50 0.33 - - 742.50 0.33 -
7.9(1) Pasangan Batu M3 32.86 1.28 32.86 1.28 32.86 1.28 - - 32.86 1.28 32.86 1.28 - - 32.86 1.28 -
JUMLAH BOBOT PEKERJAAN (%) 100.00 100.00 28.97 30.55 59.51 31.40 43.84 75.24 15.72
BOBOT BULAN INI ( % )
a. RENCANA 59.51
b. REALISASI 75.24
c. DEVIASI = ( b ) - ( a ) 15.72
HERI G. N. SAFLEMBOLO, ST, MT YESAYA JITMAU, ST, MT BARTJE F. TITALEY, ST RADIUS PRIBADI, ST
NIP. 1970 0927 1992 03 1 009 NIP. 1974 0623 2000 121 004 Supervision Engineer Site Manager
BULAN : NOPEMBER 2018
LAPORAN MINGGUAN
MINGGU KE - :7
PEMERINTAH PROVINSI PAPUA BARAT PERIODE : 29 Oktober 2018 s/d
DINAS PEKERJAAN UMUM 04 November 2018
RENCANA REALISASI
NO. KONTRAK ADDENDUM I
S/D RENCANA S/D S/D PRESTASI S/D
MATA DEVIASI
URAIAN SAT. MINGGU LALU MINGGU INI MINGGU INI MINGGU LALU MINGGU INI MINGGU INI KET.
PEMBA
YARAN BOBOT BOBOT BOBOT BOBOT BOBOT BOBOT BOBOT BOBOT
VOLUME VOLUME VOLUME VOLUME VOLUME VOLUME VOLUME VOLUME
(%) (%) (%) (%) (%) (%) (%) (%) (%)
DIVISI 1. UMUM
1.2 Mobilisasi Ls 1.00 2.63 1.00 2.63 0.50 1.32 - - 0.50 1.32 0.50 1.32 - - 0.50 1.32 -
DIVISI 7. STRUKTUR
7.1(7)(a) Beton Mutu Sedang fc'20 Mpa M3 6.75 0.45 6.75 0.45 6.75 0.45 - - 6.75 0.45 6.75 0.45 - - 6.75 0.45 -
7.3(1) Baja Tulangan U 24 Polos Kg 742.50 0.33 742.50 0.33 742.50 0.33 - - 742.50 0.33 742.50 0.33 - - 742.50 0.33 -
7.9(1) Pasangan Batu M3 32.86 1.28 32.86 1.28 32.86 1.28 - - 32.86 1.28 32.86 1.28 - - 32.86 1.28 -
JUMLAH BOBOT PEKERJAAN (%) 100.00 100.00 28.97 14.86 43.83 31.40 28.48 59.88 16.05
BOBOT MINGGU INI ( % )
a. RENCANA 43.83
b. REALISASI 59.88
c. DEVIASI = ( b ) - ( a ) 16.05
100
DIVISI 1. UMUM KURVA
1.2 Mobilisasi Ls 111,050,000.00 1.0 111,050,000.00 2.63 1.0 111,050,000.00 2.63 0.79 0.53 - - - - KURVA- 0.52 - - - 99.21
- 0.79
100.00
RENCANA
0.79 0.53 - - - - -
REALISASI - - - - - - 90
DIVISI 3. PEKERJAAN TANAH ADDENDUM I
ADDENDUM I
3.1.(2) Galian Batu M3 232,154.63 - - 1,365.0 316,891,069.95 7.51 - - 0.88 0.88 5.75 - - - - - -
87.49 - -
- - - 1.90 2.38 3.23 - - - - - - - 80
3.2(2a) Timbunan Pilihan dari sumber galian M3 425,866.46 640.5 272,775,984.96 6.47 994.0 423,308,760.38 10.04 - - 1.62 1.62 1.61 5.19 - 75.24
- - - - - -
- - - - 2.48 3.51 4.04 - - - - - -
3.3.(1) Penyiapan Badan Jalan M3 1,075.33 - - 10,896.8 11,717,613.85 0.28 - - 0.00 0.00 0.00 0.27 - - - 75.78
- - - - 70
- - - 0.12 0.16 - - - - - - KURVA
- -
3.4(1) Pembersihan dan Pengupasan Lahan M3 4,312.92 6,000.0 25,877,520.00 0.61 12,712.9 54,829,667.44 1.30 - 0.13 0.31 0.51 0.35 - 59.88
- - - - - RENCANA
- -
- 0.13 0.22 0.16 0.10 0.69 - - - - - - - 60
KONTRAK
DIVISI 5. PEKERJAAN BERBUTIR
5.4.(1) Semen untuk Lapis Pondasi Semen Tanah Ton 3,546,673.11 172.8 612,865,113.41 14.53 178.2 632,017,148.20 14.98 - - - - 0.45 2.91 2.91 2.91 57.92
2.91 2.89 - AWAL- -
- - - - - 6.73 7.74 0.52 - - - - - 50
5.4.(2) Lapis Pondasi Semen Tanah M3 392,608.65 1,440.0 565,356,456.00 13.40 1,485.0 583,023,845.25 13.82 - - - - 0.42 2.68 2.68 2.68 2.68 2.69 - - -
- - - - - 6.21 7.14 0.48 - - - - -
DIVISI 6. PERKERASAN ASPAL 40
6.1(1)(a) Lapis Resap Pengikat - Aspal Cair Liter 15,499.14 12,600.0 195,289,164.00 4.63 9,900.0 153,441,486.00 3.64 - - - - - - 0.44 0.73 0.73 0.55 0.73 0.44 -
- - - - - 31.40
- 0.73
40.04
1.10 - - - - -
6.6(1) Lapis Permukaan Penetrasi Macadam M3 3,726,410.02 630.0 2,347,638,312.60 55.66 495.0 1,844,572,959.90 43.73 - - - - - - 8.83 8.83 8.39 6.18 6.89 4.59 - 30
-
KURVA - - - - - 8.83 13.25 - - - - -
DIVISI 7. STRUKTUR REALISASI
7.1(7)(a) Beton Mutu Sedang fc'20 Mpa M3 2,825,600.64 6.8 19,072,804.32 0.45 6.8 19,072,804.32 0.45 -
KONTRAK AWAL - - - 0.45 - - - - - - - - 20
- - - - - 0.45 21.24
- - - - - - -
7.3(1) Baja Tulangan U 24 Polos Kg 18,924.40 742.5 14,051,367.00 0.33 742.5 14,051,367.00 0.33 -
-
-
-
-
-
-
-
9.44
0.33
-
-
15.65
0.33
-
-
-
-
-
-
-
-
-
-
-
-
-
- 10
7.9(1) Pasangan Batu M3 1,639,626.44 32.9 53,878,124.82 1.28 32.9 53,878,124.82 1.28 - - - 3.85
0.64 0.64
10.06
- - - - - - - -
0.00 0.79
- 1.44
- 1.66
- - 0.47 0.81 - - - - - - -
7.03
3.15 4.77 0
0.00 0.92
(A) Jumlah Harga Pekerjaan ( termasuk Biaya Umum dan Keuntungan ) 4,217,854,847.11 100.00 4,217,854,847.11 100.00
(B) Pajak Pertambahan Nilai ( PPN ) = 10% x (A) 421,785,484.71 421,785,484.71
(C) Jumlah Total Harga Pekerjaan = (A) + (B) 4,639,640,331.82 4,639,640,331.82
(D) Rekapitulasi Harga (Dibulatkan) 4,639,640,300.00 4,639,640,300.00
Bobot Kemajuan Pekerjaan Mingguan (%) 0.00 0.92 2.23 1.62 2.26 3.03 5.59 5.59 18.80 17.88 17.87 11.71 11.71 0.79
RENCANA
Bobot Kemajuan Kumulatif Pekerjaan Mingguan (%) 0.00 0.92 3.15 4.77 7.03 10.06 15.65 21.24 40.04 57.92 75.78 87.49 99.21 100.00
Bobot Kemajuan Pekerjaan Mingguan (%) 0.00 0.79 0.65 2.81 3.66 10.01 11.04 14.86 15.68 14.72 12.31 7.63 5.04 0.79
RENCANA
Bobot Kemajuan Kumulatif Pekerjaan Mingguan (%) 0.00 0.79 1.44 4.26 7.92 17.93 28.97 43.83 59.51 74.23 86.54 94.17 99.21 100.00
ADDENDUM I REALISASI
Bobot Kemajuan Pekerjaan Mingguan (%) 0.00 0.79 0.65 0.22 2.18 5.59 21.96 28.48 15.36
Bobot Kemajuan Kumulatif Pekerjaan Mingguan (%) 0.00 0.79 1.44 1.66 3.85 9.44 31.40 59.88 75.24
HERI G. N. SAFLEMBOLO, ST, MT YESAYA JITMAU, ST, MT BARTJE F. TITALEY, ST RADIUS PRIBADI, ST
NIP. 1970 0927 1992 03 1 009 NIP. 1974 0623 2000 121 004 Supervisi Engineer Site Manager
PEMERINTAH PROVINSI PAPUA BARAT
DINAS PEKERJAAN UMUM
DAN PENATAAN RUANG
Alamat : Jl. Brigjen (Purn) Abraham O. Ataruri Komplek Kantor Gubernur Papua Barat, Arfai - Manokwari LAPORAN HARIAN
NOMOR PAKET : 080.A HARI : SENIN
PAKET : PENINGKATAN JALAN SAUF - WEHALI TANGGAL : 12 OKTOBER 2020 LEMBARAN
KONTRAKTOR PELAKSANA PT. SINAR MAROS MINGGU KE : 1.0 KE - 1
NOMOR KONTRAK : 080.A/KONTR/07.17-BM/059/600/2018 BULAN KE : 1.0
TANGGAL KONTRAK : 17 SEPTEMBER 2018
NILAI KONTRAK : Rp. 4.634.000.000,-
NOMOR ADDENDUM I : 080.A/ADD-I/07.17-BM/059/600/2018
TANGGAL ADDENDUM I : 01 OKTOBER 2018
NILAI ADDENDUM I : Rp. 4.634.000.000,-
KONSULTAN SUPERVISI : PT. MISHELLA CHARITAS PRATAMA
08 - 09
09 - 10
10 - 11
11 - 12
12 - 13
13 - 14
14 - 15
15 - 16
16 - 17
17 - 18
NO. KONDISI
1 Pejab. Pemb. Komit. ........ ........ JUMLAH
2 Pejab. Pelak. Tek. Keg. ........ ........
3 Supervisi Engineer ........ ........ 1 CERAH ........... ........... ........... ........... ........... ........... ........... ........... ........... ........... ........... ...........
4 Inpespector ........ ........ 2 MENDUNG ........... ........... ........... ........... ........... ........... ........... ........... ........... ........... ........... ...........
5 Site Manager ........ ........ 3 GERIMIS ........... ........... ........... ........... ........... ........... ........... ........... ........... ........... ........... ...........
6 Pelaksana Lapangan ........ ........ 4 HUJAN LEBAT ........... ........... ........... ........... ........... ........... ........... ........... ........... ........... ........... ...........
7 Logistik ........ ........ E.2 KEJADIAN PENGHAMBAT PEKERJAAN
8 Mekanik ........ ........
9 Pembantu Mekanik ........ ........
10 Operator ........ ........
11 Pembantu Operator ........ ........
12 Sopir ........ ........
13 Pembantu Sopir ........ ........
F. USULAN / SARAN / PENGAJUAN / INSTRUKSI / KESEPAKATAN / PELAPORAN Tanda Tangan dan Nama yang Jelas
PIHAK PENYEDIA :
PIHAK KONSULTAN :
PIHAK DIREKSI :
PEMERINTAH PROVINSI PAPUA BARAT
DINAS PEKERJAAN UMUM
DAN PENATAAN RUANG
Alamat : Jl. Brigjen (Purn) Abraham O. Ataruri Komplek Kantor Gubernur Papua Barat, Arfai - Manokwari LAPORAN HARIAN
FOTO DOKUMENTASI
NOMOR PAKET KONTRAK : 080.A
KONTRAKTOR PELAKSANA : PT. SINAR MAROS
NOMOR KONTRAK : 080.A/KONTR/07.17-BM/059/600/2018
TANGGAL KONTRAK : 17 SEPTEMBER 2018
NILAI KONTRAK : Rp. 4.634.000.000,-
NOMOR ADDENDUM I : 080.A/ADD-I/07.17-BM/059/600/2018
TANGGAL ADDENDUM I : 08 OKTOBER 2018
NILAI ADDENDUM I : Rp. 4.634.000.000,-
KONSULTAN SUPERVISI : PT. MISHELLA CHARITAS PRATAMA
KONDISI 100 %
KONDISI 100 %
Kumurkek, Err:509
KONDISI 100 %
DISI 100 %
KONDISI 100 %
NOMOR KONTRAK : 080.A/KONTR/07.17-BM/059/600/2018
TANGGAL KONTRAK : 17 SEPTEMBER 2018
NILAI KONTRAK : Rp. 4.634.000.000,-
NOMOR ADDENDUM I : 080.A/ADD-I/07.17-BM/059/600/2018
TANGGAL ADDENDUM I : 08 OKTOBER 2018
NILAI ADDENDUM I : Rp. 4.634.000.000,-
KONSULTAN SUPERVISI : PT. MISHELLA CHARITAS PRATAMA
Kumurkek, Err:509
KONDISI 100 %
KONDISI 100 %
Kumurkek, Err:509
KONDISI 100 %
TANGGAL KONTRAK : 17 SEPTEMBER 2018
NILAI KONTRAK : Rp. 4.634.000.000,-
NOMOR ADDENDUM I : 080.A/ADD-I/07.17-BM/059/600/2018
TANGGAL ADDENDUM I : 08 OKTOBER 2018
NILAI ADDENDUM I : Rp. 4.634.000.000,-
KONSULTAN SUPERVISI : PT. MISHELLA CHARITAS PRATAMA
KONDISI 100 %
Kumurkek, Err:509
KONDISI 100 %
KONDISI 100 %
Kumurkek, Err:509
KONDISI 100 %
ISI 100 %
KONDISI 100 %
TANGGAL KONTRAK : 17 SEPTEMBER 2018
NILAI KONTRAK : Rp. 4.634.000.000,-
NOMOR ADDENDUM I : 080.A/ADD-I/07.17-BM/059/600/2018
TANGGAL ADDENDUM I : 08 OKTOBER 2018
NILAI ADDENDUM I : Rp. 4.634.000.000,-
KONSULTAN SUPERVISI : PT. MISHELLA CHARITAS PRATAMA
Kumurkek, Err:509
KONTRAKTOR
: 17 September 2018 s/d
30 September 2018
: PT. SINAR MAROS
NO. PAKET : 080.A
PAKET : PENINGKATAN JALAN SAUF - WEHALI
DAN PENATAAN RUANG NO. KONTRAK
TGL. KONTRAK
: 080.A/KONTR/07.17-BM/059/600/2018
: 17 SEPTEMBER 2018
Alamat : Jl. Brigjen (Purn) Abraham O. Ataruri Komplek Kantor Gubernur Papua Barat, Arfai - Manokwari LOKASI : DISTRIK SAIFI, KABUPATEN SORONG SELATAN
NILAI KONTRAK : Rp. 4.634.000.000,-
KONS. PENGAWAS : PT. MISHELLA CHARITAS PRATAMA
RENCANA REALISASI
NO. KONTRAK S/D RENCANA S/D S/D PRESTASI S/D
MATA DEVIASI
URAIAN MINGGU LALU MINGGU INI MINGGU INI MINGGU LALU MINGGU INI MINGGU INI KET.
PEMBA
YARAN BOBOT BOBOT BOBOT BOBOT BOBOT BOBOT BOBOT
SAT. VOLUME VOLUME VOLUME VOLUME VOLUME VOLUME VOLUME
(%) (%) (%) (%) (%) (%) (%) (%)
DIVISI 1. UMUM
1.2 Mobilisasi Ls 1.00 2.63 - - 0.35 0.92 0.35 0.92 - - 0.50 1.32 0.50 1.32 0.40
DIVISI 7. STRUKTUR
7.1(7)(a) Beton Mutu Sedang fc'20 Mpa M3 6.75 0.45 - - - - - - - - - - - - -
7.3(1) Baja Tulangan U 24 Polos Kg 742.50 0.33 - - - - - - - - - - - - -
7.9(1) Pasangan Batu M3 32.86 1.28 - - - - - - - - - - - - -
JUMLAH BOBOT PEKERJAAN (%) 100.00 - 3.15 3.15 - 1.44 1.44 (1.70)
BOBOT MINGGU INI ( % )
a. RENCANA 3.15
b. REALISASI 1.44
c. DEVIASI = ( b ) - ( a ) -1.70
HERI G. N. SAFLEMBOLO, ST, MT YESAYA JITMAU, ST, MT BARTJE F. TITALEY, ST RADIUS PRIBADI, ST
NIP. 1970 0927 1992 03 1 009 NIP. 1974 0623 2000 121 004 Supervision Engineer Site Manager
BULAN : SEPTEMBER 2018
LAPORAN MINGGUAN
MINGGU KE - :2
PEMERINTAH PROVINSI PAPUA BARAT PERIODE : 24 September 2018 s/d
30 September 2018
DINAS PEKERJAAN UMUM KONTRAKTOR : PT. SINAR MAROS
DAN PENATAAN RUANG PAKET : PENINGKATAN JALAN SAUF - WEHALI
NO. PAKET
NO. KONTRAK
: 080.A
: 080.A/KONTR/07.17-BM/059/600/2018
Alamat : Jl. Brigjen (Purn) Abraham O. Ataruri Komplek Kantor Gubernur Papua Barat, Arfai - Manokwari TGL. KONTRAK : 17 SEPTEMBER 2018
LOKASI : DISTRIK SAIFI, KABUPATEN SORONG SELATAN
NILAI KONTRAK : Rp. 4.634.000.000,-
KONS. PENGAWAS : PT. MISHELLA CHARITAS PRATAMA
RENCANA REALISASI
NO. KONTRAK S/D RENCANA S/D S/D PRESTASI S/D
MATA DEVIASI
URAIAN MINGGU LALU MINGGU INI MINGGU INI MINGGU LALU MINGGU INI MINGGU INI KET.
PEMBA
YARAN BOBOT BOBOT BOBOT BOBOT BOBOT BOBOT BOBOT
SAT. VOLUME VOLUME VOLUME VOLUME VOLUME VOLUME VOLUME
(%) (%) (%) (%) (%) (%) (%) (%)
DIVISI 1. UMUM
1.2 Mobilisasi Ls 1.00 2.63 0.35 0.92 - - 0.35 0.92 0.50 1.32 0.20 0.53 0.70 1.84 0.92
DIVISI 7. STRUKTUR
7.1(7)(a) Beton Mutu Sedang fc'20 Mpa M3 6.75 0.45 - - - - - - - - - - - - -
7.3(1) Baja Tulangan U 24 Polos Kg 742.50 0.33 - - - - - - - - - - - - -
7.9(1) Pasangan Batu M3 32.86 1.28 - - - - - - - - - - - - -
JUMLAH BOBOT PEKERJAAN (%) 100.00 3.15 2.23 5.38 1.44 0.65 2.10 (3.28)
BOBOT MINGGU INI ( % )
a. RENCANA 5.38
b. REALISASI 2.10
c. DEVIASI = ( b ) - ( a ) -3.28
100
DIVISI 1. UMUM
1.2 Mobilisasi Ls 1.0 111,050,000.00 111,050,000.00 2.63 0.92 - - - - - - 0.92 - - - - 0.79
0.79 0.53 - - - - - - - - - - - 90
DIVISI 3. PEKERJAAN TANAH
3.2(2a) Timbunan Pilihan dari sumber galian M3 640.5 425,866.46 272,775,984.96 6.47 - 1.62 1.62 1.62 1.61 - - - - - - - - 80
- - - - - - - - - - - - -
3.4(1) Pembersihan dan Pengupasan Lahan M3 6,000.0 4,312.92 25,877,520.00 0.61 - 0.61 0.00 - - - - - - - - - -
- 0.13 0.22 0.16 0.10 - - - - - - - - 70
DIVISI 3. PEKERJAAN TANAH KURVA
5.4.(1) Semen untuk Lapis Pondasi Semen Tanah Ton 172.8 3,546,673.11 612,865,113.41 14.53 - - - - - 2.91 2.91 2.91 2.91 2.89
RENCANA
- - - 60
- - - - - - - - - - - - -
5.4.(2) Lapis Pondasi Semen Tanah M3 1,440.0 392,608.65 565,356,456.00 13.40 - - - - - 2.68 2.68 2.68 2.68 2.69 - - -
- - - - - - - - - - - - - 50
DIVISI 6. PERKERASAN ASPAL
6.1(1)(a) Lapis Resap Pengikat - Aspal Cair Liter 12,600.0 15,499.14 195,289,164.00 4.63 - - - - - - - 1.16 1.16 1.16 0.58 0.57 - 40
- - - - - - - - - - - - -
6.6(1) Lapis Permukaan Penetrasi Macadam M3 630.0 3,726,410.02 2,347,638,312.60 55.66 - - - - - - - 11.13 11.13 11.13 11.13 11.14 -
- - - - - - - - - - - - - 30
DIVISI 7. STRUKTUR
7.1(7)(a) Beton Mutu Sedang fc'20 Mpa M3 6.8 2,825,600.64 19,072,804.32 0.45 - KURVA - - - 0.45 - - - - - - - - 20
- - - - - 0.45 - - - - - - -
7.3(1) Baja Tulangan U 24 Polos Kg 742.5 18,924.40 14,051,367.00 0.33
REALISASI
- - - - 0.33 - - - - - - - -
- - - - - 0.33 - - - - - - - 10
7.9(1) Pasangan Batu M3 32.9 1,639,626.44 53,878,124.82 1.28 - - - 0.64 0.64 - - - - - - - -
- - - - 0.47 0.81 - - - - - - -
0
(A) Jumlah Harga Pekerjaan ( termasuk Biaya Umum dan Keuntungan ) 4,217,854,847.11 100.00
(B) Pajak Pertambahan Nilai ( PPN ) = 10% x (A) 421,785,484.71
(C) Jumlah Total Harga Pekerjaan = (A) + (B) 4,639,640,331.82
(D) Rekapitulasi Harga (Dibulatkan) 4,639,640,300.00
Bobot Kemajuan Pekerjaan Mingguan (%) 0.00 0.92 2.23 1.62 2.26 3.03 5.59 5.59 18.80 17.88 17.87 11.71 11.71 0.79
RENCANA
Bobot Kemajuan Kumulatif Pekerjaan Mingguan (%) 0.00 0.92 3.15 4.77 7.03 10.06 15.65 21.24 40.04 57.92 75.78 87.49 99.21 100.00
HERI G. N. SAFLEMBOLO, ST, MT YESAYA JITMAU, ST, MT BARTJE F. TITALEY, ST RADIUS PRIBADI, ST
NIP. 1970 0927 1992 03 1 009 NIP. 1974 0623 2000 121 004 Supervisi Engineer Site Manager
Nomor :
Lampiran :
Perihal : Laporan Bulanan I
Kepada Yth : PPK Perencanaan dan Pengawasan Jalan Provinsi Papua Barat.
di -
Manokwari
Dengan Hormat,
Menunjuk Kontrak Nomor : 002.C/KONTR/18.05-BM/DTI/SS/600/2018 tanggal 17 September 2018 tentang Paket Pengawasan
Teknis Peningkatan Jalan Ayamaru - Sauf - Wehali - Batas Kabupaten Sorong Selatan, maka kami laporkan perkembangan
kegiatan tersebut untuk Bulan Ke - 1 (kesatu) yaitu bulan September 2018.
Adapun perkembangan kegiatan yang dapat kami laporkan selaku Konsultan Supervisi adalah pencapaian progress sebesar :
Pencapaian dengan deviasi positif dikarenakan kesiapan Kontraktor Pelaksana dan Keseriusan untuk menyelesaikan pekerjaan
sesuai yang direncanakan.
Demikian yang dapat kami laporkan, untuk dijadikan bahan monitoring dan evaluasi.
KONSULTAN SUPERVISI
###
BARTJIS F. TITALEY, ST
Supervision Engineer
PAKET PENGAWASAN TEKNIS PENINGKATAN JALAN AYAMARU - SAUF - WEHALI - BATAS KABUPATEN SORONG SELATAN
DAFTAR ISI
Surat ....................................................................................................................................... i
ª Intruksi/Perhatian ....................................................................................................................................... 11
ª Narasi ....................................................................................................................................... 21
Halaman
ii
ii
LAP. BULAN 02
PAKET PENGAWASAN TEKNIS PENINGKATAN JALAN AYAMARU - SAUF - WEHALI - BATAS KABUPATEN SORONG SELATAN
METODOLOGI SUPERVISI
a. Mengendalikan pelaksanaan pekerjaan agar pekerjaan dapat dikerjakan sesuai dengan, persyaratan dan ketentuan – ketentuan yang tercantum
dalam Dokumen Kontrak serta jadwal waktu yang telah ditetapkan.
b. Mengumpulkan data lapangan yang diperlukan secara terinci untuk mendukung peninjauan design (Review Design), menyusun perhitungan
desain, membuat gambar desain dan menyiapkan perintah-perintah kepada kontraktor, sehingga perubahan tersebut dapat dilaksanakan.
c. Melaksanakan pengecekan secara cermat semua pengukuran dan perhitungan volume pekerjaan yang akan dipakai sebagai dasar pembayaran,
sehingga semua pengukuran pekerjaan, perhitungan volume dan pembayaran didasarkan kepada ketentuan yang tercantum dalam dokumen
kontrak.
d. Memonitoring dan pengecekan secara terus-menerus sehubungan dengan pelaksanaan dan pengendalian mutu serta volume pekerjaan
termasuk keterlambatan pencapaian target fisik.
e. Penyusunan Laporan Bulanan (Monthly Report), Laporan Triwulan (Quarterly Report) dan Laporan Akhir (Final Report) yang mencakup
laporan kemajuan pekerjaan dan laporan keuangan serta masalah-masalah yang ditemui di lapangan serta menyusun daftar kerusakan dan
penyimpangan yang perlu diperbaiki dalam pelaksanaan Provisional Hand Over (PHO) dan Final Hand Over (FHO).
f. Prosedur Umum Pelayanan jasa Konsultan Supervisi adalah dengan cara melakukan monitoring kemajuan pekerjaan, pengendalian mutu dan
volume pekerjaan, dan masalah yang berkaitan dengan pelaksanaan pekerjaan dan dokumen kontrak. Koordinasi kegiatan Tim pengawas
teknis dilaksanakan oleh Supervision Engineer bersama-sama dengan Pengendali Kegiatan. Pekerjaan Pengawasan Teknis dilaksanakan oleh
Pelaksanaan Kegiatan Fisik yang bertindak sebagai ”Engineer” dibantu dan mendelegasikan sebagian tugas kepada Tim Pengawas Teknik
yang bertindak sebagai “Engineer Representative” sesuai dengan dokumen kontrak fisik. Tugas yang diberikan adalah tugas-tugas yang
berkaitan dengan masalah Teknis dan kontrak, tugas tersebut selanjutnya diatur dalam Kerangka Acuan Kerja ini.
g. Dinas Pekerjaan Umum dan Penataan Ruang Provinsi Papua Barat mengendalikan pelaksanaan pelayanan Jasa Konsultansi, sesuai dengan
tugas Kerangka Acuan Kerja ini.
Konsultan Pengawas ditugaskan bertanggung jawab atas koordinasi pelaksanaan kegiatan fisik, termasuk system pembayaran atas pelayanan
Jasa Konsultansi ini secara keseluruhan.
h. Membantu Pejabat Pembuat Komitmen (PPK) fisik dalam hal melaksanakan tugas peninjauan perencanaan teknis (review design) dan
pengawasan teknis, sehingga pelaksanaan fisik dapat diselesaikan sesuai dengan persyaratan yang telah ditentukan dalam dokumen kontrak.
Perubahan-perubahan atas design hanya dapat dilakukan dengan persetujuan Pejabat Pembuat Komitmen Perencanaan dan Pengawasan Jalan
Provinsi Papua Barat.
i. Membantu PPK dalam mengikutsertakan dan melaksanakan ketentuan hukum dari dokumen kontrak fisik, terutama masalah hukum yang
menyangkut "Claim" perpanjangan waktu pelaksanaan dan lain sebagainya.
j. Membantu PPK fisik dalam mengevaluasi usulan perubahan design, termasuk menyiapkan “Contract Change Order” dan atau “Addendum”
sehingga perubahan-perubahan kontrak yang diperlukan dapat dibuat secara optimum dengan mempertimbangkan aspek dana yang tersedia.
k. Melakukan pemeriksaan investigasi atas masalah khusus yang menyangkut pelaksanaan pekerjaan yang telah dilaporkan oleh Tim Pengawas
Teknik, misalnya keterlambatan pelaksanaan pekerjaan, serta membuat rekomendasi pemecahan untuk meningkatkan pencapaian kemajuan
pelaksanaan.
l. Membuat himpunan data pengendalian mutu pekerjaan terutama untuk pekerjaan-pekerjaan utama (mayor works), dan bila mana perlu
melakukan test laboratorium dan lapangan.
m. Melakukan monitoring, agar pelaksanaan system pelaporan dapat berjalan sesuai dengan ketentuan yang telah ditentukan oleh Pejabat
Pembuat Komitmen Perencanaan dan Pengawasan Jalan Provinsi Papua Barat.
Tingkat kecermatan informasi dan ketetapan waktu distribusi pelaporan harus menjadi perhatian khusus dari konsultan.
n. Memberikan petunjuk kepada Tim Pengawas Teknik dalam Pelaksanaan Kegiatan Fisik sehubungan dengan managemen pelaksanaan
pekerjaan (“Construction Management”), sehingga pekerjaan dapat dilaksanakan dengan efisien baik dari segi waktu maupun biaya.
o. Menyiapkan laporan teknis dan makalah sehubungan dengan tiap masalah yang timbul selama pelaksanaan pekerjaan.
Halaman
1
LAP. BULAN 02
PAKET PENGAWASAN TEKNIS PENINGKATAN JALAN AYAMARU - SAUF - WEHALI - BATAS KABUPATEN SORONG SELATAN
p. Membantu Pengendali Kegiatan Fisik (Direksi) dalam melaksanakan tugas dan kewajiban dalam mengendalikan pelaksanaan pekerjaan agar
pekerjaan dapat diselesaikan sesuai dengan design, persyaratan dan ketentuan-ketentuan yang tercantum dalam dokumen kontrak serta jadwal
waktu yang telah ditetapkan.
q. Membantu Pengendali Kegiatan Fisik (Direksi) dalam memahami dan melaksanakan ketentuan-ketentuan hukum yang tercantum didalam
dokumen kontrak, terutama sehubungan dengan pemenuhan kewajiban dan tugas kontraktor.
r. Melaporkan kepada Pengendali Kegiatan Fisik (Direksi Teknis/PPTK/PPK) semua masalah sehubungan dengan pelaksanaan pekerjaan
termasuk keterlambatan pencapaian target fisik, serta usaha-usaha penanggulangan dan tidak turun tangan (T3) yang diperlukan dengan
terlebih dahulu mengkonsultasikannya kepada Pengendali Kegiatan .
s. Melakukan monitoring dan pengecekan secara terus menerus sehubungan pengendalian mutu dan volume pekerjaan, serta menandatangani
“Monthly Certificate (MC)” apabila mutu dan pelaksanaan pekerjaan telah memenuhi semua ketentuan dan persyaratan yang telah ditetukan.
Konsultan harus memberitahukan secara tertulis kepada kontraktor atas adanya penyimpangan-penyimpangan dari ketentuan dan persyaratan,
baik mutu, volume bahan, pekerjaan dan copy syarat-syarat pemberitahuan tersebut harus disampaikan kepada Pengendali Kegiatan Satker
Fisik dan Pejabat Pembuat Komitmen (PPK-Fisk) dan diarsipkan secara baik.
Halaman
2
LAP. BULAN 02
AKTIVITAS KONSULTAN SUPERVISI BULAN JULI 2015
LOKASI KABUPATEN SORONG SELATAN
PAKET PENGAWASAN TEKNIS PENINGKATAN JALAN AYAMARU - SAUF - WEHALI - BATAS KABUPATEN SORONG SELATAN
KABAG. KEUANGAN
BEATRICK S.A BARANSANO, SE
NIP. 19800226 201004 2 001
BENDAHARA PENGELUARAN
NAOMI KARARBO, S.Sos
NIP. 19811123 201004 2 001
PPTK
YESAYA JITMAU, ST, MT
NIP. 1974 0623 2000 121 004
DIREKSI TEKNIS
ABEDNEGO SABTA, ST
NIP. 19800201 201104 1 001
Halaman
3
3
LAP. BULAN KE - 1
BULAN SEPTEMBER 2018
LOKASI KABUPATEN SORONG SELATAN
PAKET PENGAWASAN TEKNIS PENINGKATAN JALAN AYAMARU - SAUF - WEHALI - BATAS KABUPATEN SORONG SELATAN
SUPERVISION ENGINEER
AGUSTINUS PAGAYANG, ST
SUPPORTING STAFF
DWI HIDAYATI, SE
Halaman
4
4
LAP. BULAN KE - 1
AKTIVITAS KONSULTAN SUPERVISI BULAN SEPTEMBER 2018
LOKASI KABUPATEN SORONG SELATAN
PAKET PENGAWASAN TEKNIS PENINGKATAN JALAN AYAMARU - SAUF - WEHALI - BATAS KABUPATEN SORONG SELATAN
PERSONIL KONSULTAN
KEMBALI
TIBA
NO. POSISI / JABATAN NAMA DARI KETERANGAN
DI LAPANGAN
LAPANGAN
PROFESSIONAL STAFF
SUPPORTING STAFF
Halaman
5
5
LAP. BULAN KE - 1
AKTIVITAS KONSULTAN SUPERVISI BULAN SEPTEMBER 2018
LOKASI KABUPATEN SORONG SELATAN
PAKET PENGAWASAN TEKNIS PENINGKATAN JALAN AYAMARU - SAUF - WEHALI - BATAS KABUPATEN SORONG SELATAN
2018
NO. NAME AND POSITION SCHEDULE M/M SEPT. OKT. NOV. DES. KETERANGAN
ACTUAL 1 2 3 4
PROFESSIONAL STAFF
SUPPORTING STAFF
Halaman
6
TIME SCHEDULE
Nama Paket : Pengawasan Teknis Peningkatan Jalan Ayamaru - Sauf - Wehali - Batas Kabupaten Sorong Selatan
Nomor Kontrak : 002.C/KONTR/18.05-BM/DTI/SS/600/2018
Tanggal Kontrak : 17 September 2018
Nilai Kontrak : #NAME?
Nama Perusahaan : #NAME?
C BIAYA KANTOR
Sewa Kantor UB 1.00 7.00 2.352 1.00 7.00 2.137 0.112 2.352 0.336
Sewa Furniture Kantor Bln 1.00 7.00 0.941 1.00 7.00 0.855 0.045 0.941 0.134 30
Sewa Penunjang Kantor
a. Komputer Desktop UB 1.00 7.00 0.941 1.00 7.00 0.855 0.045 0.045 0.134 0.134 0.120 0.120 0.120 0.120 0.120 0.120 0.075
b. Laptop UB 2.00 7.00 0.941 2.00 7.00 0.855 0.045 0.045 0.134 0.134 0.120 0.120 0.120 0.120 0.120 0.120 0.075
c. Printer A3 UB 1.00 7.00 0.353 1.00 7.00 0.321 0.017 0.017 0.050 0.050 0.045 0.045 0.045 0.045 0.045 0.045 0.028
d. Printer A4 UB 2.00 7.00 0.188 2.00 7.00 0.171 0.009 0.009 0.027 0.027 0.024 0.024 0.024 0.024 0.024 0.024 0.015
Komunikasi (Pulsa Telepon + Internet) Bln 1.00 7.00 0.470 1.00 7.00 0.427 0.022 0.022 0.067 0.067 0.060 0.060 0.060 0.060 0.060 0.060 0.038
Bahan untuk Peralatan Kantor 20
- Bahan Untuk Komputer Bln 1.00 7.00 0.271 1.00 7.00 0.246 0.013 0.013 0.039 0.039 0.035 0.035 0.035 0.035 0.035 0.035 0.022
D BIAYA PELAPORAN
Laporan RMK Eks 1.00 8.00 0.108 1.00 8.00 0.098 0.108 0.108
Laporan Pendahuluan Eks 1.00 8.00 0.161 1.00 8.00 0.147 0.161 0.161
Laporan Bulanan Eks 7.00 7.00 0.988 7.00 7.00 0.898 0.141 0.141 0.126 0.126 0.126 0.126 0.126 0.126 0.126
Laporan Triwulan Eks 3.00 5.00 0.353 3.00 5.00 0.321 0.118 0.118 0.101 0.101 10
Laporan Akhir Eks 1.00 5.00 0.168 1.00 5.00 0.153 0.153
E BIAYA AKOMODASI
Sewa Mobil Kantor Bln 1.00 7.00 6.587 1.00 7.00 5.983 0.314 0.314 0.941 0.941 0.841 0.841 0.841 0.841 0.841 0.841 0.525
Sewa Mobil Lapangan Bln 1.00 7.00 8.939 1.00 7.00 8.120 0.426 0.426 1.277 1.277 1.141 1.141 1.141 1.141 1.141 1.141 0.713
Sewa Motor Lapangan Bln 3.00 6.00 1.815 3.00 6.00 1.648 0.101 0.101 0.302 0.302 0.249 0.249 0.249 0.249 0.249 0.249
Sewa Motor Lapangan Bln 2.00 5.70 1.044 0.209 0.209 0.209 0.209 0.209 0.209
0
Mess Untuk Teknisi/ Bulan Bln 2.00 7.00 2.164 2.00 7.00 1.966 0.103 2.164 0.309
KEMAJUAN PEKERJAAN BULANAN RENCANA (%) 7.71 14.38 14.26 14.26 14.38 14.26 12.48 8.15
KEMAJUAN PEKERJAAN KUMULATIF RENCANA (%) - - 3.855 7.71 14.90 22.08 29.28 36.48 43.61 50.74 57.93 65.12 72.24 79.37 85.61 91.85 95.92 100.0
KEMAJUAN PEKERJAAN BULANAN RENCANA (%) 14.33 14.33 14.43 14.33 11.18 5.64
KEMAJUAN PEKERJAAN KUMULATIF RENCANA (%) - - 26.50 33.29 40.09 47.25 54.42 61.63 68.85 76.01 83.17 88.76 94.36 97.18 100.0
Dibuat Oleh
Konsultan Supervisi
###
Agustinus Pagayang, ST
Supervision Engineer
LAP. BULAN KE - 1
AKTIVITAS KONSULTAN SUPERVISI BULAN SEPTEMBER 2018
LOKASI KABUPATEN SORONG SELATAN
PAKET PENGAWASAN TEKNIS PENINGKATAN JALAN AYAMARU - SAUF - WEHALI - BATAS KABUPATEN SORONG SELATAN
Halaman
8
LAP. BULAN KE - 1
AKTIVITAS KONSULTAN SUPERVISI BULAN SEPTEMBER 2018
LOKASI KABUPATEN SORONG SELATAN
PAKET PENGAWASAN TEKNIS PENINGKATAN JALAN AYAMARU - SAUF - WEHALI - BATAS KABUPATEN SORONG SELATAN
Permasalahan
Penyedia Jasa PT. SINAR MAROS kekurangan tenaga propesional untuk mengurus administrasi teknik dan
tenaga teknik khususnya tenaga quality, tenaga quantity, tenaga surveyor, dan tenaga Lab. karena kontraktor
mempunyai peralatan Lab. Sendiri. Untuk Penyedia Jasa PT. SINAR MAROS terlambat melakukan mobilisasi,
Tenaga maupun Peralatan yang digunakan dilapangan.
Tindakan Penyelesaian
Peyedia Jasa PT. SINAR MAROS segera mencari Tenaga yang diperlukan demi kelancaran pekerjaan. Penyedia
Jasa PT. SINAR MAROS segera melakukan mobilisasi.
Disarankan :
2. Sebaiknya kontraktor mengirim tenaganya untuk mengikuti pelatihan Lab. Penyedia Jasa
PT. SINAR MAROS secepatnya melakukukan mobilisasi.
Konsultan Supervisi
PT. Lintas Papuaraya Konsultan
Agustinus Pagayang, ST
Supervision Engineer
Halaman
9
LAP. BULAN KE - 1
AKTIVITAS KONSULTAN SUPERVISI BULAN SEPTEMBER 2018
LOKASI KABUPATEN SORONG SELATAN
PAKET PENGAWASAN TEKNIS PENINGKATAN JALAN AYAMARU - SAUF - WEHALI - BATAS KABUPATEN SORONG SELATAN
Permasalahan
Tindakan Penyelesaian
Disarankan agar kontraktor, dan pihak laboratorium saling bekerja sama untuk melakukan pemeriksaan material
dan membuat Job Mix Formula (JMF).
Konsultan Supervisi
PT. Lintas Papuaraya Konsultan
Hofnie Sualang, ST
Quality Engineer
Halaman
10
LAP. BULAN KE - 1
AKTIVITAS KONSULTAN SUPERVISI BULAN SEPTEMBER 2018
LOKASI KABUPATEN SORONG SELATAN
PAKET PENGAWASAN TEKNIS PENINGKATAN JALAN AYAMARU - SAUF - WEHALI - BATAS KABUPATEN SORONG SELATAN
Permasalahan
Tindakan Penyelesaian
Menginstruksikan kontraktor agar segera mengadakan tenaga-tenaga yang diperlukan khususnya tenaga quantity,
agar pekerjaan dapat berjalan dengan lancar
Menyarankan agar kontraktor mencari tenaga yang berpengalaman, profesional dan ahli dalam bidang yang
dibutuhkan terlebih khusus untuk tenaga quantity.
Konsultan Supervisi
PT. Lintas Papuaraya Konsultan
B. Anar Fuadi, ST
Quantity Engineer
Halaman
11
LAP. BULAN KE - 1
AKTIVITAS KONSULTAN SUPERVISI BULAN SEPTEMBER 2018
LOKASI KABUPATEN SORONG SELATAN
PAKET PENGAWASAN TEKNIS PENINGKATAN JALAN AYAMARU - SAUF - WEHALI - BATAS KABUPATEN SORONG SELATAN
Permasalahan
Kontraktor kekurangan tenaga seperti operator alat berat, dan tenaga pelaksana di lapangan kurang memahami
spesifikasi.
Tindakan Penyelesaian
Diinstruksikan agar kontraktor mencari operator, dan menempatkan tenaga yang memahmi spesifikasi agar
pekerjaan berjalan lancar.
Konsultan Supervisi
PT. Lintas Papuaraya Konsultan
Jektro Lalonsang, ST
Inspector
Halaman
12
LAP. BULAN KE - 1
AKTIVITAS KONSULTAN SUPERVISI BULAN SEPTEMBER 2018
LOKASI KABUPATEN SORONG SELATAN
PAKET PENGAWASAN TEKNIS PENINGKATAN JALAN AYAMARU - SAUF - WEHALI - BATAS KABUPATEN SORONG SELATAN
Permasalahan
Kontraktor kekurangan tenaga seperti operator alat berat, dan tenaga pelaksana di lapangan kurang memahami
spesifikasi.
Tindakan Penyelesaian
Diinstruksikan agar kontraktor mencari operator, dan menempatkan tenaga yang memahmi spesifikasi agar
pekerjaan berjalan lancar.
Konsultan Supervisi
PT. Lintas Papuaraya Konsultan
Halaman
13
LAP. BULAN KE - 1
AKTIVITAS KONSULTAN SUPERVISI BULAN SEPTEMBER 2018
LOKASI KABUPATEN SORONG SELATAN
PAKET PENGAWASAN TEKNIS PENINGKATAN JALAN AYAMARU - SAUF - WEHALI - BATAS KABUPATEN SORONG SELATAN
Permasalahan
Kontraktor kekurangan tenaga seperti operator alat berat, dan tenaga pelaksana di lapangan kurang memahami
spesifikasi.
Tindakan Penyelesaian
Diinstruksikan agar kontraktor mencari operator, dan menempatkan tenaga yang memahmi spesifikasi
agar pekerjaan berjalan lancar.
Konsultan Supervisi
PT. Lintas Papuaraya Konsultan
JEFRY TIMA, ST
Inspector
Halaman
14
LAP. BULAN KE - 1
AKTIVITAS KONSULTAN SUPERVISI BULAN SEPTEMBER 2018
LOKASI KABUPATEN SORONG SELATAN
PAKET PENGAWASAN TEKNIS PENINGKATAN JALAN AYAMARU - SAUF - WEHALI - BATAS KABUPATEN SORONG SELATAN
Permasalahan
Tindakan Penyelesaian
Kontraktor diharapkan segera memobilisasi tenaga surveyor demi kelancaran pekerjaan pengukuran di lapangan
Konsultan Supervisi
PT. Lintas Papuaraya Konsultan
Teofilus Parlindangan, ST
Surveyor
Halaman
15
LAP. BULAN KE - 1
AKTIVITAS KONSULTAN SUPERVISI BULAN SEPTEMBER 2018
LOKASI KABUPATEN SORONG SELATAN
PAKET PENGAWASAN TEKNIS PENINGKATAN JALAN AYAMARU - SAUF - WEHALI - BATAS KABUPATEN SORONG SELATAN
Permasalahan
Tindakan Penyelesaian
Kontraktor diharapkan segera memobilisasi tenaga surveyor demi kelancaran pekerjaan pengukuran di lapangan
Konsultan Supervisi
PT. Lintas Papuaraya Konsultan
LAURENSIUS MOA, ST
Surveyor
Halaman
16
LAP. BULAN KE - 1
AKTIVITAS KONSULTAN SUPERVISI BULAN SEPTEMBER 2018
LOKASI KABUPATEN SORONG SELATAN
PAKET PENGAWASAN TEKNIS PENINGKATAN JALAN AYAMARU - SAUF - WEHALI - BATAS KABUPATEN SORONG SELATAN
Permasalahan
Tindakan Penyelesaian
Kontraktor segera mencari tenaga laboratorium yang profesional untuk menjalankan pemeriksaan material di lab.
Kontraktor sendiri.
Konsultan Supervisi
PT. Lintas Papuaraya Konsultan
Amin Tohari, ST
Material Technician
Halaman
17
LAP. BULAN KE - 1
PAKET PENGAWASAN TEKNIS PENINGKATAN JALAN AYAMARU - SAUF - WEHALI - BATAS KABUPATEN SORONG SELATAN
MASALAH
1 Konsultan Supervisi menyarankan, agar pemaanfaatan optimal waktu jam kerja pada kondisi cuaca baik, dengan rujukan spesifikasi pelaksanaan.
1 PPK/Direksi meminta agar dilakukan percepatan pelaksanaan fisik dilapangan dgn tidak mengabaikan tepat mutu, tepat waktu, tepat biaya.
2 PPK/Direksi meminta kepada penyedia jasa, agar selalu memaksimalkan pekerjaan dilapangan, pada kondisi cuaca baik dilapangan (spesifikasi).
Halaman
18
18
LAP. BULAN KE - 1
AKTIVITAS KONSULTAN SUPERVISI BULAN SEPTEMBER 2018
PAKET PENGAWASAN TEKNIS PENINGKATAN JALAN AYAMARU - SAUF - WEHALI - BATAS KABUPATEN SORONG SELATAN
LINGKUP PEMERIKSAAN
DIVISI 2. DRAINASE
2.1 Galian untuk Selokan Drainase dan Saluran Air KETERANGAN
Kualitas :
V Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan spesifikasi
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan spesifikasi
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Kuantitas :
V Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan kontrak
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan kontrak
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan spesifikasi
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Kuantitas :
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan kontrak
V Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan kontrak
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan kontrak
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan kontrak
Halaman
19
LAP. BULAN KE - 1
AKTIVITAS KONSULTAN SUPERVISI BULAN SEPTEMBER 2018
PAKET PENGAWASAN TEKNIS PENINGKATAN JALAN AYAMARU - SAUF - WEHALI - BATAS KABUPATEN SORONG SELATAN
DIVISI 3. TANAH
3.1.(1a) Galian Biasa KETERANGAN
Kualitas :
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan spesifikasi
V Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan spesifikasi
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Kuantitas :
V Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan kontrak
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan kontrak
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan kontrak
V Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan spesifikasi
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Kuantitas :
V Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan kontrak
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan kontrak
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan kontrak
V Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan spesifikasi
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Kuantitas :
V Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan kontrak
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan kontrak
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan kontrak
Halaman
20
LAP. BULAN KE - 1
AKTIVITAS KONSULTAN SUPERVISI BULAN SEPTEMBER 2018
PAKET PENGAWASAN TEKNIS PENINGKATAN JALAN AYAMARU - SAUF - WEHALI - BATAS KABUPATEN SORONG SELATAN
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan spesifikasi
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Kuantitas :
V Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan kontrak
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan kontrak
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan spesifikasi
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Kuantitas :
V Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan kontrak
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan kontrak
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan spesifikasi
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Kuantitas :
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan kontrak
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan kontrak
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan kontrak
Halaman
21
LAP. BULAN KE - 1
AKTIVITAS KONSULTAN SUPERVISI BULAN SEPTEMBER 2018
PAKET PENGAWASAN TEKNIS PENINGKATAN JALAN AYAMARU - SAUF - WEHALI - BATAS KABUPATEN SORONG SELATAN
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan spesifikasi
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Kuantitas :
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan kontrak
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan kontrak
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan spesifikasi
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Kuantitas :
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan kontrak
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan kontrak
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan kontrak
Kualitas :
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan spesifikasi
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan spesifikasi
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Kuantitas :
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan kontrak
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan kontrak
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan kontrak
Halaman
22
LAP. BULAN KE - 1
AKTIVITAS KONSULTAN SUPERVISI BULAN SEPTEMBER 2018
PAKET PENGAWASAN TEKNIS PENINGKATAN JALAN AYAMARU - SAUF - WEHALI - BATAS KABUPATEN SORONG SELATAN
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan spesifikasi
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Kuantitas :
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan kontrak
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan kontrak
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan spesifikasi
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Kuantitas :
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan kontrak
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan kontrak
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan kontrak
KETERANGAN
7.9.(1) Pasangan Batu
Kualitas :
V Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan spesifikasi
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan spesifikasi
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Kuantitas :
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan kontrak
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan kontrak
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan kontrak
Halaman
23
LAP. BULAN KE - 1
PAKET PENGAWASAN TEKNIS PENINGKATAN JALAN AYAMARU - SAUF - WEHALI - BATAS KABUPATEN SORONG SELATAN
LINGKUP PEMERIKSAAN
DIVISI 2. DRAINASE
2.1.(1) Galian untuk Selokan Drainase dan Saluran Air KETERANGAN
Kualitas :
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan spesifikasi
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan spesifikasi
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Kuantitas :
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan kontrak
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan kontrak
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan spesifikasi
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Kuantitas :
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan kontrak
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan kontrak
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan kontrak
Halaman
24
LAP. BULAN KE - 1
PAKET PENGAWASAN TEKNIS PENINGKATAN JALAN AYAMARU - SAUF - WEHALI - BATAS KABUPATEN SORONG SELATAN
DIVISI 3. TANAH
3.1.(1a) Galian Biasa KETERANGAN
Kualitas :
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan spesifikasi
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan spesifikasi
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Kuantitas :
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan kontrak
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan kontrak
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan spesifikasi
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Kuantitas :
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan kontrak
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan kontrak
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan spesifikasi
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Kuantitas :
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan kontrak
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan kontrak
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan kontrak
Halaman
25
LAP. BULAN KE - 1
PAKET PENGAWASAN TEKNIS PENINGKATAN JALAN AYAMARU - SAUF - WEHALI - BATAS KABUPATEN SORONG SELATAN
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan spesifikasi
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Kuantitas :
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan kontrak
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan kontrak
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan kontrak
V Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan spesifikasi
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Kuantitas :
V Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan kontrak
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan kontrak
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan spesifikasi
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Kuantitas :
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan kontrak
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan kontrak
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan kontrak
Halaman
26
LAP. BULAN KE - 1
PAKET PENGAWASAN TEKNIS PENINGKATAN JALAN AYAMARU - SAUF - WEHALI - BATAS KABUPATEN SORONG SELATAN
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan spesifikasi
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Kuantitas :
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan kontrak
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan kontrak
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan spesifikasi
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Kuantitas :
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan kontrak
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan kontrak
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan spesifikasi
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Kuantitas :
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan kontrak
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan kontrak
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan kontrak
Halaman
27
LAP. BULAN KE - 1
PAKET PENGAWASAN TEKNIS PENINGKATAN JALAN AYAMARU - SAUF - WEHALI - BATAS KABUPATEN SORONG SELATAN
Kualitas : KETERANGAN
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan spesifikasi
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan spesifikasi
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Kuantitas :
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan kontrak
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan kontrak
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan spesifikasi
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Kuantitas :
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan kontrak
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan kontrak
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan spesifikasi
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Kuantitas :
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan kontrak
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan kontrak
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan kontrak
Halaman
28
LAP. BULAN KE - 1
PAKET PENGAWASAN TEKNIS PENINGKATAN JALAN AYAMARU - SAUF - WEHALI - BATAS KABUPATEN SORONG SELATAN
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan spesifikasi
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Kuantitas :
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan kontrak
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan kontrak
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan kontrak
Halaman
29
LAP. BULAN KE - 1
PAKET PENGAWASAN TEKNIS PENINGKATAN JALAN AYAMARU - SAUF - WEHALI - BATAS KABUPATEN SORONG SELATAN
LINGKUP PEMERIKSAAN
DIVISI 2. DRAINASE
2.1.(1) Galian untuk Selokan Drainase dan Saluran Air KETERANGAN
Kualitas :
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan spesifikasi
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan spesifikasi
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Kuantitas :
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan kontrak
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan kontrak
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan spesifikasi
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Kuantitas :
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan kontrak
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan kontrak
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan kontrak
Halaman
30
LAP. BULAN KE - 1
PAKET PENGAWASAN TEKNIS PENINGKATAN JALAN AYAMARU - SAUF - WEHALI - BATAS KABUPATEN SORONG SELATAN
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan spesifikasi
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Kuantitas :
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan kontrak
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan kontrak
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan spesifikasi
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Kuantitas :
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan kontrak
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan kontrak
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan spesifikasi
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Kuantitas :
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan kontrak
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan kontrak
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan kontrak
Halaman
31
LAP. BULAN KE - 1
PAKET PENGAWASAN TEKNIS PENINGKATAN JALAN AYAMARU - SAUF - WEHALI - BATAS KABUPATEN SORONG SELATAN
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan spesifikasi
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Kuantitas :
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan kontrak
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan kontrak
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan spesifikasi
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Kuantitas :
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan kontrak
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan kontrak
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan spesifikasi
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Kuantitas :
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan kontrak
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan kontrak
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan kontrak
Halaman
32
LAP. BULAN KE - 1
PAKET PENGAWASAN TEKNIS PENINGKATAN JALAN AYAMARU - SAUF - WEHALI - BATAS KABUPATEN SORONG SELATAN
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan spesifikasi
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Kuantitas :
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan kontrak
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan kontrak
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan spesifikasi
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Kuantitas :
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan kontrak
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan kontrak
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan spesifikasi
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Kuantitas :
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan kontrak
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan kontrak
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan kontrak
Halaman
33
LAP. BULAN KE - 1
PAKET PENGAWASAN TEKNIS PENINGKATAN JALAN AYAMARU - SAUF - WEHALI - BATAS KABUPATEN SORONG SELATAN
Kualitas : KETERANGAN
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan spesifikasi
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan spesifikasi
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Kuantitas :
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan kontrak
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan kontrak
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan spesifikasi
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Kuantitas :
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan kontrak
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan kontrak
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan spesifikasi
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Kuantitas :
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan kontrak
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan kontrak
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan kontrak
Halaman
34
LAP. BULAN KE - 1
PAKET PENGAWASAN TEKNIS PENINGKATAN JALAN AYAMARU - SAUF - WEHALI - BATAS KABUPATEN SORONG SELATAN
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan spesifikasi
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Kuantitas :
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan kontrak
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan kontrak
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan kontrak
Halaman
35
LAP. BULAN KE - 1
AKTIVITAS KONSULTAN SUPERVISI BULAN SEPTEMBER 2018
LOKASI KABUPATEN SORONG SELATAN
PAKET PENGAWASAN TEKNIS PENINGKATAN JALAN AYAMARU - SAUF - WEHALI - BATAS KABUPATEN SORONG SELATAN
Halaman
36
1 2 3 4 71 72 75 76
1 2 3 4 5 6 7 8 9 10 11 12 13 14
1 2 3 4 5 6 7 10 11
1 2 3 4 5 6 9 10
1 68 69 72 73
SUMBER KONTRAK
NO. NAMA PAKET LOKASI
DANA NO. TGL.
1 2 3 4 5 6 7 8 9
1-IX 1 PEMBANGUNAN JALAN LINGKUNGAN KOTA SORONG (PAKET 1) CV. BESAWI MARIKE HOWAY Direktris Jl. F. Kalasuat RT.001 RW.001 Malamso Malaimsimsa - Kota Sorong 90.418.547.7-951.000 149,850,000 1
Direktur
Halaman 63
1
Harga Perkiraan Sendiri (HPS) Pengadaan Poskesdes Set Dinkes-KK TA 2010 Halaman 64 / 200
IX
Harga Perkiraan Sendiri (HPS) Pengadaan Poskesdes Set Dinkes-KK TA 2010 Halaman 65 / 200
FOTO PELAKSANAAN KEGIATAN
PEMBANGUNAN JALAN LINGKUNGAN KOTA SORONG (PAKET 1)
CV. BESAWI
Item Pekerjaan :
PERSIAPAN
Kondisi Pekerjaan :
0%
Lokasi Pekerjaan :
+
No. Mata Pembayaran :
Item Pekerjaan :
PERSIAPAN
Kondisi Pekerjaan :
0%
Lokasi Pekerjaan :
+
No. Mata Pembayaran :
Item Pekerjaan :
Kondisi Pekerjaan :
0%
Lokasi Pekerjaan :
Halaman 66
FOTO PELAKSANAAN KEGIATAN
PEMBANGUNAN JALAN LINGKUNGAN KOTA SORONG (PAKET 1)
CV. BESAWI
Halaman 67
FOTO PELAKSANAAN KEGIATAN
PEMBANGUNAN JALAN LINGKUNGAN KOTA SORONG (PAKET 1)
CV. BESAWI
Item Pekerjaan :
Kondisi Pekerjaan :
50%
Lokasi Pekerjaan :
+
No. Mata Pembayaran :
Item Pekerjaan :
Kondisi Pekerjaan :
50%
Lokasi Pekerjaan :
+
No. Mata Pembayaran :
Item Pekerjaan :
Kondisi Pekerjaan :
50%
Lokasi Pekerjaan :
Halaman 68
FOTO PELAKSANAAN KEGIATAN
PEMBANGUNAN JALAN LINGKUNGAN KOTA SORONG (PAKET 1)
CV. BESAWI
Halaman 69
FOTO PELAKSANAAN KEGIATAN
PEMBANGUNAN JALAN LINGKUNGAN KOTA SORONG (PAKET 1)
CV. BESAWI
Item Pekerjaan :
Kondisi Pekerjaan :
100%
Lokasi Pekerjaan :
+
No. Mata Pembayaran :
Item Pekerjaan :
Kondisi Pekerjaan :
100%
Lokasi Pekerjaan :
+
No. Mata Pembayaran :
Item Pekerjaan :
Kondisi Pekerjaan :
100%
Lokasi Pekerjaan :
Halaman 70
FOTO PELAKSANAAN KEGIATAN
PEMBANGUNAN JALAN LINGKUNGAN KOTA SORONG (PAKET 1)
CV. BESAWI
Halaman 71
FOTO PELAKSANAAN KEGIATAN
PEMBANGUNAN JALAN LINGKUNGAN KOTA SORONG (PAKET 1)
CV. BESAWI
Item Pekerjaan :
Kondisi Pekerjaan :
100%
Lokasi Pekerjaan :
+
No. Mata Pembayaran :
Item Pekerjaan :
Kondisi Pekerjaan :
100%
Lokasi Pekerjaan :
+
No. Mata Pembayaran :
Item Pekerjaan :
Kondisi Pekerjaan :
100%
Lokasi Pekerjaan :
Halaman 72
FOTO PELAKSANAAN KEGIATAN
PEMBANGUNAN JALAN LINGKUNGAN KOTA SORONG (PAKET 1)
CV. BESAWI
Halaman 73
FOTO PELAKSANAAN KEGIATAN
PEMBANGUNAN JALAN LINGKUNGAN KOTA SORONG (PAKET 1)
CV. BESAWI
Item Pekerjaan :
Kondisi Pekerjaan :
100%
Lokasi Pekerjaan :
+
No. Mata Pembayaran :
Item Pekerjaan :
Kondisi Pekerjaan :
Lokasi Pekerjaan :
+
No. Mata Pembayaran :
Item Pekerjaan :
Kondisi Pekerjaan :
Lokasi Pekerjaan :
Halaman 74
FOTO PELAKSANAAN KEGIATAN
PEMBANGUNAN JALAN LINGKUNGAN KOTA SORONG (PAKET 1)
CV. BESAWI
Halaman 75
FOTO PELAKSANAAN KEGIATAN
PEMBANGUNAN JALAN LINGKUNGAN KOTA SORONG (PAKET 1)
CV. BESAWI
Item Pekerjaan :
Kondisi Pekerjaan :
0%
Lokasi Pekerjaan :
+
No. Mata Pembayaran :
Item Pekerjaan :
Kondisi Pekerjaan :
50 %
Lokasi Pekerjaan :
+
No. Mata Pembayaran :
Item Pekerjaan :
Kondisi Pekerjaan :
100 %
Lokasi Pekerjaan :
Halaman 76
FOTO PELAKSANAAN KEGIATAN
PEMBANGUNAN JALAN LINGKUNGAN KOTA SORONG (PAKET 1)
CV. BESAWI
Halaman 77
FOTO PELAKSANAAN KEGIATAN
PEMBANGUNAN JALAN LINGKUNGAN KOTA SORONG (PAKET 1)
CV. BESAWI
Item Pekerjaan :
Kondisi Pekerjaan :
0%
Lokasi Pekerjaan :
+
No. Mata Pembayaran :
Item Pekerjaan :
Kondisi Pekerjaan :
50 %
Lokasi Pekerjaan :
+
No. Mata Pembayaran :
Item Pekerjaan :
Kondisi Pekerjaan :
100 %
Lokasi Pekerjaan :
Halaman 78
FOTO PELAKSANAAN KEGIATAN
PEMBANGUNAN JALAN LINGKUNGAN KOTA SORONG (PAKET 1)
CV. BESAWI
Halaman 79
FOTO PELAKSANAAN KEGIATAN
PEMBANGUNAN JALAN LINGKUNGAN KOTA SORONG (PAKET 1)
CV. BESAWI
Item Pekerjaan :
Kondisi Pekerjaan :
0%
Lokasi Pekerjaan :
+
No. Mata Pembayaran :
Item Pekerjaan :
Kondisi Pekerjaan :
50 %
Lokasi Pekerjaan :
+
No. Mata Pembayaran :
Item Pekerjaan :
Kondisi Pekerjaan :
100 %
Lokasi Pekerjaan :
Halaman 80
FOTO PELAKSANAAN KEGIATAN
PEMBANGUNAN JALAN LINGKUNGAN KOTA SORONG (PAKET 1)
CV. BESAWI
Halaman 81
BACK UP DATA
NAMA PAKET : PEMBANGUNAN JALAN LINGKUNGAN KOTA
SORONG (PAKET 1)
LOKASI KEGIATAN : KOTA SORONG
KONTRAKTOR : CV. BESAWI
NOMOR KONTRAK : 115.A/SPK/45.13-CK/PKT-1/600/2020
TANGGAL KONTRAK : 12 OKTOBER 2020
KONSULTAN SUPERVISI : CV. ARFAK DESAIN KONSULTAN
NAMA DIVISI : A. PEKERJAAN PERSIAPAN
: B. PEKERJAAN TANAH
: C. PEKERJAAN STRUKTUR
SKETSA PENAMPANG
4.0 M
20 CM
0.15 CM
2.0 M 2.0 M
20 CM
0.15 CM
1 0+000 Kanan - -
110.00 110.00
JUMLAH 220.00
4.0 M
20 CM
0.15 CM
LUAS
LOKASI H L LUAS PANJANG VOLUME VOL. KUM
NO. CD RATA2
PEKERJAAN
(m) (m) (m2) (m2) (m') (m3) (m3)
JUMLAH 31.94
4.0 M
20 CM
0.15 CM
4.0 M
20 CM
0.15 CM
LUAS
LOKASI H L LUAS PANJANG VOLUME VOL. KUM
NO. CD RATA2
PEKERJAAN
(m) (m) (m2) (m2) (m') (m3) (m3)
44.00
L
PENAMPANG URPIL
Tanpa Skala
LUAS
LOKASI H L LUAS PANJANG VOLUME VOL. KUM
NO. SISI RATA2
PEKERJAAN
(m) (m) (m2) (m2) (m') (m3) (m3)
L
PENAMPANG URPIL
Tanpa Skala
LUAS
LOKASI H L LUAS PANJANG VOLUME VOL. KUM
NO. SISI RATA2
PEKERJAAN
(m) (m) (m2) (m2) (m') (m3) (m3)
L
PENAMPANG URPIL
Tanpa Skala
LUAS
LOKASI H L LUAS PANJANG VOLUME VOL. KUM
NO. SISI RATA2
PEKERJAAN
(m) (m) (m2) (m2) (m') (m3) (m3)
LAPORAN MINGGUAN
MINGGU KE - :1
PEMERINTAH PROVINSI PAPUA BARAT PERIODE : 12 Oktober 2020 s/d
RENCANA REALISASI
NO. KONTRAK S/D RENCANA S/D S/D PRESTASI S/D
MATA DEVIASI
URAIAN MINGGU LALU MINGGU INI MINGGU INI MINGGU LALU MINGGU INI MINGGU INI KET.
PEMBA
YARAN BOBOT BOBOT BOBOT BOBOT BOBOT BOBOT BOBOT
SAT. VOLUME VOLUME VOLUME VOLUME VOLUME VOLUME VOLUME
(%) (%) (%) (%) (%) (%) (%) (%)
A. PEKERJAAN PERSIAPAN
1 Mobilisasi dan Demobilisasi Alat LS 1.00 5.14 - - 0.20 1.03 0.20 1.03 - - 0.30 1.54 0.30 1.54 0.51
2 Papan Nama Proyek uk 80 x 120 CM BH 1.00 0.55 - - - - - - - - - - - - -
3 Gudang Penyimpanan Semen M2 16.00 5.29 - - - - - - - - - - - - -
4 Pembersihan Lapangan M2 220.00 4.16 - - - - - - - - - - - - -
5 Manajemen dan Keselamatan Lalu Lintas LS 1.00 0.68 - - 0.14 0.10 0.14 0.10 - - 0.17 0.11 0.17 0.11 0.02
6 Keselamatan dan Kesehatan Kerja (K3) LS 1.00 0.73 - - 0.13 0.09 0.13 0.09 - - 0.17 0.12 0.17 0.12 0.03
7 Dokumentasi dan Laporan LS 1.00 4.40 - - 0.13 0.55 0.13 0.55 - - 0.17 0.73 0.17 0.73 0.18
B. PEKERJAAN TANAH
1 Urugan Pilihan M3 31.94 6.98 - - - - - - - - - - - - -
C. PEKERJAAN STRUKTUR
1 Cor Beton Mutu fc = 19,3 Mpa, t = 20 cm M3 44.00 69.86 - - - - - - - - - - - - -
2 Bekesting Papan Kayu Kelas III M2 27.50 2.21 - - - - - - - - - - - - -
JUMLAH BOBOT PEKERJAAN (%) 100.00 - 1.77 1.77 - 2.51 2.51 0.74
BOBOT MINGGU INI ( % )
a. RENCANA 1.77
b. REALISASI 2.51
c. DEVIASI = ( b ) - ( a ) 0.74
LAPORAN MINGGUAN
MINGGU KE - :2
PEMERINTAH PROVINSI PAPUA BARAT PERIODE : 19 Oktober 2020 s/d
25 Oktober 2020
DINAS PEKERJAAN UMUM KONTRAKTOR : CV. BESAWI
DAN PERUMAHAN RAKYAT PAKET : PEMBANGUNAN JALAN LINGKUNGAN KOTA SORONG (PAKET 1)
NO. KONTRAK
TGL. KONTRAK
: 115.A/SPK/45.13-CK/PKT-1/600/2020
: 12 OKTOBER 2020
Alamat : Jl. Brigjen (Purn) Abraham O. Ataruri Komplek Kantor Gubernur Papua Barat, Arfai - Manokwari NILAI KONTRAK : Rp 149,850,000.00
LOKASI : KOTA SORONG
KONS. PENGAWAS : CV. ARFAK DESAIN KONSULTAN
RENCANA REALISASI
NO. KONTRAK S/D RENCANA S/D S/D PRESTASI S/D
MATA DEVIASI
URAIAN MINGGU LALU MINGGU INI MINGGU INI MINGGU LALU MINGGU INI MINGGU INI KET.
PEMBA
YARAN BOBOT BOBOT BOBOT BOBOT BOBOT BOBOT BOBOT
SAT. VOLUME VOLUME VOLUME VOLUME VOLUME VOLUME VOLUME
(%) (%) (%) (%) (%) (%) (%) (%)
A. PEKERJAAN PERSIAPAN
1 Mobilisasi dan Demobilisasi Alat LS 1.00 5.14 0.20 1.03 0.60 3.08 0.80 4.11 0.30 1.54 0.50 2.57 0.80 4.11 -
2 Papan Nama Proyek uk 80 x 120 CM BH 1.00 0.55 - - 1.00 0.55 1.00 0.55 - - 1.00 0.55 1.00 0.55 -
3 Gudang Penyimpanan Semen M2 16.00 5.29 - - 8.00 2.64 8.00 2.64 - - 16.00 5.29 16.00 5.29 2.64
4 Pembersihan Lapangan M2 220.00 4.16 - - 100.00 1.89 100.00 1.89 - - 50.00 1.89 50.00 0.95 (0.95)
5 Manajemen dan Keselamatan Lalu Lintas LS 1.00 0.68 0.14 0.10 0.14 0.10 0.29 0.19 0.17 0.11 0.17 0.95 0.33 0.23 0.03
6 Keselamatan dan Kesehatan Kerja (K3) LS 1.00 0.73 0.13 0.09 0.13 0.09 0.25 0.18 0.17 0.12 0.17 0.10 0.33 0.24 0.06
7 Dokumentasi dan Laporan LS 1.00 4.40 0.13 0.55 0.13 0.55 0.25 1.10 0.17 0.73 0.17 0.11 0.33 1.47 0.37
B. PEKERJAAN TANAH
1 Urugan Pilihan M3 31.94 6.98 - - 10.65 2.33 10.65 2.33 - - 7.00 1.53 7.00 1.53 (0.80)
C. PEKERJAAN STRUKTUR
1 Cor Beton Mutu fc = 19,3 Mpa, t = 20 cm M3 44.00 69.86 - - - - - - - - - - - - -
2 Bekesting Papan Kayu Kelas III M2 27.50 2.21 - - - - - - - - - - - - -
JUMLAH BOBOT PEKERJAAN (%) 100.00 1.77 11.23 13.00 2.51 12.98 14.36 1.36
BOBOT MINGGU INI ( % )
a. RENCANA 13.00
b. REALISASI 14.36
c. DEVIASI = ( b ) - ( a ) 1.36
LAPORAN MINGGUAN
MINGGU KE - :3
PEMERINTAH PROVINSI PAPUA BARAT PERIODE : 26 Oktober 2020 s/d
01 November 2020
DINAS PEKERJAAN UMUM KONTRAKTOR : CV. BESAWI
DAN PERUMAHAN RAKYAT PAKET : PEMBANGUNAN JALAN LINGKUNGAN KOTA SORONG (PAKET 1)
NO. KONTRAK
TGL. KONTRAK
: 115.A/SPK/45.13-CK/PKT-1/600/2020
: 12 OKTOBER 2020
Alamat : Jl. Brigjen (Purn) Abraham O. Ataruri Komplek Kantor Gubernur Papua Barat, Arfai - Manokwari NILAI KONTRAK : Rp 149,850,000.00
LOKASI : KOTA SORONG
KONS. PENGAWAS : CV. ARFAK DESAIN KONSULTAN
RENCANA REALISASI
NO. KONTRAK S/D RENCANA S/D S/D PRESTASI S/D
MATA DEVIASI
URAIAN MINGGU LALU MINGGU INI MINGGU INI MINGGU LALU MINGGU INI MINGGU INI KET.
PEMBA
YARAN BOBOT BOBOT BOBOT BOBOT BOBOT BOBOT BOBOT
SAT. VOLUME VOLUME VOLUME VOLUME VOLUME VOLUME VOLUME
(%) (%) (%) (%) (%) (%) (%) (%)
A. PEKERJAAN PERSIAPAN
1 Mobilisasi dan Demobilisasi Alat LS 1.00 5.14 0.80 4.11 - - 0.80 4.11 0.80 4.11 - - 0.80 4.11 -
2 Papan Nama Proyek uk 80 x 120 CM BH 1.00 0.55 1.00 0.55 - - 1.00 0.55 1.00 0.55 - - 1.00 0.55 -
3 Gudang Penyimpanan Semen M2 16.00 5.29 8.00 2.64 8.00 2.64 16.00 5.29 16.00 5.29 - - 16.00 5.29 -
4 Pembersihan Lapangan M2 220.00 4.16 100.00 1.89 120.00 2.27 220.00 4.16 50.00 0.95 110.00 - 160.00 3.03 (1.13)
5 Manajemen dan Keselamatan Lalu Lintas LS 1.00 0.68 0.29 0.19 0.14 0.10 0.43 0.29 0.33 0.23 0.17 - 0.50 0.34 0.05
6 Keselamatan dan Kesehatan Kerja (K3) LS 1.00 0.73 0.25 0.18 0.13 0.09 0.38 0.28 0.33 0.24 0.17 - 0.50 0.37 0.09
7 Dokumentasi dan Laporan LS 1.00 4.40 0.25 1.10 0.13 0.55 0.38 1.65 0.33 1.47 0.17 - 0.50 2.20 0.55
B. PEKERJAAN TANAH
1 Urugan Pilihan M3 31.94 6.98 10.65 2.33 10.65 2.33 21.29 4.65 7.00 1.53 9.00 - 16.00 3.50 (1.16)
C. PEKERJAAN STRUKTUR
1 Cor Beton Mutu fc = 19,3 Mpa, t = 20 cm M3 44.00 69.86 - - 4.00 6.35 4.00 6.35 - - 3.00 - 3.00 4.76 (1.59)
2 Bekesting Papan Kayu Kelas III M2 27.50 2.21 - - 12.00 0.96 12.00 0.96 - - 8.00 - 8.00 0.64 (0.32)
JUMLAH BOBOT PEKERJAAN (%) 100.00 13.00 15.29 28.29 14.36 - 24.78 (3.51)
BOBOT MINGGU INI ( % )
a. RENCANA 28.29
b. REALISASI 24.78
c. DEVIASI = ( b ) - ( a ) -3.51
LAPORAN MINGGUAN
MINGGU KE - :4
PEMERINTAH PROVINSI PAPUA BARAT PERIODE : 02 November 2020 s/d
08 November 2020
DINAS PEKERJAAN UMUM KONTRAKTOR : CV. BESAWI
DAN PERUMAHAN RAKYAT PAKET : PEMBANGUNAN JALAN LINGKUNGAN KOTA SORONG (PAKET 1)
NO. KONTRAK
TGL. KONTRAK
: 115.A/SPK/45.13-CK/PKT-1/600/2020
: 12 OKTOBER 2020
Alamat : Jl. Brigjen (Purn) Abraham O. Ataruri Komplek Kantor Gubernur Papua Barat, Arfai - Manokwari NILAI KONTRAK : Rp 149,850,000.00
LOKASI : KOTA SORONG
KONS. PENGAWAS : CV. ARFAK DESAIN KONSULTAN
RENCANA REALISASI
NO. KONTRAK S/D RENCANA S/D S/D PRESTASI S/D
MATA DEVIASI
URAIAN MINGGU LALU MINGGU INI MINGGU INI MINGGU LALU MINGGU INI MINGGU INI KET.
PEMBA
YARAN BOBOT BOBOT BOBOT BOBOT BOBOT BOBOT BOBOT
SAT. VOLUME VOLUME VOLUME VOLUME VOLUME VOLUME VOLUME
(%) (%) (%) (%) (%) (%) (%) (%)
A. PEKERJAAN PERSIAPAN
1 Mobilisasi dan Demobilisasi Alat LS 1.00 5.14 0.80 4.11 - - 0.80 4.11 0.80 4.11 - - 0.80 4.11 -
2 Papan Nama Proyek uk 80 x 120 CM BH 1.00 0.55 1.00 0.55 - - 1.00 0.55 1.00 0.55 - - 1.00 0.55 -
3 Gudang Penyimpanan Semen M2 16.00 5.29 8.00 2.64 8.00 2.64 16.00 5.29 16.00 5.29 - - 16.00 5.29 -
4 Pembersihan Lapangan M2 220.00 4.16 100.00 1.89 120.00 2.27 220.00 4.16 160.00 3.03 60.00 - 220.00 4.16 -
5 Manajemen dan Keselamatan Lalu Lintas LS 1.00 0.68 0.29 0.19 0.14 0.10 0.43 0.29 0.50 0.34 0.17 - 0.67 0.45 0.16
6 Keselamatan dan Kesehatan Kerja (K3) LS 1.00 0.73 0.25 0.18 0.13 0.09 0.38 0.28 0.50 0.37 0.17 - 0.67 0.49 0.21
7 Dokumentasi dan Laporan LS 1.00 4.40 0.25 1.10 0.13 0.55 0.38 1.65 0.50 2.20 0.17 - 0.67 2.94 1.28
B. PEKERJAAN TANAH
1 Urugan Pilihan M3 31.94 6.98 10.65 2.33 10.65 2.33 21.29 4.65 16.00 3.50 7.00 - 23.00 5.03 0.37
C. PEKERJAAN STRUKTUR
1 Cor Beton Mutu fc = 19,3 Mpa, t = 20 cm M3 44.00 69.86 - - 4.00 6.35 4.00 6.35 3.00 4.76 6.00 - 9.00 14.29 7.94
2 Bekesting Papan Kayu Kelas III M2 27.50 2.21 - - 12.00 0.96 12.00 0.96 8.00 0.64 12.00 - 20.00 1.61 0.64
JUMLAH BOBOT PEKERJAAN (%) 100.00 13.00 15.29 28.29 24.78 - 38.91 10.61
BOBOT MINGGU INI ( % )
a. RENCANA 28.29
b. REALISASI 38.91
c. DEVIASI = ( b ) - ( a ) 10.61
LAPORAN MINGGUAN
MINGGU KE - :5
PEMERINTAH PROVINSI PAPUA BARAT PERIODE : 09 November 2020 s/d
15 November 2020
DINAS PEKERJAAN UMUM KONTRAKTOR : CV. BESAWI
DAN PERUMAHAN RAKYAT PAKET : PEMBANGUNAN JALAN LINGKUNGAN KOTA SORONG (PAKET 1)
NO. KONTRAK
TGL. KONTRAK
: 115.A/SPK/45.13-CK/PKT-1/600/2020
: 12 OKTOBER 2020
Alamat : Jl. Brigjen (Purn) Abraham O. Ataruri Komplek Kantor Gubernur Papua Barat, Arfai - Manokwari NILAI KONTRAK : Rp 149,850,000.00
LOKASI : KOTA SORONG
KONS. PENGAWAS : CV. ARFAK DESAIN KONSULTAN
RENCANA REALISASI
NO. KONTRAK S/D RENCANA S/D S/D PRESTASI S/D
MATA DEVIASI
URAIAN MINGGU LALU MINGGU INI MINGGU INI MINGGU LALU MINGGU INI MINGGU INI KET.
PEMBA
YARAN BOBOT BOBOT BOBOT BOBOT BOBOT BOBOT BOBOT
SAT. VOLUME VOLUME VOLUME VOLUME VOLUME VOLUME VOLUME
(%) (%) (%) (%) (%) (%) (%) (%)
A. PEKERJAAN PERSIAPAN
1 Mobilisasi dan Demobilisasi Alat LS 1.00 5.14 0.80 4.11 - - 0.80 4.11 0.80 4.11 - - 0.80 4.11 -
2 Papan Nama Proyek uk 80 x 120 CM BH 1.00 0.55 1.00 0.55 - - 1.00 0.55 1.00 0.55 - - 1.00 0.55 -
3 Gudang Penyimpanan Semen M2 16.00 5.29 16.00 5.29 - - 16.00 5.29 16.00 5.29 - - 16.00 5.29 -
4 Pembersihan Lapangan M2 220.00 4.16 220.00 4.16 - - 220.00 4.16 220.00 4.16 - - 220.00 4.16 -
5 Manajemen dan Keselamatan Lalu Lintas LS 1.00 0.68 0.57 0.39 0.14 0.10 0.71 0.48 0.67 0.45 0.17 - 0.83 0.56 0.08
6 Keselamatan dan Kesehatan Kerja (K3) LS 1.00 0.73 0.50 0.37 0.13 0.09 0.63 0.46 0.67 0.49 0.17 - 0.83 0.61 0.15
7 Dokumentasi dan Laporan LS 1.00 4.40 0.50 2.20 0.13 0.55 0.63 2.75 0.67 2.94 0.17 - 0.83 3.67 0.92
B. PEKERJAAN TANAH
1 Urugan Pilihan M3 31.94 6.98 31.94 6.98 - - 31.94 6.98 23.00 5.03 8.94 - 31.94 6.98 -
C. PEKERJAAN STRUKTUR
1 Cor Beton Mutu fc = 19,3 Mpa, t = 20 cm M3 44.00 69.86 12.00 19.05 12.00 19.05 24.00 38.10 9.00 14.29 12.00 - 21.00 33.34 (4.76)
2 Bekesting Papan Kayu Kelas III M2 27.50 2.21 20.00 1.61 7.50 0.60 27.50 2.21 20.00 1.61 7.50 - 27.50 2.21 -
JUMLAH BOBOT PEKERJAAN (%) 100.00 44.70 20.39 65.10 38.91 - 61.49 (3.61)
BOBOT MINGGU INI ( % )
a. RENCANA 65.10
b. REALISASI 61.49
c. DEVIASI = ( b ) - ( a ) -3.61
LAPORAN MINGGUAN
MINGGU KE - :6
PEMERINTAH PROVINSI PAPUA BARAT PERIODE : 16 November 2020 s/d
22 November 2020
DINAS PEKERJAAN UMUM KONTRAKTOR : CV. BESAWI
DAN PERUMAHAN RAKYAT PAKET : PEMBANGUNAN JALAN LINGKUNGAN KOTA SORONG (PAKET 1)
NO. KONTRAK
TGL. KONTRAK
: 115.A/SPK/45.13-CK/PKT-1/600/2020
: 12 OKTOBER 2020
Alamat : Jl. Brigjen (Purn) Abraham O. Ataruri Komplek Kantor Gubernur Papua Barat, Arfai - Manokwari NILAI KONTRAK : Rp 149,850,000.00
LOKASI : KOTA SORONG
KONS. PENGAWAS : CV. ARFAK DESAIN KONSULTAN
RENCANA REALISASI
NO. KONTRAK S/D RENCANA S/D S/D PRESTASI S/D
MATA DEVIASI
URAIAN MINGGU LALU MINGGU INI MINGGU INI MINGGU LALU MINGGU INI MINGGU INI KET.
PEMBA
YARAN BOBOT BOBOT BOBOT BOBOT BOBOT BOBOT BOBOT
SAT. VOLUME VOLUME VOLUME VOLUME VOLUME VOLUME VOLUME
(%) (%) (%) (%) (%) (%) (%) (%)
A. PEKERJAAN PERSIAPAN
1 Mobilisasi dan Demobilisasi Alat LS 1.00 5.14 0.80 4.11 - - 0.80 4.11 0.80 4.11 - - 0.80 4.11 -
2 Papan Nama Proyek uk 80 x 120 CM BH 1.00 0.55 1.00 0.55 - - 1.00 0.55 1.00 0.55 - - 1.00 0.55 -
3 Gudang Penyimpanan Semen M2 16.00 5.29 16.00 5.29 - - 16.00 5.29 16.00 5.29 - - 16.00 5.29 -
4 Pembersihan Lapangan M2 220.00 4.16 220.00 4.16 - - 220.00 4.16 220.00 4.16 - - 220.00 4.16 -
5 Manajemen dan Keselamatan Lalu Lintas LS 1.00 0.68 0.71 0.48 0.14 0.10 0.86 0.58 0.83 0.56 0.17 - 1.00 0.68 0.10
6 Keselamatan dan Kesehatan Kerja (K3) LS 1.00 0.73 0.63 0.46 0.13 0.09 0.75 0.55 0.83 0.61 0.17 - 1.00 0.73 0.18
7 Dokumentasi dan Laporan LS 1.00 4.40 0.63 2.75 0.13 0.55 0.75 3.30 0.83 3.67 0.17 - 1.00 4.40 1.10
B. PEKERJAAN TANAH
1 Urugan Pilihan M3 31.94 6.98 31.94 6.98 - - 31.94 6.98 31.94 6.98 - - 31.94 6.98 -
C. PEKERJAAN STRUKTUR
1 Cor Beton Mutu fc = 19,3 Mpa, t = 20 cm M3 44.00 69.86 24.00 38.10 10.00 15.88 34.00 53.98 21.00 33.34 23.00 - 44.00 69.86 15.88
2 Bekesting Papan Kayu Kelas III M2 27.50 2.21 27.50 2.21 - - 27.50 2.21 27.50 2.21 - - 27.50 2.21 -
JUMLAH BOBOT PEKERJAAN (%) 100.00 65.10 16.62 81.71 61.49 - 98.97 17.26
BOBOT MINGGU INI ( % )
a. RENCANA 81.71
b. REALISASI 98.97
c. DEVIASI = ( b ) - ( a ) 17.26
LAPORAN MINGGUAN
MINGGU KE - :7
PEMERINTAH PROVINSI PAPUA BARAT PERIODE : 23 November 2020 s/d
29 November 2020
DINAS PEKERJAAN UMUM KONTRAKTOR : CV. BESAWI
DAN PERUMAHAN RAKYAT PAKET : PEMBANGUNAN JALAN LINGKUNGAN KOTA SORONG (PAKET 1)
NO. KONTRAK
TGL. KONTRAK
: 115.A/SPK/45.13-CK/PKT-1/600/2020
: 12 OKTOBER 2020
Alamat : Jl. Brigjen (Purn) Abraham O. Ataruri Komplek Kantor Gubernur Papua Barat, Arfai - Manokwari NILAI KONTRAK : Rp 149,850,000.00
LOKASI : KOTA SORONG
KONS. PENGAWAS : CV. ARFAK DESAIN KONSULTAN
RENCANA REALISASI
NO. KONTRAK S/D RENCANA S/D S/D PRESTASI S/D
MATA DEVIASI
URAIAN MINGGU LALU MINGGU INI MINGGU INI MINGGU LALU MINGGU INI MINGGU INI KET.
PEMBA
YARAN BOBOT BOBOT BOBOT BOBOT BOBOT BOBOT BOBOT
SAT. VOLUME VOLUME VOLUME VOLUME VOLUME VOLUME VOLUME
(%) (%) (%) (%) (%) (%) (%) (%)
A. PEKERJAAN PERSIAPAN
1 Mobilisasi dan Demobilisasi Alat LS 1.00 5.14 0.80 4.11 - - 0.80 4.11 0.80 4.11 0.20 - 1.00 5.14 1.03
2 Papan Nama Proyek uk 80 x 120 CM BH 1.00 0.55 1.00 0.55 - - 1.00 0.55 1.00 0.55 - - 1.00 0.55 -
3 Gudang Penyimpanan Semen M2 16.00 5.29 16.00 5.29 - - 16.00 5.29 16.00 5.29 - - 16.00 5.29 -
4 Pembersihan Lapangan M2 220.00 4.16 220.00 4.16 - - 220.00 4.16 220.00 4.16 - - 220.00 4.16 -
5 Manajemen dan Keselamatan Lalu Lintas LS 1.00 0.68 0.86 0.58 0.14 0.10 1.00 0.68 1.00 0.68 - - 1.00 0.68 -
6 Keselamatan dan Kesehatan Kerja (K3) LS 1.00 0.73 0.75 0.55 0.13 0.09 0.88 0.64 1.00 0.73 - - 1.00 0.73 0.09
7 Dokumentasi dan Laporan LS 1.00 4.40 0.75 3.30 0.13 0.55 0.88 3.85 1.00 4.40 - - 1.00 4.40 0.55
B. PEKERJAAN TANAH
1 Urugan Pilihan M3 31.94 6.98 31.94 6.98 - - 31.94 6.98 31.94 6.98 - - 31.94 6.98 -
C. PEKERJAAN STRUKTUR
1 Cor Beton Mutu fc = 19,3 Mpa, t = 20 cm M3 44.00 69.86 34.00 53.98 6.00 9.53 40.00 63.51 44.00 69.86 - - 44.00 69.86 6.35
2 Bekesting Papan Kayu Kelas III M2 27.50 2.21 27.50 2.21 - - 27.50 2.21 27.50 2.21 - - 27.50 2.21 -
JUMLAH BOBOT PEKERJAAN (%) 100.00 81.71 10.27 91.98 98.97 - 100.00 8.02
BOBOT MINGGU INI ( % )
a. RENCANA 91.98
b. REALISASI 100.00
c. DEVIASI = ( b ) - ( a ) 8.02
LAPORAN MINGGUAN
MINGGU KE - :8
PEMERINTAH PROVINSI PAPUA BARAT PERIODE : 30 November 2020 s/d
06 Desember 2020
DINAS PEKERJAAN UMUM KONTRAKTOR : CV. BESAWI
DAN PERUMAHAN RAKYAT PAKET : PEMBANGUNAN JALAN LINGKUNGAN KOTA SORONG (PAKET 1)
NO. KONTRAK
TGL. KONTRAK
: 115.A/SPK/45.13-CK/PKT-1/600/2020
: 12 OKTOBER 2020
Alamat : Jl. Brigjen (Purn) Abraham O. Ataruri Komplek Kantor Gubernur Papua Barat, Arfai - Manokwari NILAI KONTRAK : Rp 149,850,000.00
LOKASI : KOTA SORONG
KONS. PENGAWAS : CV. ARFAK DESAIN KONSULTAN
RENCANA REALISASI
NO. KONTRAK S/D RENCANA S/D S/D PRESTASI S/D
MATA DEVIASI
URAIAN MINGGU LALU MINGGU INI MINGGU INI MINGGU LALU MINGGU INI MINGGU INI KET.
PEMBA
YARAN BOBOT BOBOT BOBOT BOBOT BOBOT BOBOT BOBOT
SAT. VOLUME VOLUME VOLUME VOLUME VOLUME VOLUME VOLUME
(%) (%) (%) (%) (%) (%) (%) (%)
A. PEKERJAAN PERSIAPAN
1 Mobilisasi dan Demobilisasi Alat LS 1.00 5.14 0.80 4.11 0.20 1.03 1.00 5.14 1.00 5.14 - - 1.00 5.14 -
2 Papan Nama Proyek uk 80 x 120 CM BH 1.00 0.55 1.00 0.55 - - 1.00 0.55 1.00 0.55 - - 1.00 0.55 -
3 Gudang Penyimpanan Semen M2 16.00 5.29 16.00 5.29 - - 16.00 5.29 16.00 5.29 - - 16.00 5.29 -
4 Pembersihan Lapangan M2 220.00 4.16 220.00 4.16 - - 220.00 4.16 220.00 4.16 - - 220.00 4.16 -
5 Manajemen dan Keselamatan Lalu Lintas LS 1.00 0.68 1.00 0.68 - - 1.00 0.68 1.00 0.68 - - 1.00 0.68 -
6 Keselamatan dan Kesehatan Kerja (K3) LS 1.00 0.73 0.88 0.64 0.13 0.09 1.00 0.73 1.00 0.73 - - 1.00 0.73 -
7 Dokumentasi dan Laporan LS 1.00 4.40 0.88 3.85 0.13 0.55 1.00 4.40 1.00 4.40 - - 1.00 4.40 -
B. PEKERJAAN TANAH
1 Urugan Pilihan M3 31.94 6.98 31.94 6.98 - - 31.94 6.98 31.94 6.98 - - 31.94 6.98 -
C. PEKERJAAN STRUKTUR
1 Cor Beton Mutu fc = 19,3 Mpa, t = 20 cm M3 44.00 69.86 40.00 63.51 4.00 6.35 44.00 69.86 44.00 69.86 - - 44.00 69.86 -
2 Bekesting Papan Kayu Kelas III M2 27.50 2.21 27.50 2.21 - - 27.50 2.21 27.50 2.21 - - 27.50 2.21 -
JUMLAH BOBOT PEKERJAAN (%) 100.00 91.98 8.02 100.00 100.00 - 100.00 -
BOBOT MINGGU INI ( % )
a. RENCANA 100.00
b. REALISASI 100.00
c. DEVIASI = ( b ) - ( a ) 0.00
LAPORAN MINGGUAN
MINGGU KE - :9
PEMERINTAH PROVINSI PAPUA BARAT PERIODE : 07 Desember 2020 s/d
10 Desember 2020
DINAS PEKERJAAN UMUM KONTRAKTOR : CV. BESAWI
DAN PERUMAHAN RAKYAT PAKET : PEMBANGUNAN JALAN LINGKUNGAN KOTA SORONG (PAKET 1)
NO. KONTRAK
TGL. KONTRAK
: 115.A/SPK/45.13-CK/PKT-1/600/2020
: 12 OKTOBER 2020
Alamat : Jl. Brigjen (Purn) Abraham O. Ataruri Komplek Kantor Gubernur Papua Barat, Arfai - Manokwari NILAI KONTRAK : Rp 149,850,000.00
LOKASI : KOTA SORONG
KONS. PENGAWAS : CV. ARFAK DESAIN KONSULTAN
RENCANA REALISASI
NO. KONTRAK S/D RENCANA S/D S/D PRESTASI S/D
MATA DEVIASI
URAIAN MINGGU LALU MINGGU INI MINGGU INI MINGGU LALU MINGGU INI MINGGU INI KET.
PEMBA
YARAN BOBOT BOBOT BOBOT BOBOT BOBOT BOBOT BOBOT
SAT. VOLUME VOLUME VOLUME VOLUME VOLUME VOLUME VOLUME
(%) (%) (%) (%) (%) (%) (%) (%)
A. PEKERJAAN PERSIAPAN
1 Mobilisasi dan Demobilisasi Alat LS 1.00 5.14 0.80 4.11 - - 0.80 4.11 1.00 5.14 - - 1.00 5.14 1.03
2 Papan Nama Proyek uk 80 x 120 CM BH 1.00 0.55 1.00 0.55 - - 1.00 0.55 1.00 0.55 - - 1.00 0.55 -
3 Gudang Penyimpanan Semen M2 16.00 5.29 16.00 5.29 - - 16.00 5.29 16.00 5.29 - - 16.00 5.29 -
4 Pembersihan Lapangan M2 220.00 4.16 220.00 4.16 - - 220.00 4.16 220.00 4.16 - - 220.00 4.16 -
5 Manajemen dan Keselamatan Lalu Lintas LS 1.00 0.68 1.00 0.68 - - 1.00 0.68 1.00 0.68 - - 1.00 0.68 -
6 Keselamatan dan Kesehatan Kerja (K3) LS 1.00 0.73 0.88 0.64 0.13 0.09 1.00 0.73 1.00 0.73 - - 1.00 0.73 -
7 Dokumentasi dan Laporan LS 1.00 4.40 0.88 3.85 0.13 0.55 1.00 4.40 1.00 4.40 - - 1.00 4.40 -
B. PEKERJAAN TANAH
1 Urugan Pilihan M3 31.94 6.98 31.94 6.98 - - 31.94 6.98 31.94 6.98 - - 31.94 6.98 -
C. PEKERJAAN STRUKTUR
1 Cor Beton Mutu fc = 19,3 Mpa, t = 20 cm M3 44.00 69.86 40.00 63.51 4.00 6.35 44.00 69.86 44.00 69.86 - - 44.00 69.86 -
2 Bekesting Papan Kayu Kelas III M2 27.50 2.21 27.50 2.21 - - 27.50 2.21 27.50 2.21 - - 27.50 2.21 -
JUMLAH BOBOT PEKERJAAN (%) 100.00 91.98 6.99 98.97 100.00 - 100.00 1.03
BOBOT MINGGU INI ( % )
a. RENCANA 98.97
b. REALISASI 100.00
c. DEVIASI = ( b ) - ( a ) 1.03
WAKTU PELAKSANAAN
NO. OKT - NOV NOV - DES DES
MATA URAIAN PEKERJAAN SATUAN VOLUME HARGA JUMLAH BOBOT 12/10/20 19/10/20 26/10/20 02/11/20 09/11/20 16/11/20 23/11/20 30/11/20 07/12/20 PROGRESS
PEMBAY
ARAN SATUAN HARGA (%) s/d s/d s/d s/d s/d s/d s/d s/d s/d
(Rp.) (Rp.) 18/10/20 25/10/20 01/11/20 08/11/20 15/11/20 22/11/20 29/11/20 06/12/20 10/12/20
MG 1 MG 2 MG 3 MG 4 MG 5 MG 6 MG 7 MG 8 MG 9
1 Cor Beton Mutu fc = 19,3 Mpa, t = 20 cm M3 44.00 2,162,891.00 95,167,204.00 69.86 - -14.36 6.35 12.70 19.05 15.88 9.53 6.35 - 10
69.860.00 1.77
- - 4.76 9.53 19.05 36.52 - - -
2 Bekesting Papan Kayu Kelas III M2 27.50 109,490.00 3,010,975.00 2.21 - - 0.96 0.64 0.60 - - - -
-2.51
0
2.210.00 - 0.64 0.96 0.60 - - - -
(A) Jumlah Harga Pekerjaan ( termasuk Biaya Umum dan Keuntungan ) 136,227,611.00 100.00 100.00
(B) Pajak Pertambahan Nilai ( PPN ) = 10% x (A) 13,622,761.10
(C) Jumlah Total Harga Pekerjaan = (A) + (B) 149,850,372.10
(D) Rekapitulasi Harga (Dibulatkan) 149,850,000.00
Bobot Kemajuan Pekerjaan Mingguan (%) 0.00 1.77 11.23 15.29 16.41 20.39 16.62 10.27 8.02 0.00
RENCANA
Bobot Kemajuan Kumulatif Pekerjaan Mingguan (%) 0.00 1.77 13.00 28.29 44.70 65.10 81.71 91.98 100.00 100.00
Bobot Kemajuan Pekerjaan Mingguan (%) 0.00 2.51 11.85 10.42 14.12 22.58 37.49 1.03
REALISASI
Bobot Kemajuan Kumulatif Pekerjaan Mingguan (%) 0.00 2.51 14.36 24.78 38.91 61.49 98.97 100.00
LAPORAN BULANAN
MINGGU KE - :5
PEMERINTAH PROVINSI PAPUA BARAT PERIODE : 12 Oktober 2020 s/d
08 November 2020
DINAS PEKERJAAN UMUM KONTRAKTOR : CV. BESAWI
DAN PERUMAHAN RAKYAT PAKET : PEMBANGUNAN JALAN LINGKUNGAN KOTA SORONG (PAKET 1)
NO. KONTRAK
TGL. KONTRAK
: 115.A/SPK/45.13-CK/PKT-1/600/2020
: 12 OKTOBER 2020
Alamat : Jl. Brigjen (Purn) Abraham O. Ataruri Komplek Kantor Gubernur Papua Barat, Arfai - Manokwari NILAI KONTRAK : Rp 149,850,000.00
LOKASI : KOTA SORONG
KONS. PENGAWAS : CV. ARFAK DESAIN KONSULTAN
RENCANA REALISASI
NO. KONTRAK S/D RENCANA S/D S/D PRESTASI S/D
MATA DEVIASI
URAIAN MINGGU LALU MINGGU INI MINGGU INI MINGGU LALU MINGGU INI MINGGU INI KET.
PEMBA
YARAN BOBOT BOBOT BOBOT BOBOT BOBOT BOBOT BOBOT
SAT. VOLUME VOLUME VOLUME VOLUME VOLUME VOLUME VOLUME
(%) (%) (%) (%) (%) (%) (%) (%)
A. PEKERJAAN PERSIAPAN
1 Mobilisasi dan Demobilisasi Alat LS 1.00 5.14 - - 0.80 4.11 0.80 4.11 - - 0.80 4.11 0.80 4.11 -
2 Papan Nama Proyek uk 80 x 120 CM BH 1.00 0.55 - - 1.00 0.55 1.00 0.55 - - 1.00 0.55 1.00 0.55 -
3 Gudang Penyimpanan Semen M2 16.00 5.29 - - 16.00 5.29 16.00 5.29 - - 16.00 5.29 16.00 5.29 -
4 Pembersihan Lapangan M2 220.00 4.16 - - 220.00 4.16 220.00 4.16 - - 220.00 4.16 220.00 4.16 -
5 Manajemen dan Keselamatan Lalu Lintas LS 1.00 0.68 - - 0.57 0.39 0.57 0.39 - - 0.67 0.45 0.67 0.45 0.06
6 Keselamatan dan Kesehatan Kerja (K3) LS 1.00 0.73 - - 0.50 0.37 0.50 0.37 - - 0.67 0.49 0.67 0.49 0.12
7 Dokumentasi dan Laporan LS 1.00 4.40 - - 0.50 2.20 0.50 2.20 - - 0.67 2.94 0.67 2.94 0.73
B. PEKERJAAN TANAH
1 Urugan Pilihan M3 31.94 6.98 - - 31.94 6.98 31.94 6.98 - - 23.00 5.03 23.00 5.03 (1.95)
C. PEKERJAAN STRUKTUR
1 Cor Beton Mutu fc = 19,3 Mpa, t = 20 cm M3 44.00 69.86 - - 12.00 19.05 12.00 19.05 - - 9.00 14.29 9.00 14.29 (4.76)
2 Bekesting Papan Kayu Kelas III M2 27.50 2.21 - - 20.00 1.61 20.00 1.61 - - 20.00 1.61 20.00 1.61 -
JUMLAH BOBOT PEKERJAAN (%) 100.00 - 44.70 44.70 - 38.91 38.91 (5.80)
BOBOT BULAN INI ( % )
a. RENCANA 44.70
b. REALISASI 38.91
c. DEVIASI = ( b ) - ( a ) -5.80
LAPORAN BULANAN
MINGGU KE - :5
PEMERINTAH PROVINSI PAPUA BARAT PERIODE : 09 November 2020 s/d
06 Desember 2020
DINAS PEKERJAAN UMUM KONTRAKTOR : CV. BESAWI
DAN PERUMAHAN RAKYAT PAKET : PEMBANGUNAN JALAN LINGKUNGAN KOTA SORONG (PAKET 1)
NO. KONTRAK
TGL. KONTRAK
: 115.A/SPK/45.13-CK/PKT-1/600/2020
: 12 OKTOBER 2020
Alamat : Jl. Brigjen (Purn) Abraham O. Ataruri Komplek Kantor Gubernur Papua Barat, Arfai - Manokwari NILAI KONTRAK : Rp 149,850,000.00
LOKASI : KOTA SORONG
KONS. PENGAWAS : CV. ARFAK DESAIN KONSULTAN
RENCANA REALISASI
NO. KONTRAK S/D RENCANA S/D S/D PRESTASI S/D
MATA DEVIASI
URAIAN MINGGU LALU MINGGU INI MINGGU INI MINGGU LALU MINGGU INI MINGGU INI KET.
PEMBA
YARAN BOBOT BOBOT BOBOT BOBOT BOBOT BOBOT BOBOT
SAT. VOLUME VOLUME VOLUME VOLUME VOLUME VOLUME VOLUME
(%) (%) (%) (%) (%) (%) (%) (%)
A. PEKERJAAN PERSIAPAN
1 Mobilisasi dan Demobilisasi Alat LS 1.00 5.14 0.80 4.11 0.20 1.03 1.00 5.14 0.80 4.11 0.20 1.03 1.00 5.14 -
2 Papan Nama Proyek uk 80 x 120 CM BH 1.00 0.55 1.00 0.55 - - 1.00 0.55 1.00 0.55 - - 1.00 0.55 -
3 Gudang Penyimpanan Semen M2 16.00 5.29 16.00 5.29 - - 16.00 5.29 16.00 5.29 - - 16.00 5.29 -
4 Pembersihan Lapangan M2 220.00 4.16 220.00 4.16 - - 220.00 4.16 220.00 4.16 - - 220.00 4.16 -
5 Manajemen dan Keselamatan Lalu Lintas LS 1.00 0.68 0.57 0.39 0.43 0.29 1.00 0.68 0.67 0.45 0.33 0.23 1.00 0.68 -
6 Keselamatan dan Kesehatan Kerja (K3) LS 1.00 0.73 0.50 0.37 0.50 0.37 1.00 0.73 0.67 0.49 0.33 0.24 1.00 0.73 -
7 Dokumentasi dan Laporan LS 1.00 4.40 0.50 2.20 0.50 2.20 1.00 4.40 0.67 2.94 0.33 1.47 1.00 4.40 -
B. PEKERJAAN TANAH
1 Urugan Pilihan M3 31.94 6.98 31.94 6.98 - - 31.94 6.98 23.00 5.03 8.94 1.95 31.94 6.98 -
C. PEKERJAAN STRUKTUR
1 Cor Beton Mutu fc = 19,3 Mpa, t = 20 cm M3 44.00 69.86 12.00 19.05 32.00 50.81 44.00 69.86 9.00 14.29 35.00 55.57 44.00 69.86 -
2 Bekesting Papan Kayu Kelas III M2 27.50 2.21 20.00 1.61 7.50 0.60 27.50 2.21 20.00 1.61 7.50 0.60 27.50 2.21 -
JUMLAH BOBOT PEKERJAAN (%) 100.00 44.70 55.30 100.00 38.91 61.09 100.00 -
BOBOT BULAN INI ( % )
a. RENCANA 100.00
b. REALISASI 100.00
c. DEVIASI = ( b ) - ( a ) 0.00
08 - 09
09 - 10
10 - 11
11 - 12
12 - 13
13 - 14
14 - 15
15 - 16
16 - 17
17 - 18
2 Pejab. Pelak. Tek. Keg. 1 1 JUMLAH
3 Direksi Teknis 1 1
4 Supervisi Engineer 1 1 1 CERAH 1 1 1 1 - 1 1 1 1 1 1 10
5 Inspector 1 1 2 MENDUNG - - - - - - - - - - - -
6 Site Manager 1 1 3 GERIMIS - - - - 1 - - - - - - 1
7 Sopir 2 2 4 HUJAN LEBAT - - - - - - - - - - - -
E.2 KEJADIAN PENGHAMBAT PEKERJAAN
F. USULAN / SARAN / PENGAJUAN / INSTRUKSI / KESEPAKATAN / PELAPORAN Tanda Tangan dan Nama yang Jelas
PIHAK PENYEDIA :
MARIKE HOWAY
Direktur
PIHAK KONSULTAN :
REMAN PAWARRANGAN, ST
Supervisi Engineer
PIHAK DIREKSI :
KONTRAKTOR PELASANA :
CV. BESAWI
BACK UP DATA
KONDISI 100 %
KONTRAKTOR PELASANA :
CV. BESAWI
SCHEDULE
KONDISI 100 %
KONTRAKTOR PELASANA :
CV. BESAWI
LAPORAN BULANAN
KONDISI 100 %
KONTRAKTOR PELASANA :
CV. BESAWI
LAPORAN MINGGUAN
KONDISI 100 %
KONTRAKTOR PELASANA :
CV. BESAWI
LAPORAN HARIAN
KONDISI 100 %
KONTRAKTOR PELASANA :
CV. BESAWI
DOKUMENTASI KEGIATAN
KONDISI 100 %
KONTRAKTOR PELASANA :
CV. BESAWI
ORGANISASI PERANGKAT DAERAH
DINAS PEKERJAAN UMUM DAN PERUMAHAN RAKYAT
BIDANG CIPTA KARYA
JL.BrigjendMarinir Abraham O. Atururi, Manokwari – Papua Barat
LAPORAN PENDAHULUAN
Paket :
Nomor Kontrak :
Tanggal Kontrak :
Disampaikan Oleh :
SURAT PENGANTAR
Manokwari, 15 Oktober 2020
Nomor :
Lampiran :
Kepada Yth
Dengan Hormat,
Bersama ini kami sampaikan Laporan Pendahuluan untuk kegiatan Pengawasan Teknis Pembangunan Jalan
Lingkungan Kota Sorong, sebanyak 5 (Lima) Buku berdasarkan kontrak nomor: XXXX-XXXXXXX-
XXXXXXX-XXXXXXX, tanggal 12 Oktober 2020
Laporan ini pada dasarnya untuk menginformasikan gambaran umum Rencana Kerja Pelaksanaan Kegiatan.
Demikian Laporan Pendahuluan ini kami sampaikan, dan atas perhatian Bapak diucapkan terima kasih.
Hormat Kami.
Konsultan Supervisi
CV. ARFAK DESAIN KONSULTAN
…………………………………….
Supervisi Engineering
KATA PENGANTAR
Dengan memanjatkan Puji syukur kepada TuhanYang Maha Esa dan atas ijin dan Pertolongan-Nya Laporan Pendahuluan ini dapat
dlselesaikan, yang selanjutnya Laporan ini disampaikan kepada Pengguanajasa yaitu Pejabat Pembuat Komitmen OPD Dinas Pekerjaan
Umum Dan Penataan Ruang Provinsi Papua Barat Di Manokwari.
Laporan ini dibuat dalam rangka memenuhi kewajiban Konsultan Supervisi No Kontrak 050.C/KONTR/15.65-BM/600/2019, tanggal
02 September 2019. Paket Pengawasan Teknis Pembangunan Jalan Kota Sorong antara Pejabat Pembuat Komitmen OPD Dinas Pekerjaan
Umum Dan Perumahan Rakyat Provinsi Papua Barat sebagai Pengguna Jasa dan CV. MITRA PAPUA sebagai penyedia Jasa
Secara umum Laporan ini menjelaskan tentang pelaksanaan survey pendahuluan dan rekayasa lapangan untuk rencana penanganan yang
nantinya akan tertuang pada justifikasi teknis dan laporan pendahuluan ini.
Kami memberikan penghargaandan rasa terima kasih kepada semua pihak atas bantuan dan kerjasamanya,sehingga selesainya penyusunan
Laporan Pendahuluan ini, semoga dapat dipergunakan sebagai informasi aktual dasar untuk kepentingan kegiatan lainnya yang
berkesinambungan.
Akhimya semoga Laporan ini dapat bermanfaat,dan kami mengharapkan kritik dan saran yang membangun guna kesempumaan Laporan ini
dimasa yang akan datang.
…………………………………………………………
Site Engineer
LAPORAN PENDAHULUAN
LOKASI KOTA SORONG
DAFTAR ISI
Bulan Oktober 2020
I PENDAHULUAN
II RECONNAISSANCE
IV METODOLOGI SUPERVISI
V RENCANA PENANGANAN
Halaman ii
LAPORAN PENDAHULUAN
LOKASI KOTA SORONG
DAFTAR ISI
Bulan Oktober 2020
Halaman ii
LAPORAN PENDAHULUAN
BAB. I BULAN OKTOBER 2020
PENDAHULUAN LOKASI KOTA SORONG
PPK BIDANG CIPTA KARYA – OPD DPUPR PROVINSI PAPUA BARAT
PENGAWASAN TEKNIS PEMBANGUNAN JALAN LINGKUNGAN KOTA SORONG
I. Pendahuluan
Penyedian infrastruktur jalan merupakan suatu sektor pembangunan yang paling dibutuhkan di Kota Sorong, Papua
Barat dikarenakan ada banyak ketergantungan perkembangan ekonomi, sosial dan pendidikan dengan pembangunan
infrastruktur jalan itu sendiri. penyediaan infrastruktur jalan yang merata di wilayah Kota Sorong merupakan hal mutlak
untuk mewujudkan Kota yang mandiri, dengan pengelolaan pembangunan fisik kota yang meliputi sistem transportasi
yang terinkoneksi antar wilayah.
Jalan merupakan prasarana angkutan darat yang sangat penting untuk memperlancar kegiatan perekonomian. Usaha
pembangunan yang meningkat menuntut adanya sarana transportasi untuk menunjang mobilitas penduduk dan
kelancaran distribusi barang dari dan ke suatu daerah. Kinerja jaringan jalan sebagai hasil dari manajemen pengelolaan
didasarkan kepada beberapa indikator makro yaitu berdasarkan: (1) kemantapan; (2) kondisi dan; (3) pemanfaatan jalan
yang ada.
Peningkatan, rehabilitasi, dan Pembangunan jalan juga dilaksanakan pada wilayah permukiman yang padat
penduduk. Dengan semakin baiknya kondisi jalan semakin memicu tersebarnya kantong-kantong permukiman baru dan
perluasan permukiman yang ada, sehingga penduduk tidak terkonsentrasi pada wilayah hamparan permukiman saja.
Adanya persebaran penduduk akibat semakin baiknya pelayanan jalan ini dapat dilihat dengan mulai tumbuh
permukiman baru mengikuti badan jalan yang telah ditingkatkan tersebut.
Sesuai dengan sasaran Pembangunan Nasional, apa yang telah digariskan dalam Peraturan Pemerintah Nomor 34
Tahun 2006 tentang Jalan dan Peraturan Menteri PUPR Nomor 38/Prt/M/2015 Tentang Bantuan Prasarana, Sarana, Dan
Utilitas Umum Untuk Perumahan Umum. Peran Pemerintah Provinsi Papua Barat, melalui dinas – dinas terkait adalah
melakukan pembangunan, baik dalam pengoperasian dan pemeliharaan yang secara kontinyu, kualitas dan kuantitas.
Diantara usaha dan kebijakannya yang telah dilakukan maka salah satunya adalah dititik beratkan pada Penyediaan
Sarana dan Prasarana Jalan.
Bertambahnya pemukiman penduduk yang merata di wilayah kota sorong menjadikan jalan lingkungan sebagai
kebutuhan masyarakat yang saat ini dibutuhkan untuk kemajuaan dan pengembangan ekonomi,sosial dan pendidikan
yang merata diseluruh Wilayah Kota Sorong.
Salah satu upaya untuk mengatasi kendala diatas maka Pemerintah melalui Dinas Pekerjaan Umum Dan Perumahan
Rakyat Provinsi Papua Barat Bidang Cipta Karya pada tahun anggaran 2020 ini melaksanaan program Pembangunan
Jalan Lingkungan Kota Sorong Diharapkan upaya ini dapat dimanfaatkan langsung Oleh masyarakat yang selama
kesulitan untuk mendapatkan Akses jalan yang memadai guna meningkatkan Aktivitas serta Produktifitas masyarakat.
Halaman 127
LAPORAN PENDAHULUAN
BAB. I BULAN OKTOBER 2020
PENDAHULUAN LOKASI KOTA SORONG
PPK BIDANG CIPTA KARYA – OPD DPUPR PROVINSI PAPUA BARAT
PENGAWASAN TEKNIS PEMBANGUNAN JALAN LINGKUNGAN KOTA SORONG
1.2 Maksud dan Tujuaan
Pemahaman pekerjaan adalah pengertian konsultan mengena itu juan prinsip-prinsip, konsep dan lingkup pekerjaan
yang akan dilaksanakan. Secara umum penafsiran pelayanan jasa konsultan supervise adalah sebagai pihak penyedia
jasa yang dapat memberikan jaminan kepada pihak proyek bahwa hasil kerja kontraktor pelaksana diharapkan
memuaskan secara mutu, volume dan tepat waktu.
Kebijaksanaan untuk menjamin agar pelaksanaan konstruksi mengikuti rencana teknis / spesifikasi teknis salah
satunya yang penting adalah menyediakan jasa konsultan supervisi. Konsultan Supervisi bertindak sebagai wakil direksi
baik di kantor maupun di lapangan (Engineers Representative) sehingga akhirnya diharapkan bahwa pemerintah akan
memperoleh hasil pekerjaan yang sesuai dengan yang diharapkan yaitu Tepat waktu, Tepat Mutu dan Tepat Anggaran.
Kegiatan Paket Pengawasan Teknis Pembangunan Jalan Lingkungan Kota Sorong Provinsi Papua Barat yang
tersebar pada 4 titik pembangunan, yaitu pengawasan pada paket Teknis Pembangunan Jalan Lingkungan Kota Sorong.
Kegiatan pada paket ini adalah melaksanakan pekerjaan persiapan, pekerjaan tanah, pekerjaan cor beton. Secara
Geografis Kota Sorong terletak pada Koordinat :
Pada Pekerjaan ini yang harus dikerjakan dan harus sesuai dengan ketentuan yang disetujui oleh Direksi.
a. Pekerjaan Persiapan
Pekerjaan Persiapan meliputi Mobilisasi dan Demobilisasi, Pemasangan Papan NamaProyek, Gudang
Penyimpanan Semen, Pembersihan Lokasi dan penyediaan , Manajemen Keselamatan Lalu Lintas, Keselamatan
dan Kesehatan Kerja, Dokumentasi Laporan
b. Pekerjaan Tanah
Urugan Pilihan
Halaman 128
LAPORAN PENDAHULUAN
BAB. I BULAN OKTOBER 2020
PENDAHULUAN LOKASI KOTA SORONG
PPK BIDANG CIPTA KARYA – OPD DPUPR PROVINSI PAPUA BARAT
PENGAWASAN TEKNIS PEMBANGUNAN JALAN LINGKUNGAN KOTA SORONG
Lokasi pelaksanaan pekerjaan dapat dilihat pada peta lokasi Gambar 1.1.
Gambar 1.1 Peta Lokasi Paket Pengawasan Teknis Pembangunan Jalan Lingkungan di Kota Sorong
Sesuai dengan kontrak Paket Pengawasan Teknis Pembangunan Jalan Lingkungan di Kota Sorong, jangka waktu
pelaksanaan pekerjaan pengawasan teknis pada Paket ini adalah 2 (Dua) bulan atau 60 (EnamPuluh) hari kalender,
terhitung sejak tanggal 12 Oktober 2020 sampai dengan 10 Desember 2020.
Halaman 129
Laporan Pendahuluan
BAB. I Bulan Oktober 2020
PENDAHULUAAN
Lokasi Kota sorong
Tahun : 2020
PEKERJAAN TANAH
- Urugan Pilihan dari sumber galian sebagai mata pembayaran pekerjaan Urugan Pilihan untuk lapis awal dalam pekerjaan
Pembangunan Jalan Lingkungan ini.
Halaman Page 5]
Laporan Pendahuluan
BAB. I Bulan Oktober 2020
PENDAHULUAAN
Lokasi Kota sorong
PEMILIK KEGIATAN
Nama Instansi : DINAS PEKERJAAN UMUM DAN PERUMAHAN RAKYAT PROVINSI PAPUA
BARAT
Nama PPK : COLOMBUS Z. MANDACAN, ST
KONSULTAN SUPERVISI
Nilai Kontrak :
Nomor Kontrak :
Tanggal Kontrak :
KONTRAKTOR PELAKSANA
Nilai Amandemen : -
Nomor Amandemen : -
Tanggal Amandemen : -
Halaman Page 5]
Laporan Pendahuluan
BAB. I Bulan Oktober 2020
PENDAHULUAAN
Lokasi Kota sorong
II. RECONNAISSANCE
2.1 Umum
Lokasi kegiatan Pengawasan Teknis Pembangunan Jalan Lingkungan Kota Sorong di Kota Sorong Provinsi Papua
Barat yang tersebar di 3 titik. Kondisi Existing pada beberapa lokasi titik pekerjaan dapat dilihat pada gambar berikut
ini.
Secara geografis Secara astronomis, Kota Sorong terletak di Secara geografis, Kota Sorong berposisi pada koordinat
antara 131° 17’ Bujur Timur dan 0° 5’ Lintang Selatan dan dilalui oleh garis khatuliswa. ini memiliki total luas
1.105,00 km².
Secara administratif Kota Sorong Ditahun 2018 terbagi menjadi 10 Distrik dan 41 Kelurahan sebagaimana dapat dilihat
dalam Tabel berikut ini.
Halaman 135
BAB. II LAPORAN PENDAHULUAN
LOKASI KOTA SORONG
Bulan Oktober 2020
RECONNAISSANCE
PPK BIDANG CIPTA KARYA – OPD DPUPR PROVINSI PAPUA BARAT
PENGAWASAN TEKNIS PEMBANGUNAN JALAN LINGKUNGAN KOTA SORONG
2.2 Topografi
Keadaan topografi Kota Sorong sebagai wilayah kepulauan, maka memiliki wilayah daratan yang relatif tidak besar
dan pada umumnya topografi daerahnya didominasi oleh wilayah perbukitan yang masih dipenuhi dengan hutan alami.
Sedangkan wilayah pesisir pantai memiliki karakteristik yang beragam seperti pantai landai berpasir hitam, pantai
landai berpasir putih dengan terumbu karang yang sudah rusak sampai dengan yang masih perawan, pantai dalam dan
hutan mangrove. Kemiringan lahan wilayah perencanaan merupakan lahan dengan kemiringan antara 0% sampai
dengan di atas 40%. Sebagian wilayah berupa pegunungan daerah lereng-lereng yang curam, Daerah pegunungan ini
dapat mencapai 100 – 300 meter di atas permukaan laut. Wilayah dengan ketinggian di bawah 100 meter dpl. umumnya
terdapat pada Pulau Salawati bagian selatan. Jika dilihat dari fisiografinya, maka Kota Sorong bagian utara, yaitu
Sorong Utara dan Timur oleh pegunungan. Sedangkan pada bagian tengah daerah datarnya.
2.3 Geologi
Keadaangeologi Kondisi geologi Kota Sorong didominasi oleh formasi tanah merah, batu kapur dan batu cadas
yang terbentuk pada masa kuarter.. Pada umumnya batu gamping tersebut bersifat padat dan mengandung pasir seperti
batu gamping facet, daram, atkari, zaag, openta, sagewin, dan bogal. Jenis batuan lain di wilayah ini adalah batuan
sedimen konglomerat yang komposisinya terdiri dari bahan yang tahan lapuk berupa konglomerat aneka bahan.
2.4 Demografi
Penduduk Kota Sorong pada tahun 2017 Berdasarkan hasil Pencacahan Sensus Penduduk 2010, jumlah penduduk
Kota Sorong (Angka Sementara) adalah 190.341 jiwa, yang terdiri atas 99.898 laki-laki dan 90.446 perempuan. Jumlah
penduduk terbanyak di Distrik Sorong Utara sebanyak 44.774 jiwa dan jumlah penduduk terkecil berada di Distrik
Sorong Kepulauan dengan Jumlah penduduk 9.710 jiwa. Tahun 2017, jumlah penduduk kota ini bertambah cukup
signifakan menjadi 239.815 jiwa (laki-laki 125.015 jiwa dan perempuan 114.800 jiwa).
Komoditas unggulan Berdasarkan data Badan Pengelola Keuangan dan Aset Daerah Kota Sorong, komposisi
pendapatan daerah pada 2018 sebagai berikut:
Di sektor pariwisata, Pemerintah Mengedukasi masyarakat membangun kampung wisata di kampung-kampung yang
punya potensi keindahan alam laut Fasilitas wisata Kota Sorong adalah taman rekreasi pantai Tanjung Kasuari dengan
pesona pasir putihnya, Pulau Raam, Pulau Soop dan Pulau Doom yang terkenal dengan pantainya yang indah. Juga
pulau Dofior yang terdapat Tugu Selamat Datang di Kota Sorong dengan menggunakan bahasa Moi (suku asli di Kota
Sorong) yang ramah dan bersahabat menyambut pengunjung yang datang di Kota Sorong. Juga tembok Dofior yang
terkenal dengan pemandangan panorama laut dan keindahan alam menjelang senja.
Halaman 136
BAB. II LAPORAN PENDAHULUAN
LOKASI KOTA SORONG
Bulan Oktober 2020
RECONNAISSANCE
PPK BIDANG CIPTA KARYA – OPD DPUPR PROVINSI PAPUA BARAT
PENGAWASAN TEKNIS PEMBANGUNAN JALAN LINGKUNGAN KOTA SORONG
Sorong sangat terkenal akan surganya bawah air, karena di Sorong terdapat beberapa pantai yang menyuguhkan
keindahan bawah airnya sangat mempesona. Nama Sorong berasal dari kata Soren yang berarti laut dalam yang
bergelombang. Kemudian suku Biak Numfor menyebut kota ini “Daratan Maladum” akan tetapi para pedagang asing
menyebut Soron dengan sebutan Sorong. Sehingga kota ini mempunyai nama kota Sorong. Selain keindahan bawah air
laut kota Sorong mempunyai nilai sejarah yaitu saat zaman penjajahan Belanda kota Sorong memiliki perusahaan
minyak yang bernama Heritage Nederlans Nieuw-Guinea Petroleum Maatschappij. Keberadaan wisata menjadi
aktualisasi keterlibatan langsung masyarakat sebagai operator dan penyedia jasa wisata, turis asing yang datang hanya
sekitar 2.000 orang, tapi tahun 2010 mencapai 3.855 orang. Untuk tahun ini, sampai Oktober, sudah mencapai 6.000
orang. Wisatawan asing umumnya berkunjung pada akhir tahun, yakni Oktober-Desember. Indikator lainnya,
bertambahnya penginapan dari semula satu resort kini menjadi tujuh resort dan lima home stay di kampung wisata.
Demikian juga jumlah kapal pesiar, alternatif wahana eksklusif menikmati Kota Sorong, meningkat dari 12 kapal
menjadi 36 kapal dalam waktu tiga tahun. Tahun lalu, sebanyak 568 turis berwisata dengan kapal pesiar mengitari
perairan Kota Sorong.
Menurut Badan Meteorologi dan Geofisika Sorong, Kepulauan Kota Sorong mempunyai curah hujan rata-rata 2512
mm per tahun, dengan curah hujan tertinggi pada Juli yakni 298 mm dan jumlah hari hujan 19 hari.
Halaman 137
Laporan Pendahuluan
BAB. III Bulan Oktober 2020
KONDISI EKSISTING
Lokasi Kota sorong
PPK BIDANG CIPTA KARYA – OPD DPUPR PROVINSI PAPUA BARAT
PENGAWASAN TEKNIS PEMBANGUNAN JALAN LINGKUNGAN KOTA SORONG
3.1 UMUM
Ruas jalan Lingkungan Kota Sorong adalah salah satu program pemerintah pusat yang merupakan pembangunan jalan Lingkungan,
dimana ruas jalan tersebut merupakan jalan yang menghubungkan antar Pemukiman dikota sorong dengan Kondisi eksisting pada ruas jalan
tersebut belum layak digunakan dalam rangka memperlancar akses transportasi darat yang menghubungkan antar pemukiman Sehingga
pembangunan jalan ini adalah untuk memperlancar arus lalu lintas orang dan barang.
Kondisi Ekisting
1. Eksisting STA 0 + 000 s/d STA 0 + 055 adalah jalan tanpa lapis perkerasan
3. Pada kiri dan kanan jalan sepanjang ruas ini adalah perumahan dan tanah lapang.
Pada ruas ini belum adanya bahu jalan yang memadai, hal ini disebabkan oleh kondisi tanah pada bahu jalan berupa sirtu tanah hitam dan
berlubang, disamping itu juga sempitnya jalan eksisting pada beberapa ruas jalan ini.
Pada ruas ini telah ada saluran air mengikuti kebutuhan jalan eksisting, karna disamping itu juga pada sisi kiri dan kanan jalan merupakan
pemukiman padat penduduk dan pada beberapa ruas terdapat pula tanah lapang yang masih di dominasi material timbunan yang berlumpur .
Pada ruas ini tidak terdapat kondisi eksisting box culvert, hal ini disebabkan oleh belum fungsionalnya ruas jalan tersebut, sehingga kebutuhan
box culvert pada ruas ini belum direncanakan sebelumnya.
Maksud dan tujuan dari pekerjaan pengukuran ulang/kembali adalah sebagai berikut:
- Mempelajari lokasi area pekerjaan dan daerah-daerah sekitarnya dari segi geografis, sosial dan ekonomi secara umum
Pada kegiatan ini dilakukan investigasi pada area lokasi yang akan
dikerjakan dengan mengkondisikan hasil desain dan kebutuhan lapangan,
agar dapat diperoleh kesempurnaan dalam pelaksanaan pekerjaan. Maka
perlu dilakukan investigasi agar pencapaian konstruksi dapat sesuai dengan
yang direncanakan.
Halaman 139
LAPORAN PENDAHULUAN
BAB. IV LOKASI KOTA SORONG
METODEOLOGI SUPERVISI Bulan Oktober 2020
PPK BIDANG CIPTA KARYA – OPD DPUPR PROVINSI PAPUA BARAT
PENGAWASAN TEKNIS PEMBANGUNAN JALAN LINGKUNGAN KOTA SORONG
Kegiatan ini menjadi sangat penting agar didalam pelaksaan yang akan
dikerjakan tidak bermasalah / tidak ada complain dari pihak masyarakat
sekitar. Maka perlu dilakukan kegiatan ini dan juga komunikasi yang
berkelanjutan kepada masyarakat dan aparat kelurahan sebelum memulai
suatu pekerjaan pelaksanaan fisik.
Dari hasil pemantauaan visual dan pengukuran serta investigasi bersama direksi teknik, konsultan supervisi dan
kontraktor pelaksana maka beberapa hal yang kami jadikan kesepakatan dalam laporan pendahuluan ini :
- Perlu dilakukan komunikasi dan sosialisasi kepada masyarakat pemiliklahan di sekitar lokasi pekerjaan.
- Kerjasama dengan aparatur / perangkat kelurahan dalam memastikan batas-batas lahan di sekitar lokasi pekerjaan.
- Untuk memudahkan akses ke lokasi pekerjaan agar pembuatan jalan inspeksi dikerjakan terlebih dahulu sebelum
kegiatan yang lain.
Halaman 140
BAB. V LAPORAN PENDAHULUAN
LOKASI KOTA SORONG
V. RENCANA PENANGANAN
5.1 UMUM
Di dalam kontrak pelaksanaan fisik yang tertuang daftar kuantitas dan harga. Rencana penanganan Pembangunan Jalan Lingkungan
Kota Sorong yaitu item pekerjaan terdiri dari:
1. Pekerjaan Persiapaan
2. Pekerjaan Tanah
3. Pekerjaan Cor Beton
1. Melakukan Pembersihan lokasi pekerjaan dari tanaman maupun material yang secara teknis menganggu pelaksanaan
pekerjaan pembangunan jalan ini.
2. Melakukan Urugan Pilihan pada badan jalan yang mana sebagai lapis awal dari pelaksanaan pembangunan jalan ini.
3. Melakukan Pengecoran Beton pada badan jalan yang sebagai lapis akhir dari pelaksanaan pekerjaan ini.
4. Rencana Pembangunan jalan lingkungan ini dengan ukuran 4 meter dan tinggi 20 cm dari lapis awal yang mana lebar
jalan 4 meter ini merupakan daerah fungsi jalan.
BAB. V LAPORAN PENDAHULUAN
LOKASI KOTA SORONG
PENGECORAN
BETON PADA
BADAN JALAN
RENCANA PENANGANAN
URUGAN PILIHAN
DARI SUMBER
GALIAN
PPK BIDANG CIPTA KARYA – OPD DPUPR PROVINSI PAPUA BARAT
PENGAWASAN TEKNIS PEMBANGUNAN JALAN LINGKUNGAN KOTA SORONG
EXISTING
Bulan
Oktober 2020
LAPORAN PENDAHULUAN
LOKASI KOTA SORONG
BAB. V LAPORAN PENDAHULUAN
LOKASI KOTA SORONG
VOLUME 28 M3
TEBAL 20 CM
LEBAR 4M
PANJANG 35 M
VOLUME 28
TEBAL 15 CM
LEBAR 3.5 M
PANJANG 40 M
VOLUME 28
TEBAL 15 CM
LEBAR 3M
PANJANG 47 M
VOLUME 28
TEBAL 15 CM
LEBAR 3M
PANJANG 47 M
PENGECORAN
BETON PADA
BADAN JALAN
RENCANA PENANGANAN
URUGAN PILIHAN
DARI SUMBER
GALIAN
PPK BIDANG CIPTA KARYA – OPD DPUPR PROVINSI PAPUA BARAT
PENGAWASAN TEKNIS PEMBANGUNAN JALAN LINGKUNGAN KOTA SORONG
EXISTING
Bulan
Oktober 2020
LAPORAN PENDAHULUAN
LOKASI KOTA SORONG
STRIP MAP PENANGANAN
PENGECORAN
BETON PADA
BADAN JALAN
RENCANA PENANGANAN
URUGAN PILIHAN
DARI SUMBER
GALIAN
PPK BIDANG CIPTA KARYA – OPD DPUPR PROVINSI PAPUA BARAT
PENGAWASAN TEKNIS PEMBANGUNAN JALAN LINGKUNGAN KOTA SORONG
EXISTING
Bulan
Oktober 2020
LAPORAN PENDAHULUAN
LOKASI KOTA SORONG
LAPORAN PENDAHULUAN
BAB. VII
LOKASI KOTA SORONG
MASALAH DAN REKOMENDASI
PENYELESAIAAN Bulan Oktober 2020
PPK BIDANG CIPTA KARYA – OPD DPUPR PROVINSI PAPUA BARAT
PENGAWASAN TEKNIS PEMBANGUNAN JALAN LINGKUNGAN KOTA SORONG
6.1 MASALAH
Pekerjaan Persiapaan
1. Pada beberapa ruas terjadi masalah non teknis dalam hal mobilisasi alat-alat kerja, maupun tenanga kerja
dan lain-lain ke lokasi pekerjaan hal ini berkenaan dengan Pemalangan Jalan oleh pemilik Hak Ulayat di
lokasi pekerjaan sehingga mengharuskan pemberhentian sementara kegiataan pelaksanaan pekerjaan pada
ruas tersebut.
Pekerjaan Tanah
1. Melakukan koordinasi pemindahan lokasi pekerjaan ke lokasi yang telah disetujui serta lebih aman dalam
pelaksanaan pekerjaan.
2. Melakukan MC-0
Struktur Organisasi OPD Dinas Pekerjaan Umum dan Perumahan Rakyat T.A 2020
LAPORAN PENDAHULUAN
LOKASI KOTA SORONG
LAMPIRAN
Bulan Oktober 2020
PPK BIDANG CIPTA KARYA – OPD DPUPR PROVINSI PAPUA BARAT
PENGAWASAN TEKNIS PEMBANGUNAN JALAN LINGKUNGAN KOTA SORONG
Foto Dokumentasi
Keterangan
Kondisi 0%
Lokasi Segmen 1
Koordinat
Keterangan
Kondisi 0%
Lokasi Segmen 1
Koordinat
Keterangan
Kondisi 0%
Lokasi Segmen 1
Koordinat
LAPORAN PENDAHULUAN
LOKASI KOTA SORONG
LAMPIRAN
Bulan Oktober 2020
PPK BIDANG CIPTA KARYA – OPD DPUPR PROVINSI PAPUA BARAT
PENGAWASAN TEKNIS PEMBANGUNAN JALAN LINGKUNGAN KOTA SORONG
Foto Dokumentasi
Keterangan
Kondisi 0%
Lokasi Segmen 2
Koordinat - S 0°54'57.34"
- E 131°19'17.51"
Keterangan
Kondisi 0%
Lokasi Segmen 1
Koordinat
Keterangan
Kondisi 0%
Lokasi Segmen 1
Koordinat
LAPORAN PENDAHULUAN
LOKASI KOTA SORONG
LAMPIRAN
Bulan Oktober 2020
PPK BIDANG CIPTA KARYA – OPD DPUPR PROVINSI PAPUA BARAT
PENGAWASAN TEKNIS PEMBANGUNAN JALAN LINGKUNGAN KOTA SORONG
Foto Dokumentasi
Keterangan
Kondisi
Lokasi
STA
Koordinat
Keterangan
Kondisi
Lokasi
STA
Koordinat
Keterangan
Kondisi
Lokasi
STA
Koordinat
LAPORAN PENDAHULUAN
LOKASI KOTA SORONG
LAMPIRAN
Bulan Oktober 2020
PPK BIDANG CIPTA KARYA – OPD DPUPR PROVINSI PAPUA BARAT
PENGAWASAN TEKNIS PEMBANGUNAN JALAN LINGKUNGAN KOTA SORONG
Foto Dokumentasi
Keterangan
Kondisi
Lokasi
STA
Koordinat
Keterangan
Kondisi
Lokasi
STA
Koordinat
Keterangan
Kondisi
Lokasi
STA
Koordinat
LAPORAN PENDAHULUAN
LOKASI KOTA SORONG
LAMPIRAN
Bulan Oktober 2020
PPK BIDANG CIPTA KARYA – OPD DPUPR PROVINSI PAPUA BARAT
PENGAWASAN TEKNIS PEMBANGUNAN JALAN LINGKUNGAN KOTA SORONG
Foto Dokumentasi
Keterangan
Kondisi
Lokasi
STA
Koordinat
Keterangan
Kondisi
Lokasi
STA
Koordinat
Keterangan
Kondisi
Lokasi
STA
Koordinat
LAPORAN PROFIL KEGIATAN
SATKER :
PPK :
PAKET :
KEGIATAAN :
SUMBER DANA :
LOKASI
2020
KOTA SORONG
HALAMAN
I
LAPORAN PENDAHULUAN
BAB. VI PENYEDIA JASA LOKASI KAB RAJA AMPAT
KONSULTAN Bulan Oktober 2020
PPK BIDANG CIPTA KARYA – OPD DPUPR PROVINSI PAPUA BARAT
PENGAWASAN TEKNIS PEMBANGUNAN JALAN LINGKUNGAN KOTA SORONG
Jeni Lestari, ST
Quantity Engineer
Dhuwi Purwaningrum, ST
Inspector
LAPORAN PENDAHULUAN
BAB. VI PENYEDIA JASA LOKASI KAB RAJA AMPAT
KONSULTAN Bulan Oktober 2020
PPK BIDANG CIPTA KARYA – OPD DPUPR PROVINSI PAPUA BARAT
PENGAWASAN TEKNIS PEMBANGUNAN JALAN LINGKUNGAN KOTA SORONG
DAFTAR ISI
LOKASI KOTA SORONG
T.A 2020
DAFTAR ISI
I PENDAHULUAN
2.1 Paket Pengawasan Teknis Pembangunan Jalan Lingkungan Kota Sorong ………………………………………….. II-4
Halaman ii
LAP. PROFIL KEGIATAAN
LOKASI KOTA SORONG
KATA PENGANTAR
T.A 2020
KATA PENGANTAR
Berkenaan dengan hal tersebut diatas, selama beberapa periode telah dilakukan observasi lapangan dan
pengumpulan data atas paket Pengawasan Teknis Pembangunan Jalan Lingkungan Kota Sorong, selanjutnya
dibuat laporan singkat Profil Kegiatan. Diharapkan laporan ini dapat memberikan informasi-informasi kegiatan
Kami sebagai Konsultan Teknis dengan CV. Arfak Desain Konsultan mengucapkan terima kasih kepada
Organisasi Perangkat Daerah Dinas Pekerjaan Umum dan Perumahan Rakyat Provinsi Papua Barat, yang telah
memberikan kepercayaan untuk melaksanakan pekerjaan pengawasan teknis ini. Kritik dan saran yang
membangun dalam penyusunan laporan ini kami terima untuk penyempurnaan dan perkembangan yang lebih
baik di masa yang akan datang.
Konsultan Supervisi
CV.ARFAK DESAIN KONSULTAN
LAP. PROFIL KEGIATAAN
LOKASI KOTA SORONG
PETA LOKASI
T.A 2020
BAB I
PENDAHULUAN
Pembangunan infrastruktur jalan merupakan salah satu sektor pembangunan yang paling dibutuhkan di
Kota Sorong karena ada banyak ketergantungan pengembangan ekonomi, sosial dan pendidikan dengan
pembangunan infrastruktur jalan itu sendiri. Penyediaan infrastruktur jalan yang merata di seluruh wilayah
Kota Sorong merupakan hal mutlak untuk mewujudkan kota yang mandiri, dengan pengelolaan
pembangunan fisik kota yang meliputi sistem transportasi yang memiliki interkoneksi antar wilayah. Jalan
merupakan prasarana angkutan darat yang sangat penting untuk memperlancar kegiatan perekonomian.
Usaha pembangunan yang meningkat menuntut adanya sarana transportasi untuk menunjang mobilitas
penduduk dan kelancaran distribusi barang dari dan ke suatu daerah. Kinerja jaringan jalan sebagai hasil
dari manajemen pengelolaan didasarkan kepada beberapa indikator makro yaitu berdasarkan: (1)
kemantapan; (2) kondisi dan; (3) pemanfaatan jalan yang ada. Peningkatan dan rehabilitasi jalan juga
dilaksanakan pada wilayah permukiman yang padat penduduk. Dengan semakin baiknya kondisi jalan
semakin memicu tersebarnya kantong-kantong permukiman baru dan perluasan permukiman yang ada,
sehingga penduduk tidak terkonsentrasi pada wilayah hamparan permukiman saja. Adanya persebaran
penduduk akibat semakin baiknya pelayanan jalan ini dapat dilihat dengan mulai tumbuh permukiman baru
mengikuti badan jalan yang telah ditingkatkan tersebut. Pemerintah Provinsi Papua Barat melalui Dinas
Cipta Karya, Tata Ruang dan Perumahan terus berupaya untuk memenuhi kebutuhan masyarakat di bidang
infrastruktur jalan, khususnya jalan lingkungan. Seiring bertambahnya penduduk dan pertumbuhan wilayah,
serta untuk mewujudkan peningkatan kualitas prasarana dasar lingkungan permukiman, namun sampai saat
ini penanganan pembangunan jalan lingkungan ini belum dapat dilakukan secara optimal dengan sistem
pengelolaan yang baik.
Untuk mewujudkan arah pembangunan tersebut maka pemerintah melalui Dinas Pekerjaan Umum
Provinsi Papua Barat bidang Bina Marga pada tahun anggaran 2020 ini melaksanaan program Pengawasan
Teknis Pembangunan Jalan Lingkungan Kota Sorong. Diharapkan upaya ini akan menyentuh langsung
kemudahan transportasi masyarakat dan mendorong pertumbuhan ekonomi di Kota Sorong.
Untuk menjamin pelaksanaan pekerjaan tersebut agar sesuai dengan rencana qualitas, quantitas dan biaya
yang telah ditetapkan di dalam kontrak jasa konstruksi, maka diperlukan suatu team yang akan bertugas
sebagai pengawas yang berperan membantu Organisasi Perangkat Daerah Dinas Pekerjaan Umum dan
Penataan Ruang Provinsi Papua Barat di dalam melaksanakan pengawasan teknis pada kegiatan fisik. Team
pengawas tersebut adalah Penyedia Jasa konsultasi pekerjaan supervisi / pengawasan teknis.
Lingkup kegiatan Pengawasan Teknis Pembangunan Jalan Lingkungan yang berlokasi di Kota Sorong
Provinsi Papua Barat adalah sebagai berikut :
2. Melaksanakan pengawasan teknis terhadap pekerjaan di lapangan secara profesional, efektif dan
efisien, pada setiap tahapan kegiatan.
Halaman 165
LAP. PROFIL KEGIATAAN
LOKASI KOTA SORONG
PENDAHULUAN
T.A 2020
3. Memastikan pekerjaan berjalan sesuai yang direncanakan, tepat waktu, tepat mutu dan tepat biaya.
Maksud pengadaan Penyedia Jasa Konsultasi pekerjaan pengawasan Teknis, adalah sebagai berikut :
1. Membantu Organisasi Perangkat Daerah Dinas Pekerjaan Umum dan Penataan Ruang Provinsi
Bapua Barat, di dalam melaksanakan pengawasan teknis pada kegiatan fisik/konstruksi yang
dilaksanakan oleh Penyedia Jasa Konstruksi (Kontraktor). Hal ini dikarenakan keterbatasan tenaga
Organisasi Perangkat Daerah Dinas Pekerjaan Umum dan Penataan Ruang Provinsi Papua Barat, baik
dari segi kuantitas/jumlah maupun kualifikasinya.
2. Meminimalkan kendala-kendala teknis yang sering dihadapi oleh Penyedia Jasa Konstruksi di
lapangan di dalam menerapkan design yang memenuhi persyaratan spesifikasi teknis.
3. Membantu menyelesaikan Revisi Design, bilamana terdapat perbedaan antara design/rencana awal
dengan kondisi lapangan, atau apabila dalam implementasi pelaksanaan pekerjaan terjadi perubahan
dan /atau pengalihan penanganan pekerjaan.
Sedang tujuan Penyedia Jasa Konsultasi Pekerjaan Pengawasan Teknis, adalah untuk memperoleh hasil
pelaksanaan pekerjaan konstruksi yang memenuhi persyaratan yang tercantum dalam spesifikasi teknis, dan
dilaksanakan secara tepat mutu, volume dan tepat waktu.
Konsultan Supervisi akan bertindak sebagai wakil Pelaksana Kegiatan dalam pengawasan pekerjaan dan
menjamin bahwa semua produk pekerjaan sesuai dan memenuhi perencanaan teknis, spesifikasi teknis serta
didasarkan dokumen kontrak yang ada.
1. Melaksanakan pengawasan pelaksanaan pekerjaan harian, sehingga dapat dijamin kesesuaian dan
kebenaran material rencana serta mengikuti prosedur pelayanan pelaksanaan sesuai dengan dokumen
kontrak.
2. Secara teknis memberikan arahan, instruksi / penjelasan secara lisan dan tertulis kepada kontraktor
dengan jelas, mudah dipahami terhadap pelaksanaan pekerjaan yang sebenarnya.
3. Memeriksa seluruh material rencana yang ada di lapangan, sehingga betul-betul memenuhi
persyaratan dan spesifikasi teknis.
Halaman 166
LAP. PROFIL KEGIATAAN
LOKASI KOTA SORONG
PENDAHULUAN
T.A 2020
4. Memastikan bahwa pengukuran secara kuantitas pelaksanaan pekerjaan telah dilakukan dengan
benar, dalam rangka untuk pembayaran Terminj.
5. Memeriksa semua gambar teknis (shop drawing, detail drawing dan as built drawing) agar sesuai dan
memenuhi dengan dokumen kontrak.
Halaman 167
LAP. PROFIL KEGIATAAN
LOKASI KOTA SORONG
DATA KEGIATAAN
T.A 2020
BAB II
DATA KEGIATAAN PAKET FISIK
DATA-DATA
PENGAWASAN TEKNIS PEMBANGUNAN JALAN LINGKUNGAN KOTA SORONG
02. Nama Paket : Pengawasan Teknis Pembangunan Jalan Lingkungan Kota Sorong
BAB III
LOKASI PEKERJAAN
Lokasi Pekerjaan Paket Pengawasan Teknis Pembangunan Jalan Lingkungan Kota Sorong sebagai berikut :
1 7 November 2020 Terjadi pemalangan Ruas Jalan Segmen 1 09:00 WIT Pekerjaan dihentikan Menunggu waktu penyelesaiaan.
oleh pemilik hak ulayat atas nama marga
Ani Malaseme yang menuntut Ganti Rugi
Hak Ulayat senilai 1 Milyard Rupiah
Berkenaan dengan aktivitas Pelaksanan
pekerjaan Pembangunan Jalan
Lingkungan Kota Sorong pada Segmen 1.
2 8 November 2020 Undangan Rapat secara lisan by telepon 01:00 WIT Pekerjaan Masih dihentikan Menunggu waktu
oleh Pemilik Hak Ulayat dan RT,RW penyelesaiaan.
setempat untuk negosiasi kelanjutan
Pelaksanaan Pekerjaan, yang akan
dilaksanakan pada tanggal 9 November
bertempat di rumah RW setempat.
3 9 November 2020 Konsultan, RT, RW dan Perwakilan Pemilik 19:00 WIT Pekerjaan Masih dihentikan Menunggu waktu
Hak Ulayat bertemu dalam rapat negosiasi penyelesaiaan.
kelanjutan pelaksaan pekerjaan bertempat
dirumah RW setempat, Hasil Rapat
membuahkan hasil kesepakatan oleh
Perwakilan Pemilik Hak Ulayat untuk tetap
melanjutkan pekerjaan namun harus
memindahkan ruas pekerjaan tersebut
dilokasi lain disekitaran wilayah segmen 1
yang mana tanah pada ruas jalan tersebut
telah diselesaikan perkara adat maupun
hak ulayat dengan nama marga Ani
Malaseme.
4 10 November 2020 Masalah Pemalangan Jalan oleh Pemilik 09:00 WIT Pekerjaan Telah dapat dilanjutkan
Hak Ulayat telah Selesai dan Kontraktor
kembali dapat melanjutkan pekerjaan pada
masing-masing ruas yang telah ditunjuk.
SURAT KETERANGAN
Pada tanggal Sembilan bulan November tahun Dua Ribu Dua Puluh telah
diadakan Rapat oleh RT, RW, Konsultan dan Perwakilan Pemilik Hak Ulayat,
terkait pemalangan Jalan oleh Pemilik Hak Ulayat atas nama marga Malaseme
yang berlokasi di Kompleks Perumahan Fadila Km.14, Kel.Klablim, Distrik
Klaurung, Kota Sorong, tepatnya pada lokasi pekerjaan pembangunan jalan
lingkungan kota sorong, hasil dari rapat tersebut didapatkan kesepakatan bahwa
Pemilik Hak Ulayat bersedia dan mengizinkan untuk melanjutkan Kegiatan
Pembangunan Jalan Lingkungan namun harus memindahkan ruas pekerjaan
tersebut dilokasi lain yang mana tanah pada ruas jalan tersebut telah
diselesaikan segala perkara adat maupun hak ulayat dengan nama marga
Malaseme.
Demikian Surat Keterangan ini kami buat dengan sebenar-benarnya agar dapat
dipergunakan dengan sebagaimana mestinya.
Ketua RT Ketua RW
............................................ ............................................
PAKET : PENGAWASAN TEKNIS PEMBANGUNAN DRAINASE DALAM KOTA WAISAI
Kepada Yth : PPK Bidang Cipta Karya OPD DPUPR Provinsi Papua Barat
di -
Manokwari
Dengan Hormat,
Adapun perkembangan kegiatan PENGAWASAN TEKNIS PEMBANGUNAN SUMUR BOR DI KOTA SORONG yang dapat
kami laporkan selaku Konsultan Supervisi adalah, pencapaian progress sebesar :
Rencana : 4.141 %
Realisasi : 0.126 %
Deviasi : -4.014 %
Pencapaian dengan Deviasi negatif dikarenakan Kontraktor Pelaksana tidak melaksanakan pekerjaan sesuai yang
direncanakan.
Demikian yang dapat kami laporkan, untuk dijadikan bahan monitoring dan evaluasi.
KONSULTAN SUPERVISI,
CV. ARFAK DESAIN KONSULTAN
ANDREAS, ST
Supervision Engineer
METODOLOGI SUPERVISI :
a. Mengendalikan pelaksanaan pekerjaan agar pekerjaan dapat dikerjakan sesuai dengan, persyaratan dan ketentuan –
ketentuan yang tercantum dalam Dokumen Kontrak serta jadwal waktu yang telah ditetapkan.
b. Mengumpulkan data lapangan yang diperlukan secara terinci untuk mendukung peninjauan design (Review Design),
menyusun perhitungan desain, membuat gambar desain dan menyiapkan perintah-perintah kepada kontraktor, sehingga
perubahan tersebut dapat dilaksanakan.
c. Melaksanakan pengecekan secara cermat semua pengukuran dan perhitungan volume pekerjaan yang akan dipakai sebagai
dasar pembayaran, sehingga semua pengukuran pekerjaan, perhitungan volume dan pembayaran didasarkan kepada
ketentuan yang tercantum dalam dokumen kontrak.
d. Memonitoring dan pengecekan secara terus-menerus sehubungan dengan pelaksanaan dan pengendalian mutu serta volume
pekerjaan termasuk keterlambatan pencapaian target fisik.
e. Penyusunan Laporan Bulanan (Monthly Report), Laporan Triwulan (Quarterly Report) dan Laporan Akhir (Final Report) yang
mencakup laporan kemajuan pekerjaan dan laporan keuangan serta masalah-masalah yang ditemui di lapangan serta
menyusun daftar kerusakan dan penyimpangan yang perlu diperbaiki dalam pelaksanaan Provisional Hand Over (PHO) dan
Final Hand Over (FHO).
f. Prosedur Umum Pelayanan jasa Konsultan Supervisi adalah dengan cara melakukan monitoring kemajuan pekerjaan,
pengendalian mutu dan volume pekerjaan, dan masalah yang berkaitan dengan pelaksanaan pekerjaan dan dokumen
kontrak. Koordinasi kegiatan Tim pengawas teknis dilaksanakan oleh Supervision Engineer bersama-sama Coreteam Provinsi
Papua Barat dengan Direksi Lapangan Dinas Pekerjaan Umum Dan Perumahan Rakyat Provinsi Papua Barat serta PPK .
Pekerjaan Pengawasan Teknis dilaksanakan oleh Pelaksanaan Kegiatan Fisik yang bertindak sebagai ”Engineer” dibantu dan
mendelegasikan sebagian tugas kepada Tim Pengawas Teknik yang bertindak sebagai “Engineer Representative” sesuai
dengan dokumen kontrak fisik. Tugas yang didelegasikan oleh Pelaksanaan Kegiatan Pengawasan Bidang Pengairan Provinsi
adalah tugas-tugas yang berkaitan dengan masalah Teknis dan kontrak, tugas tersebut selanjutnya diatur dalam Kerangka
Acuan Kerja ini.
g. OPD Dinas PUPR Provinsi Papua Barat, menunjuk Pengendali Kegiatan Pengawasan Bidang Cipta Karya Provinsi untuk
mengatur dan mengendalikan pelaksanaan pelayanan Jasa Konsultansi, sesuai dengan tugas Kerangka Acuan Kerja ini.
Pengendali Kegiatan Pengawasan Bidang Cipta Karya Provinsi Papua Barat yang akan bertanggung jawab atas koordinasi
pelaksanaan tugas pelayanan Jasa Konsultansi, termasuk system pembayaran atas pelayanan Jasa Konsultansi ini secara
keseluruhan.
h. Membantu Pengendali Kegiatan Fisik (PPK OPD PUPR) dalam hal melaksanakan tugas peninjauan perencanaan teknis
(review design) dan pengawasan teknis, sehingga pelaksanaan fisik dapat diselesaikan sesuai dengan persyaratan yang telah
ditentukan dalam dokumen kontrak.
Perubahan-perubahan atas design hanya dapat dilakukan dengan persetujuan Pengendali kegiatan Pengawasan Bidang Cipta
Karya Provinsi Papua Barat.
i. Membantu PPK dalam mengikutsertakan dan melaksanakan ketentuan hukum dari dokumen kontrak fisik, terutama masalah
hukum yang menyangkut "Claim" perpanjangan waktu pelaksanaan dan lain sebagainya.
j. Membantu Pengendali Kegiatan Fisik PPK dalam mengevaluasi usulan perubahan design, termasuk menyiapkan “Contract
Change Order” dan atau “Addendum” sehingga perubahan-perubahan kontrak yang diperlukan dapat dibuat secara optimum
dengan mempertimbangkan aspek dana yang tersedia.
k. Melakukan pemeriksaan investigasi atas masalah khusus yang menyangkut pelaksanaan pekerjaan yang telah dilaporkan
oleh Tim Pengawas Teknik, misalnya keterlambatan pelaksanaan pekerjaan, serta membuat rekomendasi pemecahan untuk
meningkatkan pencapaian kemajuan pelaksanaan.
l. Membuat himpunan data pengendalian mutu pekerjaan terutama untuk pekerjaan-pekerjaan utama (mayor works), dan bila
mana perlu melakukan test laboratorium dan lapangan.
HALAMAN
1
LAP. BULAN Ke 01
m. Melakukan monitoring, agar pelaksanaan system pelaporan dapat berjalan sesuai dengan ketentuan yang telah ditentukan
oleh OPD Dinas PUPR Provins Papua Barat.
n. Memberikan petunjuk kepada Tim Pengawas Teknik dalam Pelaksanaan Kegiatan Fisik sehubungan dengan managemen
pelaksanaan pekerjaan (“Construction Management”), sehingga pekerjaan dapat dilaksanakan dengan efisien baik dari segi
waktu maupun biaya.
o. Menyiapkan laporan teknis dan makalah sehubungan dengan tiap masalah yang timbul selama pelaksanaan pekerjaan.
p. Membantu Pengendali Kegiatan PPK dalam melaksanakan tugas dan kewajiban dalam mengendalikan pelaksanaan
pekerjaan agar pekerjaan dapat diselesaikan sesuai dengan design, persyaratan dan ketentuan-ketentuan yang tercantum
dalam dokumen kontrak serta jadwal waktu yang telah ditetapkan.
q. Membantu Pengendali Kegiatan PPK dalam memahami dan melaksanakan ketentuan-ketentuan hukum yang tercantum
didalam dokumen kontrak, terutama sehubungan dengan pemenuhan kewajiban dan tugas kontraktor.
r. Melaporkan kepada Pengendali Kegiatan PPK semua masalah sehubungan dengan pelaksanaan pekerjaan termasuk
keterlambatan pencapaian target fisik, serta usaha-usaha penanggulangan dan tidak turun tangan (T3) yang diperlukan
dengan terlebih dahulu mengkonsultasikannya kepada PPK Dinas PUPR Provinsi Papua Barat.
s. Melakukan monitoring dan pengecekan secara terus menerus sehubungan pengendalian mutu dan volume pekerjaan, serta
menandatangani “Monthly Certificate (MC)” apabila mutu dan pelaksanaan pekerjaan telah memenuhi semua ketentuan dan
persyaratan yang telah ditentukan. Konsultan harus memberitahukan secara tertulis kepada kontraktor atas adanya
penyimpangan-penyimpangan dari ketentuan dan persyaratan, baik mutu, volume bahan, pekerjaan dan copy syarat-syarat
pemberitahuan tersebut harus disampaikan kepada PPK dan diarsipkan secara baik.
HALAMAN
2
LAP. BULAN Ke 01
KOORDINATOR LAPANGAN
DIREKSI LAPANGAN
HALAMAN
3
LAP. BULAN Ke 01
AKTIVITAS KONSULTAN SUPERVISI BULAN OKTOBER 2020
LOKASI KAB. RAJA AMPAT
PPK BIDANG CIPTA KARYA - OPD DPUPR PROVINSI PAPUA BARAT
PENGAWASAN TEKNIS PEMBANGUNAN DRAINASE DALAM KOTA WAISAI
DIREKTUR
THOMAS ALFA EDISON PAA, ST
SUPERVISION ENGINEER
BINTANG YUDHA DWI KURNIA, ST
QUANTITY/QUALITY CONTROL
JENI LESTARI, ST
INSPECTOR
DHUWI PURWANINGRUM, ST
INSPECTOR
DHUWI PURWANINGRUM, ST
HALAMAN
4
LAP. BULAN Ke 01
AKTIVITAS KONSULTAN SUPERVISI BULAN OKTOBER 2020
LOKASI KAB. RAJA AMPAT
PPK BIDANG CIPTA KARYA - OPD DPUPR PROVINSI PAPUA BARAT
PENGAWASAN TEKNIS PEMBANGUNAN DRAINASE DALAM KOTA WAISAI
PROFESSIONAL STAFF
HALAMAN
5
LAP. BULAN Ke 01
AKTIVITAS KONSULTAN SUPERVISI BULAN OKTOBER 2020
LOKASI KAB. RAJA AMPAT
PPK BIDANG CIPTA KARYA - OPD DPUPR PROVINSI PAPUA BARAT
PENGAWASAN TEKNIS PEMBANGUNAN DRAINASE DALAM KOTA WAISAI
ACTUAL 1 2
PROFESSIONAL STAFF
HALAMAN
6
LAP. BULAN Ke 01
SITE ENGINEER
- Mobilisasi x ANDREAS, ST
- Rapat Monitoring dan Evaluasi x
- Rapat Internal Konsultan x x x x x 0.07 0.04
- Koordinasi dengan PPK x x x x x 0.05
- Supervisi Ke Lapangan x x x x x x x x x x
- Pembuatan Laporan x x x x x x
QUANTITY/QUALITY CONTROL
- Mobilisasi x JENI LESTARI, ST
- Rapat Internal Konsultan x x x x x
- Supervisi di Lapangan x x x x x x x x x x x x x x x x
- Pengendalian Mutu di Lapangan x x x x x x x x x x x x x x x x
- Pengendalian Quantity x x x x x x x x x x x x x x x x
- Pembuatan Laporan x x x x x x x x
INSPECTOR
- Mobilisasi x DHUWI PURWANINGRUM, ST
- Rapat Internal Konsultan x x x x x
- Supervisi di Lapangan x x x x x x x x x x x x x x x x x x x x x
- Kerja Kantor Rutin / Laporan x x x x
HALAMAN
7
LAP. BULAN Ke 01
KONSULTAN SUPERVISI :
CV. ARFAK DESAIN KONSULTAN
ANDREAS, ST
SUPERVISION ENGINEER
HALAMAN
9
LAP. BULAN Ke 01
TIME SCHEDULE KONSULTAN SUPERVISI BULAN OKTOBER 2020
LOKASI KAB. RAJA AMPAT
PPK BIDANG CIPTA KARYA - OPD DPUPR PROVINSI PAPUA BARAT
PENGAWASAN TEKNIS PEMBANGUNAN DRAINASE DALAM KOTA WAISAI
KONSULTAN SUPERVISI
CV. ARFAK DESAIN KONSULTAN
ANDREAS, ST
SUPERVISION ENGINEER
HALAMAN
10
LAP. BULAN Ke 01
A. PEMBANGUNAN BENDUNG
1 Pekerjaan Persiapan KETERANGAN
Kualitas :
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan spesifikasi
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
√ Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan spesifikasi
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Kuantitas :
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan kontrak
√ Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan kontrak
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan spesifikasi
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Kuantitas :
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan kontrak
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan kontrak
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan spesifikasi
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Kuantitas :
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan kontrak
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan kontrak
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan kontrak
HALAMAN
11
LAP. BULAN Ke 01
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan spesifikasi
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Kuantitas :
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan kontrak
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan kontrak
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan spesifikasi
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Kuantitas :
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan kontrak
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan kontrak
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan spesifikasi
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Kuantitas :
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan kontrak
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan kontrak
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan kontrak
HALAMAN
12
LAP. BULAN Ke 01
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan spesifikasi
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Kuantitas :
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan kontrak
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan kontrak
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan spesifikasi
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Kuantitas :
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan kontrak
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan kontrak
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan spesifikasi
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Kuantitas :
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan kontrak
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan kontrak
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan kontrak
HALAMAN
13
LAP. BULAN Ke 01
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan spesifikasi
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Kuantitas :
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan kontrak
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan kontrak
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan spesifikasi
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Kuantitas :
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan kontrak
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan kontrak
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan spesifikasi
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Kuantitas :
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan kontrak
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan kontrak
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan kontrak
HALAMAN
14
LAP. BULAN Ke 01
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan spesifikasi
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Kuantitas :
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan kontrak
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan kontrak
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan spesifikasi
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Kuantitas :
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan kontrak
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan kontrak
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan spesifikasi
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Kuantitas :
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan kontrak
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan kontrak
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan kontrak
HALAMAN
15
LAP. BULAN Ke 01
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan spesifikasi
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Kuantitas :
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan kontrak
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan kontrak
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan spesifikasi
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Kuantitas :
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan kontrak
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan kontrak
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan spesifikasi
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Kuantitas :
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan kontrak
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan kontrak
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan kontrak
HALAMAN
16
LAP. BULAN Ke 01
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan spesifikasi
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Kuantitas :
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan kontrak
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan kontrak
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan spesifikasi
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Kuantitas :
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan kontrak
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan kontrak
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan kontrak
HALAMAN
17
LAP. BULAN Ke 01
B. SALURAN PRIMER
1 Saluran Primer Kanan KETERANGAN
Kualitas :
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan spesifikasi
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan spesifikasi
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Kuantitas :
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan kontrak
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan kontrak
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan spesifikasi
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Kuantitas :
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan kontrak
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan kontrak
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan kontrak
HALAMAN
18
LAP. BULAN Ke 01
C. SALURAN SEKUNDER
1 Saluran Sekunder Ruas 1 Kanan KETERANGAN
Kualitas :
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan spesifikasi
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan spesifikasi
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Kuantitas :
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan kontrak
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan kontrak
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan spesifikasi
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Kuantitas :
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan kontrak
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan kontrak
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan spesifikasi
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Kuantitas :
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan kontrak
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan kontrak
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan kontrak
HALAMAN
19
LAP. BULAN Ke 01
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan spesifikasi
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Kuantitas :
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan kontrak
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan kontrak
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan spesifikasi
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Kuantitas :
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan kontrak
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan kontrak
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan kontrak
HALAMAN
20
LAP. BULAN Ke 01
D. BANGUNAN PELENGKAP
1 Bangunan Bagi M2.PB1.Kiri KETERANGAN
Kualitas :
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan spesifikasi
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan spesifikasi
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Kuantitas :
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan kontrak
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan kontrak
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan spesifikasi
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Kuantitas :
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan kontrak
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan kontrak
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan spesifikasi
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Kuantitas :
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan kontrak
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan kontrak
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan kontrak
HALAMAN
21
LAP. BULAN Ke 01
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan spesifikasi
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Kuantitas :
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan kontrak
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan kontrak
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan spesifikasi
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Kuantitas :
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan kontrak
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan kontrak
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan spesifikasi
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Kuantitas :
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan kontrak
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan kontrak
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan kontrak
HALAMAN
22
LAP. BULAN Ke 01
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan spesifikasi
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Kuantitas :
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan kontrak
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan kontrak
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan spesifikasi
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Kuantitas :
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan kontrak
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan kontrak
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan spesifikasi
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Kuantitas :
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan kontrak
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan kontrak
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan kontrak
HALAMAN
23
LAP. BULAN Ke 01
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan spesifikasi
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Kuantitas :
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan kontrak
√ Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan kontrak
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan spesifikasi
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Kuantitas :
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan kontrak
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan kontrak
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan spesifikasi
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Kuantitas :
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan kontrak
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan kontrak
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan kontrak
HALAMAN
24
LAP. BULAN Ke 01
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan spesifikasi
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Kuantitas :
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan kontrak
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan kontrak
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan spesifikasi
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan spesifikasi
Kuantitas :
Lengkap / Benar Administrasi lengkap dan Pelaksanaan sesuai dengan kontrak
Lengkap / Tidak Benar Administrasi lengkap dan Pelaksanaan belum sesuai dengan kontrak
Tidak Lengkap / Benar Administrasi tidak lengkap dan Pelaksanaan sesuai dengan kontrak
Tidak Lengkap / Tidak Benar Administrasi tidak lengkap dan Pelaksanaan belum sesuai dengan kontrak
HALAMAN
25
LAP. BULAN Ke 01
26
DIREKTUR
THOMAS ALFA EDISON PAA, ST
SUPERVISION ENGINEER
BINTANG YUDHA DWI KURNIA, ST
QUANTITY/QUALITY CONTROL
JENI LESTARI, ST
INSPECTOR
DHUWI PURWANINGRUM, ST