Opnam Pak Kadek Baja Revisi
Opnam Pak Kadek Baja Revisi
NAMA PROYEK : LECTURE BUILDING UNIVERSITAS UDAYANA TOTAL NILAI PEKERJAAN : 47,353,060.7
ALAMAT PROYEK : KAMPUS UNIVERSITAS UDAYANA BUKIT JIMBARAN KUTA SELATAN, KUTA BADUNG - BALI PROGRES s/d PERIODE INI : 39,663,981.0
NAMA MADOR : I Kadek Trisnaarta Wijaya KASBON PERIODE LALU :
RETENSI 5% : 1,983,199.05
TAGIHAN PERIODE INI : 37,680,782
Sisa : 9,672,278.7
PERIODE OPNAME : 1
Harga Jumlah REALISASI OPNAME
No Item Pekerjaan Qty Sat Satuan Harga PER LALU PER INI S/D PER INI
( Rp ) ( Rp ) Qty % Rp Qty % Rp Qty % Rp
STRUKTUR
1 WF 300 7,740.03 kg Rp 4,500 34,830,135.00 6,579.03 85 29,605,614.75 6,579.03 85 29,605,614.75
ESSER 12MM 314.712 kg Rp 4,500 1,416,204.00 314.71 100 1,416,204.00 315 100 1,416,204.00
ESSER 8MM 432.438 kg Rp 4,500 1,945,968.75 345.95 80 1,556,775.00 345.95 80 1,556,775.00
2 WF 250 1,181.04 kg Rp 4,500 5,314,680.00 944.83 80 4,251,744.00 944.83 80 4,251,744.00
ESSER 12MM 54.68 kg Rp 4,500 246,058.61 54.68 100 246,058.61 54.68 100 246,058.61
ESSER 8MM 73.05 kg Rp 4,500 328,710.96 58.44 80 262,968.77 58.44 80 262,968.77
3 ESSER 12MM 306.21 kg Rp 4,500 1,377,928.35 306.21 100 1,377,928.35 306.21 100 1,377,928.35
ESSER 8MM 420.75 kg Rp 4,500 1,893,375.00 210.38 50 946,687.50 210.38 50 946,687.50
I Kadek Trisnaarta Wijaya I Putu Ertha Suryadhi, ST I Made Gede Jiwa, ST Kadek Widi Artama
NAMA PROYEK : LECTURE BUILDING UNIVERSITAS UDAYANA TOTAL NILAI PEKERJAAN : 123,719,101.88
ALAMAT PROYEK : KAMPUS UNIVERSITAS UDAYANA BUKIT JIMBARAN KUTA SELATAN, KUTA BADUNG - BALI PROGRES s/d PERIODE INI : 112,279,971.38
61.00 PROGRES PERIODE INI : 72,615,990.40
PEMBAYARAN s/d PERIODE LALU : 37,680,781.92
SEWA MOBIL CRANE : 3,000,000.00
RETENSI 5% PER INI : 3,630,799.52
RETENSI s/d PERIODE INI : 5,613,998.57
TAGIHAN PERIODE INI : 67,968,389.93
TAGIHAN PERIODE INI (PEMBULATAN) : 67,968,000.00
Sisa : 55,751,101.88
PERIODE OPNAME : 2
Harga Jumlah REALISASI OPNAME
No Item Pekerjaan Qty Sat Satuan Harga PER LALU PER INI S/D PER INI
( Rp ) ( Rp ) Qty % Rp Qty % Rp Qty % Rp
1 STRUKTUR LANTAI 2
a WF 300 9,204.36 kg Rp 4,500 41,419,620.00 6,579.03 71 29,605,614.75 1,704.90 19 7,672,043.25 8,283.92 90.00 37,277,658.00
ESSER 12MM 374.25 kg Rp 4,500 1,684,134.38 314.71 84 1,416,204.00 59.54 16 267,930.38 374.25 100.00 1,684,134.38
ESSER 8MM 514.25 kg Rp 4,500 2,314,125.00 345.95 67 1,556,775.00 168.30 33 757,350.00 514.25 100.00 2,314,125.00
b WF 250 3,036.96 kg Rp 4,500 13,666,320.00 944.83 31 4,251,744.00 1,788.43 59 8,047,944.00 2,733.26 90.00 12,299,688.00
ESSER 12MM 109.36 kg Rp 4,500 492,117.19 54.68 50 246,058.61 54.68 50 246,058.58 109.36 100.00 492,117.19
ESSER 8MM 146.09 kg Rp 4,500 657,421.88 58.44 40 262,968.77 87.66 60 394,453.11 146.09 100.00 657,421.88
2 STRUKTUR LANTAI 3
a WF 300 13,178.97 kg Rp 4,500 59,305,365.00 - - - 11,861.07 90 53,374,828.50 11,861.07 90.00 53,374,828.50
ESSER 12MM 391.26 kg Rp 4,500 1,760,685.94 306.21 78 1,377,928.35 85.06 22 382,757.59 391.26 100.00 1,760,685.94
ESSER 8MM 537.63 kg Rp 4,500 2,419,312.50 210.38 39 946,687.50 327.25 61 1,472,625.00 537.63 100.00 2,419,312.50
I Kadek Trisnaarta Wijaya I Putu Ertha Suryadhi, ST I Made Gede Jiwa, ST Putu Artha Wiguna
2 wf 250 5.7 m1 18
esser 10mm 0.0375 m2 36
esser 8mm 0.03125 m2 72
tonase
lantai 3
no uraian vol satuan jumlah
1 wf 300 5.7 m1 63
2 esser 10mm 0.0525 m2 92
3 esser 8mm 0.045 m2 184
tonase
TOTAL progress
24951.10475
I KADEK TRISNAARTA W
OPNAM PEKERJAAN PEMASANGAN BAJA BERAT
NAMA PROYEK : LECTURE BUILDING UNIVERSITAS UDAYANA TOTAL NILAI PEKERJAAN : 123,719,101.88
ALAMAT PROYEK : KAMPUS UNIVERSITAS UDAYANA BUKIT JIMBARAN KUTA SELATAN, KUTA BADUNG - BALI PROGRES s/d PERIODE INI : 112,279,971.38
PROGRES PERIODE INI : 72,615,990.40
PEMBAYARAN s/d PERIODE LALU : 37,680,781.92
RETENSI 5% : 3,630,799.52
RETENSI s/d PERIODE INI 5,613,998.57 PEMBULATAN
TAGIHAN PERIODE INI : 68,985,190.88 68,985,000.00
Sisa : 54,734,101.88
PERIODE OPNAME : 2
Harga Jumlah REALISASI OPNAME
No Item Pekerjaan Qty Sat Satuan Harga PER LALU PER INI S/D PER INI
( Rp ) ( Rp ) Qty % Rp Qty % Rp Qty % Rp
STRUKTUR LANTAI 2
1 WF 300 9,204.36 kg Rp 4,500 41,419,620.00 6,579.03 71.48 29,605,614.75 1,704.90 18.52 7,672,043.25 8,283.92 90.00 37,277,658.00
ESSER 12MM 374.25 kg Rp 4,500 1,684,134.38 314.71 84.09 1,416,204.00 59.54 15.91 267,930.38 374.25 100.00 1,684,134.38
ESSER 8MM 514.25 kg Rp 4,500 2,314,125.00 345.95 67.27 1,556,775.00 168.30 32.73 757,350.00 514.25 100.00 2,314,125.00
2 WF 250 3,036.96 kg Rp 4,500 13,666,320.00 944.83 31.11 4,251,744.00 1,788.43 58.89 8,047,944.00 2,733.26 90.00 12,299,688.00
ESSER 12MM 109.36 kg Rp 4,500 492,117.19 54.68 50.00 246,058.61 54.68 50.00 246,058.58 109.36 100.00 492,117.19
ESSER 8MM 146.09 kg Rp 4,500 657,421.88 58.44 40.00 262,968.77 87.66 60.00 394,453.11 146.09 100.00 657,421.88
STRUKTUR LANTAI 3
3 WF 300 13,178.97 kg Rp 4,500 59,305,365.00 - - - 11,861.07 90.00 53,374,828.50 11,861.07 90.00 53,374,828.50
ESSER 12MM 391.26 kg Rp 4,500 1,760,685.94 306.21 78.26 1,377,928.35 85.06 21.74 382,757.59 391.26 100.00 1,760,685.94
ESSER 8MM 537.63 kg Rp 4,500 2,419,312.50 210.38 39.13 946,687.50 327.25 60.87 1,472,625.00 537.63 100.00 2,419,312.50
I Kadek Trisnaarta Wijaya I Putu Ertha Suryadhi, ST I Made Gede Jiwa, ST Kadek Widi Artama