OPNAM PEKERJAAN PEMASANGAN BAJA BERAT

NAMA PROYEK : LECTURE BUILDING UNIVERSITAS UDAYANA TOTAL NILAI PEKERJAAN : 47,353,060.7
ALAMAT PROYEK : KAMPUS UNIVERSITAS UDAYANA BUKIT JIMBARAN KUTA SELATAN, KUTA BADUNG - BALI PROGRES s/d PERIODE INI : 39,663,981.0
NAMA MADOR : I Kadek Trisnaarta Wijaya KASBON PERIODE LALU :
RETENSI 5% : 1,983,199.05
TAGIHAN PERIODE INI : 37,680,782
Sisa : 9,672,278.7

PERIODE OPNAME : 1
Harga Jumlah REALISASI OPNAME
No Item Pekerjaan Qty Sat Satuan Harga PER LALU PER INI S/D PER INI
( Rp ) ( Rp ) Qty % Rp Qty % Rp Qty % Rp

STRUKTUR
1 WF 300 7,740.03 kg Rp 4,500 34,830,135.00 6,579.03 85 29,605,614.75 6,579.03 85 29,605,614.75
ESSER 12MM 314.712 kg Rp 4,500 1,416,204.00 314.71 100 1,416,204.00 315 100 1,416,204.00
ESSER 8MM 432.438 kg Rp 4,500 1,945,968.75 345.95 80 1,556,775.00 345.95 80 1,556,775.00
2 WF 250 1,181.04 kg Rp 4,500 5,314,680.00 944.83 80 4,251,744.00 944.83 80 4,251,744.00
ESSER 12MM 54.68 kg Rp 4,500 246,058.61 54.68 100 246,058.61 54.68 100 246,058.61
ESSER 8MM 73.05 kg Rp 4,500 328,710.96 58.44 80 262,968.77 58.44 80 262,968.77
3 ESSER 12MM 306.21 kg Rp 4,500 1,377,928.35 306.21 100 1,377,928.35 306.21 100 1,377,928.35
ESSER 8MM 420.75 kg Rp 4,500 1,893,375.00 210.38 50 946,687.50 210.38 50 946,687.50

TOTAL 47,353,060.7 - - 83.8 39,663,980.97 83.8 39,663,981.0

Badung, 22 September 2022


Disetujui Oleh : Disetujui Oleh : Diperiksa Oleh : Dibuat Oleh

I Kadek Trisnaarta Wijaya I Putu Ertha Suryadhi, ST I Made Gede Jiwa, ST Kadek Widi Artama

Biaya transfer ditanggung Penerima


Transfer ke rek. Bank : Mandiri
No. Rek : 175-00-0170640-6
Nama Pemilik Rek. : I Kadek Trisnaarta Wijaya
OPNAM PEKERJAAN PEMASANGAN BAJA BERAT

NAMA PROYEK : LECTURE BUILDING UNIVERSITAS UDAYANA TOTAL NILAI PEKERJAAN : 123,719,101.88
ALAMAT PROYEK : KAMPUS UNIVERSITAS UDAYANA BUKIT JIMBARAN KUTA SELATAN, KUTA BADUNG - BALI PROGRES s/d PERIODE INI : 112,279,971.38
61.00 PROGRES PERIODE INI : 72,615,990.40
PEMBAYARAN s/d PERIODE LALU : 37,680,781.92
SEWA MOBIL CRANE : 3,000,000.00
RETENSI 5% PER INI : 3,630,799.52
RETENSI s/d PERIODE INI : 5,613,998.57
TAGIHAN PERIODE INI : 67,968,389.93
TAGIHAN PERIODE INI (PEMBULATAN) : 67,968,000.00
Sisa : 55,751,101.88
PERIODE OPNAME : 2
Harga Jumlah REALISASI OPNAME
No Item Pekerjaan Qty Sat Satuan Harga PER LALU PER INI S/D PER INI
( Rp ) ( Rp ) Qty % Rp Qty % Rp Qty % Rp

1 STRUKTUR LANTAI 2
a WF 300 9,204.36 kg Rp 4,500 41,419,620.00 6,579.03 71 29,605,614.75 1,704.90 19 7,672,043.25 8,283.92 90.00 37,277,658.00
ESSER 12MM 374.25 kg Rp 4,500 1,684,134.38 314.71 84 1,416,204.00 59.54 16 267,930.38 374.25 100.00 1,684,134.38
ESSER 8MM 514.25 kg Rp 4,500 2,314,125.00 345.95 67 1,556,775.00 168.30 33 757,350.00 514.25 100.00 2,314,125.00
b WF 250 3,036.96 kg Rp 4,500 13,666,320.00 944.83 31 4,251,744.00 1,788.43 59 8,047,944.00 2,733.26 90.00 12,299,688.00
ESSER 12MM 109.36 kg Rp 4,500 492,117.19 54.68 50 246,058.61 54.68 50 246,058.58 109.36 100.00 492,117.19
ESSER 8MM 146.09 kg Rp 4,500 657,421.88 58.44 40 262,968.77 87.66 60 394,453.11 146.09 100.00 657,421.88

2 STRUKTUR LANTAI 3
a WF 300 13,178.97 kg Rp 4,500 59,305,365.00 - - - 11,861.07 90 53,374,828.50 11,861.07 90.00 53,374,828.50
ESSER 12MM 391.26 kg Rp 4,500 1,760,685.94 306.21 78 1,377,928.35 85.06 22 382,757.59 391.26 100.00 1,760,685.94
ESSER 8MM 537.63 kg Rp 4,500 2,419,312.50 210.38 39 946,687.50 327.25 61 1,472,625.00 537.63 100.00 2,419,312.50

TOTAL 123,719,101.9 32.06 39,663,980.97 58.7 72,615,990.40 90.8 112,279,971.38

Badung, 07 Oktober 2022


Disetujui Oleh : Disetujui Oleh : Diperiksa Oleh : Dibuat Oleh

I Kadek Trisnaarta Wijaya I Putu Ertha Suryadhi, ST I Made Gede Jiwa, ST Putu Artha Wiguna

Biaya transfer ditanggung Penerima


Transfer ke rek. Bank : Mandiri
No. Rek : 175-00-0170640-6
Nama Pemilik Rek. : I Kadek Trisnaarta Wijaya
PENGAJUAN OPNAM PEKERJAAN BAJA GEDUNG
lantai 2
no uraian vol satuan jumlah
1 wf 300 5.7 m1 44
esser 10mm 0.0525 m2 88
esser 8mm 0.045 m2 176

2 wf 250 5.7 m1 18
esser 10mm 0.0375 m2 36
esser 8mm 0.03125 m2 72
tonase

lantai 3
no uraian vol satuan jumlah
1 wf 300 5.7 m1 63
2 esser 10mm 0.0525 m2 92
3 esser 8mm 0.045 m2 184
tonase

TOTAL progress

TOTAL OPNAM RETENSI (5%) OPNAM LALU OPNAM SEKARANG


Rp 112,279,971.38 Rp 5,613,998.57 Rp 37,680,782.00 Rp 68,985,190.81
Rp 65,985,190.81
BAJA GEDUNG HUMANITY

total vol satuan BERAT SATUAN PROGRESS


250.8 41.8 btng 9204.36 kg 90% 8283.924 8283.924
4.62 1.6041667 lmbr 374.25208 kg 100% 374.25208
7.92 2.75 lmbr 514.25 kg 100% 514.25

102.6 17.1 btng 3036.96 kg 90% 2733.264


1.35 0.46875 lmbr 109.35938 kg 100% 109.35938
2.25 0.78125 lmbr 146.09375 kg 100% 146.09375
13385.275 kg 12161.1432083333
13385.275

total vol satuan BERAT SATUAN PROGRESS


359.1 59.85 btng 13178.97 kg 90% 11861.073
4.83 1.6770833 lmbr 391.26354 kg 100% 391.26354
8.28 2.875 lmbr 537.625 kg 100% 537.625
14107.859 kg 12789.9615416667

24951.10475

BADUNG, 7 OKTOBER 2022

I KADEK TRISNAARTA W
OPNAM PEKERJAAN PEMASANGAN BAJA BERAT

NAMA PROYEK : LECTURE BUILDING UNIVERSITAS UDAYANA TOTAL NILAI PEKERJAAN : 123,719,101.88
ALAMAT PROYEK : KAMPUS UNIVERSITAS UDAYANA BUKIT JIMBARAN KUTA SELATAN, KUTA BADUNG - BALI PROGRES s/d PERIODE INI : 112,279,971.38
PROGRES PERIODE INI : 72,615,990.40
PEMBAYARAN s/d PERIODE LALU : 37,680,781.92
RETENSI 5% : 3,630,799.52
RETENSI s/d PERIODE INI 5,613,998.57 PEMBULATAN
TAGIHAN PERIODE INI : 68,985,190.88 68,985,000.00
Sisa : 54,734,101.88

PERIODE OPNAME : 2
Harga Jumlah REALISASI OPNAME
No Item Pekerjaan Qty Sat Satuan Harga PER LALU PER INI S/D PER INI
( Rp ) ( Rp ) Qty % Rp Qty % Rp Qty % Rp

STRUKTUR LANTAI 2
1 WF 300 9,204.36 kg Rp 4,500 41,419,620.00 6,579.03 71.48 29,605,614.75 1,704.90 18.52 7,672,043.25 8,283.92 90.00 37,277,658.00
ESSER 12MM 374.25 kg Rp 4,500 1,684,134.38 314.71 84.09 1,416,204.00 59.54 15.91 267,930.38 374.25 100.00 1,684,134.38
ESSER 8MM 514.25 kg Rp 4,500 2,314,125.00 345.95 67.27 1,556,775.00 168.30 32.73 757,350.00 514.25 100.00 2,314,125.00
2 WF 250 3,036.96 kg Rp 4,500 13,666,320.00 944.83 31.11 4,251,744.00 1,788.43 58.89 8,047,944.00 2,733.26 90.00 12,299,688.00
ESSER 12MM 109.36 kg Rp 4,500 492,117.19 54.68 50.00 246,058.61 54.68 50.00 246,058.58 109.36 100.00 492,117.19
ESSER 8MM 146.09 kg Rp 4,500 657,421.88 58.44 40.00 262,968.77 87.66 60.00 394,453.11 146.09 100.00 657,421.88

STRUKTUR LANTAI 3
3 WF 300 13,178.97 kg Rp 4,500 59,305,365.00 - - - 11,861.07 90.00 53,374,828.50 11,861.07 90.00 53,374,828.50
ESSER 12MM 391.26 kg Rp 4,500 1,760,685.94 306.21 78.26 1,377,928.35 85.06 21.74 382,757.59 391.26 100.00 1,760,685.94
ESSER 8MM 537.63 kg Rp 4,500 2,419,312.50 210.38 39.13 946,687.50 327.25 60.87 1,472,625.00 537.63 100.00 2,419,312.50

TOTAL 123,719,101.9 32.06 39,663,980.97 58.69 72,615,990.40 90.75 112,279,971.38

Badung, 07 Oktober 2022


Disetujui Oleh : Disetujui Oleh : Diperiksa Oleh : Dibuat Oleh

I Kadek Trisnaarta Wijaya I Putu Ertha Suryadhi, ST I Made Gede Jiwa, ST Kadek Widi Artama

Biaya transfer ditanggung Penerima


Transfer ke rek. Bank : Mandiri
No. Rek : 175-00-0170640-6
Nama Pemilik Rek. : I Kadek Trisnaarta Wijaya