Fi
INDUSTRIES.
iv tuurpine com
Client: Dodsal Engineering and
Construction LLC
Project: Qarn Alam Steam Project
Surface Facilities On - Plot
DOCUMENT NUMBER: 3036/MFJ/GRE/DEC
DOCUMENT TITLE:
METHOD STATEMENT— GRE FLANGE JOINT
[ences [appre
SOWWMFRIGRPIDEC Revit
page 1 of LO=
Mervoo Sraremexr
OSES |e awae Jom
1.0 Fiberglass Flange
sence]
|
‘Contents.
44. Scope
a) Tools
b) Bolts & Nuts
4.2. Flanged Joints
4.3. Gaskets & Torques
1.4 Troubleshooting
4.5. Fiberglass Flanges - Torquing Sequence.
2036 MFUGREDEC Rev3 page ?of 10Tine
EPL, scvrsnac ssinurvoxsec|
Fane Jour Rev.:3 |
44 SCOPE
‘These instructions present Future Pipe's recommendation for the proper
instalation and use of fiberglass Nanges. Flanges must always be connected
perpendicular to the axis of the pipe. It should be remembered that GRE
flanges are thicker than the steel flanges ~ bolts should be ordered accordingly.
1, Tools
Tools necessary for assembly of lange joints
2, Ring spanner with required bolt head size
». Torque wrench with required socket size with calibration
certificate
2. Bolts and Nuts
Bolts should be wire brushed and lubricated before being used. Failure
to clean the botts will result in insufficient intial tension in the flange bolts
‘which could resut in movement of the flange during operating
Conditions. Washer and nuts shall be clean thoroughly.
Referon installation man 3
4.2. Flanged joints:
Fiberglass flanges must always be installed tension free; therefore
flanges must be accurately aligned. Pipelines must never be pulled by
means of the flange bots, If the GRE line is connected to a metal ine,
this metal ine must be anchored to prevent any movements or loads
being transmitted to the GRE line. On the GRE side of the flanged joint
the bolts and nuts must have washers to avoid excessive surface
pressure.
‘+ Clean propetly the flange face, holes and gasket
+ Inspect the gasket for any defect prior to be installed. Place the
‘gasket in position. Make sure that the holes of the gasket and the
flanges are aligned.
+ Position the other flange to be assembled to the GRE flange in the
Fight place. Make sure that the holes of the two flanges are aligned
and leveled
+ Insert the stud bolts in the holes, Bolts threads shall be clean and
lubricated to attain proper torque.
1+ Number each slud Lott starting from the top and following a clockwise
sequence. ~
+ Hand tightens all the nuts.
036MENIGRE/DEC Rev3 page 3 of 10—=—
ee snrscaante
Jeewem |
1.3 Gaskets and Torques
[As sealing for GRE flanges, several gaskets types may be used as per
‘approved isvspecificatin, ~
IMPORTANT NOTE
When assembling GRE flanges, bolts should be tightened by hand fist,
then using a forque wrench up to 30% of the max. torque values shown
in fable 1. If leakages occur, torques should be increased up fo 60% of
the max. torque values shown in table 1. Max. torque values are
Urtimate and should be avoided under normal site conditions.
“The following table shows the Maximum torque values (measured in N.m) for
‘ightening the GRE flanges. The maximum torque values are given against the
Test pressure and the Diameter ofthe pipeline,
Pine | Maximum Torgue |. sximum roraue
parc | Velurforasa so | Vatiefor ASA00
3036MENGREIDEC Revd page 4 of 19Ti
FOP ecusnes | METHOD STATEMENT 3036/MFIIGRE/DEC
| Fusnce Jowr |
1.4 Trouble Sho«
15
If assembled joint leaks, loosen and remove all the bolts, nuts, washers
‘and gaskets. Check for alignment of assembly. Rebuild to correct
aignment as required. Check the gasket for camage. if damaged,
discard and replace with new, undamaged gasket
I leak occur as a result of deficiencies in non-fibergiass components of
the piping system, consult the manufacture’ for the defective
components for recommended corrective procedures.
Clean and lubricate old threads and washers betore rejoining. Repeat
the joining procedure outlined above.
ralase - Flange Torque Sequence:
‘Tightening of the bolts of a flange must be done diagonally according to
the sequence as shown in figures below. Bolts in flanges must be placed
on either side ofthe centre line unless otherwise specifies.
30Y6MEY/GREIDEC Rev3 page Sof 10ees — |
| FPL Merton Sraremenr 3036/MFIIGREDEC
| rerun PESTS | ELawce Jom Rev.
Sequence] #Hole | @ Hole | T2Hole | TéHole | 20Hole | 24HVole | 26Hole| S2Hole
Flange | Flange | Flange | Flange Flange | Flange | Flange
1 1 1 1 1
5
3 oa 13 7.
4 Asis [a5 7_[ 9
2 S| 15 i] 25
3 [20 2] 8.
i | “10 4 | 34
22 | 16)
32
3
2
43
29
3
19
it
2
7
23
15
31
4
20
12,
28
16
7
4
a
16
8
6
14
2
70,
16
6
4
14
19,
8
7
7
12
2
3s
18
3
1s
3036 MEUGREDEC Rev page 6 of 030S MFIIGRE/DEC
Revs
|
FOR 12 & 16 HOLE FLANGE
[FLANGE TORQUNG SEQUENCE
3036 MENGRE/DEC Rev3
16 HOLE FLANGE
12 HOLE FLANGE
page 70°10Time:
ste
3036 MFSIGREDEC
Meri Srarewent
Fuace Jont
SONNE TION 9E
pag: 8 of 10
3036 MESGRE/DEC Redie
| Herc Saree |
a
SMSaMFUGREDEC
parr | Jo nes
(Rae |
FLANGE TORQUING SEQUENCE FOR 28 HOLE FLANGE
3036/MEWGREIDEC Rew
page 90f 10[ines a
seg | METHOD STATEMENT 3036/MFIIGREIDEC
Fuawoe vont
‘The holes on the flange should be numbered, with a marker pen (or a chalk), in
clockwise direction and then start to tighten the bolts as per depicted sequence,
It he desired sequence ia not found above, please consult FPI for the same
ENO
WA6MEVGREDEC Rex3 page 10 of 10— a a