J BARCELA CONSTRUCTION

33-4 Purok 3 Buntong Palay, Brgy. Silangan


San Mateo Rizal
Contact No.: 09323750027
O9278104226
joelbarcela1977@gmail.com Billing
To Aylan Construction & Trading Date: 6-May-23
Attention Engr Wen Camero Manpower 6
Project Ramp & Entrance Canopy
Subject Supply of Labor and Tools
Location Philippine Orthopedic Center, Apex Bldg.

1 Ramp Labor Cost Prev. Current Amount This Date


1.1 Board Up 4,601.84 100% 0% ₱0.00 100%
1.2 Chipping of Existing Ramp 3,620.99 100% 0% ₱0.00 100%
1.3 Earthworks 26,482.92 100% 0% ₱0.00 100%
1.4 Rebar & Concreting Works 15,448.37 100% 0% ₱0.00 100%
1.5 Installation of Temp. Gate 4,601.84 100% 0% ₱0.00 100%
Sub-total 54,755.95 ₱0.00
2 Entrance Canopy
2.1 Chipping Works 5,113.15 0% 100% ₱5,113.15 100%
2.2 Scaffolding 7,520.72 0% 100% ₱7,520.72 100%
2.3 Installation of Steel Beam 64,931.05 0% 100% ₱64,931.05 100%
Installation of Planted Steel
2.4 Column 7,765.60 0% 100% ₱7,765.60 100%
2.5 Installatiion of Pipe Brace 10,148.20 0% 100% ₱10,148.20 100%
2.6 Installation of C-Purlins 11,340.24 0% 100% ₱11,340.24 100%
2.7 Installation of Sagrod 1,278.29 0% 100% ₱1,278.29 100%
Installation of Long Span
2.8 Roofing 11,451.12 0% 0% ₱0.00 0%
2.9 Installation of Box Gutter 1,232.64 0% 0% ₱0.00 0%
2.1O Installation of Skylight 1,104.44 0% 0% ₱0.00 0%
2.11 Installation of Downspout 1,314.81 0% 0% ₱0.00 0%
2.12 Plastering of Chip Walls 3,834.86 0% 0% ₱0.00 0%
2.13 Application of Epoxy Primer 7,669.73 0% 80% ₱6,135.78 80%
2.14 Consumables(Oxygen & LPG 10,539.19 0% 70% ₱7,377.43 70%
Sub-total 145,244.04 Sub-total 121,610.47
Contract Price 200,000.00 Total ₱121,610.47
less retention ₱6,080.52
Net Amount ₱115,529.94