Download as pdf or txt
Download as pdf or txt
You are on page 1of 4

Our energy working for you.

TM

Power topic #6044 | Technical information from Cummins Power Generation

Selective coordination standards


and design challenges
■ White Paper
By Rich Scroggins, Technical Advisor, Sales Application Engineering, Cummins
Power Systems

Selective coordination is one of the The NEC defines selective coordination as:
“Localization of an overcurrent condition to
most widely debated and discussed
restrict outages to the circuit or equipment
subjects in the electrical engineering affected, accomplished by the choice of
community. There is no consensus overcurrent protective devices and their ratings
or settings.”
on what constitutes an appropriately
coordinated system. Two of the most In a selectively coordinated system, a fault
commonly applied standards — is cleared by the protective device nearest
upstream from that fault and does not result in
NFPA 70 (National Electrical Code
unnecessary power loss to other downstream
[NEC]) and NFPA 99 (Health Care loads. Selective coordination is typically
Facilities Code) — give seemingly achieved by using an Overcurrent Protective
Device (OCPD) with an instantaneous trip
contradictory definitions.
setting at the bottom of the distribution and
progressively longer time delays higher in the
With that in mind, let’s look at the system; in the event of a fault only the OCPD
closest to that fault will trip.
tradeoffs involved with designing a
coordinated system and outline the
technical and regulatory case for
applying the NFPA 99 definition of
selective coordination.
Without Selective Coordination With Selective Coordination

OPENS
NOT AFFECTED OPENS

UNNECESSARY NOT
POWER LOSS
Fault AFFECTED Fault

Figure 1: Faults with and without selective coordination

Designing a selectively coordinated system presents


a challenge to engineers; safety and equipment
protection, as well as fault isolation, need to be
addressed. The effect of using time delays on OCPDs
is to expose downstream equipment and cable to
fault current for a long period of time. When time-
delayed trip settings are used, it is critical that the
entire system must be designed for the same minimum
level of fault protection. This requirement is mandated
by NEC 110-10:

“The overcurrent protective devices, the total


impedance, the component short circuit ratings,
and other characteristics of the circuit to be protected
shall be selected and coordinated to permit the circuit
protective device used to clear a fault to do so without
extensive damage to the electrical components of
Table 1: Allowable short circuit currents for insulated copper
the circuit.” conductors

NEC 110-10 requires that cable and equipment


be sized to handle the available fault current for Table 2 — derived from NFPA 70E, Table H.4(a) —
the duration of the OCPD time delay. Table 1 illustrates that arc flash energy is a function of both
was published by the Insulated Cable Engineers fault clearing time and the available fault current.
Association and provides an illustration of how an Increasing these parameters increases the arc flash
extended fault clearing time delay will require the incident energy and may require a higher level of
use of larger cable in an application. PPE to operate and maintain equipment. Mandating
coordination for all levels of fault current is at odds with
From Table 1 we can see that a circuit fed from a the stated purpose of the NEC, which is “the practical
source with 40,000 amps of available fault current safeguarding of persons and property from hazards
should use 3/0 cable if the OCPD will clear the fault arising from the use of electricity” (NEC 90.1(A))
in 50 msec (3 cycles at 60 Hz). However, if the OCPD
has a 500 msec time delay (30 cycles), 500 kcmil cable
would be required to safely handle the fault. Fault Max 3 Phase Bolted Fault Current at
Clearing 480Vac
02 | Power Topic #6044

2 2
Oversizing the cable not only increases the cost of the Time (sec) 8 cal/cm PPE 40 cal/cm PPE
system, but also results in a higher level of arc flash 0.05 68 kA 200 kA
incident energy at downstream equipment, as the 0.1 32 kA 183 kA
cable resistance is reduced and allows more current to 0.2 15 kA 86 kA
pass through. 0.33 8 kA 50 kA
0.5 Not Recommended 32 kA

Table 2: Arc flash energy is a function of both fault clearing time and
the available fault current
Selective Coordination
Definitions
The NFPA 70 definition of selective coordination refers
to “the full range of available overcurrent, from overload
to the maximum available fault current, and for the
full range of overcurrent protective device opening
times…”

Maximum available fault current typically refers to


the current that would theoretically flow in the event
of a three phase bolted fault, although a three phase
bolted fault rarely occurs in practice. Single phase
arcing ground faults are much more common and
typically result in lower current levels for which delayed Figure 2: System showing overlapped breakers based on the NFPA
99 definition of selective coordination
interruption is more manageable. Designing a system
so that it will coordinate in the unlikely event of a three
phase bolted fault at the theoretical maximum level of
fault current results in a system that will allow higher There appears to be a conflict between NFPA 99
levels of fault current to flow in the more likely event of and NFPA 70 on whether a system needs to be
a single phase fault. This could create higher levels of coordinated for all levels of fault current and fault
arc flash incident energy at downstream equipment clearing times or only for the duration of a fault that
and compromise system safety. extends beyond 0.1 second. The NFPA has developed
a policy for resolving such conflicts. They determined
It is for this reason that NFPA 99 defines selective that NFPA 99 is responsible for the performance
coordination as achieved if it is demonstrated for all of healthcare electrical systems and NFPA 70 is
time durations greater than 0.1 seconds. The specific responsible for the installation of these systems.
text (section 6.4.1.2.1) says “Overcurrent protective NFPA 70 must defer to NFPA 99 on performance
devices serving the essential electrical system shall issues. Clearly, selective coordination describes
selectively coordinate for the period of time that a the performance of the system, so NFPA 99, the
fault’s duration exceeds 0.1 second.” In Annex A NFPA performance standard, is the appropriate standard
99 clearly states the justification for this requirement to apply.
(A.6.4.2.1.2) “It is important that the various overcurrent
devices be coordinated, as far as practicable, to NFPA 110 (Standard for Emergency and Standby
isolate faulted circuits and to protect against cascading Power Systems) has language similar to NFPA 99
operation on short circuit faults. In many cases, regarding selective coordination. Annex A (A.6.5.1)
however, full coordination could compromise safety states: “It is important that the various overcurrent
and system reliability.” devices be coordinated, as far as practicable, to
isolate faulted circuits and to protect against cascading
Requiring coordination only for time durations greater operation on short circuit faults. In many systems,
than 0.1 second gives the engineer the flexibility to however, full coordination is not practicable without
use instantaneous trip settings for high levels of fault using equipment that could be prohibitively costly or
current and use time-delayed trips on the lower level undesirable for other reasons.”
fault currents. This way the system will be protected for
all levels of fault current up to the theoretical maximum NFPA 110 applies to all emergency and standby
and will be coordinated for the likelier event of arcing power systems, and the language gives the engineer
ground faults and overload conditions. discretion in determining the level of coordination.
03 | Power Topic #6044

The engineer may cite the NFPA 99 standard of


Figure 2 illustrates a system that is coordinated based requiring coordination only in excess of 0.1 second
on the NFPA 99 definition. The trip curves for the two as a best practice. NFPA 70 Articles 700 (Emergency
breakers in this example overlap in the instantaneous Systems), 701 (Legally Required Standby Systems)
region; however, there is no overlap for longer time and 708 (Critical Operations Power Systems) all
durations, so this system would meet the NFPA 99 state: “Selective coordination shall be selected by
selective coordination requirements. a licensed professional engineer or other qualified
persons engaged primarily in the design, installation,
About the author
Rich Scroggins is a Technical Advisor in the and remote monitoring products and has developed
Application Engineering group at Cummins and conducted seminars and sales and service training
Power Generation. Rich has been with Cummins internationally on several products. Rich received his
for 20 years in a variety of engineering and bachelors degree in electrical engineering from the
product management roles. Rich has led product University of Minnesota and an MBA from the University
development and application work with transfer of St. Thomas.
switches, switchgear controls and networking

or maintenance of electrical systems. The selection


shall be documented and made available to those
authorized to design, install, inspect, maintain, and
operate the system.”

The language in these standards has been interpreted


as allowing a licensed PE discretion over system
performance. The PE is allowed to use engineering
judgment in determining that selectively coordinating
the system only for faults beyond 0.1 second and
allowing OCPDs to clear instantaneously in the
event of higher levels of fault current are the best
ways to balance system reliability and performance
considerations with the NEC purposes of safety and
fire prevention.

Summary
Designing a selectively coordinated system presents
challenges. The engineer needs to balance the risks of
temporarily cutting power to the system against safety
risks and the risk of permanent system damage due to
the increased level of arc flash energy.

A requirement for “total” selective coordination


means that OCPDs must be coordinated for all
faults, including a three-phase bolted short circuit, a
worst case scenario and one not commonly seen in
real applications. Delaying interruption of such high
levels of fault current results in exposing downstream
equipment and cables to excessively high levels of fault
energy and could increase the risk of arc flash.

Requiring coordination only for time durations greater


than 0.1 second gives the engineer the flexibility to use
instantaneous trip settings for very high levels of fault
current and use time-delayed trips on the lower level
04 | Power Topic #5590

fault currents, which are more likely to occur.

power.cummins.com

©2015 Cummins Power Generation Inc.


All rights reserved. Cummins Power Generation
and Cummins are registered trademarks of
Cummins Inc. “Our energy working for you.”
is a trademark of Cummins Power Generation.
GLPT-6044-EN (01/15)

You might also like