Kabupaten : Majalengka Jenis Prasarana : Kontraka

Kecamatan : Ligung PERHITUNGAN VOLUME Lokasi :


Desa : Buntu Volume : 6 x 18 m

Analisa Perhitungan Bahan dan Upah :

1. Pekerjaan Pemasangan Bouwplank


Panjang = 99.00 m

6m Bahan :
Kaso 5/7 (Albasia) = 0.010 x 99.00 m = 0.990 m3 = 71
Paku = 0.030 x 99.00 m = 2.970 kg

Upah :
Pekerja = 0.030 x 99.00 m = 2.97 HOK

2. Pekerjaan Galian Tanah :


La = 1.65 m Lb = 0.80 m T = 0.85 m P = 99.00
Volume galian tanah = 104.07 m3
Upah :
Pekerja = 0.400 x 104.07 m3 = 41.63 HOK

1.65 3. Pekerjaan Pasir Urug :


Volume 1 = 0.05 x 0.80 x 99.00 = 3.96 m3
Volume 2 = 0.05 x 6.00 x 6.00 = 1.80 m3
85 Volume urugan pasir = 5.76 m3
Bahan :
Pasir urug = 1.200 x 5.76 m3 = 6.912 m3
80 Upah :
Pekerja = 0.400 x 5.76 m3 = 2.30 HOK

4. Pekerjaan Pasangan Batu Kosong :


25 Volume pas. batu kosong = 0.80 x 0.20 x 99.00 = 15.84 m3
Bahan :
Batu kali = 1.200 x 15.84 m3 = 19.01 m3
60 Pasir urug = 0.100 x 15.84 m3 = 1.58 m3
Upah :
20 Pekerja = 0.500 x 15.84 m3 = 7.92 HOK
60 5 Tkg batu = 0.563 x 15.84 m3 = 8.91 HOK

80 5. Pekerjaan Pasangan Batu Kali : Camp (1 : 4)


La = 0.25 m Lb = 0.60 m T = 1 m P = 154.00
Volume pasangan = 65.45 m3
Bahan :
Batu belah = 1.100 x 120.45 m3 = 132.50 m3
Semen = 3.260 x 120.45 m3 = 392.67 Zak
Pasir psg = 0.520 x 120.45 m3 = 62.63 m3
Upah :
Pekerja = 1.500 x 65.45 m3 = 98.18 HOK
Tkg batu = 0.600 x 65.45 m3 = 39.27 HOK
6. Pekerjaan Urugan Tanah kembali :
Volume 1 = 104.07 - 3.96 - 15.84 - 65.45 = 18.82 m3
Volume 2 = 0.175 x 6.00 x 6.00 = 6.30 m3
Volume urugan tanah kembali = 25.12 m3
Upah :
Pekerja = 0.192 x 25.12 m3 = 4.82 HOK
7. Pekerjaan Beton Bertulang Sloof, Kolom Dan Ring Balk (1 : 2 : 3) :
2.5 Beton site mix
11 15
Panjang sloof = (4x6)+(2x3)+1,5 = 99.00 m
Panjang kolom = ( 7x2,82)+(31x3,62) = 131.96 m
11 Panjang ring balk = (5x6) = 99.00 m
15 Panjang total = 329.96 m
Volume beton bertulang = 0.15 x 0.15 x 329.96 = 7.42 m3

Tanggal Survei : Dibuat Ole


Kader Teknis
Kabupaten : Majalengka Jenis Prasarana : Kontraka
Kecamatan : Ligung PERHITUNGAN VOLUME Lokasi :
Desa : Buntu Volume : 6 x 18 m
Bahan :
Semen = 6.640 x 7.42 m3 = 49.30 zak
Pasir = 0.520 x 7.42 m3 = 3.86 m3
Split 2/3 = 0.780 x 7.42 m3 = 5.79 m3
Upah :
Pekerja = 1.650 x 7.42 m3 = 12.25 HOK
Tkg batu = 0.250 x 7.42 m3 = 1.86 HOK
Besi tulangan
Tulangan Pokok Tulangan Se
Uraian Jml Pjg Jml Jml Pjg
Balok Btg Skg
7 6 14.00 287 49
24 3 5.00 504 49
7 2.82 2.00 139 49
31 3.62 7.00 779 49
1 1.5 0.50 11 49
Jumlah 28.50
Berat besi tulangan pokok Ø 12 = 28.50 btg x 10.68 kg/btg =
Berat besi tulangan sengkang Ø 8 = 71.66 btg x 4.68 kg/btg =
Berat total besi tulangan = 639.73 kg
Bahan :
Besi Ø 12 = 1.050 x 28.50 btg = 29.93 btg
Besi Ø 8 = 1.050 x 71.66 btg = 75.24 btg
Kawat beton = 0.015 x 639.73 kg = 9.60 kg
Upah :
Tkg besi = 0.007 x 639.73 kg = 4.48 HOK
Papan Bekisting
4 Panjang beton = 329.96 m Luas = 2 x 0.15 x 329.96
Bahan
Kaso 5/7 kls 2(2 x pakai) = 0.017 x 98.99 = 1.683 m3 = 120.
Papan Terentang (2 x pakai) = 0.024 x 98.99 = 2.376 m3 = 148.
18 34 Paku = 0.400 x 98.99 = 39.595 kg
34 Upah
36 Pekerja = 0.300 x 98.99 m2 = 29.70 HOK
231.072 290.8 Tkg kayu = 0.300 x 98.99 m2 = 29.70 HOK

1 8. Pekerjaan Pasangan 1/2 bata (1 : 4 ) :


P1 = (2,9x2,4) 8 Luas pembatas ruang = {((4x6)+(2x3)+1,5)x3,32}+{2x(0,5x4.5x1,84)} = 300
= 9.900 m2 292.2 Luas pintu dan jendela = (2,9x2,4)+(1,10x2,4)+(1x1,95)+2x(2,5x1,75) = 33
P2 = (1,1x2,4) Luas pasangan bata = 300.00 - 33.66 = 266.34 m2
= 14.400 m2 Bahan :
P3 = (1,0x1,95) Bata merah = 70.000 x 266.34 m2 = 18,644 bh
= 9 m2 PC (50 kg) = 0.194 x 266.34 m2 = 52 zak
J = 2x(2,5x1,75) Pasir psg = 0.045 x 266.34 m2 = 12 m3
= 8.750 m2 Upah :
Pekerja = 0.320 x 266.34 m2 = 85.23 HOK
Tk. Batu = 0.100 x 266.34 m2 = 26.63 HOK

9. Pekerjaan Plesteran Dinding 1 : 5+ Acian :


Luas plesteran dinding = 2x 266.34 = 532.68 m2
Bahan :
PC (50 kg) = 0.086 x 532.68 m2 = 46 zak
Pasir psg = 0.023 x 532.68 m2 = 12 m3
Upah :
Pekerja = 0.200 x 532.68 m2 = 106.54 HOK
Tk. Batu = 0.150 x 532.68 m2 = 79.90 HOK

Tanggal Survei : Dibuat Ole


Kader Teknis
Kabupaten : Majalengka Jenis Prasarana : Kontraka
Kecamatan : Ligung PERHITUNGAN VOLUME Lokasi :
Desa : Buntu Volume : 6 x 18 m
10. Pekerjaan Lantai Keramik 30/30 :
Luas lantai = 18.00 x 6.00 = 108.00 m2
Bahan :
Keramik 40/40 = 1.010 x 108.00 m2 = 109.08 DUS
PC (50 kg) = 0.167 x 108.00 m2 = 18.06 kg = 0.36
0.96 Pasir psg = 0.023 x 108.00 m2 = 2.48 m3
Semen warna = 0.090 x 108.00 m2 = 9.72 kg
Upah :
Pekerja = 0.2500 x 108.00 m2 = 27.00 HOK
Tk. Batu = 0.1200 x 108.00 m2 = 12.96 HOK
11. Pekerjaan Kusen Pintu dan Jendela
23 Kayu 6/15 ( kusen pintu ) = 12 x 3.00 btg = 36.00 btg
Kayu 6/15 (kusen pintu ) = 1 x 0.00 btg = 0.00 btg
430 Kayu 6/15 (kusen pintu ) = 1 x 0 btg = 0.00 btg
Kayu 6/15 (kusen jendela) = 7 x 2 btg = 14.00 btg
Papan 2/20 = ((1,02+0,82+0,82+0,72)*1,91)/0,8 50.00
= 0.00 lbr
Volume kayu kusen pintu & jendela = (16x0,06x0,15x4) + (8x0,02x0,20x4)
= 5.18 m3
Bahan :
Kayu 6/15 = 1.000 x 50.00 btg = 50.00 btg
Papan 2/20 = 1.000 x - lbr = - lbr
Paku = 2.5000 x 5.18 m3 = 12.96 kg
Lem putih (Fox) = 1.0000 x 5.18 m4 = 5.18 kg
Upah :
Pekerja = 4.000 x 5.18 m3 = 20.74 HOK
Tk. Kayu = 15.500 x 5.18 m3 = 80.35 HOK

12. Pekerjaan Daun Pintu :


Daun Pintu Panel 1
Luas rangka pintu = (0,82 x 1,91)
= 9.40 m2
Bahan :
Papan 4/20 = 0.040 x 9.40 m2 = 0.376 m3
= 0.376 / ( 0,04 x 0,20 x 4 ) = 11.75 Lbr
= 2.00 Lbr
Lem putih (Fox) = 0.7500 x 9.40 = 7.05 kg
List kayu = 4.0000 x 9.40 = 37.59 btg
Upah :
Pekerja = 0.600 x 9.40 m2 = 5.64 HOK
Tk. Kayu = 2.600 x 9.40 m2 = 24.43 HOK
Daun Pintu Panel 2
Luas rangka pintu = 1,02 x 1,91
= - m2
Bahan :
Papan 4/20 = 0.040 x - m2 = - m3
= - / ( 0,04 x 0,20 x 4 ) = 0.00 Lbr
= 3.00 Lbr
Lem putih (Fox) = 0.7500 x - = - kg
List kayu = 4.0000 x - = - btg
Upah :
Pekerja = 1.000 x 0.00 m2 = - HOK
Tk. Kayu = 2.500 x 0.00 m2 = - HOK
Daun Pintu Panel 2
Luas rangka pintu = 0,72 x 1,91
= - m2
Bahan :
Papan 4/20 = 0.040 x - m2 = - m3
= - / ( 0,04 x 0,20 x 4 ) = 0.00 Lbr
= 2.00 Lbr
Lem putih (Fox) = 0.7500 x - = - kg
List kayu = 4.0000 x - = - btg
Upah :
Pekerja = 1.000 x 0.00 m2 = - HOK
Tk. Kayu = 2.500 x 0.00 m2 = - HOK

Tanggal Survei : Dibuat Ole


Kader Teknis
Kabupaten : Majalengka Jenis Prasarana : Kontraka
Kecamatan : Ligung PERHITUNGAN VOLUME Lokasi :
Desa : Buntu Volume : 6 x 18 m

13. Pekerjaan Daun Jendela Kaca (Tanpa Kaca) :


Papan 3/20 (rangka jendela) = 4 x 0.5 lbr = 2.00 lbr
Luas daun jendela kaca = 4 x 0,62 x 1,22 = 3.03 m2
Luas rangka = 4x{(2x0,07x0,62)+(2x0,07x1,22)} = 1.5456 m2
Bahan :
Papan 3/20 = 0.035 x 1.55 m2 = 0.054 m3 = 2.25 lbr
Lem putih (Fox) = 0.7500 x 1.55 = 1.159 kg
List kayu = 4.0000 x 1.55 = 6.182 btg
Upah :
Pekerja = 0.800 x 1.55 m2 = 1.24 HOK
Tk. Kayu = 2.000 x 1.55 m2 = 3.09 HOK
14. Pekerjaan Kuda-kuda :
Balok tembok 8/12 = - btg = 0.00 m3
Balok gording 8/12 = - btg = 0.00 m3
Balok nok 8/12 = - btg = 0.00 m3
Balok bubung 8/12 = - btg = 0.00 m3
Balok tarik 8/12 = - btg = 0.00 m3
Kaki kuda-kuda 8/12 = - btg = 0.00 m3
Tiang kuda-kuda 8/12 = - btg = 0.00 m3
Balok sokong 8/12 = - btg = 0.00 m3
Balok jepit 5/10 = - btg = 0.00 m3
Ikatan Angin 5/10 = - btg = 0.00 m3
Papan suri-suri 2/20 = - lbr = 0.00 m3
Konsol 8/12 = - btg = 0.00 m3
Volume kayu = 0.00 m3
Bahan :
Balok 8/12 = 1.100 x - btg = - btg
Balok 5/10 = 1.100 x - btg = - btg
Papan 2/20 = 1.100 x - lbr = - lbr
Besi Strip = 15.000 x - m3 = - kg
Paku 8-12 = 0.800 x - m3 = - kg
Upah :
Pekerja = 4.000 x 0.00 m3 = - HOK
Tk. Kayu = 12.000 x 0.00 m3 = - HOK
15. Pekerjaan Rangka Atap :
Luas atap = 2x(3.7x 7,4)+(1,8x7,4) = 120.00 m2 120.00
Bahan :
Kaso 5/7 = 0.012 x 120.00 m2 = 1.44 m3 = 102.86
Reng 2/3 = 0.003 x 120.00 m2 = 0.36 m3 = 150.00
Paku 5-7 = 0.150 x 120.00 m2 = 18.00 kg
Upah :
Pekerja = 0.100 x 120.00 m2 = 12.00 HOK
Tk. Kayu = 0.100 x 120.00 m2 = 12.00 HOK

16. Pekerjaan Penutup Atap Genteng Palentong (Press Jatiwangi) :


Luas atap = 2x(3.7x 7,4)+(1,8x7,4) = 0.00 m2
Bahan :
Genteng Press = 25.000 x - m2 = - bh
Upah :
Pekerja = 0.150 x 0.00 m2 = - HOK
Tk. Kayu = 0.075 x 0.00 m2 = - HOK

17. Pekerjaan Bubungan Atap Genteng Bubung Palentong Ex Jatiwangi :


Panjang bubungan = 15.00 m
Bahan :
Genteng bbg = 5.000 x 15.00 m = 75.00 bh
PC (50 kg) = 8.000 x 15.00 m = 120.00 kg = 2.40 zak
Pasir psg = 0.021 x 15.00 m = 0.32 m3
Upah :
Pekerja = 0.400 x 15.00 m = 6.00 HOK
Tk. Batu = 0.200 x 15.00 m = 3.00 HOK

18. Pekerjaan List Plank 3/20 :


Panjang list plank = (2x7,4) + 2 (2x3,4)+(2.7x2) = 33.80 m
Bahan :
Papan 3/20 = 0.0070 x 33.80 m = 0.24 m3 = 9.858 lbr
Paku = 0.1000 x 33.80 m = 3.38 kg
Upah :
Pekerja = 0.070 x 33.80 m = 2.37 HOK
Tk. Kayu = 0.200 x 33.80 m = 6.76 HOK

Tanggal Survei : Dibuat Ole


Kader Teknis
Kabupaten : Majalengka Jenis Prasarana : Kontraka
Kecamatan : Ligung PERHITUNGAN VOLUME Lokasi :
Desa : Buntu Volume : 6 x 18 m
19. Pekerjaan Langit-langit (Plafond) GRC Rangka kayu kls 2 :
Luas plafond = 8,4 X 7,4 = 62.16 m2
Bahan :
Kaso 5/7 = 0.014 x 62.16 m2 = 0.87 m3 = 62
Kayu 5/10 = 0.004 62.16 m2 = 0.22 m3 = 11
Paku = 0.220 x 62.16 m2 = 13.68 kg
Triplek 3mm = 1.000 x 62.16 m2 = 62.16 m2 = 22
Upah :
Pekerja = 0.280 x 62.16 m2 = 17.40 HOK
Tk. Kayu = 0.400 x 62.16 m2 = 24.86 HOK

20. Pekerjaan Pengecatan Dinding dan Plafond :


Luas pengecatan dinding = 2 x 266.34 = 532.68 m2
Luas plafond = 7,5 x 9,4 = 70.50 m2
Luas pengecatan = 532.68 + 70.50 = 603.18 m2
Bahan :
Plamir = 0.100 x 603.18 m2 = 60.32 kg
Cat dasar = 0.100 x 603.18 m2 = 60.32 kg
Cat penutup 2x = 0.260 x 603.18 m2 = 156.83 kg
Rol cat = 0.010 x 603.18 m2 = 6.03 bh
Ampelas = 0.500 x 603.18 m2 = 301.59 lbr

Pekerja = 0.020 x 603.18 m2 = 12.06 HOK


Tk. Cat = 0.063 x 603.18 m2 = 38.00 HOK

21. Pekerjaan Pengecatan Kayu Berikut Meni :


Ksn pintu = (9,6x11,6)+(4,4x9,6)+(4,4x7,8)x0,04 =
Daun pintu 1 = (1,02x1,91) + (0,04 x 5,46) =
Daun pintu 2 = ((0,82x1,91)+(0,04x5,46)) =
Daun pintu 3 = (0,72 x 1,91) + (0,04 x 9,68) =
Kusen jendela = (0,25x7,9)+(0,40x5,4)+(18x0,24x0,4) =
Daun jendela = 4x2x0,7x(0,62+0,62+1,22+1,22) = 2
List plank = 0,23 x Pjg list plank = 0.23 x 33.80 =
Luas pengecatan =
Bahan :
Meni kayu = 0.200 x 48.05 m2 = 9.61 kg
Plamir kayu = 0.150 x 48.05 m2 = 7.21 kg
Cat dasar = 0.170 x 48.05 m2 = 8.17 kg
Cat penutup 3x = 0.350 x 48.05 m2 = 16.82 kg
Ampelas kayu = 0.400 x 48.05 m2 = 19.22 lbr
Minyak terpentin= 0.150 x 48.05 m2 = 7.21 ltr
Kwas 3" = 0.050 x 48.05 m2 = 2.40 bh
Upah :
Pekerja = 0.070 x 48.05 m2 = 3.36 HOK
Tk. Cat = 0.105 x 48.05 m2 = 5.05 HOK

21. Pekerjaan Kloset Jongkok


Volume = 6 bh
Bahan :
Kloset Jongkok Porselen = 1.000 x 6.00 bh = 6.00 bh
Semen Portland = 6.000 x 6.00 bh = 36.00 kg = 0.
Pasir Pasang = 0.010 x 6.00 bh = 0.06 m3
Bata Merah = 7.000 x 6.00 bh = 42.00 bh
Upah :
Pekerja = 1.000 x 6.00 bh = 6.00 HOK
Tk. Batu = 1.500 x 6.00 bh = 9.00 HOK

22. Pekerjaan Bak Mandi Batu Bata Lapis Kramik 0,6 x 0,6 x 0,85 m
Volume = 1 bh
Bahan :
Batu Bata = 167.000 x 1.00 bh = 167.00 bh
Semen Portland = 127.000 x 1.00 bh = 127.00 kg = 2.
Pasir Pasang = 0.300 x 1.00 bh = 0.30 m3
Kramik Dinding 20 x 25 = 3.790 x 1.00 bh = 3.79 m2
Semen Warna = 6.000 x 1.00 bh = 6.00 kg
Upah :
Pekerja = 6.000 x 1.00 bh = 6.00 HOK
Tk. Batu = 3.000 x 1.00 bh = 3.00 HOK

Tanggal Survei : Dibuat Ole


Kader Teknis
Kabupaten : Majalengka Jenis Prasarana : Kontraka
Kecamatan : Ligung PERHITUNGAN VOLUME Lokasi :
Desa : Buntu Volume : 6 x 18 m
23. Pekerjaan Septick Tank 2,5 x 1,5 x 2 m
Volume = 6 unit

Galian Tanah 7,5 m3


Volume galian tanah = 45.00 m3
Upah :
Pekerja = 0.400 x 45.00 m3 = 18.00 HOK

Pasir Urug 0,357 m3


Volume urugan pasir = 2.14 m3
Bahan :
Pasir urug = 1.200 x 2.14 m3 = 2.570 m3
Upah :
Pekerja = 0.400 x 2.14 m3 = 0.86 HOK

Lantai Kerja 3,75 m3


Bahan
Semen = 10.000 x 3.75 m3 = 37.50 kg = 0.75 Zak
Pasir = 0.260 x 3.75 m3 = 0.98 m3
Split 2/3 = 0.040 x 3.75 m3 = 0.15 m3
Upah :
Pekerja = 1.150 x 3.75 m3 = 4.31 HOK
Tkg batu = 0.020 x 3.75 m3 = 0.08 HOK

Pas. Bata 1:3 (25 m2)


Volume = 25 m2
Bahan :
Bata merah = 70.000 x 25.00 m2 = 1,750 bh
PC (50 kg) = 14.350 x 25.00 m2 = 359 kg = 7.18
Pasir psg = 0.054 x 25.00 m2 = 1.35 m3
Upah :
Pekerja = 0.429 x 25.00 m2 = 10.73 HOK
Tk. Batu = 0.214 x 25.00 m2 = 5.35 HOK

Plesteran + Acian 1:3 (25 m2)


Volume = 25 m2
Bahan :
PC (50 kg) = 6.480 x 25.00 m2 = 162 kg = 3.24
Pasir psg = 0.019 x 25.00 m2 = 0.48 m3
Upah :
Pekerja = 0.286 x 25.00 m2 = 7.15 HOK
Tk. Batu = 0.214 x 25.00 m2 = 5.35 HOK

Plat Beton Penutup + Balok 0,5 m3 (t=10cm)


Beton Bertulang 1 : 2 : 3
Volume = 2,5 x 2 x 0,10 = 0.5 m3
Bahan
Semen = 336.000 x 0.50 m3 = 168.00 zak = 3.36 Zak
Pasir = 0.540 x 0.50 m3 = 0.27 m3
Split 2/3 = 0.810 x 0.50 m3 = 0.41 m3

Upah :
Pekerja = 2.000 x 25.00 m3 = 50.00 HOK
Tkg batu = 0.350 x 25.00 m3 = 8.75 HOK
Beton Bertulang 1 : 2 : 3
p = 2.5 m n = 21 bh Jlh Btg =
p = 2m n = 26 bh Jlh Btg =
Berat besi tulangan pokok Ø 10 = 8.75 btg x 7.44 kg/btg =
Berat total besi tulangan = 65.10 kg
Bahan :
Besi Ø 10 = 1.050 x 8.75 btg = 9.19 btg
Kawat beton = 0.010 x 65.10 kg = 0.65 kg
Upah :
Tkg besi = 0.007 x 65.10 kg = 0.46 HOK

Tanggal Survei : Dibuat Ole


Kader Teknis
Kabupaten : Majalengka Jenis Prasarana : Kontraka
Kecamatan : Ligung PERHITUNGAN VOLUME Lokasi :
Desa : Buntu Volume : 6 x 18 m
Pipa PVC 4" + Sambungan 9 m'
Bahan :
Pipa PVC Ø 4" = 1.200 x 9.00 m = 10.80 m = 2 btg
Sambungan = 1.000 x 2.00 bh = 2.00 bh
Upah :
Pekerja = 0.135 x 9.00 kg = 1.22 HOK
Tkg batu = 0.225 x 9.00 kg = 2.03 HOK

Pipa GL 1½" 2m'


Bahan :
Pipa GL Ø 1½" = 1.200 x 2.00 m = 2.40 m = 1 btg
Upah :
Pekerja = 0.108 x 2.00 kg = 0.22 HOK
Tkg batu = 0.180 x 2.00 kg = 0.36 HOK

Galian Tanah Untuk Rembesan 5,625 m3


Upah :
Pekerja = 0.400 x 5.625 m3 = 2.25 HOK

Pasangan Ijuk 9 kg
Bahan :
Ijuk = 6.000 x 9.00 m3 = 54.000 kg
Upah :
Pekerja = 0.150 x 9.00 m3 = 1.35 HOK

Urugan Kerikil 1,75 m3


Bahan :
Seplit 2/3 = 1.200 x 1.75 m3 = 2.100 m3
Upah :
Pekerja = 0.150 x 1.75 m3 = 0.26 HOK

Urugan Kembali Perataan Tanah 1,875 m3


Upah :
Pekerja = 0.192 x 1.875 m3 = 0.36 HOK

Bahan :
1 PC (50 Kg) = 577.79 zak = 578 zak
2 Semen Warna = 15.72 kg = 16 kg
3 Batu belah = 151.50 m3 = 152 m3
4 Seplit 2/3 = 8.45 m3 = 8 m3
5 Pasir Pasang = 96.96 m3 = 97 m3
6 Pasir Urug = 11.07 m3 = 11 m3
7 Bata Merah = 20,603 bh = 20,603 bh
8 Besi Ø 12 = 39.11 btg = 39 btg
9 Besi Ø 8 = 75.24 btg = 75 btg
10 Kawat Beton = 10.25 kg = 10 kg
11 Balok 6/15 Klas 2 = 50.00 btg = 50 btg
12 Balok 8/12 Kayu kls 2 = - btg = - btg
13 Balok 5/10 Kayu kls 2 = 12.34 btg = 12 btg
14 Kaso 5/7 Kayu kls 2 = 173.36 btg = 173 btg
15 Reng 2/3 Kayu kls 2 = 150.00 btg = 150 btg
16 Papan 4/20 Kayu Kls 2 = 7.00 lbr = 7 lbr
17 Papan 3/20 Kayu klas 2 = 12.11 lbr = 12 lbr
18 Papan 2/20 Kayu Klas 2 = - lbr = - lbr
19 Papan Baugisting = 148.48 lbr = 148 lbr
20 Kaso 5/7 Albasia = 190.91 lbr = 191 lbr
21 Kramik Polos 40/40 = 109.08 m2 = 109 m2

Tanggal Survei : Dibuat Ole


Kader Teknis
Kabupaten : Majalengka Jenis Prasarana : Kontraka
Kecamatan : Ligung PERHITUNGAN VOLUME Lokasi :
Desa : Buntu Volume : 6 x 18 m
22 Genteng Palentong Jtw = - bh = - bh
23 Genteng Bubung Jtw = 75.00 bh = 75 bh
24 GRC = 24.48 m2 = 24 m2
25 Paku = 79.46 kg = 79 kg
26 Cat Tembok = 217.14 kg = 217 kg
27 Cat Kayu = 24.99 kg = 25 kg
28 Plamir Tembok = 60.32 kg = 60 kg
29 Plamir Kayu = 7.21 kg = 7 kg
30 Meni Kayu = 9.61 kg = 10 kg
31 Minyak Terpentin = 7.21 ltr = 7 ltr
32 Kunci Tanam Royal = 2.00 psg = 2 btg
33 Engsel Pintu/Jendela = 7.00 psg = 7 btg
34 Grendel Pintu/Jendela = 7.00 psg = 7 btg
35 Hak Angin = 4.00 psg = 4 btg
36 Kaca Polos 3 mm = 5.27 m2 = 5 m2
37 Rol cat = 6.03 bh = 6 bh
38 Ampelas = 301.59 lbr = 302 lbr
39 Ampelas kayu = 19.22 lbr = 19 lbr
40 Kwas 3" = 2.40 bh = 2 bh
41 Keramik Dingding = 3.79 m2 = 4 m2
42 Ijuk = 54.00 kg = 54 kg
43 Pipa PVC Ø 4'' = 2.00 btg = 2 btg
44 Pipa GL Ø 4'' = 1.00 btg = 1 btg
45 Sambungan keni = 2.00 bh = 2 bh
46 Kloset jongkok = 1.00 bh = 1 bh
47 Besi strip = - Kg = - Kg
48 Lem putih fox = 7.05 Kg = 7 Kg
49 List kayu Jendela = 37.59 lmbr = 38 btg
50 List Palafon = 23.00 btg = 23 btg

Upah :
Pekerja = 580.793 HOK = 581 x 6/5 = 697 Hok
Tukang = 433.148 HOK = 434 x 6/5 = 521 Hok

Tanggal Survei : Dibuat Ole


Kader Teknis
Form : 19
Jenis Prasarana : Kontrakan Bumdes

6 x 18 m

Btg

Dibuat Oleh :
Kader Teknis
Form : 19
Jenis Prasarana : Kontrakan Bumdes

6 x 18 m

Tulangan Sengkang
Pjg Jml
Btg
49 11.96
49 21.00
49 5.78
49 32.46
49 0.46
71.66
304.38 kg
335.35 kg

= 98.99 m2

120.20 Btg
148.48 Lbr

300.00 m2
33.66 m2

Dibuat Oleh :
Kader Teknis
Form : 19
Jenis Prasarana : Kontrakan Bumdes

6 x 18 m

Zak

Dibuat Oleh :
Kader Teknis
Form : 19
Jenis Prasarana : Kontrakan Bumdes

6 x 18 m

btg
btg

Dibuat Oleh :
Kader Teknis
Form : 19
Jenis Prasarana : Kontrakan Bumdes

6 x 18 m

btg
btg

lbr

7.517 m2
2.167 m2
1.785 m2
2.335 m2
5.863 m2
20.608 m2
7.77 m2
48.05 m2

0.72 zak

2.54 zak

Dibuat Oleh :
Kader Teknis
Form : 19
Jenis Prasarana : Kontrakan Bumdes

6 x 18 m

zak

zak

5.25 btg
3.50 btg
65.10 kg

Dibuat Oleh :
Kader Teknis
Form : 19
Jenis Prasarana : Kontrakan Bumdes

6 x 18 m

Dibuat Oleh :
Kader Teknis
Form : 19
Jenis Prasarana : Kontrakan Bumdes

6 x 18 m

Dibuat Oleh :
Kader Teknis
1,981,000

45,000

119,000
2,145,000

1,666,000 = 0.00 m3

1,072,000
93,000
1,165,000

3,422,000
246,000
317,000
491,000
4,476,000

23,850,000
1,000
12,214,000
3,928,000
39,993,000

193,000
1,000
753,000
1,622,000
490,000
103,000

12

63
1,669,492

3,592,000
3,236,000
192,000
247,000

6,611,000
3,713,000
m2 594,000
1,188,000
1,634,000
25,645,567

PJ1 = (0,9x2,4)+(1,6x1,75)
= 4.960 m2
14,916,000 PJ2 = (1,1x2,4)+(1,6x1,75)
1,000 = 5.440 m2
2,338,000 J = 2,3x1,75 = 4.025 m2
3,410,000 V1 = 2x0,5 = 1.000 m2
1,465,000 V2 = 0,5x1,28x0,81
22,130,000 = 0.518 m2

1,000
4,395,000
2,390,000
4,262,000
4,395,000
15,443,000
1,000
5,236,000
29,000
485,000
98,000
1,081,000
713,000
7,642,000

7,751,000
1,000
830,000

4,420,000
13,002,000

321,000
226,000
1,344,000

321,000
1,000
1,000

321,000
1,000
1,000

2,537,000
316,000
50,000
171,000
537,000

16.2

30 4.25
8

2.250
5.063
7.313 7.29

10.8
1,000
1,000
#REF!
1,000
1,000
1,000
1,000
#REF!

5,658,000 a2=b2+c2
1,351,000 C=√a+b
271,000
481,000 5.11
661,000

8,422,000

1,000
481,000
1,000
483,000

226,000
188,000
62,000
241,000
166,000
883,000

#REF!
51,000
95,000
372,000
#REF!

balok 5/10 = 9.400 btg


3,878,000
233,000
1,665,000

790,000
1,552,000
8,118,000

1,086,000
1,508,000
3,921,000
121,000
905,000
483,000
2,091,000
10,115,000

11.6
4.8
9.6

173,000
202,000
344,000
707,000
68,000
65,000
21,000
135,000
278,000
1,993,000

75,967,000

120

127
10

14.35

6.48

6.72
23.6
29.6
36
3
92.2

23.05
RENCANA ANGGARAN BIAYA ( RAB )
DESA : Sambimaya No RAB :
KECAMATAN : Juntinyuat Bidang : Pemb, Desa
KABUPATEN
PROPINSI :: Indramayu
Jawa Barat Kegiatan
Volume :0Gedung Posyandu
Lokasi 6 x 18 m
Jumlah
Kategori Total
No. Uraian Vo l u m e Satuan
Biaya Harga satuan
( Rp ) (Rp.)
I Bahan
I. 1 PC (50 Kg) 578 Zak I.b 78,000 45,084,000
###
I. 2 Semen Warna 16 bh I.b 10,000 160,000
###
I. 3 Batu belah 152 m3 I.a 180,000 27,360,000
###
I. 4 Seplit 2/3 8 M3 I.a 280,000 2,240,000
###
I. 5 Pasir Pasang 97 m3 I.a 195,000 18,915,000
###
I. 6 Pasir Urug 11 m3 I.a 155,000 1,705,000
###
I. 7 Bata Merah 20,603 bh I.a 800 16,482,700
###
I. 8 Besi Ø 12 39 kg I.b 120,000 4,680,000
###
I. 9 Besi Ø 8 75 btg I.b 43,000 3,225,000
###
I. 10 Kawat Beton 10 btg I.a 20,000 200,000
###
I. 11 Balok 6/15 Klas 2 50 btg I.a 155,000 7,750,000
###
I. 12 Balok 8/12 Kayu kls 2 - btg I.a 148,000 ###
-
I. 13 Balok 5/10 Kayu kls 2 12 btg I.a 63,000 756,000
###
I. 14 Kaso 5/7 Kayu kls 2 173 lbr I.a 55,000 9,515,000
###
I. 15 Reng 2/3 Kayu kls 2 150 lbr I.a 9,000 1,350,000
###
I. 16 Papan 4/20 Kayu Kls 2 7 lbr I.a 160,000 1,120,000
###
I. 17 Papan 3/20 Kayu klas 2 12 lbr I.a 140,000 1,680,000
###
I. 18 Papan 2/20 Kayu Klas 2 - lbr I.a 88,000 ###
-
I. 19 Papan Baugisting 148 lbr I.a 25,000 3,700,000
###
I. 20 Kaso 5/7 Albasia 191 lbr I.a 28,000 5,348,000
I. 21 Kramik Polos 40/40 109 bh I.a 45,000 4,905,000
###
I. 22 Genteng Palentong Jtw - bh I.a 2,000 ###
-
I. 23 Genteng Bubung Jtw 75 m2 I.a 3,000 225,000
###
I. 24 GRC 24 kg I.a 68,000 1,632,000
###
I. 25 Paku 79 kg I.a 15,000 1,185,000
###
I. 26 Lem Putih Fox 7 kg I.a 20,000 140,000
I. 27 Cat Tembok 217 kg I.a 25,000 5,425,000
###
I. 28 Cat Kayu 25 kg I.a 42,000 1,050,000
###
I. 29 Plamir Tembok 60 kg I.a 18,000 1,080,000
###
I. 30 Plamir Kayu 7 ltr I.a 28,000 196,000
###
I. 31 Meni Kayu 10 ps I.a 18,000 180,000
###
I. 32 Minyak Terpentin 7 ps I.a 9,000 63,000
I. 33 Kunci Tanam Royal 2 ps I.a 15,000 30,000
I. 34 Engsel Pintu/Jendela 7 ps I.a 15,000 105,000
I. 35 Grendel Pintu/Jendela 7 ps I.a 10,000 70,000
I. 36 Hak Angin 4 m2 I.a 10,000 40,000
I. 37 Kaca Polos 3 mm 5 bh I.a 110,000 550,000
I. 38 Keramik Dingding 4 btg I.a 48,000 192,000
I. 39 Ijuk 54 bh I.a 10,000 540,000
I. 40 Pipa PVC Ø 4'' 2 bh I.a 68,000 136,000
I. 41 Pipa GL Ø 4'' 1 Kg I.a 200,000 200,000
I. 42 Sambungan keni 2 bh I.a 2,500 5,000
I. 43 Kloset jongkok 1 bh I.a 180,000 180,000
I. 44 Besi strip - kg I.a 15,000 -
45 Lis Kayu 38 Lmbr I.b 2,000 76,000
46 Lis Kayu 23 btg I.b 20,000 460,000
Sub Total 1) 169,935,700
RENCANA ANGGARAN BIAYA ( RAB )
DESA : Sambimaya No RAB :
KECAMATAN : Juntinyuat Bidang : Pemb, Desa
KABUPATEN
PROPINSI :: Indramayu
Jawa Barat Kegiatan
Volume :0Gedung Posyandu
Lokasi 6 x 18 m
Jumlah
Kategori Total
No. Uraian Vo l u m e Satuan
Biaya Harga satuan
( Rp ) (Rp.)
II Alat
II. 1 Roll Cat 6 Bh II.a 20,000 120,000
###
II. 2 Ampelas 302 Bh II.a 3,000 906,000
###
II. 3 Ampelas Kayu 19 Bh II.a 3,500 66,500
###
II. 4 Kwas 3" 2 Bh II.a 8,500 17,000
###
Sub Total 2) 1,109,500
III Upah
III. 1 Pekerja 697 Hok III.a 50,000 34,860,000
###
III. 2 Tukang 521 Hok III.a 60,000 31,248,000
###
Sub Total 3) 66,108,000
###
IV Mekanikal dan mebeler
IV 1 Kabel NYM 100 m I.b 8,000 800,000
IV 2 Stop kontak 6 bh I.b 15,000 90,000
IV 3 Saklar ganda 6 bh I.b 20,000 120,000
IV 4 Saklar tunggal 6 bh I.b 15,000 90,000
IV 5 Fiting Plafond 18 bh I.b 10,000 180,000
IV 6 Paralon listrik 12 btg I.b 10,000 120,000
IV 7 Lampu 18 pkt I.b 35,000 630,000
IV 8 bh I.b 1,000,000 -
IV 9 bh I.b 120,000 -
IV 10 bh I.b 80,000 -
IV 11 pkt I.b 1,200,000 -
Sub Total 3) 2,030,000
V Biaya
V 1 Biaya Tim Pelaksana 1 Ls III.c 1,250,000 1,250,000
V 2 Papan Kegiatan 1 Pkt II.a 150,000 150,000
V 3 Prasasti 1 Pkt Ii.a 400,000 400,000
Sub Total 4) 1,800,000
Total 240,983,200

- Kategori Biaya :
I.a. Pembelian bahan hasil tenaga manusia
I.b. Pembelian bahan hasil industri
II.a. Pembelian alat tangan
II.b. Pembelian/penyewaan alat mesin
III.a. Pembayaran tenaga kerja untuk konstruksi
III.b. Pembayaran tenaga untuk pengumpulan bahan
Sambimaya, …………………………..

Mengetahui Tim Penyusun RKP Desa


Kuwu

( ................................... ) ( .................................... )
12.5

52

GENTENG PLENTONG +150

Genteng Palentong Jtw


Genteng Bubung Jtw
Triplek 3 mm
Paku
Cat Tembok

Cat Kayu
Plamir Tembok
Plamir Kayu
Meni Kayu
Minyak Terpentin
Kunci Tanam Royal
Engsel Pintu/Jendela
Grendel Pintu/Jendela
Hak Angin
Kaca Polos 3 mm
Keramik Dingding
Ijuk
Pipa PVC Ø 4''
Pipa GL Ø 4''
Sambungan keni

237,153,200
6587588.889

Kloset jongkok
Besi strip

72

18.2
#REF!

#REF!

#REF!

#REF!
Form 23
HASIL SURVAY HARGA BAHAN/ALAT

NAMA DAN ALAMAT SUPLIER HARGA MINIMUM


NO URAIAN SATUAN
(Rp.)

1 PC (50 Kg) zak Rp 52,000 Rp 78,000 1


2 Semen Warna kg Rp 5,000 Rp 10,000 2
3 Batu Belah m³ Rp 100,000 Rp 180,000 3
4 Seplit 2/3 m³ Rp 150,000 Rp 280,000 4
5 Pasir Pasang m³ Rp 100,000 Rp 195,000 5
6 Pasir Urug m³ Rp - Rp 155,000 6
7 Bata Merah bh Rp 400 Rp 800 7
8 Besi Ø 12 btg Rp 38,500 Rp 120,000 8 Kayu Balok ( Borneo ) M3
9 Besi Ø 8 btg Rp 30,000 Rp 43,000 9 Kayu Papan ( Borneo ) M3
10 Kawat Beton kg Rp 18,000 Rp 20,000 10 Kayu kaso Borneo 5/7 M3
11 Balok 6/15 Kayu Kls 2 btg Rp 216,000 Rp 155,000 11 Kayu reng Borneo 2/3 M3
12 Balok 8/12 Kelas 2 btg Rp 211,200 Rp 148,000 12 Papan ( Kayu Borneo ) M3
13 Balok 5/10 Kelas 2 btg Rp 110,000 Rp 63,000 13 Papan Cor ( Papan Terentang ) M3
14 Kaso 5/7 Kelas 2 btg Rp 49,000 Rp 55,000 14
15 Reng 2/3 Kelas 2 btg Rp 8,400 Rp 9,000 15 0.0384 26.04167 207,360.00 8/12
16 Papan 4/20 Kayu Kls 2 lbr Rp 192,000 Rp 160,000 16 0.036 27.77778 194,400.00 6/15
17 Papan 3/20 Kayu Kls 2 lbr Rp 144,000 Rp 140,000 17 0.014 71.42857 57,400.00 5/7
19 Papan 2/20 Kayu Kls 2 lbr Rp 96,000 Rp 88,000 19 0.0024 416.6667 10,800.00 2/3
21 Papan Baugisting lbr Rp 13,500 Rp 25,000 21 0.02 50 80,000.00 5/10
22 Kaso 5/7 Albasia btg Rp 28,000 22
24 GRC lbr Rp 45,000 Rp 68,000 24 Papan
25 Kramik Polos 40/40 m² Rp 28,000 Rp 45,000 25 0.032 31.25 208,000.00 4/20
26 Genteng Palentong Jtw bh Rp 850 Rp 2,000 26 0.024 41.66667 156,000.00 3/20
27 Genteng Bubung Jtw bh Rp 2,000 Rp 3,000 27 0.016 62.5 104,000.00 2/20
28 Paku kg Rp 13,000 Rp 15,000 28
29 Lem Putih Fox kg Rp 20,000 Rp 20,000 29 0.016 62.5 36,800.00 2/20
30 Cat Tembok kg Rp 14,000 Rp 25,000 30 0.014 71.42857 35,000.00 5/7
31 Cat Kayu kg Rp 40,000 Rp 42,000 31
32 Plamir Tembok kg Rp - Rp 18,000 32
NAMA DAN ALAMAT SUPLIER HARGA MINIMUM
NO URAIAN SATUAN
(Rp.)
33 Plamir Kayu kg Rp - Rp 28,000 33
34 Meni Kayu kg Rp - Rp 18,000 34
35 Minyak Terpentin ltr Rp - Rp 9,000 35
36 Kunci Tanam Royal psg Rp - Rp 80,000 36
37 Engsel Pintu/Jendela psg Rp - Rp 15,000 37
38 Grendel Pintu/Jendela psg Rp - Rp 15,000 38
39 Hak Angin psg Rp - Rp 10,000 39
40 Kaca Polos 5 mm m² Rp - Rp 110,000 40
41 Roll Cat bh Rp 15,000 Rp 20,000 41
42 Ampelas Tembok lbr Rp 4,000 Rp 3,000 42
43 Ampelas Kayu lbr Rp 3,500 Rp 3,500 43
44 Kwas 3 " bh Rp 7,000 Rp 8,500 44
45 Kloset Jongkok Porselen bh Rp 180,000 45
46 Kramik Dinding 20 x 25 m2 Rp 48,000 46
47 Pipa PVC Ø 4" btg Rp 68,000 47
48 Sambungan Keni Ø 4" bh Rp 2,500 48
49 Pipa GL Ø 1½" btg Rp 200,000 49
50 Ijuk kg Rp 10,000 50
51 Linggis bh Rp 25,000 Rp 50,000 51
52 Cangkul bh Rp 3,000 Rp 60,000 52
53 Sekop bh Rp 1,500 Rp 60,000 53
54 Ember Aduk bh Rp 40,000 Rp 4,000 54
55 Benang Clouse bh Rp 60,000 Rp 1,000 55
56 Belincong bh Rp 20,000 Rp 70,000 56
57 Palu 7 kg bh Rp 20,000 Rp 20,000 57
58 Palu Kecil bh Rp 7,500 Rp 15,000 58
59 Kakak Tua bh Rp 20,000 59
60 Sendok Aduk bh Rp 7,500 60
61 Lis Kayu Btg Rp 2,000 61
62 Besi Strip Kg Rp 15,000
Lis Plafon btg Rp 20,000

Mengetahui
Ketua TPK
NAMA DAN ALAMAT SUPLIER HARGA MINIMUM
NO URAIAN SATUAN
(Rp.)
...........................
5,400,000.00
5,900,000.00
4,100,000.00
4,500,000.00
6,500,000.00
2,300,000.00
2,500,000.00
148,000.00
155,000.00
55,000.00
9,000.00
63,000.00

160,000.00
140,000.00
88,000.00

25,000.00
28,000.00
PROGRAM DANA DESA
Gording 8/12 Balok sokong 8/12
PENYERTAAN MODAL
BUMDES

Ring balok 8/12 PROVINSI JAWA BARAT


Kaki kuda-kuda 8/12
Reng 2/3 KABUPATEN MAJALENGKA
KECAMATAN LIGUNG
Balok bumbung 8/12
Usuk 5/7 DESA
BUNTU
JENIS PRASARANA
KONTRAKAN BUMDES
LOKASI
DUSUN GEMAH RIPAH
JUDUL GAMBAR
RENCANA ATAP
Dibuat oleh
TPK / KPMD Teknis

( ……………………… )
Diperiksa

Diketahui
RENCANA ATAP
Ketua Bumdes Desa Buntu

MAMAT RAHMAT HIDAYAT

Lembar ………dari …….lembar


Program Nasional
Pemberdayaan Masyarakat
Mandiri Perdesaan

PROVINSI JAWA BARAT


KABUPATEN MAJALENGKA
KECAMATAN LIGUNG
DESA
BUNTU
JENIS PRASARANA
KONTARAKAN BUMDES
RENCANA PONDASI LOKASI
DUSUN GEMAH RIPAH
JUDUL GAMBAR
RENCANA PONDASI,
TAMPAK DEPAN
Dibuat oleh
TPK / KPMD Teknis

( ……………………… )
Diperiksa
FT

Diketahui
Ketua BUMDES Desa Buntu

MAMAT RAHMAT HIDAYAT


Lembar ………dari …….lembar

You might also like