1 Pre - work 3 days

Mobilisasi Tools, Equipment, Manpower & Set Up Tool 1 days


Mobilisasi Material to Working Area 1,5 days
Safety Induction 0,5 days

2 Work Sequence

Fabrication Erection and Instal Ducting 26 days


Dismantling Pipe 16'' and 6'' stage 1 2 days
Erection Pipe 16'' and 6'' stage 1 3 days
Instal Ducting 16'' and 6'' stage1 4 days
Dismantling Pipe 16'' and 6'' stage 2 2 days
Erection Pipe 16'' and 6'' stage 2 3 days
Instal Ducting 16'' and 6'' stage 2 4 days
Dismantling Pipe 16'' and 6'' stage 3 2 days
Erection Pipe 16'' and 6'' stage 3 2 days
Instal Ducting 16'' and 6'' stage 3 4 days

3 Work final 1 days

BASTP 1 days

Total 30 days

Project :
Working Fabrication and Erection Pipe CHWP Summary
at Mall Mangga Dua
Work
Date : 17 February 2023
Note : Area Laydown Material Provide by Mall Mangga Dua
: Electrical dan Lighting Provide By Mall Mangga Dua
: Blasting Room Provide By Bakrie
: Working Area Provide By Mall Mangga Dua