Brecker Checklist KC

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 2

KUNAL CONSTRUCTION

PROJECT :JSW STEEL COATED PRODUCT LIMITED


CHECKLIST FOR BREAKER INSPECTION
NAME OF LOCATION : FREQUENCY :
NAME OF CONTRACTOR / EMPLOYEE : INSPECTION BY (NAME):
DATE OF RAGISTRATION : EQUIPMENT SERIAL NO:
DATE OF INSPECTION :

4
3

SR NO. POINT OF INSPECTION YES NO N/A


1 Breker should be physically should and in good
condition
2 Flexible cord should be provided to keep cable tree
from damage.
3 Handle should be provided for better control.

4
Bit should be in free from defect and in good conditon.

5 Double insulation to be free from damage.

6 All cable should be free from damages.

7 Switch should be free from defect and in working


condition.
8 Power connection to be taken through industrial plug
only.
Acceptable If not acceptable - equipment
Overall Observation : (Yes/No) removed from site (Date)

Checked By Date
Contractor's Supervisor :
Site Incharge :
JSW/SHE/2023/04/PCC/01
IMITED REV: 0

MINIMUM ONNCE IN A WEEK

7
5

OBSERVATION DETAILS

Corrective / Preventive action taken on ( Date)

Signature

You might also like