Name of PMO: PPA Head Office Date of Receipt of IAD Report: _________
1 Deficiency in monitoring of PMO’s compliance The Acting PCMD Manager committed to:
with PPA MC No. 01-2014, re: Guidelines in the
Classification, Documentation & Funding of 1. Review the current Systems and
Expenditures for Infrastructure Projects. Procedures of PCMD particularly on the
evaluation of PMO’s POWs.
A. PMO Infrastructure projects with above 2. Conduct a joint review of PPA MC
20% repair cost of the netbook value and No. 01-2014 together with the Finance
below 80% operational efficiency were personnel and other Engineering
classified/funded under R&M instead of Departments for further improvement and
CAPEX. proper guidance of its implementation.
B. PMO’s infrastructure projects were
classified as “CAPEX” in the submitted
Annex A but were budgeted under “R&M”.
C. Some of the scope of works and/or
description indicated on the approved
POWs conflicts with the classification of
infra projects on Annex A.
2 Weak monitoring in the provisions of PPA The Acting PCMD Manager committed to:
Memorandum Order No. 01-2000.
1. Revisit and strengthen the internal control in
A. Non-submission of Prioritized List of place.
Proposed Engineering Projects (PLOPEP)
on the 2nd week of March of the current
year.
B. Delayed submission of “updated
Page 1|4
PLOPEP”.
C. Non-submission of Midyear
Accomplishments Report.
3 Weak internal control in the preparation of the The DSD Manager committed to:
Initial Project Procurement Management Plan
(PPMP). 1. Conduct review on the process of
preparation of initial PPMP in coordination
with BAC and OAGME.
6 Weakness in the preparation, posting, and The AGME and BAC Chairperson committed
submission of the Approved Annual Procurement to:
Plan (APP).
1. Use the prescribed APP form. (AGME)
A. Head Office’s APP is not in the prescribed 2. Ensure that all projects will be included in
format. the APP. (BAC Chairperson)
B. Non-inclusion of some projects in the 3. Deliberate with the Management the
Page 2|4
Approved APP. matters on RDA and RA 9184
C. Weak compliance with the required requirements. (AGME and BAC
signatories of APP per RA 9184. Chairperson)
D. Non-compliance in the preparation of 4. Prepare and submit the required Posting
Posting Certification of the Approved Certification for the APP. (BAC
Annual Procurement Plan (APP). Chairperson)
7 Weakness in the preparation and submission of The BAC Chairperson committed to:
the Procurement Monitoring Report (PMR).
1. Use the latest prescribed format of the PMR
A. Outdated format of PMR. and to prepare the required Posting
B. Non-preparation of PMR Posting Certification.
Certification.
9 There is an observed gap in internal control in the The Acting PCMD Manager committed to:
determination of allocation of funds for
Maintenance of Physical Facilities (MPF). 1. Establish internal control to determine
allocation of funds for the MPF.
Page 3|4
10 Weakness in the application of authorized The AGME committed to:
signatories per Approved Revised Delegation of
Authority (RDA) on Engineering Matters. 1. Revisit and to strengthen the RDA for
Engineering Matters.
A. LFP PMO
Unauthorized signatories in the POWs of
two (2) Locally-Funded Projects (LFP)
which was implemented by the Port
Management Office (PMO).
B. Dredging Projects
Signatories on the Programs of Work
(POW) and Drawings (Project Design) of
Dredging Projects LFP HO are contrary to
the Approved RDA on Engineering
Matters.
11 Six (6) personnel, from the Head Office Bids and The BAC Chairperson committed to:
Awards Committee (BAC), its Secretariat and
Technical Working Group (TWG), have no, 1. Ensure that the BAC, its Secretariat and
insufficient and/or outdated GPPB recognized TWG have the required procurement
Procurement Training/Seminar. training and are updated with the latest
requirements of RA 9184 and GPPB.
Page 4|4