VSL TECHNOLOGY SOUTH EAST ASIA MALAYSIA POST-TE N SI O N I NG

FOUR SEASONS PLACE - J1501


DATE
2015-2017

CARRYING OUT POST-TENSIONING LOCATION


Kuala Lumpur

FOR A PRESTIGIOUS HOTEL OWNER


Venus Assets Sdn Bhd

ARCHITECT
NRY Architects Sdn Bhd

F
our Seasons Place is a 65-floor block put pressure on staff and meant that efficient
comprising the Four Seasons Private strategies had to be developed. ENGINEER
Residences Kuala Lumpur and the Notably, each floor had to be divided into several Meinhardt (Malaysia)
Four Seasons Hotel Kuala Lumpur, small pours to avoid the need for delivery of Sdn Bhd
together with basement car parks, ready-mixed concrete during the hours of the
a lobby and podium for commercial purposes. heaviest traffic in this very densely developed MAIN CONTRACTOR
The new structure is located on Jalan Lumba area of town. CRCC Malaysia Bhd
Kuda, off Jalan Ampang, a prime spot right next
to the iconic Petronas Twin Towers, in the heart VSL also had to face technical constraints during
of Kuala Lumpur. the works, as the stanchion of the vertical
protection system obstructed the tendon- SCOPE OF WORKS
The main contractor – CRCC Malaysia BH, one stressing operation at the edge of the building.
of many construction companies linked to the As a result, the tendons had to be stressed at a Post-tensioning installation
Chinese government – needed help with the later stage, once the stanchion had been moved
installation of the post-tensioning (PT). out of the way and working platforms had been Technical support
erected.
VSL carried out the PT works using a tailor-made Production of post-
approach. The group also assisted and advised PT was installed at every floor from level 7 to tensioning shop drawings
CRCC in all PT-related matters and produced the level 65. VSL’s GC 6-12 and GC 6-22 components
PT shop drawings. were used up to level 8 and VSLAB was used for
all the remaining levels. KEY FIGURES
Space constraints were a challenge when ——371 tonnes of 15.2mm-
performing the PT works for the hotel, as In total, 371 tonnes of 15.2mm-diameter strands diameters strands
it is located in the very centre of town. As a were required for the works, which started
solution, much of the rebar was prefabricated in November 2015 and were completed in
before delivery. The confined space also limited September 2017.
the number of passenger hoists available, which

www.vsl.com
1/1